11-2.4 - (T) Risk Assessment Guides and Method Statement

Download as pdf or txt
Download as pdf or txt
You are on page 1of 112
At a glance
Powered by AI
The key takeaways are that risk assessments are a legal requirement to identify hazards and control measures to ensure worker safety. A risk assessment should involve identifying hazards, evaluating risks, recording findings, and reviewing regularly. A method statement is used to describe safe work procedures and is informed by the risk assessment.

The purpose of conducting a risk assessment is to identify hazards in the work activity and put in place control measures to eliminate or reduce risks to health and safety arising from those hazards.

The main steps involved in conducting a risk assessment are to identify hazards, determine who might be harmed and how, evaluate the risks, record findings, and review the assessment regularly if anything changes.

QCS 2014 Section 11: Health and Safety Page 1

Part 2.4.01: Risk Assessment Guides and Method Statement

2. SAFETY AND ACCIDENT PREVENTION MANAGEMENT / ADMINISTRATION SYSTEM


(SAMAS) ....................................................................................................................................

2.4 RISK ASSESSMENT GUIDES AND METHOD STATEMENT .................................................

2.4.1 INTRODUCTION 2
2.4.2 What is risk assessment? 2
2.4.3 Legal requirements for risk assessment and written method of Work 3
2.4.4 Risk assessment in practice 3
2.4.5 Hazard and risk 3
2.4.6 Risk assessment Process 6
2.4.6.1 Identify the Hazards 6
2.4.6.2 Work out who might be harmed and how 6
2.4.6.3 evaluates the risks and decides on precautions 6
2.4.6.4 Record your findings and implement them 7
2.4.6.5 Review your risk assessment and update if necessary 7
2.4.7 Suitable and sufficient risk assessment 7
2.4.8 Recording the assessment 8
2.4.8.1 Qualitative and quantitative risk assessments 8
2.4.8.2 Qualitative assessments 8
2.4.8.3 Quantitative assessments 9
2.4.9 Consultation in development of risk assessment 11
2.4.10 Young persons and children 11
2.4.11 Language issues 12
2.4.12 Safety Culture and other Behavioral Safety issues 12
2.4.13 Other issues 13
2.4.14 Health Surveillance 13
2.4.15 Example of work activities requiring risk assessment 13
2.4.16 Safe method of work (Method statement) 14
2.4.17 Review of the method statement 14
2.4.18 Communication of risk assessment and method statement 14
2.4.19 Training programmes 15
2.4.20 Appendix 16
QCS 2014 Section 11: Health and Safety Page 2
Part 2.4.01: Risk Assessment Guides and Method Statement
2.4.1 INTRODUCTION

1 Risk assessment is a fundamental principle in the management of health and safety. It is an


important step in protecting workers and business, as well as complying with the law. It helps you
focus on the risks that matter in or in connection to your work activity or construction work.

2 Section 1.1.7 of the Regulatory Document places legal duty on Contractors and the self-employed
to assess the risks to the health and safety of their employees and others that arise out of or in
connection with their work activities. They are also legal duty to develop written methods of work
commonly referred to as method statement.

3 A risk assessment can be interpreted as a structured examination of a work activity so as to identify


what could cause harm to people (employees or others) and how appropriate control measures can
be put in place to eliminate or control risks.

4 For any risk assessment is to be effective, it is essential that the person who carries it out is familiar
with all aspects of the task being assessed, specialist advice is sought where necessary and those
to deliver the work activities are consulted in development of the risk assessment.

5 For any risk assessment to be effective, it is essential that the risks and controls are communicated
to those affected.

6 The legal requirement on contractors to carry out risk assessments and written method of work
support the requirements for a Contractor to provide for their employees

(a) A safe place of work

(b) Safe access and egress to and from that place of work

(c) Safe method of work

(d) Safe plant and equipment

7 Risk assessment and written method of work should identify the requirements for the contractor to
provide for his employees

(a) information about how to undertake the work activity safety and without risk to their health

(b) implementation of instructions for undertaking the work activity safety and without risk to
their health

(c) necessary training to employees so that they have the understanding and skills to undertake
the work activity without risk to their health and safety

(d) implementation of supervision of the work activity

2.4.2 What is risk assessment

1 A risk assessment is a careful examination of what, in your work, could cause harm to people, so
that you can weigh up whether you have taken enough precautions or should do more to prevent
harm. Workers and others have a right to be protected from harm caused by a failure to take
reasonable control measures.

2 A risk assessment should usually involve identifying the hazards present in any working activity
and identifying the associated risks, evaluating them, identifying those affected and putting in place
suitable and sufficient mitigation. The exercise should take into account any existing precautions
and their effectiveness.

3 Accidents and ill health can ruin lives and affect business too if output is lost, machinery is
damaged, insurance costs increase or you have to go to court. Contractors are legally required to
QCS 2014 Section 11: Health and Safety Page 3
Part 2.4.01: Risk Assessment Guides and Method Statement
assess the risks for or in connection to their work so that a plan to control the risks are put in place
and implemented

2.4.3 Legal requirements for risk assessment and written method of work

1 Section 1.1.7 of the Regulatory Document requires all contractors (employers and self-employed
people) to assess the risks to workers and any others who may be affected by their work activity or
construction work. The risk assessment will enable them to identify the measures they need to
have in place and implement in order to comply with section 1.1.7.

2 There are requirements to undertake suitable and sufficient risk assessment, to record the
assessment and to monitor & review its implementation. Development of risk assessment shall
involve consultation with expert knowledge as required and it findings shall be communicated to
those affected.

3 Any risk assessment shall give consideration to young persons and take into account risk barriers
such as safety culture, behavioral safety and language issues as applicable to the place of work.

4 There are requirements for risk assessments to be supported by effective and written method
statement identifying and implementation of training needs, instruction and supervision.

5 The contractor should work with other contractors, subcontractors to identify the hazards and
assess the risks related to their work, including the risks they may create for others.

2.4.4 Risk assessment in practice

1 The principle of risk assessment to eliminate and control risk to safety and health is not new. In
fact, many Contractors will have been carrying out risk assessments to their day to day business as
part of business planning and success. However section 1.1.7 imposes specific legal requirements
on the Contractor to undertake risk assessment for health and safety.

2 If the task to be assessed is substantial, difficult or complex then, it will not be practical or effective
to carry out a single risk assessment to cover the whole of the work. The job will need to be broken
down into separate elements or work activities, each of which will have to be assessed separately.

3 Many Contractors, who have recognized potential problems in course of their business as they
occur, will have taken the necessary action to avoid an incident (including near misses and
accidents). Conducting risk assessment, proper recording and ongoing review of the risk
assessments is an essential process in preventing incidents.

4 Factors that need to be considered during the risk assessment process is the complexity of the
activity, the number of persons involved or affected, the plant or equipment being used, and the
types and nature of the materials involved. The environment where the work will be carried out is
also a factor which should be taken into account.

5 In many instances, straightforward measures can readily control risks, for example ensuring
spillages are cleaned up promptly so people do not slip, or cupboard drawers are kept closed to
ensure people do not trip. For most, that means simple, cheap and effective measures to ensure
your most valuable asset your workforce is protected.

2.4.5 Hazard and risk

1 A hazard is something with the potential to cause harm and this can include articles, workplace,
substances, plant or machines, tools, methods of work, the working environment and other aspects
of work organization and includes the potential to harm/damage the environment and/or causing a
statutory nuisance.

2 A risk is the likelihood of potential harm from that hazard being realized. The extent of the risk will
depend on:
QCS 2014 Section 11: Health and Safety Page 4
Part 2.4.01: Risk Assessment Guides and Method Statement
(a) the likelihood of that harm occurring

(b) the potential severity of that harm, i.e. of any resultant injury or adverse health effect; and

(c) the population which might be affected by the hazard, i.e. the number of people who might
be exposed

(d) The frequency and time of exposure

Risk = consequence x probability and is classed as either Acceptable or Unacceptable,


depending on the results of the quantifying matrix

3 A risk is the chance, high or low, that somebody could be harmed by these and other hazards,
together with an indication of how serious the harm could be. i.e. is the likelihood of potential harm
from that hazard being realized. The extent of the risk will depend on:

(e) the likelihood of that harm occurring

(f) the potential severity of that harm, i.e. of any resultant injury or adverse health effect; and

(g) the population which might be affected by the hazard, i.e. the number of people who might
be exposed

(h) The frequency and time of exposure

Risk = consequence x probability and is classed as either Acceptable or Unacceptable,


depending on the results of the quantifying matrix

4 It is very important to distinguish between hazard and risk; the two terms are often confused.

5 Construction works are inherently hazardous and the risk associated with it will be reduced as
controls are implemented. The level of risk remaining when controls have been adopted is known
as the residual risk. There should only be high residual risk where there is poor health and safety
management and inadequate control measures.

6 Reasonably practicable is a narrower term than physically possible a computation must be


made by the owner in which the quantum of risk is placed on one scale and the sacrifice involved in
the measures necessary for averting the risk (whether in money, time or trouble) is placed in the
other, and that, if it be shown that there is a gross disproportion between them the risk being
insignificant in relation to the sacrifice the defendants discharge the onus on them.

7 Who is responsible for managing risk?

All employers (and self-employed) are required to take reasonably practicable steps to assess the
risk to both employees and others who could be affected by the undertakings of their business.
Others who could be affected include:
(a) Visitors to the workplace

(b) Consumers of products or services

(c) Service providers working on the premises

(d) Work colleagues and fellow persons working in the vicinity

(e) Neighbours or residents in the surrounding area


QCS 2014 Section 11: Health and Safety Page 5
Part 2.4.01: Risk Assessment Guides and Method Statement
Risk Assessment Methodology

Major injury, damage or environment impact

Fatality building loss, catastrophic environment


Minor injury, damage or environment impact
No injury, damage or environment impact

impact
Risk Factor

1 2 3 4

Almost no probability 1 A A A U

A small probability 2 A A U U

A high probability 3 A U U U

Almost Certain 4 A U U U
Acceptable Unacceptable
Consequence X Probability = Risk
14 4

Risk Level Action

No further preventative action. Consideration shall be given to


more cost-effective solutions or improvements that impose no
Acceptable Additional cost burden. Monitoring required to ensure that
Controls in place are properly maintained.

Work shall not be started or continued until the risk level has
Been reduced to an acceptable risk level. While the control
measures selected shall be cost-effective, legally there is an
Unacceptable absolute duty to reduce the risk, this means that if it is not
possible to reduce the risk even with unlimited resources, then
the work shall not be started or shall remain prohibited.
QCS 2014 Section 11: Health and Safety Page 6
Part 2.4.01: Risk Assessment Guides and Method Statement
2.4.6 Risk assessment Process

1 A risk assessment is a five-stage process:

(a) Identification of all the hazards and associated risks

(b) Work out who might be harmed and how

(c) Evaluate the risks and decide on precautions

(d) Record your findings and implement them

(e) Review your assessment and update if necessary

2.4.6.1 Step 1: Identify the Hazards


1 Identification is simply working out how people could be harmed. Some techniques for risk
identification are: brainstorming, refer to sources of information such as relevant legislation, code of
practice and guidance, supplier manuals and manufacturers instructions, data sheets, safety
alerts, lessons learnt, use information supplied by designers (pre-construction information), the
residual risk supplied by designers, seeking advice from experts and competent sources and
guidance from trade associations, etc.

2 Identification of hazards can also be undertaken by walking around the place of work and consult
with employees or their representative about concerns in relation to the place or work or the work
activity.

3 Checking the accident and ill-health records often helps to identify the less obvious hazards.

4 A valuable source for such information is obtainable from the UK governing body for Health and
safety; known as the Health and Safety Executive (HSE). The HSE publishes practical guidance on
where hazards occur and how to control them. Visit the HSE website (www.hse.gov.uk).

2.4.6.2 Step 2: Work out who might be harmed and how


1 For each hazard you need to be clear about who might be harmed; it will help identify the best way
of managing the risk. That doesnt mean listing everyone by name, but rather identifying groups of
people (e.g. people working in the storeroom or passers-by). In each case, identify how they
might be harmed, i.e. what type of injury or ill health might occur. For example, shelf stackers may
suffer back injury from repeated lifting of boxes.

2 Remember that some workers have particular requirements, e.g. young persons or others with
impaired mobility, expectant mothers etc.

3 Extra thought will be needed for some hazards to visitors, other contractors, members of the public
etc if they could be hurt by your activities.

2.4.6.3 Step 3 Evaluate the risks and decide on precautions


1 Having spotted the hazards, you then have to decide what to do about them. The law requires you
to protect people from harm. You can work this out for yourself, but the easiest way is to compare
what you are doing with good practice.

2 Think about what controls you have in place and how the work is organized. Then compare this
with the good practice and see if theres more you should be doing to bring yourself up to standard.
In asking yourself this, consider: Can I get rid of the hazard altogether? If not, how can I control the
risks so that harm is unlikely?

3 When controlling risks, apply these principles: try a less risky option (e.g. switch to using a less
hazardous chemical); prevent access to the hazard (e.g. by guarding); organize work to reduce
exposure to the hazard (e.g. put barriers between pedestrians and traffic); issue personal
QCS 2014 Section 11: Health and Safety Page 7
Part 2.4.01: Risk Assessment Guides and Method Statement
protective equipment (e.g. clothing, footwear, goggles etc); and provide welfare facilities (e.g. first
aid and washing facilities for removal of contamination).

2.4.6.4 Step 4: Record your findings and implement them


1 Putting the results of your risk assessment into practice will make a difference when looking after
people and your business. Writing down the results of your risk assessment, and sharing them with
your staff, encourages you to do this. When writing down your results, keep it simple, for example
Tripping over rubbish: bins provided, staff instructed, weekly housekeeping checks, or Fume from
welding: local exhaust ventilation used and regularly checked.

2 You need to be able to show that: a proper check was made; you asked who might be affected;
you dealt with all the significant hazards, taking into account the number of people who could be
involved; the precautions are reasonable, and the remaining risk is low; and you involved your staff
or their representatives in the process.

2.4.6.5 Step 5: Review your risk assessment and update if necessary


1 The risk assessment should be appropriate to the nature of the work and should identify the period
of time for which it is likely to remain valid. This will enable the existing control measures to be
reviewed and modified, and to put in place as necessary.

2 Construction sites do not stay the same. Thus hazards would be dynamic as the environment
changes and works progresses and also with the bringing in of new equipment and substances etc.
It makes sense, therefore, to review what you are doing on an ongoing basis. This means that any
significant change to a place of work, process, or activity requires the risk assessment to be re-
evaluated or the introduction of any new process, activity or operation to be subject to a new risk
assessment.

3 Look at your risk assessment again and the changes. Consult workers and lessons learnt from
accidents or near misses.

4 Make sure your risk assessment stays up to date and set a review date proportionate to the
complexity of the work activity or construction works. If there is any significant change to activities
or a new sub/work package contractor starting work which could lead to new hazards then these
shall be incorporated into the assessment. The need for review will depend upon the level of risk
but in every case will be reviewed on sites at the same time as the Contract Management Plan or
at permanent locations annually.

5 A risk assessment should always therefore be viewed as a live document and must be reviewed
following certain trigger events, or at least annually.

6 Risk Assessments should be reviewed when: -

(a) There has been an incident (accident or near miss)

(b) Any significant change to processes, equipment or substances occurs

(c) When there have been changes in the law

(d) When enforcement action has taken place

(e) When people identify an opportunity for improvement

2.4.7 Suitable and sufficient risk assessment

1 An assessment required under The Management of Health and Safety at Work which:

(a) Correctly identifies a hazard


QCS 2014 Section 11: Health and Safety Page 8
Part 2.4.01: Risk Assessment Guides and Method Statement
(b) Disregards negligible hazards and those associated with life in general

(c) Determines the likelihood of injury, harm or loss

Probability of exposure

Maximum probable loss

Number of persons at risk and/or the financial loss to the company

(d) Identifies any specific legal duty or requirement relating to the hazard

(e) Provides sufficient information to enable appropriate control measures to be taken

(f) Enables control measures to be prioritized

2 Suitable and sufficient risk assessment means the risk assessment should do the following:

(f) Should identify the risks arising from or in connection with work

(g) The level of detail in a risk assessment should be proportionate to the level of risk the work
activity entails

(h) The level of risk arising from the work activity should determine the degree of sophistication
of the risk assessment; for example risks which require specialist knowledge such as a
particularly complex process or technique, or large and complex projects, hazardous sites
will require the most developed and sophisticated risk assessments to address the level of
risks.

(i) Risk assessments must also consider all those who might be affected by the undertaking,
whether they are workers or others such as members of the public.

(j) Whenever specialist advisers are used, contractors shall ensure that the advisers have
sufficient understanding of the particular work activity they are advising on, this will often
require effective involvement of everyone concerned contractor, subcontractor, employees
and specialist.

2.4.8 Recording the assessment

1 Risk assessment shall be recorded in writing. This means writing down the significant hazards
identifying the associated risks coming, evaluate the risks by identifying those affected, the impacts
and the controls put in place.

2.4.8.1 Qualitative and quantitative risk assessments


1 The risk of something going wrong is considered in terms of probability (likelihood) and the
consequences (seriousness).

2.4.8.2 Qualitative assessments


1 The probability of a hazard actually causing harm or an accident is rated as being High, Medium or
Low in accordance with the following:

(a) HIGH: it will happen regularly, or it could be a usual or a common occurrence

(b) MEDIUM: it is less regular, but is still recognized as being likely to happen

(c) LOW: it has not happened for a long time, is known to be infrequent and is not likely to
happen
QCS 2014 Section 11: Health and Safety Page 9
Part 2.4.01: Risk Assessment Guides and Method Statement
2 The consequences of the event, should it happen, can then be categorised as follows:

(a) HIGH: the result could be a fatal accident or multiple injuries / major property damage /
substantial pollution or environmental impact

(b) MEDIUM: it would probably cause serious injuries, or persons would be off of work for over
three days due to their injuries / substantial property damage / there may be some pollution

(c) LOW: there would be minor injuries to persons or some slight damage to property

3 Probability and consequences can then be shown on a matrix as follows

High
Probability Medium
Low
Low Medium High
Consequences

4 Probability and consequences can then be assessed and the highest outcome of the two entered in
the matrix as follows

High High High High


Probability Medium Medium Medium High
Low Low Medium High
Low Medium High
Consequences

(a) A combined risk of HIGH should be totally unacceptable and the work should not be
undertaken until the risk has been reduced MEDIUM: it would probably cause serious
injuries, or persons would be off of work for over three days due to their injuries / substantial
property damage / there may be some pollution.

(b) When there is a combined risk of MEDIUM, action must be taken, and work stopped if
necessary, to reduce the risk level.

(c) If the combined risk is LOW, start the work as long as everything reasonably practicable has
been done in order to reduce the risk, and that the assessment is reviewed at regular
intervals

5 Using this information, decisions can now be made on whether an activity is safe to continue, or
whether control measures are necessary, either to completely change the way that the job is done
or measures put in place so as to bring the risks down to an acceptable level. In the ideal situation,
both probability and consequences should be LOW.

6 Probability and consequences can then be shown on a matrix as follows

2.4.8.3 Quantitative assessments


1 The principle is the same as for Qualitative assessments, but numerical scores rather than a grade
are assigned to probability and consequences.

2 The probability or likelihood of the event is rated on a scale of 1 to 5 as follows:

(a) It is certain to happen.

(b) It is very likely to happen, and would not be at all unusual


QCS 2014 Section 11: Health and Safety Page 10
Part 2.4.01: Risk Assessment Guides and Method Statement
(c) Likely to happen, and would not be totally unexpected

(d) Unlikely to happen, but not by any means impossible

(e) Very unlikely to happen

3 The consequences or the severity of the event, should it happen, are also then rated on a scale of
1 to 5 as follows:

(a) No injury. It would be a 'near miss'. Minor property damage.

(b) Minor injury. Less than three days' work time lost. Property damage more than just minor
likely to happen, and would not be totally unexpected.

(c) Reportable injury to the HSE with over three days time lost, but not a major injury.
Substantial property damage or something causing environmental damage.

(d) Major injury, long term absence. Major damage, serious environmental impact.

(e) Fatal accident or multiple major injuries. Public or others could be involved as well.

(f) A matrix can then be constructed using these numbers, as follows

5
4
Probability 3
2
1
1 2 3 4 5
Consequences

4 All possible resulting numbers are calculated by multiplying all the probability figures by all the
consequence figures. These are included in the matrix, as shown below. This means that once a
risk assessment has been made on a particular activity, and the probability factor is multiplied by
the consequence factor, the number produced indicates where the assessment places the risk
associated with the activity on the matrix

5 5 10 15 20 25
4 4 8 12 16 20
Probability 3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5
1 2 3 4 5
Consequences

5 Clearly, the higher the resulting number, the less acceptable the level of risk. The matrix shows
where actions need to be taken to reduce either the probability or the consequences in order to
reduce the risks to an acceptable level

5 5 10 15 20 25
4 4 8 12 16 20
Probability 3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5
1 2 3 4 5
QCS 2014 Section 11: Health and Safety Page 11
Part 2.4.01: Risk Assessment Guides and Method Statement
Consequences

6 Contractors themselves can use these numbers to set in-house criteria, if desired, along the
following lines, and as indicated by the shaded areas in the above matrix:

(a) Risks with a rating above 16 are totally unacceptable and the work will not be undertaken
until the risk has been reduced.

(b) Where the risk rating is between 10 and 15, immediate action must be taken, including a
stoppage of work if necessary, to reduce the risk level.

(c) If the rating is between 5 and 9, the risk is acceptable provided that everything reasonably
practicable has been done to reduce the risk.

(d) With a rating of 4 or less then the risk is acceptable, provided that the assessment is
reviewed at regular intervals and further reduced if possible.

Note: - It is stressed that it is for individual companies or managers to decide where the boundaries between
what is and what is not acceptable lie, and the numerical score at which certain actions should be taken

If either the qualitative or quantitative methods are used in conjunction with a simple form, then the
Contractors will have a straightforward basic risk assessment procedure

2.4.9 Consultation in development of risk assessment

1 Consulting employees or their representatives about matters to do with their health and safety and
in developing risk assessment is a requirement under section 1.1.7 of the Regulatory document
and is a good management practice as well.

2 Any risk assessment shall involve effective consultation with the workforce who will undertake the
job.

3 Thus contractors need to involve employees concern or their representative in developing risk
assessment.

2.4.10 Young persons and children

1 Contractors are required to specifically assess and review the risks to the health and safety of
children and young persons due to their lack of maturity, lack of experience and lack of knowledge
of potential risks.

2 There is a requirement that young people should not carry out certain types of work, except in
circumstances involving training and supervision where the young person is no longer a child.

3 A 'child' is anyone under the minimum school leaving age and a 'young person' is anyone over the
minimum school leaving age but less than 18 years of age.

4 A young person under 16 years of age cannot be employed at all in a Qatar workplace; this is
stated in Labor Law 14, Article 86.

5 Before a young person is employed, the Contractors must ensure that any risk assessments
pertaining to the job take account of the following factors in relation to the young person:

(a) their inexperience

(b) their immaturity and lack of awareness of risks


QCS 2014 Section 11: Health and Safety Page 12
Part 2.4.01: Risk Assessment Guides and Method Statement
(c) the tools and equipment that they may have to use as part of their training

(d) the layout of the workplace and the environment in which they may have to work.

(e) any hazardous substances with which they may come into contact

(f) exposure to physical, chemical or biological hazards

(g) the organization of work processes and activities

(h) the extent of health and safety training that is to be provided

5 Careful consideration must be given to the way in which information is conveyed to young persons
to ensure that it is fully and readily understood.

6 Where children are employed either for work experience or work in offices then the Contractors
must, before commencing the employment of the child, provide that child's parents or guardians
with details of any risk assessment which has been carried out. This information must contain
details of any risk and a description of any preventative or protective measures, whether the risk
arises from the Contractors own activity or the activities of others at the workplace.

7 Contractors are further required to consider the special nature of young persons due to their lack
of experience, knowledge of risks and the fact that they are not fully mature. To that end, young
people must not be employed in any work.

(a) with which they cannot physically or psychologically cope

(b) that exposes them to a range of hazardous substances, including any carcinogen, toxic
substance or radiation

(c) where they might not recognize the risk of accidents due to their inexperience or lack of
training

(d) where their health would be at risk from excessive cold, heat, noise or vibration

8 The prohibition above does not apply when a young person is undergoing recognized training, or
being properly supervised by a competent person, or when any risks identified in a risk assessment
have been reduced to the lowest level that is reasonably practicable.

2.4.11 Language issues

1 Site workers who have a poor or no understanding of either written or spoken Arabic must be taken
into account when compiling risk assessments. Effective communication is an essential element of
controlling risk; how such communication can be established must be a priority issue where there is
the potential for language difficulties on site.

2.4.12 Safety Culture and other Behavioral Safety issues

1 Site workers coming from abroad have different backgrounds and different perception of risks and
safety culture. The contractor needs to consider this as an important factor in developing the risk
assessment and implementing it.

2 The contractor must be proactive in monitoring behavioral safety issues and address them as part
of the risk assessment.

3 The contractor must implement a positive health and safety culture which means the avoidance,
prevention and reduction of risks at work must be accepted as part of the organizations approach
and attitude to all its activities. It should be recognized at all levels of the organization, from junior
to senior management.
QCS 2014 Section 11: Health and Safety Page 13
Part 2.4.01: Risk Assessment Guides and Method Statement
2.4.13 Other issues

1 While it is a legal obligation for contractors to regularly review risks at the place of work, some
other issues to consider would be persons with impaired mobility and new and or expectant
mothers. The assessment will help to decide additional action that needs to be taken in such
scenarios.

2 Any such risks identified must be included and managed as part of the general workplace risk
assessment.

3 The contractor must implement a positive health and safety culture which means the avoidance,
prevention and reduction of risks at work must be accepted as part of the organizations approach
and attitude to all its activities. It should be recognized at all levels of the organization, from junior
to senior management.

2.4.14 Health Surveillance

1 The contractor is required have in place health surveillance programmes where the findings of a
risk assessment identify health risks to employees that can be eliminated or reduced by applying
health surveillance techniques.

2 Health surveillance should be introduced where the risk assessment indicates that:

(a) there is an identifiable disease or adverse health condition related to the work concerned

(b) there are valid detection techniques

(c) there is a reasonable likelihood that the disease or condition may occur under the particular
conditions of work

(d) health surveillance has the potential to increase the protection of the health of the
employees concerned.

The contractor must implement a positive health and safety culture which means the avoidance,
prevention and reduction of risks at work must be accepted as part of the organizations approach
and attitude to all its activities. It should be recognized at all levels of the organization, from junior to
senior management.

2.4.15 Example of work activities requiring risk assessment

1 Example of work activity that need to be risk assessed are:

(a) the use of hazardous substances

(b) noise in the place of work

(c) manual handling activities

(d) the presence of asbestos

(e) work at height

(f) Work with vibrating tools and equipment

2 See appendix A for more examples of work activities and guidance for undertaking risk
assessment.
QCS 2014 Section 11: Health and Safety Page 14
Part 2.4.01: Risk Assessment Guides and Method Statement
2.4.16 Safe Method of Work (Method Statement)

1 A written method of work is commonly referred to as a method statement which is developed for
construction activities including temporary works. The method statement describes the logical
sequence of how a work activity is to be carried out safely and without risk to health. It should
identify the risks and the controls to be put in place, responsibilities like induction supervision
training and other elements needed to complete the work e.g. man power, plant, equipment etc.

2 It is good practice at planning stage of construction to identify a list of work activity which will need
development of method statement. This is sometimes referred to a schedule of method statement
which gets updated in the construction phase of the project as and when required, according to the
project complexity and the level of risks it entails.

3 The Contractor shall submit a Method Statement Schedule to the Engineer for approval no later
than thirty (30) days from the start of the Contract. The Method Statement Schedule shall define all
Method Statements to be prepared for the Works forming part of the Contract and the target dates
for their submission to the Engineer for approval.

4 The Contractor shall submit Method Statement for his work activities to the Engineer for approval
thirty (30) days prior to the commencement of the work activity covered by a Method Statement.

5 The method statement should be developed prior to undertake any such work activity identified as
mentioned above and should be unique to each work activity means No work covered by a Method
Statement shall begin until it has been approved by the Engineer.

6 The risk assessment will provide support to the development of the method statement.

7 Any development of method statement shall involve consultation with the workforce and shall
identify the requirements for:

(a) information about how to undertake the work safety and without risk to health

(b) implementation of instructions for undertaking the work safety and without risk to health

(c) identify and conduct necessary training to employees before execution of the activity; so
that they have the understanding and skills to undertake the work activity without risk to their
health and safety

(d) implementation of supervision of the work activity

8 The method statement should be briefed and acknowledged by the supervisor and the worker
respectively before undertaking of the work activity.

9 An example template for method statement is at appendix B.

2.4.17 Review of the method statement

1 Any method statement needs to be reviewed after any incident in undertaking or related to the
works, so that additional necessary mitigation can be embedded into the work procedure.

2.4.18 Communication of risk assessment and method statement

1 Any risk assessment and safe working method will be as good as the way they are communicated
to those affected.

2 The contractor should make sure they are communicated to employees and their representatives
so that they are aware of the health and safety risks for a work activity and the preventive and
protective measures in place. Thus establishing effective means of communication should be
devised by the contractor.
QCS 2014 Section 11: Health and Safety Page 15
Part 2.4.01: Risk Assessment Guides and Method Statement
3 Effective communication will ensure that employees are provided with sufficient information and
they understand the risks and control measures can be implemented effectively.

The method statement should be developed prior to undertake any such work activity identified as
mentioned above and should be unique to each work activity

2.4.19 Training programmes

1 The contractor needs to have in place and implement necessary training to employees so that they
have the understanding and skills to undertake the work activity without risk to their health and
safety.

2 Risk assessment should identify opportunities for training of workers and ensure they are
competent for the work activity.

3 Contractor should maintain training records.


QCS 2014 Section 11: Health and Safety Page 16
Part 2.4.01: Risk Assessment Guides and Method Statement
2.4.20 Appendix

2.4.20.1 Appendix A: Example of work activities requiring risk assessment

NUMBERED ASSESSMENTS
Associated with this project (Tick boxes)

REF NO. 1 SITE ESTABLISHMENT

REF NO. 2 HOARDING/FENCING (TEMPORARY)

REF NO. 3 DEMOLITION GENERAL

REF NO. 4 DEMOLITION (ASBESTOS REMOVAL)

REF NO. 5 BUILDINGS ADJACENT TO WORKS

REF NO. 6 OVERHEAD SERVICES/OBSTRUCTIONS

REF NO. 7 UNDERGROUND SERVICES

REF NO. 8 PILING (DRIVEN/BORED/BENTONITE)

REF NO. 9 EXCAVATIONS (SHALLOW/DEEP/CONTAMINATED)

REF NO. 10 HAUL ROAD CROSSINGS ON CONSTRUCTION SITES

REF NO. 11 BULK EARTHWORKS

REF NO. 12 REDUCED LEVEL DIG AND IMPORTED FILL

REF NO. 13 CONTAMINATED GROUND (WORKING WITH)

REF NO 13B POTENTIALLY CONTAMINATED GROUND/BUILDING FABRIC (ANTHRAX)

REF NO. 14 ENVIRONMENTAL ISSUES

REF NO. 15 WORKING ON PUBLIC ROADS

REF NO. 16 WORKING OVER OR ADJACENT TO WATER

REF NO. 17 WORKING OVER OR ADJACENT TO RAILWAYS

REF NO. 18 CONCRETE WORKS AND REINFORCEMENT

REF NO. 19 CONCRETING, CONCRETE REPAIR, CONCRETE FINISHING

REF NO. 20 PRE CAST CONCRETE STAIRS, WALLS AND FLOORS

REF NO. 21 SCAFFOLD (ALL TYPES)

REF NO. 22 STRUCTURES (WORKING AT HEIGHTS)

REF NO. 23 STEEL ERECTION (GENERAL)


QCS 2014 Section 11: Health and Safety Page 17
Part 2.4.01: Risk Assessment Guides and Method Statement
REF NO. 24 WELDING, BURNING, STEELWORK

REF NO. 25 ROOFWORK/WORK NEAR FLOOR ETC OPENINGS

REF NO. 26 INFILLING OF FLOOR OPENING(S)

REF NO. 27 ROOFWORK (FLAT)

REF NO. 28 ROOF STRUCTURE (PLATES/TRUSSES/TIMBER)

REF NO. 29 ROOF COVERINGS (FELT/BATTEN/TILE)

REF NO. 30 EXTERNAL CLADDING (INC GLAZING)

REF NO. 31 WATER STORAGE DEVICES

REF NO. 32 LIFTING OPERATIONS

REF NO. 33 MANUAL HANDLING

REF NO. 34 SITE PLANT MOVEMENT/CARE

REF NO. 35 TOOLS (ELECTRIC/PNEUMATIC/CARTRIDGE)

REF NO. 36 CONFINED SPACES

REF NO. 37 NIGHT WORK

REF NO. 38 SPECIALIST SUB-CONTRACTOR PROCESSES e.g. BITUMINOUS SURFACING,


PAINTING WATERPROOFING, SILANE

REF NO. 39 STORAGE OF HIGHLY FLAMMABLE MATERIALS (COVERS SOME USAGE

REQUIREMENTS)

REF NO. 40 INSTALLATION OF FIRE PROTECTION COATINGS (BOARD)

REF NO. 41 INSTALLATION OF FIRE PROTECTION COATINGS (SPRAY)

REF NO. 42 LIFT INSTALLATION

REF NO. 43 ELECTRICAL/MECHANICAL SERVICES

REF NO. 44 PLUMBING WORKS

REF NO. 45 CARPENTRY/JOINERY

REF NO. 46 PLASTERING AND EXTERNAL RENDERING

REF NO. 47 CEILING FIXING

REF NO. 48 FLOOR AND WALL TILING

REF NO. 49 PAINTING AND PAPERING


QCS 2014 Section 11: Health and Safety Page 18
Part 2.4.01: Risk Assessment Guides and Method Statement
REF NO. 50 USE OF SPECIALIST EQUIPMENT (e.g. NUCLEAR DENSOMETERS, THERMIC

WELDERS AND LANCES, LASERS H.P. WATER JETTING

REF NO. 51 USE OF CLASS 3B LASERS (PREDOMINANTLY IN CONFINED OR

RESTRICTED AREAS)

REF NO. 52 ARC WELDING

REF NO. 53 RADIOGRAPHY

REF NO. 54 COMMISSIONING PLANT

REF NO. 55 BLOCK PAVING, FLAGGING KERBS AND EDGINGS

REF NO. 56 ROAD/PATH SURFACING

REF NO. 57 FENCING (PERMANENT)

REF NO. 58 LANDSCAPING

REF NO. 59 TREE SURGERY/CHAINSAW WORK

REF NO. 60 FIRE PREVENTION IN WORK AREAS

REF NO. 61 FIRE IN OFFICES

REF NO. 62 OFFICE ENVIRONMENT (PERMANENT/TEMPORARY)

REF NO. 63 YOUNG PERSON IN CLERICAL POSITION (SITE)

REF NO. 64 CABLE PULLING OPERATIONS

REF NO. 65 WORKING IN CHEMICAL/RADIOACTIVE DRAINS

REF NO. 66 BRICK/BLOCKWORK OPERATIONS

REF NO. 67 CLEANING/BUILDER'S CLEAN

REF NO. 68 LADDERS

REF NO. 69 LEAD BURNING/PLUMBING WORK

REF NO. 70 MOBILE ELEVATED WORKING PLATFORMS (MEWP's)

REF NO. 71 UNLOADING OF VEHICLES

REF NO. 72 USE OF STEP LADDERS

REF NO. 73 TRAFFIC MANAGEMENT

REF NO. 74 BLANK GENERIC ASSESSMENT FORM


QCS 2014 Section 11: Health and Safety Page 19
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 1

Assessment for: SITE ESTABLISHMENT


Significant risks: Falls of persons, falling objects, Moving plant/equipment,
Trapping of personnel/limbs, Overhead obstruction.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Layout drawings prior to delivery of cabins. Location of services (gas,
water, electric, sewer and telephone).

Instruction General safety instruction before activity commences e.g. Toolbox talks on
general risks etc.

Training General health and safety. Certificated crane/HIAB operator. Banks man
training where appropriate.

Supervision Competent person familiar with activity. Check no power lines/overhead


services in vicinity of lift.

Access Safe access for vehicles suitable base. Safe access/egress to roof of
temporary accommodation to fix or unfix lifting slings. Proper access to
cabin doorways to be provided. Secure doors at first/second floor levels not
provided with staircases.

Environment Establish ground loading and set up before delivery. Check location of
necessary services.

Equipment Crane/HIAB and lifting slings check Safe Working Load (SWL) and radii.
Check statutory documents before lift. Adequate ladder for access to roof
level.

Emergencies Standard COMPANY procedures to be in place ie. Mobile/phones/radios,


first aid etc.

Communications Activity to be under the control of one competent person familiar with
task/activity/types of hazards.

COSHH Check that ground is not highly contaminated. If so conduct COSHH


assessment.

PPE Hard hats, safety footwear, gloves and outdoor clothing. Harness at roof
level if appropriate.

Other Keep third parties/general public well away from lifting operation area.
Obtain certificate for electrical integrity for inclusion in COMPANY register.
Fire precautions.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 20
Part 2.4.01: Risk Assessment Guides and Method Statement

REF NO. 2
RISK ASSESSMENT GUIDE
Assessment for: SITE FENCING/HOARDING
Significant risks: Manual handling, striking underground services,
crushing/trapping by plant & equipment

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Emergency telephone numbers. Permits to dig contact all service
companies and private service owners for service plans and tracings. Site
boundary lines structuring and height of fence/hoarding details.
Operatives to work to Safety method statements. Operatives to sign Safety
Instruction/Training method statements. Operatives to be advised on hitting buried services.
Do Not assume depth. Use of detection equipment. Operatives to
temporarily fence when working adjacent to public.

Supervision To be fully conversant with services in work area. Must be qualified to


working in public highways/footpaths. If using crane/HIAB banks man to be
present.

Access Traffic management for works in public highways/footpaths. Compliance


with relevant guidance when working adjacent to overhead lines. Ground
conditions. Exclusion zone prior to concrete curing.

Environment Working adjacent to buildings. Overhead services. Traffic. Consider


effects of tree/shrub removal. Consider washing out facilities for concrete
delivery vehicles. Consider emergency action plan when near water
courses.

Equipment As applicable. Detection equipment. Temporary support for fence


posts/gates/hoardings as applicable whilst concrete cures.

Emergencies Liaise with emergency services and service providers. First aid kit, fire
protection, evacuation, accident reporting and investigation. Major incident
response plan. Emergency procedure to be detailed in contract safety plan.
Ensure openings/gates in hoardings/fencing are suitable for emergency
services.

Communications Warning signs. Hazard tape. Phone/radio.

COSHH As applicable for products used. Possible ground contamination.

PPE High visibility clothing, hardhats, protective footwear, ear protection, gloves,
goggles.

Other Detailed review of service drawings. Consider colour scheme for hoardings.
Viewing panels for security in hoardings.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 21
Part 2.4.01: Risk Assessment Guides and Method Statement

REF NO. 3
RISK ASSESSMENT GUIDE

Assessment for: DEMOLITION GENERAL


Significant risks: Falls from height, entrapment, health hazards. Injury from
falling/flying objects to operatives and general public,
sudden collapse of buildings/structures, fragile roofs, fires,
flooding, explosion, electrocution, contamination.
Inadequate access/egress.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Surveys, Safety Method Statements, structural assessments, scoping exercise
for hazards, equipments and structures etc. Previous drawings and plans. Site
history, past use, desk top study. Consultation at all levels.
Instruction Description of work to be carried out and methods to be used i.e. piecemeal or
controlled collapse. Specific responsibilities for plant and tools to be used.
Restrict others from area. Operatives to sign Safety Method Statement.
Induction: Lifting and manual handling; hazardous materials and hazardous
Training areas; oxygen and fuel cutting equipment; abrasive wheels; confined spaces
when applicable.

Supervision Work to be placed under competent person qualified and experienced in


demolition operations of work. Monitor certification of drivers. Monitor works.
Access Essential to restrict access of personnel at place of work being carried out. Effect
on adjacent areas. Prohibition of unauthorised persons. Traffic marking of
danger zones.
Environment State of existing property. Adequate welfare facilities. Overhead and general
services. Security of site during operations. General public, traffic, contaminated
material, dust, noise etc. No rubbish burning. Effect on residents, monitoring
requirements.
Equipment Provision of all relevant certification. Type to be approved as suitable to carry out
operations. Warning notices. Monitoring equipment. Consider transport safety.
Use of harnesses and equipment checks.
Emergencies Standard first aid, fire protection, evacuations, accident and investigation
reporting. Emergency procedures to be detailed in the contract safety plan.
Communications Other workers in the vicinity should be made aware of restricted access. Use of
lookouts, warning signs, letter drops to public, advice to other sub-contractors.
COSHH Handling of explosives, adhesives used for temporary support fixings, dust,
biological hazards and various chemical hazards must be identified and actioned.
PPE Hard hats, boots, protective clothing, goggles, ear protection, face masks,
harnesses.
Other Discuss storage/operations/use of explosives with Qatar Police as appropriate.
Carry out administration and monitoring on daily basis. Structural assessments
must be carried out by a suitably competent person.
Disposal of smoke sensor heads must be in accordance with manufacturers
recommendations due to heads containing radioactive isotopes.
Because hot/cold water systems may be contaminated, i.e. legionella, personnel
involved in the dismantling/demolition of such systems should wear suitable
respiratory protective equipment. Contact/discuss with your Safety SHE Dept
prior to commencing work.

The above controls have been selected to protect the health and safety of operatives and others who
may be affected by the work. This assessment must take into consideration all relevant Company
Safety Documents and must be used when compiling a site specific method/task
statement/procedure.
QCS 2014 Section 11: Health and Safety Page 22
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 4

Assessment for: DEMOLITION (ASBESTOS REMOVAL)


Significant risks: Asbestosis lung disease, mesothelioma, respiratory infections
to operatives and public. Increased risk for smokers.
Dust inhalation, ingestion and absorption.
Contaminated clothing.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Analysis of type of asbestos and evaluate the required measures. Safety Method
Statements. Provide specification for work. Survey the area.

Instruction Consult the Safety and Environmental Department, strict control of personnel to
trained persons. Medical surveillance. Operatives to sign Safety Method
Training Statement. Normally a specialist operation. Personnel to be fully trained in the
handling and removal of asbestos. Check all details.

Supervision Specialist training is required for all persons supervising the plant, equipment and
labour associated with asbestos.

Access Clean, tidy. Consider airlocks into work area decontamination unit. Designated
and controlled access are to be used. Exclusion zones.

Environment Zoning of areas to be established provision of ventilation etc. Consider sealed


working area to control dust, damping down and effects of weather, i.e. wind and
rain. Monitor atmosphere against the allowed levels of exposure. Clearance
tests if applicable. Disposal as special waste.

Equipment Consider suitable decontamination plant and materials to seal area, and dispose
of asbestos. Good separate welfare facilities. Air monitoring equipment.

Emergencies Clearance tests, first aid (seek medical advice). Fire protection, evacuation,
accident reporting and investigation. Major incident response plan. Emergency
procedures to be detailed in the contract safety plan.

Communications Standard warning signs and labelling of material for disposal. Advise all persons
who may be affected by work. Warning systems in event of emergencies.

PPE Suitable respirators, disposable overalls, gloves, goggles, masks.

Other This is a highly specialised activity; seek advice from Safety and Environmental
Department.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 23
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 5


Assessment for: BUILDINGS ADJACENT TO WORKS
Significant risks: Collapse/settlement. Associated services. Effect upon
occupiers from vibration and general inconvenience etc.
Undermining

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Details of existing construction and condition of the adjacent structure
should be used to produce a method statement. A detailed sequence, after
consultation with a qualified engineer, should be arrived at where
applicable. Design checks on excavations. Consider dewatering risks.
Instruction Site induction, briefing in position of existing services, methods to be
employed and special measures to limit noise, dust etc. Operatives to sign
Safety Method Statement.
Training Ensure all plant and equipment operators are certificated.

Supervision Supervisors to mark all services and monitor building, and wherever
possible verify details of foundations etc. Permits to dig to be issued and
possible additional supervision of operations.

Access Safe access and egress to be provided for operators and occupiers.
Consideration to be given to restricted access zone.

Environment Noise, dust and vibration to be kept to a level that does not interfere with
client installation or operations and monitored if applicable.

Equipment As required by specific operation, possible monitoring equipment required


for noise, dust, movement and vibration.

Emergencies Standard site first aid, reporting procedures. Emergency procedures for
occupiers to be considered. Major incident response plan.

Communications Warning signs and hazard markers.

COSHH Depends on exact activity undertaken.

PPE Standard for activities being undertaken.

Other Agreed dilapidation survey of structure prior to work commencing (if


possible). Temporary works coordinator involvement.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 24
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 6


Assessment for: OVERHEAD SERVICE/OBSTRUCTIONS
Significant risks: Electrocution, structural damage to services, injury from
structural collapse or plant capsize.
Disruption to client/public services. Explosion

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Contact service provider and clients for plans, details and exclusion zones.
Seek possibility of isolation of overhead electrics.

Instruction All employees advised of location of all overhead services (with sketches
and clearances) and nature of services (electricity, gas, steam, air etc.).
Working Safety Method Statements are to consider installation dangers.
Operatives to sign Safety Method Statements.

Training All personnel in the work area are to be inducted and given Safety
Awareness Talks on handling long object and plant movements in vicinity of
overhead services.

Supervision Regular inspection of barriers and notices. To be fully conversant with


services in the work area.

Access Consider exclusion zones, designated accesses and ground conditions.

Environment Consider the effects of weather and ground conditions. In particular wind
and rain e.g. heightened risks of arcing.

Equipment Provide crash deck where possible. Barriers to be of suitable construction


and design. Warning signs, hazard tapes and markers. Use of non-
conductive material. Height restrictions in plant.

Emergencies Liaise with Civil Defence (Fire Department) Standard site first aid, fire
protection, evacuation, accident reporting and investigation. Emergency
procedures to be detailed in contract safety plan.

Communications Emergency contacts to be posted as applicable. Warning signs and hazard


markers.

COSHH As appropriate to the operations.

PPE Hard hats and as appropriate to operations.

Other Note that the highest risks often exist at the time of erection and removal of
barriers and height restrictions.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 25
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 7


Assessment for: UNDERGROUND SERVICES
Significant risks: Electrocution, explosion, asphyxiation, serious injuries,
working in vicinity of underground services with mechanical
equipment, disruption to public/client services.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Emergency telephone numbers. Permits to work. Contact service provider
and private service owners for service plans, tracings, as available. Marking
and hand excavation as appropriate.
Instruction Working to Safety Method Statements. Operatives to sign Safety Method
Statements. Operators to be advised on hitting buried services, (tracing
services). Do not assume depth.
Training Use of detection equipment, confined spaces.

Supervision To be fully conversant with services in the work area.


Access Consider exclusion zones. Review on hourly/daily basis to suit service in
work area.

Environment Working adjacent to buildings. Overhead services. Traffic. Consider the


effects of water/flooding/weather on services and possible
emissions/discharges from services.

Equipment As applicable. Detection equipment. Possible shoring, Protection and


Support systems.

Emergencies Liaise with Civil Defence (Fire Department). Standard site first aid, fire
protection, evacuation, accident reporting and investigation. Major Incident
Response Plan. Emergency procedure to be detailed in contract safety
plan.

Communications Warning signs, hazard tape and markers.

COSHH As applicable for possible emissions/discharges, ground contamination.

PPE High visibility clothing, hard hats, protective footwear, ear muffs, goggles,
gloves etc.

Other Detailed review of available plans for identification of buried services. Note
also the following that may be in the area, Cable television, hydraulic,
process fluids, pneumatics, Railway signalling, petroleum fuel oils, private
communications, civil aviation, military authorities, also gas transmission
pipe lines (refer to owners requirements). Plastic pipes not detectable.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 26
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 8


Assessment for: PILING (DRIVEN/BORED/BENTONITE)
Significant risks: Crushing/laceration and entrapment injuries, drowning,
damage to plant and structures, plant and equipment
instability, reversing and slewing machinery, noise and dust.
Lifting reinforcing cages, piling gates, top men.
Contact with contaminated ground.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Obtaining information relating to services, ground conditions, adjacent
structures/foundations. Produce Safety Method Statement.
Employees are to be briefed on the Safety Method Statement and correct
Instruction use of equipment. Operatives to sign Safety Method Statement. Visitors
are to be escorted.
Personnel are to receive Safety Awareness Talks as appropriate.
Training Operators, banks men and piling hands are to be suitably trained and
certificated where appropriate.

Supervision Supervisors to ensure that plant and equipment is operated and banked
ONLY by persons who have been trained, certificated and authorised to do
so. Ensure that weekly registers and maintenance requirements are
performed.

Access Keep work area clear and tidy. Consider exclusion zones. Stabilise or
harden and maintain the piling mat/work area as appropriate for the work
proposed.

Environment Consider weather, adequate lighting, ground conditions, ground water,


nearness of buildings, traffic, noise, fumes, dust and vibration. Consider
disposal of arisings in particular those contaminated.

Equipment To be suitable for operations being carried out and test certificated
(including sub- contractors). Regular inspection, maintenance, cleaning
and reporting on condition. Check condition of plant and equipment upon
arrival on site. Weighted or anchored covers to Bentonite filled holes and
bored holes.
Emergencies Standard site first aid, fire protection, evacuation, accident reporting and
investigation. Major incident response plan.

Communications Warning signs, hazard lights and markers, audible warning units. Consider
the use of radio/transmitters.

COSHH As applicable to materials used.

PPE As appropriate together with high visibility clothing, ear defenders and head
protection, boots in particular for driven piling.

Other Refer to generic risk assessment lifting equipment and contaminated land.
Avoid inhalation of Bentonite powder. Seek specialist advice as necessary.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 27
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 9


Assessment for: EXCAVATIONS
(SHALLOW/DEEP/CONTAMINATED/BORROW PITS)
Significant risks: Water ingress/flooding. Collapse of adjacent structures.
Injury from falling equipment and materials. Entrapment,
Contact with overhead/underground service, personal
injury to oneself or others. Failure to check and ensure
safe use of equipment. Overturning of vehicles/plant etc.
Collapse of excavation sides.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Check for services in area , evaluate ground conditions and investigate possible
flooding. Obtain adequate propping material before commencement. Major
excavations must be the subject of design check. Check for buildings, scaffolds
and other operations around trench. Operatives to enter and leave excavation
by safe access only. Monitor for possible gas. Prevent access to public
(remember blind persons require firm barriers). Adequate lighting and signs.
Check for contaminated ground. Prevent unauthorised access to excavation.
Method statement for installation and removal of support system, also services
Instruction support systems. Operatives to sign Safety Method Statement. Permit to dig
system to be adopted in identified areas of service location i.e. urban areas,
factory premises etc.
Operatives to be trained in the use of support systems and gas monitors.
Training Machine drivers to be conversant with support systems, also banks man and
possible confined space training. Advice on any identified risk and control
measures.

Supervision Competent person must be in attendance at all times. Daily/shift checks on


trench/support system. Weekly inspection and register kept up to date. Watch
for deterioration of ground in wet conditions. Materials and plant not stored too
close to edges of excavations. Edge protection.

Access Safe access and egress in and around excavation to be provided. Use ladders,
ramps, cut in steps. Well lit at night. Handrails to top of batters. Stop blocks for
vehicles.
Environment Excavations area to be kept clear of unnecessary material or plant. Keep any
water levels to acceptable levels (ensure adequate sumps). Rain could affect
ground conditions. Monitor for gases and contaminated ground. Consider
disposal of pumped water.
Equipment Plant and equipment to be suitable for operation especially support system.
Adequate supply of support materials. Pumping equipment to be available if
water present.
Emergencies Standard first aiders. Rescue procedure in place. Possible major incident
response plan to be put in action. Emergency procedures to be established in
contract safety plan.
Communications Surrounding area for excavation to be adequately signed. Quick safe warning
system considered.
COSHH Monitor for gas, contaminated ground and general assessments of all materials
to be used. Identify any control methods such as the provision of mechanical
ventilation.
PPE Hard hats, suitable footwear, possible disposable overalls, gloves and high
visibility vests.
Other Machine operatives to have good vision of work in progress if possible. Cross
reference to confined space generic risk assessment for further information.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents and
must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 28
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 10


Assessment for: HAUL ROAD CROSSINGS ON CONSTRUCTION SITES
Significant risks: Impact injury due to collision of plant and machinery with
private vehicles or pedestrians.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Temporary Traffic Orders for speed restriction on approach to crossing
points. Method statements for installation of such schemes will also be
required on major schemes, to include all identified requirements of a safe
Instruction system of work.

Training Appropriate experienced personnel only to be used for actual


installation/removal of traffic management works.
Specific training for all drivers using crossing points and those who will
operate the crossing.
Supervision An experienced member of staff to be nominated as the Traffic Safety
Manager with special responsibility for plant crossings.

Access Crossing to be kept clean and free of debris. Lights and warning signs on
both haul road and main road to be cleaned regularly.

Environment Consideration must be given to poor visibility during adverse weather


conditions. Lights and signs soon become observed by dirt. Similarly
during extremely dry weather dust will be a problem.

Equipment All traffic management equipment to conform confirm to current standards


and to be regularly maintained/washed.

Emergencies Emergency call out/liaison list to be established. Standard site first aid, fire
protection, evacuation, accident reporting and investigation. Emergency
procedures to be detailed in contract safety plan.

Communications Radios for traffic management team. Mobile phone/radios for traffic safety
coordinator. Information signs. Close liaison with police.

COSHH If using portable generators, noise and handling of fuel.

PPE High visibility clothing, hard hats etc.

Other Provision of shelter and adequate welfare facilities especially for plant
crossing operatives well away from temporary offices.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 29
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 11


Assessment for: EARTHWORKS
Significant risks: Injuries from plant movements, unstable
excavations/embankments, tipping vehicles,
overhead/underground services, contaminated ground, dust.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Safety Method Statements. Detailed review of available plans for
identification of buried services. Detailed review of ground
conditions/boreholes before commencement. Desk study, advice from
Engineering Department. Operatives to be instructed on safe system of
Instruction work appropriate to the type of operation. Operatives to sign safety method
statements.
Training Induction and Safety Awareness Talks to include the care to be taken on
earthworks operations. Supervisors responsible for daily/weekly inspections
are to be suitably trained. Operators to be suitably trained and certified for
the equipment used and Banks man duties as required.
Supervision Work is to be controlled by an appropriately competent experienced
earthworks supervisor. Inspections before work shift commences. Site
register to be completed weekly. Temporary Works coordinator to be
appointed.

Access Designated routes, access points and exclusion zones. Consideration is to


be given to separation from, and control of, public and non-earthworks traffic
within the working area. Safe haul route.

Environment Evaluate ground conditions to establish nature, groundwater, nearness of


buildings or traffic. Weather and flooding should be considered when
planning operations. Consider the stability of stockpiles and batters; and
the control of noise, dust and fume. Consider any details of contamination.

Equipment Plant inspection and periodic testing, buried service detectors, guard rails,
barriers, warning signs, adequate lighting. Air monitoring equipment where
appropriate. Wheel wash facilities. Reversing alarms.

Emergencies Standard site first aid, fire protection, evacuation, accident reporting and
investigation. Major incident response plan.

Communications Warning signs, hazard tape, markers, hazards lights and audible warning
units. Consider use of radio/transmitters. Use traffic signs.

COSHH Not applicable, except on contaminated ground where a COSHH evaluation


of ground contaminants will be required to determine protection required.

PPE Hard hats, protective footwear, protective clothing in adverse weather


conditions, high visibility clothing etc.

Other Consider use of speed limits and mobile welfare facilities.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 30
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 12


Assessment for: REDUCED LEVEL DIG AND IMPORTED FILL
Significant risks: Contact with plant, reversing vehicles, overhead and
underground services, dust, noise, contaminated land.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Equipment to be certificated, inspected and records kept. Underground
services drawings. Safety signs, warning notices.

Instruction Competent, certificated and authorised plant operators. Banks men


Training required for reversing vehicles/plant movement. All operatives to sign
method statement as understood.

Supervision Supervisors to ensure plant and equipment only operated by certificated,


authorised persons.

Access Segregate plant from pedestrians.

Environment Dust suppression methods. Ground conditions. Daily log of dust emissions.
Protection of features/foundations/safe batters/support/proper compaction.
Equipment Good working order, regularly maintained. Overhead power lines to be
suitably protected by high/low level barriers. Segregate from pedestrians.

Emergencies All plant to be fitted with fire extinguishers.

Communications Warning signs, barriers and audible warning units.

COSHH Dependent upon soil analysis/as applicable during breakdown/regular


maintenance to plant and equipment.

PPE Banks men to wear high visibility clothing, safety footwear/safety helmets to
be worn at all times. Hearing protection to be worn as applicable.

Other Stop blocks required for reversing plant where applicable.


Ref contaminated land risk assessment No 9 if appropriate.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 31
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 13


Assessment for: CONTAMINATED GROUND
Significant risks: Contact with toxic, irritant corrosive harmful and radioactive
materials. Injury through skin absorption, skin
puncture, ingestion, inhalation or radiation. Toxic/explosive
fumes or materials.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Seek all information available and where this is inadequate obtain the
appropriate chemical analysis before commencement/recommencement of
the work. Produce detailed hazard risk assessments and Safety Method
Statements. Operatives to sign Safety Method Statement. Personnel are to
Instruction be made aware of the type of contamination and possible dangers.
Operatives are to be given safety awareness talks. Operatives to be made
aware of procedure if coming into contact with unexpected material/smells.
Demonstrations and briefings are to be given to personnel on the method of
Training handling contaminated material, the effects and remedies, the correct use of
protective clothing and personal hygiene. This should be updated as
necessary.

Supervision A competent person is to obtain the appropriate information on the


contaminated material and ensure that operatives are given and adhere to
the training information above. Designate a waste controller as appropriate.
Regularly monitor the material exposed and ensure adequate testing.

Access Exclusion zones and designated safe access as necessary related to the
type and level of contaminant exposed.

Environment Evaluate the effects of weather, heat, dust, vibration, corrosion, polluted
atmosphere/water, ground conditions (stability).

Equipment To be individually assessed to suit the operation. Consider gas monitors,


breathing apparatus, chemical indicator tubes, wheel washers,
decontamination units.

Emergencies Together with standard procedure for first aid, fire protection, evacuation
and reporting; specific procedures are to be considered to suit the operation
and contaminants present. Procedures for environmental emergencies i.e.
spill, groundwater contamination etc.

Communications Warning signs, hazard markings and exclusion zones as appropriate.

COSHH As appropriate. Specialist advice to be sought where necessary.

PPE Consider suitable, masks, goggles, gloves, boots, barrier creams, and suits
etc. Also consider whether these should be disposable/regularly renewed.

Other Good welfare, washing and hosing down facilities. Seek advice from Safety
& Environmental Department where necessary.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 32
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 13 B


Assessment for: POTENTIALLY CONTAMINATED GROUND/BUILDING FABRIC

Significant risks: Infection through skin absorption, skin puncture, ingestion or inhalation

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Seek all information available about the site including site investigation reports,
trial pit records, maps and plans. Produce Safety Method Statements.
Operatives to sign Safety Method Statements.
Personnel are to be made aware of the type of contamination and possible
dangers. Operatives are to be given safety awareness talk.
Instruction Operatives to be made aware of procedure if coming into contact with
unexpected material. Demonstrations and briefings are to be given to personnel
Training on the method of handling contaminated material, the effects and remedies, the
correct use of protective clothing and personal hygiene. This should be updated
as necessary. Give operatives information on the level of residual risk.
Supervision A designated, competent person is to obtain the appropriate information on the
potentially contaminated material and ensure that operatives are given and
adhere to the training information above. Designate a waste controller as
appropriate. Regularly monitor the material exposed and ensure adequate
identification/testing.
Effective procedures for health surveillance to enable early diagnosis of
infection.
Access Exclusion zones and designated safe access as necessary related to the type
and level of contaminant exposed.
Environment Evaluate the effect of weather, wind strength and direction, heat, dust, polluted
water. Measures to prevent exposure of the general public to wind borne
contamination.
Equipment To be individually assessed to suit the operation. Consider breathing
apparatus, wheel washers, and decontamination units.
Emergencies Together with standard procedure for first aid, fire protection, evacuation and
reporting, specific procedures are to be considered to suit the operation and
contaminants present. Procedures for environmental emergencies, ie spills,
groundwater contamination, etc.
Prior contact shall be established with a local general practitioner.
Communications Warning signs, hazard markings and exclusion zones as appropriate.
COSHH As appropriate. Specialist advice to be sought where necessary.
PPE Check for and protect skin cuts or scratches before using PPE.
Consider suitable masks, goggles, gloves, boots, barrier creams and suits, etc.
Also consider whether these should be disposable/regularly renewed
Facilities for decontamination or disposal of clothing.
Other Adopt procedures for decontamination by heat treatment or chemical
disinfecting of any animal remains encountered during the work.
Consider immunisation
Good welfare, washing and hosing down facilities. Seek advice from Safety &
Environmental Department where necessary.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents and
must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 33
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 14

Assessment for: ENVIRONMENTAL ISSUES


Significant risks: Demonstrations/sabotage, pollution, damage/destruction of
flora, fauna, ancient monuments or protected areas etc.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Obtain details of all information and restrictions relevant to the operational
area from the Enforcing Authority, the client/employer.

Instruction Induct personnel appropriately in relation to the information obtained above


and any effects on methods of working.
Training Safety awareness talks environmental awareness are to be given where
applicable. Consideration should be given as to whether further specialist
training is necessary for certain operations or localities

Supervision The site manager where appropriate will make personnel aware of
information/restrictions and institute suitable controls.

Access Consideration to be given to restricted zones, security measures and


damage caused by equipment/plant movements.

Environment Consideration to be given to the effects of weather, noise, dust


contamination and construction methods upon the local
environment/population/watercourses.

Equipment Fencing, covers, bunds (soil), noise and atmosphere monitors and security
equipment as applicable.

Emergencies Standard site first aid, fire protection, evacuation, accident reporting and
investigation. Establish environmental emergency response if applicable.

Communications Warning signs, contact Health and Safety Department, emergency


telephone list.

COSHH As appropriate.

PPE As appropriate.

Other Record photographs, incident/insurance reports. Diesel/oil/flocculants/silt


laden water are potentially major environmental problems. Please refer to
Safety Department for further guidance.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 34
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 15

Assessment for: WORKING ON PUBLIC QATAR ROADS


Significant risks: Injury from passing/reversing vehicles, debris, services,
Subsidence. Dangers to public from construction operations.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Safety Method Statements Permits to work on highways. Notify and liaise
with the appropriate authorities. Traffic management assessment,
requirements for emergency routes for vehicle access i.e. ambulance, Civil
Defence (Fire Department), Police etc. Wearing of high visibility clothing.
Instruction Form of traffic control. Access and egress routes. Crossing points,
pedestrian routes, specific risks involved requirements of speed limits.
Training Inductions on traffic management and working on public highways.

Supervision To be suitably qualified. Monitor work to Safety Method Statements. Action


any non-conformities.

Access Maintain public and property access where possible or make alternative
arrangements. Establish suitably signed works access. Adequate signing
of access and egress points.

Environment Evaluate: noise, dust, fumes, identification of sensitive locations such as


schools, hospitals, surgeries, shops, public services when planning works.
Consider the hazards to blind persons.

Equipment Plant/equipment flashing lights (if appropriate).

Emergencies Standard first aid, fire protection, evacuation, accident reporting and
investigation. Liaise with all emergency services, and highways
departments dates, times etc., work being carried out. Major incident
response plan. Emergency procedures to be detailed in contract safety
plan.

Communications Warning and information signs. Hazard markers. Traffic control


requirements. Liaise with local residents.

COSHH As required may include use of various materials such as black top or
assessment for dust and fumes generated by traffic.

PPE High visibility clothing. Hard hats, protective footwear, ear muffs, goggles,
gloves, wet weather clothing.

Other Monitor approved Traffic Diversions Plans on a regular basis and review if
needed.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration Qatar Work Zone Traffic Management
Guide, all relevant Company Safety Documents and must be used when compiling a site specific
method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 35
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 16


Assessment for: WORKING OVER OR ADJACENT TO WATER SOURCES
Significant risks: Drowning. Shock. (Fatigue with clothing on
in water). Possible Weils disease.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Operatives advised on risk of falling/slipping into water while working in and
around docks, swimming pools, tanks and water retaining structures/pits.
Operatives advised of risk of falling/slipping into water. Safety Awareness
Instruction Talks. Safe methods of working. Access and egress routes. Rescue
procedures. Tide tables, weather.

Inductions, Safety Awareness Talks, use of life jacket, harness, lifebuoys,


Training throwing lines, warning systems. Communications. Rescue procedures.
First aiders. Rescue boats. Hygiene Weils disease.

Supervision Competent supervisor to monitor and check safety and rescue equipment
and working method.

Access Scaffold if possible over water. Handrails beside water, or fencing. Safe
access and egress route to and from work areas.

Environment Good lighting. Weather, tides and ground conditions.

Equipment Safety boat. Life jackets, lifebuoys, safety nets, throw lines, radios,
harnesses, scaffolds, pontoons, rescue lines, audible alarms etc.

Emergencies Trained first aiders. Rescue procedures in place. Audible alarms.


Standard site first aid/reporting procedures.

Communications Good communications, i.e. radios, telephones or hand signals. Post list of
emergency contact numbers. Warning signs.

COSHH Considerations to be given if water is contaminated - weils disease.

PPE Life jackets, safety harnesses. Loose, warm, high visibility clothing.
Suitable warm footwear. Hard hats, etc.

Other Good welfare facilities. Adjacent water traffic movement to be considered.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 36
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 17


Assessment for: WORKING OVER OR ADJACENT TO RAILWAYS RISK CATEGORY
Significant risks: Electrocution/Collision of plant and operatives with trains. BEFORE CONTROLS
Possible collapse or subsidence of railway equipment. H M L
Derailment.

Tick as appropriate

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Obtain from the relevant railway authority all information relative to the
operation, such as structural gauge and fencing. All safety method
Instruction statements to be agreed with railway before commencement of work.
Possessions, if required, to be agreed with railway authority.
Training

Supervision Ensure all rail procedures and Safety Method Statements are adhered to.

Access Use only identified walking routes and work areas as agreed in Safety
Method Statements. Possessions to be agreed with railways. Establish
exclusion zones as necessary.

Environment Consider the effect of dust, weather and construction operations upon the
railway. Good lighting required.

Equipment Check requirement for structural barriers. Consider the limitation of


construction plant adjacent to railway operations. Comply with railway
authority requirements for non-conductive equipment such as
wheelbarrows, ladders, approved CAT scanner, etc.

Emergencies Standard site first aid (with particular reference to electric shock), fire
protection, evacuation, accident reporting and investigation. Major incident
response plan.

Communications Site wardens and lookouts to be used as required. Warning signs and
hazard markers as required by railway authority. Consider use of approved
radio/transmitters. Rail emergency telephone number to be prominently
posted.
COSHH As applicable to the operations.

PPE Approved high visibility vests. Hard hats (white), suitable footwear (No
Rigger Boots) Harnesses if working at height.
Other Only personnel with good hearing and eyesight are to work on or adjacent
to railways

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 37
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 18


Assessment for: REINFORCEMENT
Significant risks: Collapse of reinforcement. Poor housekeeping, falls when
accessing structures. Access across reinforcement

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Relevant drawings and reinforcement/structural engineers
recommendations N.B. temporary requirements relating to stability
especially in wind.

Instruction/Training Ensure all personnel are subject of induction and are briefed in method
statement/risk assessment content.

Supervision Competent supervision to be in attendance for duration of operation.


Ensure method statement content is applied at workface.

Access Ensure board walkways 600mm wide are provided across slab reinforcing.
Ensure guarded and boarded platforms are provided for fixing reinforcement
at height: prohibit the use of ladders. Provide scaffold stair towers. Prohibit
the climbing of reinforcement. Expedite the installation of permanent
staircases. Provide protection to exposed starter bars.

Environment Caution required on damp plywood decks or following application of release


agents. Limit and control mechanical and manual handling of shutters in
high wind.

Equipment Cut off wheel operations to be certificated.

Emergencies See site general emergency procedure.

Communications Works to be closely coordinated with erection of false work and form work.
Formal paperwork system to be applied for control of loading and striking
formwork.

COSHH Low risk for handling steel, tying wire and spacers.
Assessment as appropriate for any other substances.

PPE Safety helmet, boots, eye protection and rigger gloves. Full body harness
only when attachment location identified and agreed in method statement.
Eye protection recommended when using tying wire.

Other Agree methods of attachment of slings when mechanically lifting fabricated


cages.
See Risk Assessment No19 for concrete works.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 38
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 19


Assessment for: CONCRETING, CONCRETE REPAIR, CONCRETE FINISHING.
Significant risks: Plant and equipment, noise/vibration, concrete burns, dermatitis,
working at heights, protruding reinforcement, manual handling,
failure of materials/equipment.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Method statements. Safety signs. Warning notices.

Instruction/Training Operatives to sign method statements. Operator certificated and


competent to use items of plant/equipment. Manual handling/vibration
training.
Supervision Constantly monitoring concreting operations, particularly situations where
point loading/collapse could occur. Rotate workers on vibratory tools where
feasible.

Access Consideration of mechanical access equipment. Provision of safe means


of access/egress suitably secured. Segregate pedestrians from plant and
equipment. Edge/hole protection.

Environment Consider noise produced from plant and equipment particularly for out-of-
hours working on curing concrete. Dust suppression methods. Adequate
lighting. Dust from mixing dry concrete locate mixers externally. Protect
vertical ends of protecting starter bars.

Equipment Good working, least vibration order, regularly maintained and records kept.
Operators to be certificated / competent.

Emergencies Suitable First Aid facilities to be available, particularly eye-bath stations to


be situated nearby. Operatives aware of emergency procedure and
location of assembly points. Establish systems of work/emergency contact
numbers for out of hours working.

Communications Provision of suitable safety signs warning and barriers.

COSHH Assessments/information and instructions to be given to operatives on


materials. Personal hygiene essential when dealing with concrete/content.

PPE Suitable protective footwear, including wellington boots where necessary.


Hand, head and eye protection. Hearing protection where necessary.

Other Safe system of work for dismantling/stripping formwork to prevent falls onto
persons to be included in method statement.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 39
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 20


Assessment for: PRE-CAST CONCRETE, STAIRS, WALLS AND FLOORS
Significant risks: Falls from height, crushing, collapse, handling, access,
lifting appliances, heavy plant.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Operatives to be given appropriate information to ensure full knowledge of
possible hazards associated with the fixing of pre-cast concrete units.
Details of designed safe Method Statements to include specific risks.
Instruction/Training Where applicable, operatives to be inducted on the construction methods.
Operatives to be trained by competent person in use of plant and
equipment.

Supervision The installation and fixing of pre-cast units to be controlled by experienced


supervisor.

Access Designated safe access/egress to be provided to all work areas. Control of


access of pedestrians and plant to be in place to prevent unauthorised work
under pre-cast flooring/wall installation.

Environment Monitor for noise. Consider the effect of wind loadings on hoisted sections,
and ground conditions to be checked for cranage equipment.

Equipment All cranage/lifting gear/mobile and static scaffolds to be properly maintained


and inspected.

Emergencies Emergency procedures to be drawn up for the recovery of persons working


at height, to include contact numbers and location of first-aider. Standard
first aid equipment and accident reporting.

Communications Radios to be used if possible. Systems to be in place for tandem lifting on


heavy/large pre-cast sections. Signs and hazard markers.

COSHH N/A

PPE Hard hats, boots, high-visibility vests and harnesses.

Other Transportation of long/wide loads to be planned with Police if applicable.


Unique Method/Risk Assessments to be drawn up for individual erection
processes with sub-contractor.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 40
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 21


Assessment for: SCAFFOLD (ALL TYPES)
Significant risks: Injury from falling equipment and materials. Danger of
collapse in exposed places, falling from height.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Usage of scaffolding and adequate materials/fittings. Equipment to be
used. Safety Method Statements. Evaluate ground and loading conditions.
Assess the need for any design requirements. Operatives to be provided
safe access and egress. Prevent unauthorised access. Prevent access to
any incomplete areas. Tie-ins. Drawings of system being erected.
Number/width of platforms.
Instruction Provision of handover certificates on completion.
Training Inductions. Safety Awareness Talks Working at Heights. Interpretation
of scaffold design drawings. No scaffold to be erected modified or
dismantled, except under the supervision of a competent person.

Supervision All scaffold erection must be under the supervision of a competent person.
Thoroughly examine before first use, after substantial alteration after bad
weather, or every 7 days. Receive scaffold handover certificate as
appropriate. Keep platforms and area base clear.

Access Keep access area to scaffold clean and tidy. Notice warning of dangers.
Identify incomplete scaffold. Adequate widths of access platforms.
Further consideration required if access by hoist, etc.

Environment Evaluate ground conditions. Proximity to water/buildings or traffic.


Overhead services. Consider the general public. Consider weather
conditions such as wind loadings on sheeted scaffolds.

Equipment To suit requirements.

Emergencies Standard first aid. Accident reporting and investigation. Contract safety
plan emergency procedures.

Communications Inform others working in area of proposed scaffolding to be erected.


Supply information to other employees who may be using the scaffold.
Warning signs and hazard tape and markers (lighting/traffic protection in
urban areas).
COSHH N/A
PPE Hard hats, protective footwear, harnesses, gloves.

Other Review scheme if modification takes place. Ensure that a scaffold


handover certificate is issued where appropriate. Secure scaffold against
unauthorised access. Carry out manual handling assessment of the work.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 41
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 22


Assessment for: STRUCTURES (WORKING AT HEIGHTS)
Significant risks: Injuries from falls, falling materials and equipment,
reinforcement instability, structural failure, harmful substances,
pressure bursts, power tools, entrapment, plant instability,
splinters, dust, fragments, excessive noise, vibration,
fumes, confined spaces.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Operatives are to be given the appropriate information to ensure that they
are conversant with the hazards of operations and equipment associated
with false work, reinforcement, concrete placement, scabbling / grit-blasting,
working at heights, roof work as applicable to the type of structure. Details
of design risk assessment to be incorporated into Safety Method Statement.
Hierarchy of secure platform/workplace safety nets safety harnesses to
be determining fall protection measures.
Instruction Where applicable, operatives are to be inducted on the construction
methods, and given potential hazard details. Operatives to sign Safety
Training Method Statements. Operators to be trained by competent person in use of
plant and equipment.

Supervision Work is to be controlled by a competent experienced supervisor and


temporary works coordinator as required. Appropriate registers to be
completed.

Access Designated safe access is to be provided to all areas of work.

Environment Monitor for noise, vibration, dust atmosphere. Evaluate access, wind
loading, weather, ground conditions, watercourses, nearness of buildings,
traffic or services, stacking of materials at ground level and above.

Equipment Access equipment/platforms, guard rails, adequate lighting, false work /


scaffold design and inspection, lifting equipment.

Emergencies Standard site first aid, fire protection, evacuation, accident reporting and
investigation. Major incident response plan. Emergency procedures to be
detailed in contract safety plan for recovery of persons injured at heights.

Communications Emergency contact names, organisations, telephone numbers. Warning


signs.

COSHH All materials to be assessed for COSHH.

PPE Hard hats, protective footwear, protective clothing, goggles, high-visibility


clothing, masks, harnesses, etc., as appropriate.

Other Management individual to be appointed to have responsibility for co-


ordination of design and procurement of false work and access scaffold, etc.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 42
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 23


Assessment for: STEEL ERECTION (GENERAL)
Significant risks: Lifting, Work at Heights. Injuries from falls/falling objects

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Detailed Safety Method Statements particularly in respect of lay down
facilities sequence, access, temporary stability and safety are required.
Location of anchor points.

Instruction Site Induction, safety awareness, unique Safety Method Statement briefing.
Operatives to sign Safety Method Statements.

Competent steel erectors only should be used familiar, as a minimum,


Training with rigging, erection methods, lifting equipment, tools and plant, erection of
accesses (mobile and static). Individual training for unique types of plant
such as mobile lift platforms. Certification of Banks men.

Supervision Competent supervisors with knowledge of lifting duties, planning, safety


equipment as well as general operative training above. Operative training
certification verified and registered.

Access Generally via fixed scaffold system, cradles, mobile platforms or harnesses
etc. Fixed access to be properly erected and inspected. Mobile plant to be
certificated. Consider exclusion zones.

Environment Ground conditions to be checked for cranage/mobile access equipment.


Services to be marked etc. Monitor weather conditions.

Equipment All cranage/lifting gear/mobile and static platforms, to be properly


maintained and inspected.

Emergencies Emergency procedures to be drawn up for recovery of persons injured at


height including contact numbers and location of first aider. Standard site
first aid, fire protection, evacuation, accident reporting and investigation.

Communications Radios to be used if possible. Signs and hazard markers.

COSHH N/A

PPE High visibility vests, harnesses, helmets and boots.

Other Unique assessments should be drawn up for individual erection processes


with sub-contractor.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 43
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 24


Assessment for: WELDING, BURNING, STEEL WORK
Significant risks: Fires, explosion, respiratory disease/eye damage. Various
occupational health risks.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Use Hot Work Permit System. Welding procedures, details of gases to be
used and storage details is included.

Instruction Site induction, explanation of unique Safety Method Statement.

Training Welding and burning should only be performed by suitably


trained/certificated individuals who can show proof of such training
appropriate to the operation.
Supervision Generally by a suitably experienced supervisor who does not have to be a
certificated welder but must be experienced in welding safety, working at
heights etc.

Access As general steel erection, however, due allowance must be made for safe
positioning of equipment, screens, hoses and welding leads.

Environment Storage of bottles must be controlled with oxygen at least 3 meters from
LPG/ACETYLENE, in open air, upright, out of sunlight. Firefighting
equipment must be present. Flash guards whilst welding.

Equipment To be regularly maintained with daily checks on hoses, regulators, leads,


flashback arrestors leak tests, etc. Only proprietary fittings to be used.
Secure bottle storage as above. Handling to be via trolleys etc.

Emergencies Standard site first aid, fire protection, evacuation, accident reporting and
investigation. Additional firefighting facilities locally.

Communications N/A

COSHH Materials to be welded / cut should be identified and full COSHH


assessment performed. Give particular attention to coatings on materials to
be welded / cut. Iron oxide (vapour), carbon monoxide and nitrous fumes
may be created, natural ventilation generally OK, but induced ventilation
may be required in confined spaces.

PPE Specialist welding visors, goggles, helmets, masks, gauntlets and overalls
to protect bare skin.
Other Assess the need for fire watchmen, screen the public from welding.
Unburnt gas builds up in voids behind work piece from preheating
operations.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 44
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 25


Assessment for: ROOF WORK/WORK NEAR FLOOR ETC OPENINGS
Significant risks: Falls from height. Falls of materials/tools etc.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Loading sequence/Lifting arrangements. Operatives advised of contents of
risk assessment/Safety Method Statements. Operatives to sign Safety
Method Statements.

Instruction/Training Instruction on fall arrest equipment, edge protection, wearing of harness,


fragile materials, equipment/material control.

Supervision Competent supervisor to be present for all associated works. Supervision to


implement Safety Method Statement requirements.

Access Guard rails/toe boards/material guards provided and used. Adequate ladder
access etc.

Environment Weather implications i.e. winds, sand factors etc.

Equipment Adequate access. Where used safety netting properly secured. Anchorage
points for clip-on facilities for full arrest equipment.

Emergencies First aid, evacuation, recovery arrangements for possible injured person and
fire control.

Communications Warning notices and where appropriate segregation at ground level to


protect pedestrians.

COSHH As appropriate to roof work type e.g. Hot Bitumen etc.

PPE Inertia reels for fall arrest. Full body harnesses, safety helmet, boots, warm
clothing etc.

Other Material movement onto roof and loading sequence be controlled. Consider
point loading.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 45
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 26


Assessment for: INFILLING OF FLOOR OPENING(S)
Significant risks: Falls of person, falls of materials, collapse of support work
(temporary or permanent). Health risk from contact with
materials. Muscular skeletal injuries.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information All persons involved in the work will receive information regarding the
hazards associated with the operation and the precautions to be taken.

Instruction/Training The supplier of bolts and fixings should be requested to instruct installers on
the correct procedures to be used for the fixings specified.

Supervision All work involving the support at floor infills shall be under the control of a
competent person experienced in the methods used.

Access Proper access must be provided for installation of support system. Barriers
must be provided to the edges of the opening prior to the infilling operations.
Where appropriate fall protection to be provided.

Environment All support work whether temporary or permanent must be subject to a


methodical system of checking to include, connections, fixings, access etc
and compliance with design drawings and specification prior to loading.
Permit system to be introduced prior to loading system with concrete.

Equipment All equipment must be checked for good condition and suitability prior to
being used.

Emergencies Arrangement to be put in place for recovering persons injured etc whilst
carrying out work on high level areas.

Communications All relevant information including Safety Method Statements and Risk
Assessments, Manufacturers Instructions and design drawings should be
communicated to all persons involved.

COSHH Assessments should be made for materials classified under COSHH which
should be communicated to all persons.

PPE May include, eye protection, clothing, footwear, safety helmet and hearing
protection.

Other Safety Method Statements must be produced for all elements of the works
including preparation of existing structure, installation and inspection of
support system and access systems. Installation of Formwork and pre-
loading checks.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 46
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 27


Assessment for: ROOF WORK (FLAT)
Significant risks: Falls from height, falls of materials, fragile materials,
unsecured materials, manual handling.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Sequence of work. Location of materials, raising of materials to roof level.
Means of providing fall protection. To elevations leading edge and
openings. Handling of large sheets.

Instruction/Training Operatives and supervisors must be trained and competent. Must be


inducted and briefed in method statement content.

Supervision Competent supervisor to be in attendance for duration of operation. Ensure


method statement is formally discussed with all roofing operatives.
Supervision to review roof operations daily.

Access Provide ladder or access tower or identify other means of access.

Environment Confirm maximum safe working wind speed for type of roofing. Be aware of
increased risk in dusty conditions.

Equipment NB the options for protection are (in order of preference):-


1 safety nets;
2 Lead guard type leading edge protection trolley systems;
3 Safety harnesses/running lines/ fall arrestors.
Adequate access. Where used safety netting properly secured by
certificated erectors. Anchorage points / clip-on facilities for full arrest
equipment. Anemometer.

Emergencies Agree emergency procedure for recovery and treatment of person injured at
a height. Ensure adequate firefighting and first aid provision available.

Communications Warning notices and where appropriate segregation or protection at ground


level to protect pedestrians.

COSHH Assessments as appropriate for materials to be used.

PPE Full body harnesses, safety helmets, boots, warm clothing. Gloves, eye
protection

Other Confirm controls for hot works and storage of flammables at height.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 47
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 28


Assessment for: ROOF STRUCTURE (including wall plates/trusses/timber)
Significant risks: Falls, falling objects, manual handling, fire.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Agree safety method statement. Store materials in a safe manner. Provide
suitable working platform. Precautions to be taken to prevent operatives
falling whilst installing trusses e.g. safety nets or boarding. Visually check
electrical tools and leads. Obtain COSHH assessments. Ensure circular
saws are in good working order with guard and dust extraction bag in place.
Instruction Carry out manual handling assessment, use lifting appliances to lift trusses
into position. Complete crane checklist. Inspect lifting gear before use.
Keep work area free from tripping hazards. Store waste material in the
proper bins.
Training Operatives to receive risk, manual handling and COSHH assessment.
Carry out induction, all relevant assessments to be given as Tool Box Talks.
If using Mobile Elevated Work Platforms adequate training must be given.
Slingers to be properly trained.

Supervision Competent person to inspect working platforms and work areas before work
starts. Inspection of working platforms to be entered in Site Register.
Crane controller to complete crane checklist.
Access Provide suitable ladders, properly secured. Keep access free of materials
and electrical leads.

Environment Weather implications i.e. winds and dusty conditions.

Equipment All electrical equipment to be inspected on a regular basis by a competent


electrician, these should be tagged with details of last inspection. Carry out
manufacturers instructions for maintaining Mobile Elevated Work Platforms.
Safety nets to be properly secured. Crane and lifting gear certificates to be
kept in site register.
Emergencies Provide first aider. Provide fire extinguishers. Operatives to be informed of
all emergency procedures at induction.
Communications PPE, Danger Men Working Overhead, Scaff tag or similar to be displayed.
COSHH Assessment for all materials to be obtained.

PPE Hard hats, safety footwear, gloves, eye protection, dust mask and ear
protection. If using mobile elevated work platforms fall body harnesses
must be worn.

Other Do not overload scaffold platforms, provide suitable roof truss rack.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 48
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 29


Assessment for: ROOF COVERINGS (felt/batten/slate/tile/cladding)
Significant risks: Falls, falling objects, manual handling

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Agree Safety Method Statement. Store materials in a safe manner. Provide
suitable working platform. Precautions to be taken to prevent operatives
falling i.e. safety nets. Visually check electrical tools and leads. Abrasive
wheels to be kept in good order and guards in place. Obtain COSHH
Instruction assessments. Carry out manual handling assessment, use lifting
appliances to lift materials into position. Complete crane checklist. Inspect
lifting gear before use. Keep work area free from tripping hazards. Store
waste material in the proper bins.
Training Operatives to receive risk, manual handling and COSHH assessment.
Carry out induction, all relevant assessments to be given as tool box talks,
abrasive wheel operator to be trained in its use and how to change the
abrasive wheels safely.

Supervision Competent person to inspect working platforms and areas before work
starts. Inspection of working platforms to be entered in Site Register.
Crane controller to complete crane checklist.

Access Provide suitable pitched roof/ridge ladders, properly secured. Keep access
areas free of materials and electrical leads. Access on tile batten to be
agreed with roofers. Prohibit walking on tiled areas.
Environment Weather implications i.e. winds and dust etc.

Equipment All electrical equipment to be inspected on a regular basis by a competent


electrician, these should be tagged with details of last inspection. Safety
nets to be properly secured. Crane and lifting gear certificates to be kept in
site register.

Emergencies Provide First Aider. Operatives to be informed of all emergency procedures


at induction.

Communications PPE, Danger Men Working Overhead, Inspection report or similar to be


displayed.

COSHH Assessment for all materials to be obtained. Dust generation from cutting
tiles with powered abrasive cutters.

PPE Hard hats, safety footwear, gloves, eye protection, dust mask and ear
protection.

Other Do not overload scaffold platforms, only load out on loading bay. Consider
material movement onto roof and load points.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 49
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 30


Assessment for: EXTERNAL CLADDING
Significant risks: Falls of persons, handling panels at high levels, falling
materials, broken glass or unprotected edges of panels.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Instruction for supervisors and operatives in the safe storage and working
procedures.
Instruction Induction training should cover site rules and action to be taken in the event of
an emergency.
Training Operatives should be certificated for the erection of mobile scaffolds
Where appropriate training must be provided in the operation of Mobile Elevated
Work Platforms (MEWPs). Operatives must be trained in working at heights.
Operatives to be instructed to work to Safety Method Statements, operatives to
sign Safety Method Statements.

Supervision Works are to be controlled by an appropriately competent and experienced


supervisor. Supervisors to ensure that equipment and plant is operated and
erected ONLY by persons who have been trained, certificated and authorised to
do so. Supervisors to ensure that Safety Method Statements are being worked
to and those materials are being properly handled and stored.
Access Safe means of access/egress must be provided and maintained. If working at
height, an assessment should be carried out and suitable control measures
employed. Ladders should be tied or footed; mobile scaffolds and access
platforms must be properly erected with guardrails fitted and inspection details
recorded. Where MEWPs are used, operatives must wear and use safety
harnesses when working at height, operatives must not leave the confines of the
MEWP whilst at height. Exclusion zone must be established at work location.

Environment Works must be restricted in windy conditions. Consideration must be given to


working in the vicinity of overhead services.

Equipment Equipment must be kept in good working order and be regularly maintained with
records being kept. Any mobile towers, scaffolding etc. should be checked at
least every seven days with a record of inspection being kept. MEWPs must
not be used as a lifting device to transport men or materials e.g. used as a hoist.

Emergencies At least one person in any glazing team should have been trained in first aid.
Each glazing team should have appropriate first aid equipment available to
them.
Communications Warning signs, notices and barriers used as appropriate.
COSHH Assessments must be produced for hazardous materials e.g. sealants and
training provided.
PPE Safety harnesses, goggles, gloves, safety footwear, helmets must be worn.
Other Consideration must be given to adequate segregation of the works with other
contractors employees and members of the public. See also Risk Assessment
no. 32 - use of lifting appliances/gear to lift/move/store stillages and panels
where appropriate.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents and
must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 50
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 31


Assessment for: WATER STORAGE DEVICES

Significant risks: Falls from heights, falling materials, eye injuries during
drilling operations. Inhalation, skin absorption or ingestion
of harmful substances.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Instruction for supervisors and operatives in the safe storage and working
Instruction procedures.
Induction training should cover site rules and action to be taken in the event
of an emergency.
Operatives should be certificated for the erection of mobile scaffolds.
Training Where appropriate training must be provided in the operation of Mobile
Elevated Work Platforms (MEWP). Operatives must be trained in working
at heights. Operatives to be instructed to work to Safety Method
Statements, operatives to sign Safety Method Statements.

Supervision Works are to be controlled by an appropriately competent and experienced


supervisor. Supervisors to ensure that equipment and plant is operated and
erected only by persons who have been trained, certificated and authorised
to do so. Supervisors to ensure that Safety Method Statements are being
worked to and that material are being properly handled and stored.
Access Safe means of access/egress must be provided and maintained. If working
at height, an assessment should be carried out and suitable control
measures employed. Ladders should be tied or footed, mobile scaffolds
and access platforms must be properly erected with guardrails, mid rails,
and toe boards fitted. Where MEWPs are used, operatives must wear and
use safety harnesses when working at height, operatives must not leave the
confines of the MEWP whilst at height. Exclusion zone must be established
at work location.

Environment Works must be restricted in windy conditions. Consideration must be given


to working in the vicinity of overhead services.
Equipment Equipment must be kept in good working order and be regularly maintained
with records being kept. Any mobile towers, scaffolding etc. should be
checked at least every seven days with a record of inspection being kept.
MEWPs must not be used as a lifting device to transport men or materials
e.g. used as a hoist.

Emergencies Provide First Aider. Operatives to be informed of all emergency procedures


and first aid provision at induction.
Communications Warning signs, notices and barriers used as appropriate i.e. "Danger Men
Working Overhead".
COSHH Assessments must be produced for hazardous materials e.g. sealants and
training provided.
PPE Safety harnesses, goggles, gloves, safety footwear, helmets must be worn.
Other Consideration must be given to adequate segregation of the works with
other contractors employees and members of the public.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 51
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 32


Assessment for: LIFTING OPERATIONS
Significant risks: Injury from falling equipment and materials. Entrapment,
personal injury to oneself or others. Failure to check and
ensure safe use of equipment. Overturning of crane/excavators
used as cranes.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Operatives to be advised of risks from lifting by manual or mechanical
means. Proximity of any overhead services. Safety Method Statement
required. Advice to be given on any specific control measures including
safe systems of work and Safety Method Statements. Colour coding of
Instruction lifting equipment. Operatives to sign Safety Method Statements. Moving
unusual objects. Using correct equipment. Check all crane and lifting test
certificates are in date. Check equipment supplied. Visual inspection of
equipment prior to any lifting operations. Identify if a dedicated method
Training statement is needed, i.e. over 10 ton. Induction mechanical and manual
lifting, banks man training certificated. The use of competent/certificated
drivers. Specifics of individual tasks.
Supervision Appoint a lifting supervisor. Nominate crane coordinator to assess local
conditions and lift requirements. Determine weight, centre of gravity, sharp
edges, condition of load. Visual inspection of equipment being used.
Reporting. Monitor drivers performance.
Access Plan route and assess any hazards. Keep work area clear. Ground
conditions. Exclusion zones where appropriate. Level area for lifting.
Environment Check ground conditions. Closeness of buildings, excavations and
services. Monitor lighting and weather (including response actions during
high wind conditions).

Equipment Check valves fitted to excavator. To be suitable for operations being carried
out and test certificated. Setting up of equipment to be adequate and
verified by crane coordinator. Assess the need for a planned preventative
maintenance scheme.

Emergencies Standard first aid, evacuations, accident reporting and investigation. Major
incident response plan. Emergency procedures in contract safety plan.

Communications Other workers to be informed of lifting operations being carried out.


Warning signs. Hazard markers etc. Radio/transmitters. Ability to hear
audible warnings during lifting operations. One banks man only directing
crane driver.
COSHH As required.

PPE Hard hats, high visibility clothing, gloves and footwear etc. Identification of
banks man.

Other Excavators used for lifting must be rated or exempt with current
documentation. Provision of equipment such as tag lines. Further
considerations for lifting operations in tunneling or for man-riding will be
needed.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 52
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 33


Assessment for: MANUAL HANDLING
Significant risks: Various back injuries (i.e. strains, slipped discs etc.)
possible injury through dropping, torn ligaments, tendons,
hernias, general cuts and abrasions.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Operatives informed of possible back injury and strains and sprains due to
lifting tasks on site and in office. Issue Manual Handling information to
personnel. Clear labelling of weights if possible. Assess all the details and
working practices of the work to be done. Complete specific assessment
Instruction form as appropriate. Avoid manual handling if possible. Use mechanical
means if appropriate. Seek help from others if no mechanical aid available.
Follow the control methods detailed in an assessment.
Training Operatives trained in correct method of lifting and handling. Not to exceed
personal capability.

Supervision Constantly monitor storing and stacking to keep manual handling as minimal
as possible. Ensure specific instructions are followed, supervisors to be
aware of manual handling requirements.

Access Good flat, clear, stable ground and scaffolds are free of obstacles and
debris.

Environment Areas to be kept clean and tidy. Free of trip hazards. Well lit. Special
attention to areas of restricted space.

Equipment Various lifting aids available to assist manual handling. Ensure lifting aids
are subject to any applicable inspection testing etc.

Emergencies Standard site first aid, fire protection, spillage control, accident reporting and
investigation.

Communications Good communications between operatives in dual handling.

COSHH Possible hazards from material being handled in case of spillage.

PPE Gloves, foot protection, hard hats, possible eye protection, masks as
appropriate.

Other Size of packaging to be reviewed to give consideration to manual handling.


Operatives should be screened to assess the suitability of the person to the
task.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 53
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 34


Assessment for: SITE PLANT MOVEMENT/CARE
Significant risks: Crushing/laceration and entrapment injuries, damage to
structures and plant, plant instability, structural failure,
reversing vehicles, slewing machinery. Loss of loads.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Operatives and visitors to be aware of dangers of equipment and related
locations. Produce Safety Method Statements where appropriate. Ensure
that plant manuals are kept with equipment where appropriate. Any
traffic/pedestrian routing to be detailed in safety plan and clearly marked.
Instruction Visitors to be inducted/escorted, operatives to receive appropriate safety
awareness talks. Use of banks man in movement areas if applicable.
Training Operators and banks men to be competent suitably trained and certificated.
Supervision Supervisors to ensure that plant and equipment is operated and banked
ONLY by persons who have been trained, certificated and authorised to do
so. Ensure that weekly registers and maintenance requirements are
performed. Regular inspection of any traffic management systems to
ensure safe access etc.

Access Safe access to be assessed and provided before movement of plant.


Assess requirements for level ground. Consider pedestrian segregation and
high visibility clothing.

Environment Consider weather, ground conditions, adequate lighting, dust, nearness of


excavations/buildings, traffic, noise and fumes. Suitably plan any cleaning,
wheel washing, sheeting areas, loading. Damp down in dry weather. Bund
diesel tanks.

Equipment Regular inspection, reporting of condition, maintenance procedures and


manuals, periodic tests, cleaning. Instructions to be in English. Hazard
lights and audible warning units where applicable. Adequate marking.

Emergencies Standard site first aid, fire protection, evacuation, accident reporting and
investigation.
Communications Use warning signs, hazard markers and audible warning units where
appropriate. Personnel in the vicinity should be made aware of plant
movements. Consider use of radio/transmitters. Use of dedicated banks
man using the appropriate signals.

COSHH As applicable to maintenance activities. Specific hazardous loads to be


loaded and carried may need assessing.

PPE As appropriate to maintenance operations, together with high visibility


clothing.
Other Check condition of plant upon arrival on site.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 54
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 35


Assessment for: TOOLS (ELECTRICAL/PNEUMATIC/CARTRIDGE)
Significant risks: Personal injuries due to misuse and failure such as
electrocution and laceration; excess noise, dust and vibration.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Assess tool requirements, location of use and obtain data sheets as
appropriate. Any relevant marking requirements e.g. ear protection (symbol
visible on the tools).
Instruction Regular tool box talks with individual reference to unusual tools.
Certificate and Authorisation of Plant Operators. Cartridge tool operators
Training are to be certificated by the manufacturer/supplier.

Supervision Supervisors are to monitor condition, inspection records, certification and


use.
Access Consider exclusion zones and controlled issue of tools. Adequate working
space is to be provided for the safe use of tools.

Environment Evaluate weather, water, earthing requirements, vibration, noise, dust,


fumes, dry storage area, security etc. Safe storage for cartridges/gas
cylinders.

Equipment Delivery test certificates where appropriate. Maintenance, cleaning,


periodic testing and regular inspection. Ensure electrical equipment is 110v
and properly earthed.

Emergencies Standard site first aid, fire protection, evacuation, accident reporting and
investigation. Give particular consideration to electrocution in conductive
environments.

Communications Tool box talks, warning signs.

COSHH As applicable. Consideration to be given to dust, swarf, oils, greases,


cleansing fluids, epoxy etc. Consider the presence of asbestos.

PPE Goggles, ear muffs, gloves, masks, etc. Consider ventilation/breathing


apparatus.

Other Two of the most important considerations with tools are PPE and adequate
training.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 55
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 36


Assessment for: CONFINED SPACES
Significant risks: Asphyxiation from lack of oxygen or poisoning of noxious fumes/gases,
explosive gases, entrapment, flowing solid material overcome by high
heat conditions, drowning if present, fall injuries. All possibly exacerbated
by the introduction of mechanical or electrical equipment into confined areas .

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Seek all available information on the ground/location to be entered and
establish safe systems of work. Undertake all appropriate tests to identify
the nature of the environment to be entered e.g. sludges, rust (lack of
oxygen). Procedures to be developed to take account of complexity of
Instruction confined spaces e.g. tunnels, underground shelters, caverns, vessels etc.
and the number of persons within confined spaces. All employees who
have involvement with any confined spaces work (including the writing of
Safety Method Statements) to be given specific instruction concerning
Training particular spaces to be entered and relevant information. This includes
supervision, employees entering confined spaces persons employed as top
men and rescue personnel. All personnel to sign Safety Method
Statements/Permits to enter and/or work. All employees entering confined
spaces are to receive training for entry procedures, atmospheric testing
equipment, emergency evacuation, lifesaving equipment and procedures.
The practical use of equipment will also be covered. Emergency rescue
team to be formed and trained where appropriate.
Supervision Designate the category if space to be entered. A trained competent
person is to be appointed to carry out tests before entry and be in
continuous attendance during work within confined space. Entry controlled
by permit system. Safe and unrestricted access to/from confined spaces to
be monitored and ensured by this person at all times. Supervisor to be
aware if the requirements of confined space work.
Access Unrestricted access and egress essential. Use tally boards where
appropriate to monitor entry and exit. Forces ventilation and requirements
must be assessed but they are to be mandatory in any area where any
possibility of oxygen deprivation or noxious gases identified or known to
exist, unless a system utilising working BA has been established. Traffic
management scheme to be drawn up and implemented for protection of
access/egress points in roadway.
Environment Evaluate for ventilation requirements, consider need for non-spark
(intrinsically safe) lighting and equipment. The effects of flooding or
weather, hot or cold temperatures, contaminated ground to be established.
Identify toxic or flammable atmospheres to ensure that continuous gas
monitors are compatible. Consider the effects of noise, dust and fumes.
Provide emergency lighting.
Equipment Saver rescue and working breathing apparatus, ventilation units, gas
detectors, man hoist and harness, chemical indicator tubes to identify
fumes/gases or substances. Also consider the intrinsic safeness of all
electrical systems. Ventilation systems to have visual or audible warning in
event of failure.
Emergencies Consider pre-determined system of shouts/whistles/horns etc, between all
members of the team. Clear access to be maintained to the working area
for emergency services. Standard site first aid, fire protection, recovery,
evacuation, accident reporting and investigation. Major incident response
plan.
Communications Emergency boards, drawings, telephone numbers etc. to be displayed at
point of entry. Consider internal telephone/radio/transmitters/bell/rope
signals.
COSHH Consider the hazards of all material such as epoxies, resins, adhesives,
fuels, cleansing fluids, solvents, dust, concrete, paints etc, when used in
confined spaces.
QCS 2014 Section 11: Health and Safety Page 56
Part 2.4.01: Risk Assessment Guides and Method Statement
PPE Hard hats, protective footwear, protective clothing, goggles, masks, hearing
protection, harnesses etc. as appropriate and breathing equipment. Gas
monitors.
Other Consideration should be given to confined space procedures when
personnel enter restricted spaces within form work or reinforcement cages.
Contact with Safety and environmental Department.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 57
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 37


Assessment for: NIGHT WORK
Significant risks: Injury from falling/tripping/fatigue in particular, plus generally
increased risks due to limited visibility.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Generally a method statement either unique to a single nights work or to an
activity over a number of nights, should be prepared incorporating the
requirements of the preceding shift and personal response alarms.
All involved should be given a briefing on the work involved including which
Instruction accesses are to be used and which areas are suitable for working. Give
specific induction and safety awareness talks on night work.
Training Refer to specific risk assessments and Safety Method Statements.

Supervision Plan safe and adequate lighting both in place of work and access there to
(i.e. working and background lighting).
Access Ensure all access ways are completely lit, are of good standard and free of
materials. Establish exclusion zones and designated working areas. Give
particular attention to edge protection and barriers.

Environment Good lighting. Special attention to all edges, trip hazards, noise and
vibration. Consider weather i.e. low temperatures and slippery surfaces.
Avoid lighting that may have stroboscopic effect particularly if using moving
equipment. If practical check lighting levels. Prevent nuisance/risk to public
from lighting/dust/noisy operations.

Equipment All equipment required for night work, especially lights, should be checked
during prior daylight shift. Special attention to lighting cables.

Emergencies Checks to be made on availability of night cover from local hospitals etc.
Standard site first aid and reporting procedures to apply, list of
emergency/night call out numbers. Where applicable emergency lighting
shall be provided on emergency access routes.

Communications Greater use of radios to minimise unnecessary movements at night. A tally


system may be required on certain operations.

COSHH As required by activity.

PPE As well as normal helmets and boots, high visibility clothing should be
utilised. Attention to warm clothing, as required, should also be made.

Other Shifting of labour resources to be arranged to prevent prolonged day and


night shift working. Consider increased supervision in working areas and
control of unauthorised access. Consider use of light sensitive cells for
lighting systems.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 58
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 38


Assessment for: SPECIALIST SUB-CONTRACTOR PROCESSES eg. BITUMINOUS SURFACING,
PAINTING, WATERPROOFING, SILANE ETC.
Significant risks: Depends on process, however tend to be more COSHH/pollutant
orientated. Burns, skin complaints and asphyxiation etc.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Ensure that a Safety Method Statement risk assessment and COSHH
assessment have been supplied by the sub-contractor. Ensure that the
sub-contractor is appropriately experienced. Special care in confined
spaces and using highly flammable materials.
Instruction Require the sub-contractor to brief a member of your supervisory staff on
ALL safety requirements/hazards etc. Ensure that any employees who may
come into contact with the specialist work have been briefed, tool box talks
inductions etc.
Training Sub-contract personnel to be trained and certified as appropriate.

Supervision Ensure that the sub-contractor adequately supervises his works and works
to the Safety Method Statement. Hot work permit to be issued where
appropriate.

Access As required to ensure safe access and egress.

Environment Monitor environment and set up exclusion zones etc. as appropriate.

Equipment As required for activity. Consider standoff distances, atmospheric


monitoring and ventilation.

Emergencies Ascertain from the sub-contractor if specialist measures are necessary.


Check fire precautions etc. Standard site first aid, fire protection,
evacuation, accident reporting and investigation.

Communications As appropriate, warning signs.

COSHH Obtain COSHH information assessment from sub-contractor. Ensure


compliance. Check disposal of waste etc.

PPE To be established with sub-contractor/Safety Environmental Department as


appropriate.

Other Seek advice from Safety and Environmental Department as necessary.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 59
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 39


Assessment for: STORAGE AND LIMITED USE OF HIGHLY FLAMMABLE MATERIALS ETC

Significant risks: Explosion, fire, vapours, manual handling injuries.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Assess type and quality of gases/liquid/materials to be used, quantities to
be minimised, storage/fire precaution recommendations from suppliers to be
obtained as required.
Instruction Personnel to be briefed on suppliers information safety precautions. Safety
awareness talks.
Training Ensure that all employees who come into contact have cause to use
materials and are trained on safe usage, storage disposal and fire
procedures.
Supervision Implement checks on storage and usage. On larger sites with greater
usage have formal issue/collection system. Establish demarcated remote
storage location.

Access Control access to secure storage area.

Environment Individual outdoor stores to be constructed to recommended type, including


all relevant signing and fire points precautions. Ensure no sources of ignition
including electrical.

Equipment Gas cylinders etc. to be obtained from company suppliers only. Any
damage being reported and bottles/containers exchanged immediately. Dry
powder extinguishers.

Emergencies Fire summon Civil Defence (Fire Department) and inform them
accordingly of type and quantities of bottles and containers. Ensure that dry
powder extinguishers are available but do not endanger life, clear area.
Standard site first aid, fire protection, evacuation, accident reporting and
investigation.

Communications Clear signage, including type of materials stored and no smoking signs.

COSHH Perform COSHH assessments on individual materials particularly for


inhalation of fumes.

PPE Depends on materials being stored. In the case of adhesives/resins,


particular care to be taken when handling.

Other Flammable paints/resins may not be suitable for external storage. Consider
ventilated/controlled temperature stores. Consider storing and removing
waste.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 60
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 40


Assessment for: INSTALLATION OF FIRE PROTECTION COATINGS (BOARD)
Significant risks: Manual handling, falls, trailing leads, electricity, circular saws,
noise, housekeeping, storage of materials.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Provide suitable working platform. Visually check electrical tools and leads.
Carry out Manual Handling assessment. Obtain COSHH assessment.
Ensure circular saw is in good working order with guard and dust extract
bag in place, if using bench saw provide push stick and emergency stop
Instruction button. Store materials in a safe manner. Keep work area free from tripping
hazards. Store waste material in the proper bins. Ensure adequate task
lighting.
Training Operatives to receive Risk, COSHH and Manual Handling assessment.
Carry out Induction, all relevant assessments to be given as Tool Box Talks.
Operatives to be trained in the safe use of circular saw. If using Mobile
Elevated Work Platforms or Mobile Towers operatives to be suitably trained.

Supervision Competent person to inspect working platforms and work areas before work
starts. Inspection of working platforms to be entered in Site Register.

Access Provide suitable ladders, properly secured. Keep access areas free of
materials and electrical leads.

Environment Dust levels to be kept suppressed.

Equipment All electrical equipment to be inspected on a regular basis by a competent


electrician, these should be tagged with details of last inspection. Carry out
manufacturers instructions for maintaining Mobile Elevated Work Platforms.

Emergencies Provide First Aider. Operatives to be informed of all emergency procedures


at induction.

Communications PPE notices to be displayed and if working at height Danger Men Working
Overhead.

COSHH Assessment for the fire protection coating board and adhesives.

PPE Hard hats, safety footwear, eye protection, dust mask and ear protection. If
using Mobile Elevated Work Platforms fall body harnesses must be worn.

Other If there is a lot of cutting of boards to be carried out it may be worth


considering job rotation to prevent one person being exposed to the noise
and dust problem.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 61
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 41


Assessment for: INSTALLATION OF FIRE PROTECTION COATINGS (SPRAY) APPLIED

Significant risks: Materials, inhalation, skin contact, falls.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Agree method statement. Store materials in a safe manner. Provide
suitable working platform. Visually check electrical tools and leads. Obtain
COSHH assessments. Provide and maintain suitable extract equipment.
Enclose work area. Keep work area free from tripping hazards. Store
waste material in the proper bins. Ensure adequate task lighting.
Instruction/Training Operatives to receive Risk and COSHH assessment.
Carry out Induction, all relevant assessments to be given as Tool Box Talks.
If using Mobile Elevated Work Platforms of Mobile Towers operatives to be
suitably trained.

Supervision Competent person to inspect working platforms and work areas before work
starts. Inspection of working platforms to be entered in Site Register.

Access Provide suitable ladders, properly secured. Keep access areas free of
materials and electrical leads.

Environment Provide suitable extract equipment to maintain a clean and healthy


environment for all workers. Segregate/enclose work area.

Equipment All electrical equipment to be inspected on a regular basis by a competent


electrician, these should be tagged with details of last inspection. Carry out
manufacturers instructions for maintaining Mobile Elevated Work Platforms.
Screening of scaffolding to prevent overspray will require checks carried out
on number of ties.

Emergencies Provide First Aider. Operatives to be informed of all emergency procedures


at Induction.

Communications PPE notices to be displayed and if working at height Danger Men Working
Overhead. No Unauthorised Persons Beyond this Point notices to be
displayed outside the enclosure.

COSHH Assessment for all materials to be obtained.

PPE Hard hats, safety footwear, overalls, gloves, eye protection, dust or fume
mask (in poorly ventilated area a Fresh Air Feed mask) and ear protection.
If using Mobile Elevated Work Platforms fall body harnesses must be worn.

Other If operatives are exposed to Man Made Mineral Fibres (MMMF) over a
prolonged period there is a danger of serious damage to their health.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 62
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 42


Assessment for: LIFT INSTALLATION

Significant risks: Falls from height, manual handling, confined spaces, electrocution.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Obtain layout of plant rooms/switchgear/isolation points prior to starting
work.
Instruction/Training
Working Safety Method Statements are to consider installation dangers.
Operatives to sign Safety Method Statements. Tool Box Training to be
given on relevant topics.

Supervision Work to be carried out under the supervision of a competent experienced


person.

Access Access to lift shafts and plant rooms to be strictly controlled. Where
scaffolds are used for access these must comply with the relevant
requirements.

Equipment Work equipment e.g. power tools etc. to be tested in accordance with
manufacturers requirements.

Emergencies Method Statement to include procedures for rescue of persons from the
shaft in emergency situations.

Communications Permit to Enter Shafts and Plant room to be in place and displayed.
Warning signs and barriers to be in place.

COSHH As applicable to materials used e.g. Hydraulic Oils.

PPE As site rules and appropriate to hazard i.e. gloves when lifting machine
parts etc.

Other Refer to Generic Risk Assessment No. 14, 20, 22, and 23.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 63
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 43


Assessment for: ELECTRICAL/MECHANICAL SERVICES
Significant risks: Electrocution/fire, fume inhalation, entanglement, vibration,
explosion, fall from height, manual handling, paint use/radiation

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Risk Assessments and Safety Method Statements, PPE, Permits to Work
(Hot Work), Flash Screens, Fire Precautions, Permits to Work (Electrical
Systems), Tower Scaffolds, Display Notices, Locking off Procedures.
Documentation for lifting appliances/gear
Instruction/Training
Inductions, Safety Awareness Talks, Permit to Work Procedures, Scaffold
Erection (Towers), Abrasive Wheels.
Supervision Permit to Work issue. Competent persons appointment. Electrical Duty
Holder. Operation of visible inspection system displayed. Work Place
Inspections.

Access Position of temp. Cables, step ladders inspected and of sufficient length
(split head trestles not used as steps). Ladders inspected and secure
gangways clear.

Environment Welding fume control, noise control assessments, non-destructive testing,


dust control (drilling), housekeeping (Inc. flammable debris), waste disposal
(conduit off cuts), oil drips (threading machines).

Equipment Guarding of threading machines/welding machines to external air, fire


extinguisher adjacent to machines, flash back arrestors, bottle stands/gas
storage, equipment inspection procedures.

Emergencies Evacuation procedures/fire procedures/emergency lighting, access routes,


alarm systems, first aid, gas check.

Communications Posters, Notices, Tool Box Talks.

COSHH COSHH assessment for and including welding fume, cutting oils, paints,
fluxes, dusts (grinding) oxygen, acetylene propane etc.

PPE Head protection, foot protection, overalls, including visors, eye protection,
noise protection, gloves, RPE etc.

Other Ducting installation (Geanie hoists).


Special precautions for special welding operation.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 64
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 44


Assessment for: PLUMBING WORKS

Significant risks: Potential for inhalation, ingestion or absorption of toxic


substances (e.g. lead, solvents etc.). Fire whilst undertaking
hot work, entanglement with pipe threading machine,
vibration from percussion tools. Confined working.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information COSHH assessment details made available. Detailed method statement for
pressure testing and non-destructive testing.

Instruction/Training COSHH, manual handling, fire prevention training required.

Supervision Effective supervision for hot work and working with lead. Health
surveillance required for significant exposure.

Access Safe access required to all work locations.

Environment Disposal of waste in accordance with waste procedure.

Equipment Maintain in good condition.

Emergencies Site arrangements and local segregation.

Communications Tool Box Talks.

COSHH Assessment required for flux, lead, solvents, epoxy resins, maintain.

PPE Safety helmets, safety footwear, gloves, overalls, RPE where identified in
COSHH assessment.

Other No smoking or eating whilst exposed to lead fume. Specific welfare for
specific lead work.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 65
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 45


Assessment for: CARPENTRY/JOINERY
Significant risks: Dust (hard and soft wood), fall from height, contact with
cutting machinery, glues, manual handling, treated timber,
slips and trips.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Risk assessments, safety method statements, information posters, safety
reminders.

Instruction/Training Inductions, safety awareness talks, cartridge gun training, tower scaffold
training, manual handling, wood working machine training.

Supervision Working at height supervision, scaffold inspections, work place inspections,


small tool inspections, tools in good order.

Access Ladders secured and in good order, gangways clear, staircases as


alternative to ladders.

Environment Housekeeping, dust controlled at source, flammable material, solvent glues.

Equipment Electrical equipment in good order, hand tools in good condition, vibration
(hammer drill) checked.

Emergencies Induction site plans and notices displayed. Access routes clear. Sufficient
staircases.

Communications Induction/safety awareness, site notice boards, duty holders indicated,


supervision training, risk assessments and safety method statements
explained.

COSHH COSHH assessments, materials use training, data sheets, Sypol system.

PPE Head protection, foot protection, respiratory protection (dust mask), noise
protection, gloves, eye protection and overalls.

Other

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 66
Part 2.4.01: Risk Assessment Guides and Method Statement

REF NO. 46
RISK ASSESSMENT GUIDE
Assessment for: PLASTERING AND EXTERNAL RENDERING
Significant risks: Falls from height, falling objects/material, manual handling,
skin contact with wet mortar, dust from mixing unit.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information General safety information on safe access e.g. ladders etc.

Instruction/Training Manual handling of equipment/materials

Supervision Scaffold use above 2 meters to be under control of competent person.

Access Suitable access to be provided to all work locations e.g. hop-ups to full
scaffolds etc. segregate lower work areas whilst working in elevated
situations.

Environment Consider weather conditions.

Equipment Suitable access equipment to work location. Maintain equipment in good


condition.

Emergencies General site arrangements for first aid and evacuation.

Communications General information and tool box talks.

COSHH As appropriate to substances in use e.g. mortar.

PPE Safety helmets, safety footwear, warm clothing, gloves etc. Face mask
when mixing.

Other Maintain good standards of personal hygiene.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 67
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 47


Assessment for: CEILING FIXING
Significant risks: Entanglement, fall from height, manual handling,
electrocution, hand injuries from sharp components,
eye injuries during drilling operations.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Risk assessments and safety method statements, PPE, permits to work,
tower scaffolds.
Instruction/Training Inductions, safety awareness talks, permit to work procedures, scaffold
erection (towers), abrasive wheels.

Supervision Permit to work issue. Competent persons appointment. Electrical duty


holder. Operation of a visible inspection system. Work place inspections.

Access Position of temp, cables, and step ladders inspected and of sufficient length
(split head trestles not used as steps). Ladders inspected and secure
gangways clear. Erection of suitable scaffold. Use of MEWPs.

Environment Noise control assessments, dust control (insulation), housekeeping (inc


flammable debris) and waste disposal.

Equipment Equipment inspection procedures. Scaffold inspection system visible to


operatives.

Emergencies Evacuation procedures/fire procedures/emergency lighting, access routes,


alarm systems, first aid.

Communications Posters, notices, tool box talks, wage packet inserts, videos, supervision.

COSHH COSHH assessment for and including dusts (grinding) insulation.

PPE Head protection, foot protection, overalls, eye protection, noise protection,
gloves, RPE etc.

Other

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 68
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 48


Assessment for: FLOOR AND WALL TILING

Significant risks: Inhalation, skin absorption or ingestion of harmful substances.


Falls from heights, fire or explosions.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Operatives should be made aware of what materials are being used, The
associated hazards and the required control measures to be applied.
Instruction Induction training should cover site rules and action to be taken in the event
of an emergency. Where appropriate operatives should be certificated for
Training the erection of mobile tower scaffolds. Training should be provided in the
safe use of respiratory equipment.

Supervision Supervisors to ensure that equipment and plant is operated and erected
ONLY by persons who have been trained, certificated and authorised to do
so. Ensure that COSHH assessments have been produced and training
provided. Ensure that suitable access is being provided and used and that
all highly flammable materials are being stored in a safe manner.

Access Safe means of access/egress must be provided and maintained. If working


at height, an assessment should be carried out and suitable control
measures employed.
Mobile scaffold and access platforms must be properly erected with
guardrails fitted where required and inspection details displayed.
Environment Adequate ventilation must be provided. Consideration should be given to
the safe storage of flammable materials. Controlled waste must be properly
disposed of.
Equipment Equipment must be kept in good working order and be regularly maintained,
with records being kept. The ventilation system provided should be
checked regularly. Any mobile towers, scaffolding should be checked at
least every seven days with a record of inspection being kept.
Emergencies If overcome by adhesive vapours, remove to fresh air, keep warm and fetch
first aider, contact emergency services if necessary. Suitable fire
procedures should be in place and fire extinguishers should be available.
Standard site first aid, fire protection, evacuation, accident reporting and
investigation procedures should be applied.
Communications Warning signs and notices and barriers as appropriate.
COSHH Alternatives to harmful adhesives should be considered. Adequate
ventilation should be provided, backed by respiratory protective equipment
where necessary. Barrier cream or suitable gloves can be used to protect
hands, overalls to protect remainder of body. Adequate hygiene facilities
should be provided. Operatives should not eat, drink or smoke at the work
location or when their hands are contaminated.
PPE Appropriate respiratory equipment if required. Goggles/glasses, gloves,
safety footwear, overalls, helmets must be worn.
Other Consideration should be given to work in confined spaces e.g. small rooms

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 69
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 49


Assessment for: PAINTING & PAPERING

Significant risks: Inhalation, skin absorption or ingestion of harmful substances.


Falls from heights, falling materials, slips on spillages, fire or explosions.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Operatives should be made aware of what materials are being used, the
associated hazards and the required control measures to be applied.
Instruction Induction training should cover site rules and action to be taken in the event
of an emergency. Operatives should be certificated for the erection of
Training mobile scaffolds. Where appropriate training must be provided in the
operation of MEWPs. Training should be provided in the safe use of
respiratory equipment. Safety method statement to be signed by all
operatives.

Supervision Supervisors to ensure that equipment and plant is operated and erected
ONLY by persons who have been trained, certificated and authorised to do
so. Ensure that COSHH assessments have been produced and training
provided. Ensure that suitable access is being provided and used and that
all highly flammable materials are being stored in a safe manner.
Access Safe means of access/egress must be provided and maintained. If working
at height an assessment should be carried out and suitable control
measures employed. Ladders should be tied or footed. Mobile scaffolds
and access platforms must be properly erected with guardrails fitted where
required and inspection records displayed.

Environment Consideration should be given to the safe storage of flammable materials.


Adequate ventilation must be provided. Controlled waste must be properly
disposed of.
Equipment Equipment must be kept in good working order and be regularly maintained,
with records being kept. The ventilation system if provided should be
checked regularly. Any mobile towers, scaffolding etc. should be checked
at least every seven days with a record of inspection being kept.
Emergencies If overcome by paint vapours, remove to fresh air, keep warm and fetch first
aider, contact emergency services if necessary. Suitable fire procedures
should be available. Standard site first aid, fire protection, evacuation,
accident reporting and investigation procedures should be applied.
Communications Warning signs and notices and barriers as appropriate.
COSHH Alternatives to harmful paints, varnishes or adhesives should be considered.
Adequate ventilation should be provided, backed by respiratory protective
equipment where necessary. Barrier cream or suitable gloves can be used
to protect hands, overalls to protect remainder of body. Adequate hygiene
facilities should be provided. Operatives should not eat, drink or smoke at
the work location or when their hands are contaminated with paint.
PPE Appropriate respiratory equipment if required. Goggles/glasses, gloves,
safety footwear, overalls, helmets must be worn.
Other Consideration should be given to work in confined spaces.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 70
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 50


Assessment for: USE OF SPECIALIST EQUIPMENT (NUCLEAR DENSOMETERS, THERMIC
WELDERS AND LANCES, LASERS) H.P. WATER JETTING

Significant risks: Varies according to equipment i.e. radiation injuries,


eye damage, general injuries to public and personnel.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Normally a specialist operation requiring Safety Method Statements. List of
specialist equipment likely to be required to be drawn up and discussed with
Instruction safety adviser. Establish and issue Safety Method Statements. Information
from suppliers of equipment.
Training Sub-contractor or manufacturers recommendations/training to be sought
and personnel instructed as appropriate. Certificated operators.
Information obtained will establish the extent of instruction required.
As required for the particular type of specialist operation.

Supervision Designated responsible person to be nominated to ensure that equipment is


correctly used and method statement adhered to.

Access Exclusion zones where appropriate.

Environment To be monitored/controlled as required by manufacturers/codes of practice


etc.

Equipment To be obtained and used as manufacturers/specialist recommendations.


Appropriate storage required.

Emergencies Specialist first aid information to be obtained. Specialist emergency


procedures to be set up as appropriate (nuclear densometer). Standard site
safety reporting procedures apply.

Communications Warning signs, hazard markers.

COSHH As applicable to particular process.

PPE As required by particular process.

Other A specific assessment should always be performed for an item of specialist


equipment.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 71
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 51


Assessment for: USE OF CLASS 3B LASERS (PREDOMINANTLY IN CONFINED OR
RESTRICTED AREAS)

Significant risks: Exposure to non ionising radiation (laser light) being caused by striking
persons directly or indirectly (reflection) physical risks include eye damage,
production of toxic gases, electrical hazards.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information All personnel exposed to hazard/risk from the use of class 3B lasers shall
receive information, instruction and training regarding the hazards and risks.
Instruction/Training Information should be sought from the supplier.
All the above measures also include the provision, fitting and wearing of
PPE.

Supervision The requirements for medical supervision should be assessed, in particular


in the event of injury due to ocular exposure. Overall supervision shall be
controlled by a competent person who has received adequate training.
Access Class 3B lasers are potentially hazardous if a direct beam or specular
reflection is viewed by the unprotected eye and therefore access must be
strictly controlled to those people who have received the adequate
information, instruction and training.
Environment The entrance to areas should be posted with a standard laser warning sign.
The laser beam should be terminated where possible at the end of its path
by suitable diffusion material. Reflections must be avoided. Location and
direction of beam must be clearly marked.
Equipment The equipment must be suitable for use and any maintenance requirements
detailed.

Emergencies Emergency procedures must be linked in with the specific site procedures in
particular when considering the hazards that exist including fire,
electrocution etc.
Communications All relevant information should be communicated to all personnel involved.
COSHH An assessment must be made if there are any identified hazardous
environments in particular contamination from chlorine, hydrogen sulphide
and bromine.
PPE The need to use PPE against the hazardous effects of laser operation
should be kept to a minimum by admin controls, engineering design and
beam enclosure. However where the risk exists the PPE may include eye
protection, clothing, respiratory etc.
Other A safe system of work should be devised (with all the other controls listed
above) that reduces the risk by means of cutting down the operational
times.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 72
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 52

Assessment for: ARC WELDING

Significant risks: Fire/flammable atmospheres, electric shock, noise,


substances/chemicals/fumes/dusts, burns, radiation, heat,
falls, trips and slips, flying particles, vibration, oxygen
depletion, asphyxiation, manual handling.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Permits to work. (Confined space/hot work) Method statements.

Instruction/Training Operatives trained in fire prevention methods/precautions.

Supervision Regular inspection of barriers, fireproof screens and notices.

Access Safe access egress to be provided and maintained. Consideration to be


given to restricted access zone.

Environment Good lighting. Dust and noise suppression methods.

Equipment Flameproof welding screens. Fire protective equipment sited adjacent to


welding set. Earthling of work piece.

Emergencies Standard first aid, fire protection. Operatives inducted in emergency


procedures and assembly points.

Communications Warning signs and barriers. Permits to work.

COSHH Local exhaust ventilation and others as required for location/materials used
for welding.

PPE Welding gloves, flameproof overalls, boots, spats, eye protection, and
respiratory protection. Local exhaust ventilation.

Other

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 73
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 53

Assessment for: RADIOGRAPHY

Significant risks: Radioactive substances, burns, inhalation radiation,


contamination damaged/lost sources.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Risk assessment/method statements. Permit to work. Approved sub-
contractors.
Instruction/Training All operatives to sign method statement/local rules. All operatives to receive
induction training.

Supervision Regular inspection of working barriers, signs and notices.

Access Safe means of access/egress to provide and maintain to work area.

Environment Safety zones/storage of sources. Audible warning systems available.

Equipment Good working order regularly maintained. Records kept.

Emergencies Operatives aware of emergency procedures and assembly points. Details


of radiation protection adviser.

Communications Barricade areas, warning notices posted, audible warnings of exposure of


isotope.

COSHH Assessment, information and instruction to all personnel

PPE Film badges, safety helmet/footwear worn at all times. Eye/hearing


protection as/when required. Hand/body protection as required.

Other Ensure supervision for out of hours working. Work to be carried out, outside
normal working hours. Account will be taken of project standard
requirements.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 74
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 54

Assessment for: COMMISSIONING PLANT

Significant risks: Electrocution, steam/hot liquid scalds, toxic/flammable gas


or liquid release, bursting of vessels/pipes/joints under pressure,
falls from height, trapping or being struck by plant in motion.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Induction training should cover site rules and action to be taken in the event of
an emergency.
Instruction/Training All operatives must be briefed on the hazards, precautions and emergency
procedures before testing and commissioning starts. Operatives should be
trained in the operation of the permit to work procedure and the actions required
by the system.
Supervision A formal testing/commissioning procedure must be prepared before
testing/commissioning commences and operatives signed to confirm
understanding. Leak testing will precede pressure testing; pressure testing
should be carried out at the lowest pressure acceptable to the specifier /
specification and should be avoided unless there are sound technical reasons
for carrying out such tests. Hydraulic testing should be the preferred method
where practicable. Supervisor must ensure that only authorised, experienced
and competent persons will carry out testing and commissioning operations.
Supervisor must ensure that the permit to work system is being properly
operated and that all appropriate elements of the plant have been isolated
locked off and specified safety devices have been provided.
Access Safe means of access/egress must be provided and maintained. If working at
height, an assessment should be carried out and suitable control measures
employed. Ladders should be tied or footed, mobile scaffolds and access
platforms must be properly erected with guardrails fitted and inspection records
displayed.

Environment Access to commissioning and test areas must be restricted. Consideration must
be given to the surrounding environment e.g. plant, operations etc. when
planning and carrying out the works. Prior to the commencement of electrical
testing and commissioning works a check should be made to verify that all
switch rooms/control rooms have been cleared of loose materials and that all
temporary installations have been removed. Equipment covers and doors are to
be closed and guards refitted to machinery. Any circuits to be worked on will be
treated as live until verified as dead.
Equipment Equipment must be kept in good working order and be regularly maintained with
a record of maintenance being kept. Only suitable and appropriate equipment
must be used for testing and commissioning works.
Emergencies Suitable fire procedures should be in place and fire extinguishers available.
Standard site first aid, fire protection, evacuation, accident reporting and
investigation procedures should be applied.
Communications Warning signs, hazard markings and exclusion zones as appropriate.
COSHH Assessments produced for material used in testing and commissioning
operations, including possible emissions/discharges from plant in operation.
PPE Hard hats, protective footwear, gloves, goggles, overalls and any specialist
equipment required e.g. insulation mats etc.
Other

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents and
must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 75
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 55

Assessment for: BLOCK PAVING, FLAGGING KERBS AND EDGINGS

Significant risks: Manual handling, materials/substances, plant and


equipment, power tools, cutting, noise, dust, underground
services, public protection (to and from).

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Necessary permits when adjacent to underground services. Safety signs,
warning notices.
Instruction/Training Operatives to sign method statement as understood. Certification for
abrasive wheel changing.

Supervision Competent supervision, monitoring work activity.

Access Safe means of access/egress provided and maintained.

Environment Dust/noise suppression/reduction methods e.g. enclosure for omitting


operations. Traffic protection coning/signing/safety zones.

Equipment Good working order regularly maintained. Records maintained. Segregate


plant from pedestrians. Manholes cover handling equipment. Wet cutting of
materials.

Emergencies Operatives aware of emergency procedures and assembly point.

Communications Provision of suitable safety signs, warning notices and barriers.

COSHH Assessments, information and instructions given to operators. Personal


hygiene essential.

PPE Safety helmets, footwear to be worn at all times. Eye/hearing protection to


be worn as necessary. Yellow waistcoats adjacent to traffic.

Other N/A

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 76
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 56

Assessment for: ROAD/PATH SURFACING

Significant risks: Manual handling, materials and substances, reversing vehicles,


plant and equipment, underground services, noise, heat and fumes.
Fire/explosion.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Method statements, safety signs, warning notices.

Instruction/Training All operatives to sign method statement applicable to their work activity.

Supervision Supervisors to ensure plant and equipment only operated by certificated


authorised persons. Traffic management.

Access Safe means of access/egress in/around plant and equipment segregate


plant from pedestrians/traffic.

Environment Noise and dust suppression. Traffic protection coning/signing/safety


zones.

Equipment Good working order regularly maintained. Records kept. Overhead power
lines suitably protected. Reversing alarms fitted to equipment.

Emergencies Operatives aware of emergency procedure and assembly points. First aid
treatment for burns.

Communications Warning signs, audible warnings, suitable barriers.

COSHH Assessment, information and instructions.

PPE Safety helmets/footwear to be worn at all times. High visibility clothing to be


worn at all times. Eye/hearing protection to be worn when necessary.
Hand/body protection as required.

Other Traffic management schemes.


Interface/overlap with Client personnel/members of public.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 77
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 57

Assessment for: FENCING (PERMANENT)

Significant risks: Manual handling, materials and substances, noise,


underground/overhead services, plant and equipment.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Method statement/utilities drawings/permit to dig.

Instruction/Training All operatives inducted in site requirements/manual handling/buried


services.
All operatives to sign method statement applicable to their work activity.

Supervision Competent supervision. Supervisor to ensure on trained, certificated


authorised persons use/operate plant and equipment.

Access Safe means of access/egress to provide and maintain to work area.


Segregate plant/equipment from pedestrians.

Environment Noise and dust suppression methods. Soil analysis.

Equipment Good working order, regularly maintained and records kept. Overhead
power lines suitably protected.

Emergencies Operatives aware of emergency procedure and assembly points.

Communications Warning signs and notices, suitable barriers and audible warnings on plant
and equipment. As appropriate to work/location.

COSHH Assessment, information and instruction given to all operatives e.g.


preservatives/paints.

PPE Safety helmets/footwear to be worn at all times. High visibility clothing when
adjacent to traffic routes. Eye hearing protection as necessary.

Other Interface/overlap with Client personnel/members of public.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 78
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 58

Assessment for: LANDSCAPING

Significant risks: Manual handling, materials and substances, plant and


equipment, overspray of substances, noise.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Method statements, safety signs, warning notices, buried services,
overhead services.

Instruction/Training Operatives trained in use of pesticides. All operatives to attend induction


training. All operatives to sign method statement applicable to their work
activity.

Supervision Competent supervision. Supervisors to ensure only trained certificated and


authorised persons use pesticides, plant and equipment.

Access Safe means of access/egress to provide and maintain segregation of plant


from pedestrians.

Environment Noise and dust suppression methods. Safe storage of pesticides/disposal


of containers.

Equipment Good working order regularly maintained. Records kept. Check gradability
of plant on slopes.

Emergencies Operatives aware of emergency, procedure and assembly points.

Communications Warning signs, warning notices, suitable barriers and audible warnings.

COSHH Assessment, information and instruction given to all operatives.

PPE Safety helmets/footwear to be worn at all times. High visibility clothing to be


worn when adjacent to traffic routes. Eye/hearing protection when
necessary. Respiratory protection as required.

Other Interface/overlap with Client personnel/members of public.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 79
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 59


Assessment for: TREE SURGERY AND CROSS CUTTING OF TIMBER WITH A CHAINSAW

Significant risks: Falling from heights, falling objects, uncontrolled fall of


trees/limbs, personal injury from cutting equipment, injury to
members of the public/passing vehicles.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Safety method statement to be signed by operatives.
All operatives felling trees to have received training from recognised body in
Instruction/Training Tree Surgery. Those engaged in cross cutting of timber with a chainsaw
are to have received, as a minimum, training in use of chainsaw cross
cutting.

Supervision Whilst cutting operations in progress a minimum of one person trained as


above to supervise. No burning of debris on site.

Access If possible low level branches to be cut from footed ladders or mobile
scaffolds, high level tree cutting to be done using approved harness and
lines. Ensure that operative attaches away from cutting point and above.

Environment Consider noise, refueling away from drains/watercourses. Ensure saw


dust/chips not causing airborne hazard.
Equipment All chainsaws to have chain break. Chains to be sharp. Test certificates for
harnesses and ropes.

Emergencies Rescue from height of injured person. Ensure communications are


available on site. First aider to be on site. Fire extinguisher for refuelling
operations

Communications Radio/mobile phones to communicate in the case of emergency.

COSHH COSHH assessments required for petrol, chain oil and two stroke oil.
Check type of wood being cut, sawdust of some trees could be a hazard.

PPE Forestry type safety helmet, visor and ear protection, chainsaw protective
trousers, jacket and gloves. Respirator protection as appropriate to type of
wood being cut forestry type safety boots. High visibility tabard when
working in traffic management. NOTE: harnesses for tree surgery are
different from general purpose harnesses.
Other

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 80
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 60

Assessment for: FIRE PREVENTION WORKING AREAS

Significant risks: Burning, explosion, asphyxiation, electrocution and structural collapse.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Obtain material manufacturers data where applicable. Provide site fire
plan. Liaise with the Civil Defence (Fire Department) as appropriate to the
construction undertaken. If applicable fire points to be identified and put on
plan and post at relevant positions.
Instruction Induct employees on methods and procedures where fire risk is apparent.
Safety awareness talks.
Training Where applicable employees are to be trained in evacuation and the proper
use of the correct types of fire extinguishers.

Supervision Site management to ensure that sufficient suitable fire extinguishers are
correctly positioned, maintained and inspected and additionally ensure that
accesses are kept clear and materials suitably stored. Use of fire watchmen
during and after hot work operations. Issue/monitor hot work permit.

Access Suitable accesses/escape routes are to be kept clear of obstructions.

Environment Consideration is to be given to the safe storage of flammable materials and


fuels. Ensure cleanliness, tidiness, control of burning, regular disposal of
waste. Consider damping down where there may be a risk of self ignition.
Establish no smoking zones/site where risk is apparent.

Equipment Site electrical equipment is to be tested and certified at 3 monthly intervals.


Monitor plant for leakage/fuel spillage.

Emergencies Standard site first aid, fire protection, evacuation, accident reporting and
investigation. Major incident response plan.

Communications Warning signs and audible alarms where appropriate.

COSHH N/A

PPE Use as appropriate to operation i.e. welding, burning.

Other Hot work permits will be required in high risk areas.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 81
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 61


Assessment for: FIRE PREVENTION IN OFFICE

Significant risks: Burning, explosion, asphyxiation, electrocution.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Carry out a risk assessment on the premises and produce a fire plan.
Induct employees on escape procedures and the hazards of construction,
Instruction convection, radiation and direct burning. Instruction manuals are to be
provided for equipment.
Safety awareness talks. Staff must be trained in evacuation and the proper
Training use of the correct types of fire extinguishers.

Supervision Appoint fire warden as appropriate. The office manager is to ensure that
sufficient and suitable fire extinguishers are correctly positioned, maintained
and inspected together with carrying out 6 monthly fire drills where
applicable.
Access Emergency routes and exits are to be clearly identified and kept clear of
obstructions, establish suitable assembly points. Emergency exits are to
remain unlocked on the inside at all times.

Environment Consideration to be given to the effects of weather and in particular dust,


externally, rain leakage, wind and flooding. Consideration is to be given to
the safe storage and flammability of solvents, fluids and canisters.

Equipment Electrical equipment is to be electrically tested and certificated at intervals


no greater than 12 months, temporary office accommodation every 3
months. Alarms, extinguishers, hose reels, sprinklers, smoke detectors to
be tested in accordance with procedures. Emergency lighting is
installed/tested where appropriate.

Emergencies Standard site first aid, fire protection, evacuation, accident reporting and
investigation.

Communications Warning advisory signs and alarms.

COSHH N/A

PPE Generally not applicable.

Other Ensure tidiness, control of smoking, regular disposal of waste. Give


attention to the effects of dust on office equipment. Ensure availability of
water and clear access for emergency services.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 82
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 62


Assessment for: OFFICE ENVIRONMENT (PERMANENT AND TEMPORARY INSTALLATIONS)

Significant risks: Fire, visual fatigue, manual handling injuries, poor internal
environmental i.e. ventilation, temperature etc. Poor design and layout.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Obtain details of hazards from manufacturers for any special
equipment/materials. Assessment on VDU operators and provision of
appropriate information. Manual handling review.
Instruction/Training Regular fire practices, instruction on safe use of specialist
equipment/materials. Also instruction on use of fire extinguishers. Safety
awareness talks. As appropriate to equipment used and task being
undertaken.
Supervision Appoint a fire warden. Ensure regular checks on firefighting equipment etc.
as well as all electrical installations/equipment. Keep register.

Access To be maintained as required by fire precautions also in generally good


condition. Prevent trip/fall hazards from trailing leads.

Environment To be kept clean and clear of debris. Noise to be monitored if immediately


adjacent to the works. Consider limitations on smokers. Establish
adequate ventilation and temperature controls. Lighting requirements
ergonomic layout of work stations. Security/location (access for visitors).
No smoking policy.

Equipment To be kept clean, regularly maintained and tested.

Emergencies Standard first aid, fire protection, evacuation, accident reporting and
investigation.

Communications Warning advisory signs, hazard markers and use of notice boards as
appropriate.

COSHH As appropriate to solvents, fluids and adhesives etc.

PPE Not applicable

Other Ensure general welfare conditions such as toilet facilities and heating are to
requirements. Give consideration to disabled facilities. Regular inspection.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 83
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 63


Assessment for: YOUNG PERSON IN CLERICAL POSITIONS (SITE)

Significant risks: Fire, visual fatigue, manual handling injuries,


slips trips and falls, overturning filing cabinets, electricity,
office machinery.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Induction carried out.
Instruction Site specific induction required.
Training required in specific items of office equipment involved in tasks.
Training Manufacturers/suppliers equipment information to be available.

Supervision Close supervision required.

Access Safe means of access/egress to be provided and maintained. Trailing


cables to be protected / routed to eliminate possible slips/trips/falls.

Environment Adequate ventilation, temperature. Lighting and cleanliness provided and


maintained.

Equipment Young persons to be trained in use of all types of office equipment involved
in tasks. Do not overload electrical sockets. Cabinets to be secured to
prevent overturning.

Emergencies Emergency routes not to be obstructed. Fire test/drills to be observed and


acted upon where necessary. All accidents however minor to be reported.

Communications Use of notice boards as appropriate. Direct contact with line managers.

COSHH Should not be applicable except in use of solvent based correction fluid.

PPE Not applicable in present environment if on site must be closely


supervised and wear appropriate PPE i.e. safety helmet, safety footwear.

Other Manual handling assessment to be carried out for replacing paper rolls on
large printer. When assessment formulated young person to receive copy
and be advised of contents/trained. Work area to be checked by young
person at end of each shift to ensure no cigarettes/combustible materials
smoldering.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 84
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 64


Assessment for: CABLE PULLING OPERATIONS

Significant risks: Electrocution, falls of persons, falls of materials, fire,


manual handling

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Risk assessments and safety method statements. Permits to work
(electrical systems). Operatives to work to safety method statements.
Operatives to sign safety method statements. Documentation for lifting
equipment/gear. PPE. Layout drawings. Design checks.

Instruction/Training Inductions. Safety Awareness Talks. Permit to work procedures. Mobile


tower erection. PPE.

Supervision Permit to work issue. Competent persons appointment. Electrical Duty


Holder. Operation of scaff tag system. Workplace inspections. Work under
competent person. Careful planning of cable route.

Access Provision of adequate access equipment. Inspection training in erection.


Use of competent persons to erect.

Environment Waste disposal of offcuts. Overhead services. Adjacent existing services.


Integrity of existing tray supports to be investigated. Suitable anchor points
for attaching harnesses. NB Not from tray supports unless properly
tested for adequacy. Suitable access for vehicles. Level ground for jack
supports.

Equipment Certification for winches/tirfors. Check SWL. Barriers of suitable


construction and design. Adequate number of rollers available. Rollers of
correct size and type. Appropriate size cable stacking to be provided.
Appropriate support of cable drum.

Emergencies Evacuation procedure/fire procedure/emergency lighting. Access routes,


alarm systems, first aid.

Communications Tool box talks, supervision, warning signs, liaison with other
contractors/client personnel.

COSHH Assessments as appropriate to operation.

PPE Head protection, safety footwear, (high visibility clothing, hearing protection,
eye protection as identified in risk assessment).

Other Segregation of third parties from operations.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 85
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 65


Assessment for: WORKING IN CHEMICAL/RADIOACTIVE DRAINS

Significant risks: Contact with unsealed sources of chemicals and radiation,


injury through skin puncture, ingestion, absorption, toxic/explosive fumes,
entrapment and fall injuries, spread of contamination,
improper disposal

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Obtain information from the Client and establish a safe system of work
within the requirements of a permit to work system. Produce a detailed
Instruction/Training hazard risk assessment. Operatives to sign safety method statement.
Personnel to be made aware of the types of chemicals/radiation and the
possible dangers. If classified personnel are to work in radioactive drains
their current dosage rates must be assessed and taken into account before
entry into the drain is permitted. Operatives to be made aware of
procedures for contact with chemicals or radioactive substances.
Operatives taking samples or wipe testing ductwork must be made aware of
the procedures laid down in the safety method statement and suitable
demonstrations and briefings on the methods of handling contaminated
materials must take place and must include the correct use of PPE and
personal hygiene.
Supervision A competent person is to obtain appropriate information e.g.
previous/current used materials/concentrations on the contaminated
substances and supply reports and results of analysis.

Access Exclusion zones to be set up with permit to work system. Designated safe
access as necessary to the type and level of contamination discovered.

Environment Consider the risk of local flooding to drains especially if ductwork has been
stopped with drainage bungs. Special waste to be considered.

Emergencies Together with standard procedures for first aid, evacuation, fire and
explosion. Specific procedures to suit any contaminants present.

Communications Warning signs, Bio-hazard, chemical hazard markings and exclusion zones
as are appropriate.

COSHH Specialist advice to be sought from a Radiological Protection Adviser.

PPE Visor, gauntlets, waders/wellingtons, chemical suit as levels demand.

Other Full BA or airflow system. Rescue winch, safety harness, special waste
bags for disposal of contaminated equipment, Geiger counter, sample
tubes, air monitor, compressor for airflow system, wash down matting,
communication system e.g. radio.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 86
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 66


Assessment for: BRICK/BLOCKWORK OPERATIONS

Significant risks: Falling from height/through work-face, slips, trips and falls,
manual handling, contact with hazardous substances, noise/vibration,
confined spaces, contact with machinery/transport, dermatitis,
falling from ladders, cut/abrasions, eye injury, falling through floor voids.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information / Instruction / Specific risk assessment and safety method statement explained to
Training operatives, copies issued as requested and signatures obtained. Daily
briefings of operatives by supervisors.
Safety induction carried out and signatures obtained. Manual handling
training including repetitive injury identification. COSHH training identified.
Supervision Supervision to update general risk assessment as project progresses.
Ensure workplace is inspected prior to operative placement ensure statutory
registers and plant certification is up to date.
Access Ensure safe access and egress is provided and of sufficient width. Identify
all aspects of access on safety method statement, ensure routes are free of
debris and safe.
Environment Area free of contaminates including dust, slippery conditions and lighting
sufficient. Confined spaces (permits completed). Plant/transport/operative
separation. All required edge protection around working platforms in
place/precautions in place to eliminate falling through work-face and/or
internal fall protection platforms or rails etc. provided. Hop-up systems at
suitable width. Brick-guards in place prior to loading out platforms.
Other persons not to work below brick/block work operations.
Equipment Tools, mixers, scaffolding, clippers, fork-lift trucks, low vibration tools
obtained. All lifting equipment in good order and certificated /inspected.
Emergencies All emergency notices displayed, all personnel induction will include
emergency alarms escape routes/directional notices. Emergency
procedures displayed, first aid identified and drills carried out.
Communications Tool box talks on regular basis, safety reminders, no access notices and
incomplete notices displayed.
COSHH COSHH information obtained for all products including MMMF,
assessments carried out alternative materials/systems of work identified.
PPE Safety helmets, gloves, safety footwear, eye protection, noise
protection(noise assessments done), cover-alls.
Other

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 87
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 67


Assessment for: CLEANING STRUCTURE INTERNALLY PRIOR TO HANDOVER
Significant risks: Falls from heights, slips, trips and falls, cuts/abrasions,
contact with hazardous substances(including biological agents),
noise/vibration, contact with machinery, contact with electricity,
manual handling.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information / Instruction / Specific risk assessment and safety method statement explained to
Training operatives copies issued as requested and signatures obtained. Daily
briefings of operatives by supervisors.
Safety induction carried out and signatures obtained. Manual handling
training including repetitive strain injury identification. COSHH training
identified.
Training and instruction provided in correct use of plant and equipment.
Supervision Adequate levels of competent supervision to be maintained.
Supervision to update general risk assessment as project progresses.
Ensure workplace is inspected prior to operative placement ensure statutory
registers and plant certification is up to date.
Access Ensure safe access and egress is provided and of sufficient width. Identify
all aspects of access on safety method statement, ensure routes are free of
debris and are maintained in a safe condition. Work to be planned so that
only one trade working in an area at a time. Proper and suitable access
equipment to be provided.
Environment Sufficient lighting to be provided, area to be kept clear of obstructions and
all trailing cables managed and minimised. Warning notices to be placed on
wet floors, electric shock possible by the overzealous use of water in the
vicinity of electrical sockets (isolation of electrical supply maybe required).
Equipment All sharp tools to be carried in holder/sheath, plant/equipment inspected and
maintained in good order, low vibration tools used where possible.
Emergencies All emergency notices displayed, all personnel induction will include
emergency alarms escape routes/directional notices. Emergency
procedures displayed, first aid identified and drills carried out.
Communications Tool box talks on regular basis, safety reminders, no access notices and
incomplete notices displayed.
COSHH All substances potentially hazardous to health will have COSHH
assessments carried out on them and the circumstances of their use,
alternative materials/systems of work identified. If biological hazards are
encountered COSHH assessment to be carried out.
PPE Safety helmets, gloves, safety footwear, eye protection, noise
protection(noise assessments done), cover-alls. Do not use plastic over-
shoes when working from steps or ladders.
Other Limitation of access permits for clean areas.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 88
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 68


Assessment for: USE OF LADDERS TO CARRY OUT GENERAL TASKS AT HEIGHT

Significant risks: Falls from heights, contact with overhead power lines

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information / Staircases to be used as an alternative to ladders. Ladders are only to be
used as a result of a specific risk assessment that shows no alternative can
be identified. Safety method statement to be explained to operatives copies
issued as requested and signatures obtained. Daily briefings of operatives
by supervisors.
Instruction / Training Safety induction carried out and signatures obtained. Manual handling
training, instruction and training in the safe erection, use and lowering of
ladders required.
Supervision Adequate levels of competent supervision to be maintained.
Supervision to update general risk assessment as project progresses.
Ensure workplace is inspected prior to operative placement.
Access Ensure safe access and egress is provided and of sufficient width. Identify
all aspects of access on safety method statement/risk assessment, ensure
routes are free of debris and are maintained in a safe condition, avoid
others working below/near the ladder. NB: remember three points of
contact rule when working from a ladder. Do not carry equipment/materials
whilst climbing ladders. Climb holding onto the rungs when climbing vertical
ladders and it is safer using this method on inclined ladders.
Environment Sufficient lighting to be provided, area to be kept clear of obstructions,
ensure equipment is only used in the correct environment (firm level
ground), if un-insulated over-head power lines are present all operatives to
be informed of potential contact hazard - do not use metal ladders.
Equipment Regular inspection of equipment to ensure safe use, all ladders to be tied off
or footed when 3m or more high. Always foot the ladder whilst securing.
Never climb to very top rung/tread of ladder/step, all damaged equipment to
be removed from service immediately, where reasonably practicable use a
safe means of access.
Emergencies All emergency notices displayed, all personnel induction will include
emergency alarms escape routes/directional notices. Emergency
procedures displayed, first aid identified and drills carried out.
Communications Tool box talks on regular basis, safety reminders.
COSHH Not Applicable
PPE Safety helmets, gloves, safety footwear.
Other Ladders should only be used for short term work, and priority must be given
to other forms of access particularly if plant or equipment is to be used at
height. Operate Permit system.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 89
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 69


Assessment for: LEAD BURNING/PLUMBING WORK - Lead burning(welding) of lead sheet or
pipe
Significant risks: Inhalation, ingestion or absorption of the toxic substance.
Manual handling heavy lead, fire, lead spatter from molten lead.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information / Instruction / Specific risk assessment and safety method statement explained to
Training operatives copies issued as requested and signatures obtained. Daily
briefings of operatives by supervisors.
Safety induction carried out and signatures obtained. Manual handling
training required, operatives should be informed of associated hazards and
relevant control measures before work begins, operatives should have
received extensive trade &safety training in this work, operatives should be
trained in fire prevention and use of fire extinguishers.
Managers/supervisors should be adequately trained to monitor work.
Supervision Adequate levels of competent supervision to be maintained.
Supervision to update general risk assessment as project progresses.
Ensure workplace is inspected prior to operative placement. Ensure that
safety equipment provided is used correctly and control measures followed.
Ensure "Hot Work" permit system used.
Access Ensure safe access and egress is provided and of sufficient width. Identify
all aspects of access on safety method statement, ensure routes are free of
debris and are maintained in a safe condition. Work to be planned so that
only one trade working in an area at a time. Proper and suitable access
equipment to be provided.
Environment Eating, drinking and smoking prohibited in all areas likely to be
contaminated by lead. Adequate washing & changing facilities
provided/used by operatives to ensure good personal hygiene, workers
must wash hands/arms thoroughly & scrub under nails to remove traces of
lead.
Equipment All equipment must be inspected and maintained in a good condition.
Firefighting equipment must be inspected and be of a suitable type.
Emergencies All emergency notices displayed, all personnel induction will include
emergency alarms escape routes/directional notices. Emergency
procedures displayed, first aid identified and drills carried out.
Communications Tool box talks on regular basis, safety reminders.
COSHH The degree of exposure to lead should be assessed by a competent person
to determine if exposure is significant or not, where exposure significant
local exhaust ventilation should be used to reduce exposure levels to an
insignificant level.
Medical surveillance should be carried out if exposure is significant
PPE Appropriate personal protective equipment (PPE) should be issued to and
worn by operatives, this will include safety helmets, safety footwear, gloves,
eye protection, respiratory protection and cover-alls. No contaminated
clothing or PPE should be taken into canteens/welfare facilities.
Other

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 90
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 70


Assessment for: MOBILE ELEVATED WORKING PLATFORMS

Significant risks: Falls of persons, falls of materials, striking against fixed structures,
collision with other plant, overturning platform.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information / Instruction / Specific risk assessment and safety method statement explained to
Training operatives copies issued as requested and signatures obtained. Daily
briefings of operatives by supervisors.
Safety induction carried out and signatures obtained.
Only trained and certificated operatives to operate plant.
Supervision Adequate levels of competent supervision to be maintained.
Supervision to update general risk assessment as project progresses.
Ensure workplace is inspected prior to operative placement. Ensure that
safety equipment provided is used correctly and control measures followed.
Access Ensure safe access and egress is provided and of sufficient width. Identify
all aspects of access on safety method statement, ensure routes are free of
debris and are maintained in a safe condition. Work to be planned so that
only one trade working in an area at a time, control traffic and pedestrians,
segregate the work area, beware of use of trailing leads for power tools
(entanglement or tripping).
Environment Ensure ground conditions are suitable
Equipment Inspected and maintained in a good condition. The manufacturer's
maintenance schedule should be followed, proof of maintenance, inspection
and testing must be obtained. Ensure MEWP's SWL (Safe Working Load) is
adequate for the work. Stabilisers used where necessary, MEWP's should
not be moved at height unless designed for it.
Emergencies All personnel induction will include emergency alarms, escape
routes/directional notices. Emergency procedures displayed, first aid
identified and drills carried out. Emergency plan and safety method
statement shall include need to get persons from the platform whilst still
elevated. (Control key available at ground level where needed to operate
controls from that position)
Communications Tool box talks on regular basis, safety reminders.
COSHH Not Applicable
PPE Appropriate personal protective equipment (PPE) should be issued to and
worn by operatives, this will include safety helmets, safety footwear, gloves,
eye protection, respiratory protection and cover-alls depending on work
carried out from platform. Safety harnesses must be worn and secured to a
suitable anchorage point whilst operatives are in the platform.
Other Collision with any structure or other plant should be reported immediately
and the damaged assessed.
NB: frequent accidents occur when operatives trap their hands between the
upper guard rail of the MEWP and fixed structures. Regularly remind
operators of this hazard.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 91
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 71


Assessment for: UNLOADING OF VEHICLES

Significant risks: Being struck by a maneuvering vehicle, falling objects,


falls of persons off the load platform.

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information / Specific risk assessment and safety method statement explained to
operatives copies issued as requested and signatures obtained. Daily
briefings of operatives by supervisors.
Instruction / Training Safety induction carried out and signatures obtained.
Only trained and certificated operatives to act as banks man. Only trained
and certificated operatives to use plant for unloading (cranes, hiab, fork-lift,
excavators). Instruction on loads to be obtained, instruction on safe
methods required eg. Sequences of unloading and release of restraints.
Supervision Adequate levels of competent supervision to be maintained.
Supervision to update general risk assessment as project progresses.
Ensure workplace is inspected prior to operative placement. Ensure that
safety equipment provided is used correctly and control measures followed.
Access Ensure safe access and egress is provided and of sufficient width. Identify
all aspects of access on safety method statement/risk assessment, ensure
routes are free of debris and are maintained in a safe condition. Work to be
planned so that access by traffic and pedestrians is controlled, segregate
the work area.
Environment Ensure ground conditions are suitable, ensure offloading area is as level as
possible, if unloading area is sloping, extra care must be taken with whole
sequence of events. Ensure good standard of lighting for the work area.
Minimise number of people in offloading area.
Equipment All equipment must be inspected and maintained in a good condition.
Ensure SWL (Safe Working Load) of lifting equipment and gear is adequate
for the work, obtain load weights and centre of gravity before moving
anything. Stabilisers to be used where necessary.
Emergencies All personnel induction will include emergency alarms escape
routes/directional notices. Emergency procedures displayed, first aid
identified and drills carried out.
Communications Tool box talks on regular basis, safety reminders. Delivery driver to be fully
consulted and briefed prior to unloading.
COSHH COSHH assessment should be carried out prior to handling potentially
hazardous materials; this should take cognisance of possible spilled
materials.
PPE Appropriate personal protective equipment (PPE) should be issued to and
worn by operatives, this will include safety helmets, safety footwear, gloves,
cover-alls and high visibility clothing. Eye protection, respiratory protection
may be required depending on materials being handled,
Other Wherever possible, minimise human involvement by using mechanical
handling methods, where manual handling is required ensure that enough
trained handlers are available. Follow safe system for release of all load
restraints and sequence of unloading, inspect load for shift prior to release
as load may have worked loose during transit.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 92
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 72


Assessment for: USE OF STEP LADDERS

Significant risks: Falls from heights, contact with overhead power lines,
falling tools & materials

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information Safety induction carried out and signatures obtained. Specific risk
assessment and safety method statement explained to operatives and
signatures obtained. Manual handling training, instruction and training in the
Instruction / Training safe erection, use and lowering of step ladders required. Stress over-
stretching as main cause of falls and never to climb to very top tread / step -
the knees of the person using the step ladder should be kept below the top
of the steps. Daily briefings of operatives by supervisors.
Supervision Adequate levels of competent supervision to be maintained. Supervision to
update general risk assessment as project progresses. Ensure workplace is
inspected prior to operative placement. Check training/instruction given to
all operatives.
Access Ensure clear, well-lit access/egress.
Identify all aspects of access on safety method statement/risk assessment
Environment Sufficient lighting to be provided, area to be kept clear of obstructions.
Step-ladders should only be used on firm, level ground.
If un-insulated over-head power lines are present all operatives to be
informed of potential contact hazard - do not use metal ladders.
Avoid others working near / below the step ladder.
Equipment Where risk assessment dictates a safer means of access should be

used, i.e. mobile access scaffold or mobile elevated work platform

(scissor lift / cherry picker) etc.

Regular inspection of equipment to ensure the treads /steps, bolts, screws


and fixings are sound and secure. Retaining cords or hinges should be
equal length and in good condition, all damaged equipment to be removed
from service immediately. The step-ladder must be stable when open and
standing on a level base. The legs of the step-ladder should be positioned
as far apart as the retaining cord or hinges allow, with all four legs firmly on
the ground. They should be set at right-angles to the work, whenever
possible.
Emergencies All emergency notices displayed, all personnel induction will include
emergency alarms escape routes/directional notices. Emergency
procedures displayed, first aid identified and drills carried out.
Communications Safety awareness talks on regular basis, safety reminders.
COSHH
PPE Safety helmets, gloves, safety footwear, overalls. The use of plastic over-
shoes should be avoided on step-ladders.
Other Step-ladders should only be used for short-term work or where space
restricts the use of safer working places particularly if plant or
equipment is to be used at height.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 93
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 73


Assessment for: TRAFFIC MANAGEMENT

Significant risks: Impact injury to workforce/accidents to public and vehicles

CONTROL ITEM DETAILS OF CONTROL MEASURES


Information A full traffic management scheme detailed out which caters for: flow of
public vehicles; access and egress of work vehicles; safety zones;
pedestrian routes; provision for Emergency Services. Method statements
for installation of such schemes will also be required on major schemes.

Instruction To include all identified requirements of safe system of work and method
statements.
Training Layout drawings, appropriate experienced personnel only to be used for
actual installation/removal of traffic management works.

Supervision An experienced member of staff to be nominated as the Traffic Safety Co-


ordinator to check all traffic management works and monitor systems.
Access By designated signed access and egress points only. Prevent unauthorised
access.
Environment Adverse weather to be taken into consideration. Glare, live traffic, lighting,
snowing, any obscured traffic signs must be cleaned as soon as reasonably
practicable or work stopped if practicable
Equipment Suitably marked vehicles with flashing lights if required. Assess the need
for a planned preventative maintenance scheme.
Emergencies Emergency lane if required. Emergency call out/liaison list to be
established. Vehicle recovery to be in attendance if specified. Standard
site first aid, fire protection, evacuation, accident reporting and investigation.
Emergency procedures to be detailed in contract safety plan.
Communications Radios for traffic management team. Mobile phones/radios for traffic safety
co-ordinator. Information signs. Close liaison with police.
COSHH No Applicable

PPE High visibility clothing, hard hats, etc.

Other Ensure adequate provision of spare signs, cones and markers to cover loss
and waste.

The above controls have been selected to protect the health and safety of operatives and others who may be
affected by the work. This assessment must take into consideration all relevant Company Safety Documents
and must be used when compiling a site specific method/task statement/procedure.
QCS 2014 Section 11: Health and Safety Page 94
Part 2.4.01: Risk Assessment Guides and Method Statement

RISK ASSESSMENT GUIDE REF NO. 74

Assessment for:

Significant risks:

CONTROL ITEM
Information

Instruction

Training

Supervision

Access

Environment

Equipment

Emergencies

Communications

COSHH

PPE

Other
QCS 2014 Section 11: Health and Safety Page 95
Part 2.4.01: Risk Assessment Guides and Method Statement

2.4.20.2 Appendix B: Example of a risk assessment for erecting roof trusses

Contract number / name............................................. Risk assessment number.................................

Risk assessment compiled by...................................... Signature.......................... Position in company..................................

Date risk assessment compiled............................. Date risk assessment due a review ..................

Level of
Risk and identity of persons Assessed level of Action placed on, and
Process Hazard uncontrolled Controls introduced to reduce risk
who might be harmed remaining risk by when
risk

Work at height only carried out by workers who


Serious injury, death (anyone are competent to do so
Workers falling from height High
working at height) Low
A safe working platform with edge protection and
a safe means of access and egress provided

Working platform to be fully boarded and


adequately sheeted or netted. Entrances to
buildings protected by nets or fans. Exclusion
Injury, possibly serious, or death zones to be created and monitored where
Workers being struck by falling from being struck by a falling necessary Site manager
Working at height High
objects object (anyone on site who Low
(general) might be passing below) Debris guards properly fitted to all elevations of Before work at height
working platform starts

All waste materials transferred to ground level via


a waste chute

If possible, arrange for supply to be turned off for


duration of job. As a minimum, arrange for
Electrocution - serious burns electricity supply company to sheath the cables
Presence of live overhead
and death (anyone working at High Toolbox talk on electrical safety given to all who Low
electrical cables
height) will be required to work at height, including
scaffold contractors
If cables remain live, monitoring that safety
distances are being maintained
QCS 2014 Section 11: Health and Safety Page 96
Part 2.4.01: Risk Assessment Guides and Method Statement
Level of
Risk and identity of persons Assessed level of Action placed on, and
Process Hazard uncontrolled Controls introduced to reduce risk
who might be harmed remaining risk by when
risk

All contractors instructed to clear up their waste


Slips and trips at height (anyone materials within a reasonable time of it being
Debris left on scaffold platforms Medium
working at height) created and before it becomes a hazard Site manager
Low
Working at height Waste skips provided to enable the disposal and Before work at height
(general) segregation of waste starts
(continued)

Slips and trips at height and


Work suspended during adverse weather Low
Adverse weather conditions during access/egress (anyone Medium
conditions. Site manager to monitor Low
working at height)

Off-loading trusses from delivery Manual handling injuries


Medium Trusses off-loaded and transported Low
lorry (delivery driver/carpenters)

Raising trusses to roof height Medium Low


Manual handling injuries Roof truss assembly to be prefabricated at ground
(carpenters) level and crane to be hired to lift it into place

Close-boarded scaffold platform, complete with


Falling through trusses whilst Cuts, broken bones, serious guard-rails erected at eaves height. Consider Site manager
High Low
fixing injury, death (carpenters) installing safety nets across span of building if
Erection of roof suitable fixing points and sufficient clear height Before handling of roof
trusses below net are available. Otherwise install soft trusses starts
landing system below

Electricity supply company contacted to establish


Electrocution - serious burns and minimum safe working distance for crane
Presence of live overhead
death (anyone working at height High Low
electrical cables
and crane driver) Lifting operation to be under the control of a
competent person. Safe working distance
between electrical cables and crane to be
maintained at all times
QCS 2014 Section 11: Health and Safety Page 97
Part 2.4.01: Risk Assessment Guides and Method Statement

Risk and identity of persons Level of Controls introduced to reduce risk


Assessed level of Action placed on, and
Process Hazard who might be harmed uncontrolled
remaining risk by when
risk

Contract lift organised using the equipment and


Unstable and unsafe lifting Medium Site manager
staff of a reputable crane-hire company
operation resulting in equipment
Lifting operations Low
failure and/or dropped load Before handling of roof
(anyone in the vicinity) Persons not involved in lifting operation excluded
trusses starts
from the area

Workers being run over or Medium


All plant operated by trained, competent
suffering crush injuries (any site
operators
worker on foot)

Erection of roof Other plant activity Physical segregation of plant and pedestrians as Low
trusses Injury to pedestrians caused by Medium far as is possible
(continued) insecure load falling from
machine (any site worker on foot) Toolbox talk on safe plant operations given to
everyone on site

Person injury resulting from the Low


All tools fit for purpose and maintained in good
use of defective hand tools
condition
(carpenter)
Use of hand tools and power
Low
tools
Electric shock resulting from the Battery tools used where practical. Otherwise
use of defective power tools Medium only 110 volt tools used. Checks made that all
(carpenter) power tools have a current PAT test sticker
QCS 2014 Section 11: Health and Safety Page 98
Part 2.4.01: Risk Assessment Guides and Method Statement

2.4.20.3 Appendix C: Example of a risk assessment for loading out and fixing tiles

Contract number / Name............................................. Risk assessment number.................................

Risk assessment compiled by...................................... Signature.......................... Position in company..................................

Date risk assessment compiled............................. Date risk assessment due a review ..................

Level of
Risk and identity of persons Assessed level of Action placed on, and
Process Hazard uncontrolled Controls introduced to reduce risk
who might be harmed remaining risk by when
risk

Working at height See risk assessment for handling


generally and erecting roof trusses

Abrasions to the skin of the


Rigger gloves to be provided and worn at all
hands potentially leading to Medium Low
times that tiles are being manually handled
dermatitis (tiling contractors)

Manual handling injury from Palletised tiles to be moved to vicinity of where Site manager
Loading out and carrying tiles they will be used by telehandlers
fixing tiles Before manual handling
Strains and other manual Powered inclined hoist to be used to transfer tiles of tiles commences
handling injuries (tiling Medium to roof level. Hoist to be loaded, off-loaded and Low
contractors) operated by a competent person

Toolbox talk on manual handling to be given to


tiling contractors
QCS 2014 Section 11: Health and Safety Page 99
Part 2.4.01: Risk Assessment Guides and Method Statement

Level of
Risk and identity of persons Assessed level of Action placed on, and
Process Hazard uncontrolled Controls introduced to reduce risk
who might be harmed remaining risk by when
risk

Investigate feasibility of electrical supply being


turned off. As a minimum, arrange for electricity
company to sheath cables
Site manager
The presence of live overhead Serious burns and death (tiling Toolbox talks on electrical hazards to be given
High Low
electrical cables contractors) to tiling contractors Before manual handling
of tiles commences
Inclined hoist to be positioned to maintain a safe
working distance from cables

Tiling contractors to observe minimum safety


distance. Site manager to periodically monitor

Loading out and


fixing tiles
(continued)
Necessary load rating of scaffold agreed at
contract stage. Loading bays to be included

Serious injuries or death


Scaffold erected and inspected as necessary by
(anyone working at height or at
Scaffold collapse Medium a competent scaffold contractor Low
ground level in vicinity of
scaffold)
Tiling contractor informed of loading [imitations
around eaves-level working platform. Periodic
monitoring by site manager

Person injury resulting from the Site manager


All tools fit for purpose and maintained in good
use of defective hand tools Low
condition
(carpenter)
Before handling of roof
Use of hand tools Low trusses starts
Slips and trips resulting from
All tools returned to tool box or tool-belt when
tools being left lying around Medium
not in use
(carpenter)
QCS 2014 Section 11: Health and Safety Page 100
Part 2.4.01: Risk Assessment Guides and Method Statement
2.4.20.4 Appendix D: Suggested Structure for Written Method of Work (Section 1.1.7 of
the Regulatory Document)

The structure for a complete written method of work is composed of:


(a) Site Checklist template,
(b) theThe Method Statement and
(c) theThe Inspection and Tests plan.

A suggested template for the Site Checklist and the Method Statement are given below. A template
for the Inspection and Test plan can be found in Section 2.

(A) SITE CHECKLIST TEMPLATE

Occupational Health and Safety Checklist / Questionnaire Template

Affairs : Department :

Project Manager : Project Name :


Project Starting Project Completed
Date: Date:
Consultant : Project No. :

Contractor : Inspection Date : Report No.:

Completion & Stamped By Consultant andthen Reviewed &/


Approved By Project Manager (Mob: ------------------)

Satisfactory
Comments /
Item Description Submission
Yes No N/A Hold Points
Date (If No)
Ref. to: (QCS: 1.10.1.8/9/14 + 1.10.2 + 11.1.1
+ 11.2.1 + 11.2.3 + 11.2.4).
1 MANAGEMENT
(CDD / Fire Safety Handbook / Building
Worksite Safety / 3 Page 35).
OH&S plan submitted for approval Within 30
days of the award of the contract?
OH&S organization chart available
OH&S Policy displayed
Regular meetings record
Responsibilities defined
Near Miss & Hazard reporting and follow up
Provision for visitors
Monitoring effectiveness implementation of
OH&S program
Generic Risk Assessment & Management
Monitoring & Control Sub-contractor to
comply with all existing rules & regulations?
In general, contractor following the
government rules & regulation.

2 SAFETY STAFF Ref. to: (QCS: 1.10.1.3 + 11.1.1.8 + 11.2.1.5).


OH&S Safety Staff CV submitted for
approval within 30 days of the award of the
contract?
QCS 2014 Section 11: Health and Safety Page 101
Part 2.4.01: Risk Assessment Guides and Method Statement
Satisfactory
Comments /
Item Description Submission
Yes No N/A Hold Points
Date (If No)
OH&S Officer available during all working
hours
OH&S Officer is exclusive for site & for H&S
jobs

Ref. to: (QCS: 11.1.1 + 11.2.2 + 11.2.3.6).


3 TRAINING
(Labor Law: Article 99).
Orientation / Site Induction
Tool Box Talk (TBT) daily documented
Task specific (Equipment Operators,
Scaffolders, Riggers, Fire Watchers,
Emergency Drill, etc)
Management
Refresher courses

Ref. to: (QCS: 1.10.9 + 1.10.10 + 11.1.2 +


11.2.2 + 11.2.3.15).
4 WORK ENVIRONMENT (Worker Rights Booklet 2009 Page 41
& 45). (CDD / Fire Safety Handbook /
Building Worksite Safety / 3 Page 9 & 10).
Ventilation
Removal of fumes and dust
Dust controls preventive measures
Noise levels (instrument available?)
Vibration
Lighting:
General purpose for evening work
For a particular task around construction
site
Absence of glare
Work area
Corridors
Exterior
Ergonomics - layout of work area
The disposal of surplus water and the
accompanying growth of trees and the
proliferation of insects and rodents
Does the site pose danger to the
surrounding environment?
Site office furniture?

Ref. to: (QCS: 1.10.9 + 1.10.10 + 11.1.2)


5 WELFARE FACILITIES
(Labor Law: Article 103,106 & 107).
Clean toilets with exhaust fan
Toilets & Sanitary in good condition?
Potable water provided
Eating and resting areas
Messing / Canteen facilities
Washing facilities
Regularly cleaned area
Work clothes lockers and hanging areas
Prevent the breeding of mosquitoes on the
site
QCS 2014 Section 11: Health and Safety Page 102
Part 2.4.01: Risk Assessment Guides and Method Statement
Satisfactory
Comments /
Item Description Submission
Yes No N/A Hold Points
Date (If No)
Ref. to: (QCS: 1.10.6 + 11.1.2.4 + 11.1.6 +
6 FIRST AID & MEDICAL 11.2.2 + 11.2.3). (Labor Law: Article
100,104,105 & 115).
Less than 100)
Paramedics available & names displayed First Aider
(according to number of workers) (100) above
Average Manpower = ---------------------- Nurse
Labor (500) Above
Doctor &Nurse
Accident reporting, records available &follow
up
Periodic medical examinations for workers and
follow up
Medical record book existing
Paramedics Telephone numbers displayed
Adequate first aid kits supplies & expiration First aid box
dates (as per Hamad Medical Corporation for each 25
Requirement) labor
(500) Above
Adequate first aid equipment
Clinic
Availability of stretcher / ambulance /
Standby Vehicle
Clean room with potable water supply
Doctor, Site Nurse & Site Clinic must be
approved from Supreme Council of Health

Ref. to: (QCS: 1.10.7.2).


(Labor law: Article 100).
7 EMERGENCY EQUIPMENT (CDD / Fire Safety Handbook / Fire Safety
Provisions For Construction Worksites / 2
Page 16).
Procedures
Assembly / Muster point
Conducted Emergency Drill Training every 6
month
Availability of Fire / Smoke / Gas detection
mobile devices
Emergency contact telephone numbers /
Communications
Breathing apparatus and / or respirators (if
applicable)
Torches
Loud Hailer
Emergency lighting
Adequate and safe Emergency Exit / Doors
are provided
Escape routes, access ways to assembly
points, extinguishers, hydrants and other
firefighting equipment's and first aid kits kept
clear of obstruction at all times

Ref. to: (Labor Ministry Decision No. 20 of


2005). (CDD / Fire Safety Handbook / Fire
8 HOUSEKEEPING & TIDINESS
Safety ProvisionsSafety Provisions For
Construction Worksites / 2 Page 17).
Segregation of waste and scrap
Sufficient bins
QCS 2014 Section 11: Health and Safety Page 103
Part 2.4.01: Risk Assessment Guides and Method Statement
Satisfactory
Comments /
Item Description Submission
Yes No N/A Hold Points
Date (If No)
Waste and scrap regularly collected &
removed from site
No build up of flammable materials
Removal of combustibles

Ref. to: (QCS: 11.1.2.7).


(Worker Rights Booklet 2009 Page 45).
(CDD / Fire Safety Handbook / Fire
9 STORAGE - RACKS, BINS, SHELVES Safety ProvisionsSafety Provisions For
Construction Worksites / 2 2 Page 10).
(CDD / Fire Safety Handbook / Building
Worksite Safety / 3 Page 12).
Aisles and walkways kept clear
Neat and orderly
Not too high
Heavy items kept low
Sufficient space to access items
Are chemicals, paints, flammable liquids and
gas cylinders stored only in designated
areas?

10 SITE SECURITY & ACCESS Ref. to: (QCS: 1.10.9.2 + 11.1.1.12).


Adequate transportation between working
site & accommodations
Security check correctly performed
Guardhouse continuously manned
Round check register updated
Perimeter fence intact
Inspection of materials gate passes
Need for the existence of surveillance
cameras inside the site
Need for security personnel within the site

Ref. to: (QCS: 1.10.9.2 + 11.1.2 + 11.2.3).


11 PERSONAL PROTECTIVE EQUIPMENT
(Labor Law: Article 101).
Coveralls
Eye protection
Head protection
Hand protection
Foot protection
Hearing Protection
Safety reflecting vests
Dust mask
Any other protection

Ref. to: (Worker Rights Booklet 2009 Page


12 SAFE WORK PRACTICES
45).
Avoid manual handling (Use mechanical
handling equipment)
Not working alone
Cap (cover) for rebar / reinforcement steel
QCS 2014 Section 11: Health and Safety Page 104
Part 2.4.01: Risk Assessment Guides and Method Statement
Satisfactory
Comments /
Item Description Submission
Yes No N/A Hold Points
Date (If No)
Ref. to: (QCS: 1.10.5.5 + 11.1.5.4 + 11.2.2 +
11.2.3).
13 EXCAVATIONS (CDD / Fire Safety Handbook /
Building WorksiteBuilding Worksite Safety /
3 Page 19).
Location of existing utilities confirmed
Signs posted
Adequate hard barrier installed
Adequate warning tape & lighting
Bracing & Shoring provided (if applicable)
1m spoil clearance from the excavated pit
Sloping maintained (if applicable)
Correctly made ladders provided for access
into excavation
Appropriate access provided (temporary
bridges & footpaths)

Ref. to: (QCS: 1.10.5.3 + 11.1.1.4).


(Worker Rights Booklet 2009 Page 46).
14 MECHANICAL
(CDD / Fire Safety Handbook / Building
Worksite Safety / 3 Page 10).
Adequate guarding on machines
Inspected regularly with color code sticker &
maintenance records
Grounding installed to equipment/machine
Unused machines electrically isolated
Emergency isolation switches
Safety devices
Heating equipment

Ref. to: (QCS: 1.10.5.14 + 11.1.5.3 + 11.2.2).


(Worker Rights Booklet 2009 Page 46).
15 ELECTRICAL
(CDD / Fire Safety Handbook / Building
Worksite Safety / 3 Page 10).
Insulation, cables, industrial plugs in good
condition
Cables suspended using S hooks and lead
stands
Inspected regularly with color code sticker
ELCB provided to site power boards
Qualified electrician hired to install (Name &
Qualification)
Protection of fittings against external
damage
Trailing leads used?
Ovens and furnaces in good condition?

Ref. to: (QCS: 1.10.5.10 + 11.1.3 + 11.2.3.12).


16 SCAFFOLDS & LADDER (CDD / Fire Safety Handbook / Building
Worksite Safety / 3 Page 19).
Certified scaffold supervisor and scaffolders
Scaffolds correctly erected
Scaffolds properly secured
Toe boards, guardrails (top & mid rail),
handrails & access checked
QCS 2014 Section 11: Health and Safety Page 105
Part 2.4.01: Risk Assessment Guides and Method Statement
Satisfactory
Comments /
Item Description Submission
Yes No N/A Hold Points
Date (If No)
Fully boarded platforms
Scaffolds correctly tagged
Materials in good condition

Ref. to: (QCS: 1.10.5.13 + 11.1.3 + 11.2.3).


17 WORKING AT HEIGHT (CDD / Fire Safety Handbook / Building
Worksite Safety / 3 Page 11, 12 & 19).
Personnel working above 1.2 m using fall
protection devices
Fall protection devices condition / Certificate
Adequate safe access in place to working
height elevations
Personnel properly trained in the selection
and use of fall protection devices
All loose material & tools at heights secured
or removed

Ref. to: (QCS: 1.10.5.3 + 11.1.4 + 11.2.2 +


18 PLANT & EQUIPMENT
11.2.3.5/10).
Qualifications of operators available
Available Qatar license for drivers /
operators
Banks man available
Used as per its design (for intended
purpose)
Vehicle and equipment condition
Reverse alarm installed
Flashing light installed
Generators and welding machine in good
condition?
Compressors and water pumps in good
condition?
Oil / fuel leak causing environmentally
pollution

Ref. to: (QCS: 1.10.5.8 + 11.1.4 + 11.2.3.10).


(Worker Rights Booklet 2009 Page 45).
19 LIFTING OPERATIONS
(CDD / Fire Safety Handbook / Building
Worksite Safety / 3 Page 19).
Available Qatar license/third party certificate
for operators and certificate of training for
banks men and riggers
Load capacity displayed
Certification updated
Condition of access and ground
Lifting locations barrier off
Outriggers/supports fully extended
Hoist limiting device and SWL indicator
working

Ref. to: (QCS: 1.10.5.9 + 11.1.4 + 11.2.3.10).


(Worker Rights Booklet 2009 Page 45).
20 LIFTING GEAR
(CDD / Fire Safety Handbook / Building
Worksite Safety / 3 Page 19).
QCS 2014 Section 11: Health and Safety Page 106
Part 2.4.01: Risk Assessment Guides and Method Statement
Satisfactory
Comments /
Item Description Submission
Yes No N/A Hold Points
Date (If No)
Ropes, Chains, Shackles etc. in good
condition
Identity number and SWL displayed
Color-code system in place
Available 3rd party certificate for every lifting
gear
Damaged lifting devices removed from the
workplace

21 COMPRESSED GAS CYLINDERS Ref. to: (QCS: 1.10.5.12 + 11.1.2.14).


Stored upright, valves protected
Regulators Gauges working; hoses
inspected
Flashback arrestor fitted
Cylinders are securely tied or with trolley
Type of gas clearly marked on cylinders
Segregation of incompatible gases
Transported on appropriate trolley
Correct signage

22 SAFETY OF THE PUBLIC (For Road Works) Ref. to: (QCS: 1.10.5.4 + 1.10.8 + 11.1.1.10).
Approval from PWA, then from Traffic Dep.
& Environmental ministry
International Warning signs
Warning yellow lights
Adequate Barricades (to comply with Traffic
law no. 19)
Railing
Pedestrians pathway signs & not interacted
with work zoon
Adequate safe access to all properties
Night watchman available
To provide road hump to reduce & control
speed with approval from Traffic
Department.

Ref. to: (QCS: 1.10.1.6 + 1.10.5.6 + 11.1.8.2).


23 SAFETY SIGNAGE & NOTICE BOARD
(Labor Ministry Decision No. 20 of 2005).
Clearly displayed
Shall be in Arabic, English & other
languages
Clean and legible
Enough traffic diversion signboard?
Adequate warning signs and guides are
provided
Shall be fully illustrated and provide details
of key safety procedures to be followed

24 WORK PERMITS Ref. to: (QCS: 1.10.5.1/4/11 + 11.2.2 + 11.2.3).


Confined Space
Hot Work
Excavation
Scaffolding
QCS 2014 Section 11: Health and Safety Page 107
Part 2.4.01: Risk Assessment Guides and Method Statement
Satisfactory
Comments /
Item Description Submission
Yes No N/A Hold Points
Date (If No)
Electrical Work
Work permit correctly issued and signed
Ashghal s work permit enforced

Ref. to: (QCS: 1.10.7 + 11.1.7 + 11.2.2 +


11.2.3.13).
25 FIRE PROTECTION / PREVENTION (Fire Safety Handbook / Fire Safety
Provisions For Construction Worksites / 2
Page 8).
Is the firefighting equipment which approved
by Civil Defense available at working area?
Welding and grinding at working area
properly secured
Firefighting equipment not obstructed
Expiration date of firefighting equipment
checked.
Monthly firefighting equipment visual
inspected & recorded
Availability of Fire / Smoke / Gas detection
system
Alarm and Emergency Evacuation system
Are Alarms audible in all areas
Minimum quantities of flammable material
shall kept on site with full precautions
required
Access for Fire Brigade cleared

Ref. to: (QCS: 11.1.2.3 + 11.2.2 + 11.2.3).


26 HAZARDOUS SUBSTANCES (CDD / Fire Safety Handbook / Building
Worksite Safety / 3 Page 15, 16, 17 & 18).
Toxic/ hazardous substance correctly
tagged/ labeled and secured
Adequate & proper storage provided
Appropriate spill containment provided
Disposal Spill kit (location, appropriate, easy
access)
Material Safety Data Sheet (MSDS) present
& required training delivered to concerned
employees
Class B fire extinguisher near by
Correct signage
Register of chemicals
Correct labeling

Ref. to: (QCS: 1.10.5.7 + 11.1.5.5).


27 CONFINED SPACES (CDD / Fire Safety Handbook / Building
Worksite Safety / 3 Page 13 & 14).
Gas detectors/monitors with rechargeable
batteries and battery charger (2 No.)
Full body safety harnesses with lifelines and
shackles (6 No.)
Lifting frame with fall arrest device (1 No.)
Constant flow escape breathing apparatus
complete with storage cases (2 No.)
QCS 2014 Section 11: Health and Safety Page 108
Part 2.4.01: Risk Assessment Guides and Method Statement
Satisfactory
Comments /
Item Description Submission
Yes No N/A Hold Points
Date (If No)
Automatic positive pressure self contained
breathing apparatus with storage case (1
No.)
To train employee for confined space activity
& supervision monitoring
All equipment maintained & calibrated up to
date with 3rd party certificate (record is
available)

28 OTHER RELATED SAFETY ITEMS













QCS 2014 Section 11: Health and Safety Page 109
Part 2.4.01: Risk Assessment Guides and Method Statement

Key Performance Indicator (KPIs)


Indicator No. Description No. Per Last Month Accumulating up to Date
1. No. of Medical Treatment Cases
2. No. of First Aid Cases
3. No. of Near-Miss
4. No. of Fatal Cases
5. No. of RTA (Road Traffic Accidents)
6. No. of Manpower (Average)
7. No. of Direct Man-hours
8. No. of Hours Lost
9. No. of Man-hours from Last Lost Time Accident
10. No. of Lost Time Accidents
11. No. of Safety Meeting
12. No. of Emergency Drill
13. No. of Audit
14. Kilometres Driven
Accumulative Accident Rate = (Clasue1+4+5+10) x 100,000

Caluse6 (No. of Manpower Average)

Monthly Accident Rate = (Clasue1+4+5+10) x 100,000

Caluse6 (No. of Manpower Average)

Accumulative Frequency Accident = (Clasue1+4+5+10) x 1000,000

Caluse7 (No. of Direct Man-hours)

Monthly Frequency Accident = (Clasue1+4+5+10) x 1000,000

Caluse7 (No. of Direct Man-hours)

Consultant Name:
Filled By: Mob. No.:
Signature:
Date:
Stamp:

References:
QCS (Qatar Construction Specification Latest Edition).
Labor Law No. 14 of the year 2004.
Qatar Traffic Law No. 19 of the Year 2007.
Environmental Protection Law No. 30 of the Year 2002.
CDD (Civil Defense Department) Fire Safety Handbook.
Law No. 13 of 1997 - Civil Defense
Law No. 9 of the Year 2012 - Amending some provisions of Law No. 13 of 1997
Concerning the Civil Defense
Worker Rights Booklet 2009 (National Human Rights Committee).
QCS 2014 Section 11: Health and Safety Page 110
Part 2.4.01: Risk Assessment Guides and Method Statement

Site Checklist Approval Log (Supplementary Element Specific Log)

SITE APPROVAL LOGCHECKLIST


(TITLE / NAME) REF: Issue:
To be signed before work activity is undertaken

Work Activity:

PROJECT NAME:

Corridor No: Corridor Name:

LOCATION FROM: COMMENTS:

Approvals: signature/date
Checks
Contractor Engineer Other

1
(locate & confirm), Check corridor
e.g: Check licenses are received

specific Environmental issues,


arrangements, Check utilities
from MOPW, Check TM

3
etc

Note:
Contractor to ensure that checklist is signed off by all relevant parties before work activity can begin

Confirmation that work completed in accordance with contract, safety and quality
requirements:
Construction Manager: date:

HSEQ Manager: date:


QCS 2014 Section 11: Health and Safety Page 111
Part 2.4.01: Risk Assessment Guides and Method Statement

(B) METHOD STATEMENT TEMPLATE


Project Name:

Method Statement Number:

Work Activity:

Prepared By: Date:

Reviewed By: Date:

Approved By: Date:

Item Person
Responsible
1 PURPOSE, SCOPE AND LOCATION MAP INCLUDE PERSONS
WITH RESPONSIBILITY
BRIEF DESCRIPTION OF THE CONTENT OF THIS MS, THE PURPOSE AND DETAIL ON THE SCOPE OF
FOR TASK
WORKS. AND INCLUDE LOCATION MAP AND REFERENCES

2 MANDATORY INDUCTION, TRAINING, SUPERVISION AND WHO IS RESPONSIBLE


INSTRUCTION REQUIREMENTS FOR MAKING SURE
WORKERS ARE
LIST ALL MANDATORY REQUIREMENTS FOR THE WORK ACTIVITY IN TERMS OF INDUCTED, TRAINED
INDUCTION FOR THE WORK
TRAINING ACTIVITY, WORKS ARE
INSTRUCTED AND
INSTRUCTION
SUPERVISED E.G. SITE
SUPERVISION
ENGINEER/
SUPERVISOR
3 PRELIMINARIES WHO IS RESPONSIBLE
TO MAKE SURE THAT
LICENSES RELEVANT LICENSES,
TRAFFIC MANAGEMENT TMS ETC ARE IN PLACE
DETECTION AND ISOLATION OF UTILITIES AND COORDINATING

DISCONNECTION/ RECONNECTION OF SERVICES AND MANAGING


UTILITY WORKS

4 SEQUENCE OF WORKS INCLUDE PERSONS


WITH RESPONSIBILITY
WRITE OUT THE JOB PROCEDURE STEP BY STEP FOR AUTHORISING A
USE ACTIVE, NOT PASSIVE VOICE CONTINUATION OF
SEQUENCE IDEAS LOGICALLY WORKS AT EACH HOLD

KEEP SENTENCES SHORT AND CLEAR POINT

INCLUDE:
PRECAUTIONS TO BE TAKEN
HAZARDS
HOLD POINTS
PERMIT REQUIREMENTS, COORDINATION, APPROVAL AUTHORITIES ETC
QCS 2014 Section 11: Health and Safety Page 112
Part 2.4.01: Risk Assessment Guides and Method Statement
5 IDENTIFIED HAZARDS/RISKS AND CONTROLS IN PLACE INCLUDE WHO IS
RESPONSIBLE TO
LIST ALL IDENTIFIED HAZARDS AND RISK IMPACTING ON THE WORK ACTIVITY AND THE COMMUNICATE RISKS
CONTROLS IN PLACE AND CONTROLS IN
INCLUDE REFERENCE TO RISK ASSESSMENT PLACE FOR THE WORK
ACTIVITY
6 ENVIRONMENTAL CONSIDERATIONS AND IMAPCT CONTROL ALSO INCLUDE WHO IS
MEASURES RESPONSIBLE FOR
NEIGHBOURHOOD
LIST ENVIRONMENTAL IMPACTS, MITIGATION AND PRECAUTIONS
LIAISON
IDENTIFY PUBLIC NUISANCE AND SOURCES OF NUISANCE FOR NEIGHBOURING
PEOPLE/PROPERTIES

7 MANDATORY PPE FOR THE WORK ACTIVITY E.G SUPERVISOR

LIST ALL IDENTIFIED MANDATORY PPE FOR THE WORK ACTIVITY

8 EMERGENCY PROCEDURES: INCLUDE WHO WILL BE


RESPONSIBLE FOR
IDENTIFY EMERGENCY TYPES AND ARRANGEMENTS INCLUDING SITE EVACUATION
COMMUNICATIONS
WHO IS RESPONSIBLE FOR CALLING THE EMERGENCY SERVICES REGARDING
CONTACT DETAILS FOR OUT-OF-HOURS EMERGENCIES EMERGENCIES

9 QUALITY CONTROLS E.G. QUALITY


MANAGER, SITE
REFERENCE TO INSPECTION AND TEST PLAN NUMBERS
ENGINEER, QUALITY
INSPECTOR
10 INTERFACES WHO RESPONSIBLE TO
COORDINATE
IDENTIFY ALL INTERFACES AND LIAISON REQUIREMENTS IMPACTING ON THE WORK
INTERFACES IMACTING
ACTIVITY ON AND IMPACTED BY
THE WORK ACTIVITY

11 SAFETY OF THE PUBLIC AND OCCUPIERS WHO WILL ENSURE


THAT THE HEALTH AND
DESCRIBE HOW THE HEALTH AND SAFETY OF THE PUBLIC AND OTHERS AS RELEVANT
SAFETY OF THE PUBLIC
WILL BE PROTECTED.

12 RESOURCE PLANNING E.G. SITE ENGINEER,


SUPERVISOR
PERSONNEL
PLANT AND EQUIPMENT
MATERIALS
13 REFERENCES

WORK PROGRAMME
DRAWINGS
RISK ASSESSMENTS
COORDINATION PROCEDURE
WORK CHECKLIST
INSPECTION AND TEST PLAN
ETC

(C) INSPECTION AND TEST PLAN


Refer to Section 2 for template Inspection and Test Plan

END OF PART

You might also like