Relay Testing Procedure
Relay Testing Procedure
Relay Testing Procedure
PRACTICES
PSN RAJU
Programme runs as follows
20-10-14 Introduction on protection
system
Testing practices hands on training using
microprocessor based test kit(MPRT)
PROTECTION SYSTEM
3
COMPONENTS OF PROT. SYSTEM
.
Connectivity of protection
elements
Supporting systems
Protection philosophy
.
protection
Testing of these elements individually
then connectivity
33kv capacitor
132kv line
220kv line
400kv line
Taps=25,
5N,
1.25% voltage raise for each tap
Ihv=70, Ilv=280 amp
CT ratios---100/1 and 400/1
In 5n tap is 87 works well
When for extreme tap 25(worst case),87
may operate for normal conditions.
At 25 tap, voltage raise= 20*1.25%=25%
HV side current=93.3 (from70 amp to 93.3
amp)
Lv side current= 280 amp (no change)
I diff=.93-.7=0.23 so relay operates
Addition to this CT mis-match error due to
tap change, instruments errors further
magnifies the problem.
for External faults(10 times
rated),Idiff=2.3
CONTD..
To overcome this problem, percentage
bias concept introduced in the
differential relay.
%Bias=Iop/Ibias
Bias coils creates restraining force
I bias proportional to load current/
through fault current
I diff vectorial sum of two currents
I diff(actual)>Iop, then relay operates,
otherwise no operation
Case1: normal current(full load)
I op=% bias*I bias=0.3*I bias=
0.3*(0.93+0.7)/2=0.24
I diff=0.23 , which is less than Iop. Hence
no realy operation
Through fault
If=10 times rated
Iop=2.4,
Idiff=2.3 which is again less than Iop
Hence no trip
case2
Internal fault
case3
The operating characteristics of percentage bias differential
relay is shown in the figure.
The current flowing through the operating coil of the relay
should be nearly zero during normal operating conditions and when
external short circuit occurs.
While setting the differential relay on a transformer, the
(mismatch) current through differential element at normal tap and
positive and negative extreme taps are to be computed. Differential
element pickup setting and/or bias settings is adopted based on
maximum percentage mismatch adding some safety margin.
Differential Current = | I1 -I2 |
Bias Setting = | I1-I2 |
-----------
(I1+I2)
C T Ratios and connections for differential relay:
1. A simple rule of thumb is that the CTs on any Wye (Star)
winding of a Power transformer should be connected in delta
and the CTs on any delta winding should be connected in Wye
(Star).
YNyn0,
Dyn11
YNaod11
Yd1
DIFFERENTIAL PROTECTION- CT CONNECTIONS.
STAR / STAR TRANSFORMER
DIFFERENTIAL PROTECTION CT CONNECTIONS.
DELTA / STAR TRANSFORMER (Dy11)
DIFFERENTIAL PROTECTION STAR / STAR
TRANSFORMER
Delta / Delta CTs filter Zero Seq. Current & ensure Stability.
settings
I min-diff
Slope1
Slope2
2nd harmonic
5th harmonic
Transformer protection : Electrical
BASIC SCHEME
Restricted Earth Fault Protection (REF) : -
This relay is operative only for the internal faults of the
transformer and thus fast operating time can be achieved.
SETTING CRIETERIA
If B-CTfullyactivewhile
IfRelaycurrentsettingisIs
= Vs/Is Zr Ohms.
Fault current for external fault If = 2500 A (assume)
C.T.Ratio (line and neutral) - 300/1 A
2500
Secondary fault current = ------ = 8. 33 A (Sec.)
300
RCT = C.T. Resistance
TL = Lead Resistance = 7.41 Ohms/Km (2.5 sq mmCu)
Voltage developed across CT (Saturated)
(Vk) = If (RCT + 2RL)
= 8.33(5 + 3)
= 66.64 Volts
Relay burden = l VA
Relay Operating
Current = 0.2 A (Set value)
Relay Operating Voltage
VR =
Relay burden
------------------
Relay Operating current
= 1/0.2 = 5 Volt
Stabilizing Resistor SR = VK - VR
-----------
ISet
= 66.64 - 5.0
---------------
0.2
= 308.2 Ohms
Set SR = 310 Ohms
If the calculated value of SR exceeds the existing range, the
current settings can be raised accordingly and arrived at suitable
SR value.
REF for AUTO
TRANSFORMER
Over current relays
DT relays
IDMT relays
Current setting
Time setting
DT RELAYS
Over current Protection
Definite (Independent) Time Relays
TIME
TOP
IS Applied Current
(Relay Current Setting)
PS,TMSare two settings available for
adopting
PSM,TIME---are X-axis,Y-axis respectively
---plays in getting inverse
curve
IDMT relays
Over current Protection
IDMT
TIME
IS Applied Current
(Relay Current
Setting)
Inverse Definite Minimum Time characteristic
Over current Protection
IEC Characteristics
1000
SI t = 0.14
(I0.02 -1) 100
VI t = 13.5
(I2 -1) SI
1
LTI t = 120 VI
(I - 1) EI
0.1
1 10 100
Current (Multiples of Is)
CFB
TURE
DOBLE
OMICRON
FREJA
CHAINA KIT(PUNOVA)
TESTING KITS
OVER CURRENT RELAYS
Starting current & IDMT characteristics
verification
Starting current = current at which disc
starts/start LED glows
IDMT
Current applied to relay= PSM*PS
Time of operation = time*TMS
Graph of normal inverse characteristic(IDMT)
1.35 2 4 10 20 PSM
30 10 5 3 2.2 time
DIRECTIONAL RELAYS
Distance Relays: -
Introduction:
Measuring units: -
They are generally of a mho or reactance
or a combination of mho, reactance and
resistance types.
Phase Fault Units:-
Auxiliary relays: -
Distance scheme comprises of several
auxiliary relays, which perform functions
such as flag indications, trippings,
signaling, alarm etc.
Additional Features in distance
schemes: -
i) Transient Faults:-
These are cleared by the immediate
tripping of circuit breakers and do not recur
when the line is re-energised.
v) Reclaim Time:-
The time following a successful closing
operation measured from the instant the
auto-reclosing relay closing contacts making
which must elapse before the auto-reclosing
relay initiated another reclosing attempt. In
other words, it may be said to be the time
between 1st and 2nd re-closure.
Types of Auto-reclosing schemes (based
on phase):
a) Three phase Auto-reclosing:
This type of auto-reclosing causes an
immediate drift apart of the two systems and
hence no interchange of synchronizing power
can take place during the dead time.
b) Single Phase Auto-reclosing:
In this only the faulty phase (which already
has tripped on SLG fault) is reclosed without
causing interruption in interchange of
synchronizing power between two systems
through other two healthy phases.
Types of Auto-reclosing schemes (case on
attempts of
reclosure):
a) Single Shot Auto-reclosing:-
In this scheme, breaker is reclosed only once
on a given fault before lockout of circuit
breaker occurs. High speed auto-reclosing for
EHV system is invariably single shot.
b) Multi-shot Auto-reclosing:-
In this scheme, more than one reclosing
attempt is made for a given fault before
lockout of the circuit breaker occurs.
Repeated closure attempts with high fault
level would seriously affect the circuit breaker,
i) Circuit Breaker Limitations:-
Ability of circuit breaker to perform several
trip close operations in quick succession.
i)132 KV Lines: -
A switched type distance scheme
supplemented by three numbers directional
O/L relays and 1 No. directional E/L relay.
ii) 220 KV Lines: -
Two Distance Schemes: -
Main-I: - Non-switched scheme fed
from bus PT.
Main-II: - A switched scheme fed from
line CVT.
A provision is generally made for the
changeover of voltage supply for the
distance schemes from the bus PT to line
CVT and vice-versa.
Each distance scheme is fed from
independent CT secondary cores.
iii) 400 KV Lines:-
Two Distance Schemes:-
Main-I:-Non-switched or Numerical
distance schemes
Main-II:-Non-switched or Numerical
distance schemes
Recording devices have existed for many years,
from the first ink chart recorders to the digital
recording equipment available today.
Modern digital equipment has the capability to
monitor a larger number of analog and binary
inputs that could not be monitored in the earlier
disturbance recording devices. The introduction
of microprocessor relays provided another
method of disturbance recording.
The increased capability of disturbance recording
devices and microprocessor relays with
Disturbance Recorders
disturbance recording capability, have created
analysis challenges for the engineer.
Disturbance - Any perturbation to the
electric system.