The following constitutes pre-commissioning tests at site.
(a) Insulation resistance test
(b) Ratio test on all taps..
(c) Open circuit test for measurement of magnetizing current.
(d) Short circuit test.
(e) Operation test on OLTC if provided.
(f) Measurement of winding resistance of all windings, at all taps in winding having taps.
(g) Determination of Vector group and polarity test.
(h) Measurement of capacitance and tan delta of transformer bushings of EHT voltage rating.
(i) Core balance test.
(j) Tests on bushing CTs if provided.
1. INSULATION RESISTANCE:
Purpose
Instrument required
2.5 KV Megger
Procedure:-
First remove the cover of the terminal block. In normal condition the three terminals
CL,CC&G are shorted by using metal plate. For core insulation testing disconnect the
closing link that connects the two terminals CL and G. Connect the +ve terminal of the
megger in CL terminal and -ve terminal to CC+G. Before testing the tank should be
grounded. Apply 2.5 KV D.C supply between CL and CC+G.
The insulation value after 1 minute test should be more than 1000 M ohm for the
newly installed transformer.
The purpose of this testing is to check the soundness of the transformer insulation. This
test reveals the condition of degree of dryness of paper insulation, presents of any
foreign
PROCEDURE
(a) HV/E + LV
Result
If dielectric absorption is above 1.3 and Polarization Index is more than 1.25 then
insulation quality is assumed to be good.
Purpose
Transformer winding resistance is measured to check for any abnormalities due to loose
connections, broken strands and high contact resistance in tap changers.
Instrument required
Transformer winding resistance meter (10 to 25 A will inject)
Procedure
c. Repeat the testing by changing tap position up to 17. (Temperature should also
taken)
Normally the resistance will be below 1 ohm. All the winding temperature reading
should be recorded and the resistance at 75c be calculated as follows.
t=Winding temperature
Purpose
To determine the phase relationship and polarity of Transformers.
Procedure
1R1-1Y1,1Y1-1B1,1B1-1R1,3Y1-1B1,3Y1-1Y1,3R1-N,3Y1-N,3B1-N,2R1-N,2Y1-
N,2B1-N
Ensure 2R1-N=2Y1-N=2B1-N
Ensure 3R1-N > 3Y1-N > 3B1-N And 3Y1-1B1 > 3Y1-1Y1
1. Dd0
CONDITIONSA) 1U-1V=1U-2V+2V-2U
B) 1U-1W=1U-2W+2W-1W
C) 1V-2V=2W-1U
D) 1V-2V=1W-2W
2. YNO0d1
C) (1V-3V<1V-3W)
3. YN0OD11
B) 3U-N>3V-N>3W-N
C) 3V-1W>3V-1V
1U2V = 304.00
1U2W = 308.00
1V2U = 405.40
1V2V = 136.50
1V2W = 305.90
1W2U = 409.60
1W2V = 293.70
1W2W = 125.30
1U,2U
1V 2V = 1W 2W
136.5 = 125.30
IV 2V < 1V 2W> 2W
2V
136.5 <305.90
1W 2W< 1W 2V
1W 1V
125.3 < 293.7
1. 1U & 3U shorted
2. 3 Phase Voltage applied to HV
3. Voltage Applied in Volts. Voltage Measured in Volts.
1V-3W = 409.00
1W-3U = 410.00
3W 1W-3V = 394.80
1W-3W = 394.00
3V
1V 3W > 1W 3W
1V 3W > 1V 3V
1V
3W
1U, 2U
4. YNyn0
B)1V-2V=1W-2W 2W 2N
2V
1W 1V
C)1U-1N=1U-1N+1N-1V
1N
5. YNyn6
Measure the voltage at the terminals of 1U-1N, 1W-1N, 1V-1N, 1W-2W, 1V-2V, 1V-2W,
and 1W-2V.
B) 1V-2V>1W-2V
C) 1W-2V=1V-2W
6. Dyn5
Measure the voltage at the terminals of 1U-1V, 1U-1W, 1V-1W, 2U-2N, 2V-2N, 2W-2N,
and 1V-2V. 1V-2W, 1U-2N, 1W-2V, 1W-2W.
B) 1U-1W=1U-1V
C) 1V-2N=1V=2U+2U-2N
D) 1V-2V>2N-1V
7. Dyn1
Measure the voltage at the terminals of 1U-1V, 1U-1W, 1V-1W, 2U-2N, 2V-2N, 2W-2N,
and 1V-2V. 1V-2W, 1U-2N, 1W-2V, 1W-2W.
B) 1W-2W=1W2V
C) 1U-1W=1U-1N+1N-1W
8. YNd11
B) 1U-1V=1U-1N+1N-1V
C) 1U-1N=2U-2W+2W-1N
Purpose
Instrument required
Procedure
Ratio: HV/IV
Keep the tap position of the transformer in lowest position and IV and LV terminals
open.The voltage should be applied only in the high voltage winding in order to avoid
unsafe voltage.
Ratio measurement must be made on all the taps to confirm the proper alignment and
operation of the tap changer.
Ratio: HV/LV
Ratio :IV/LV
Definition
Excitation/ Magnetizing current is the current required to force a given flux through the
core
Purpose
c. Measure the voltages applied on each phase (Ph-Ph) and phase current in each
HV winding
a. Keep the tap position of transformer in the Normal (9b) position and put HV
and LV terminals in open.
h. Measure the voltages applied on each phase (Ph-Ph) and phase current in each
IV winding.
Evaluation
Purpose
Procedure
Apply 3 Ph 415V to the high voltage winding and make the measurement in the
IV winding with respect to neutral and neutral point to ground.
Then apply 3 Ph 415V to the intermediate voltage winding and make the
measurement in the tertiary winding with respect to neutral and neutral point to
ground.
Result:-
Purpose
The test is conduct to check the balance in the magnetic circuit in three phase
transformers
Procedure
Apply single phase voltage (230V) between phase and neutral of a winding
(R- Ph to N in HV) and measure the voltage induced in other two phases of the
same winding(Y ph to N & B ph to N in HV)
Result
Zero voltage or very negligible voltage induced in any of the other two phases
shall be investigated.
All the time take the primary voltage and short circuit current
%ofimpedence
IMPEDENCE VOLTAGE:
100
HV SIDE VOLTAGE
appliedvoltage
PRIMARY SHORT CURRENT: Hvcurrent
impedencevoltage
appliedvoltage
SECONDARY SHORT CURRENT: Lvcurrent
impedencevolts
(OR)
Purpose
Definition
Dissipation factor / loss factor (Tan delta) is defined as the ratio of resistive component
of current to that of capacitive current flowing in an insulating material.
Instruments required
Measurements of capacitance and dissipation factor under high voltage condition are
commonly made using a Schering Bridge.
Testing modes
This is used when specimen do not have two specific points (isolated from ground)
This test is conducted by applying a test voltage up to 10KV by using Tan delta
kit.
Result
Purpose
Capacitance and Tan delta measurement of winding is carried out to ascertain the
general condition of the ground and inter winding insulation of transformer.
Testing modes
Procedure
For ICT, Tan delta measurement of winding is to be done in GST MODE in Three
combinations
1. HV+IV/LV+TANK+G
2. Procedure
1. Remove the grounding strap from the neutral bushing of the HV winding.
2. HV+IV+LV/ TANK+G
Procedure
1. Remove the grounding strap from the neutral bushing of the HV winding.
2. LV/HV+IV+TANK+G
Procedure
1. Remove the grounding strap from the neutral bushing of the HV winding.
Note: The Tan delta value of winding should be less than 0.007.