17thedition Mock Exam3
17thedition Mock Exam3
12. The prospective short circuit current at the origin of the consumers
installation must be taken into account when:
a) assessing the value of the external earth loop impedance
b) selecting the number of ways required for the main distribution
board
c) assessing the methods to be used to provide basic protection
d) selecting the type of overcurrent protective device to be installed
15. The requirements for both basic and fault protection can be provided
by SELV. One suitable source of SELV would be a:
a) 50 V storage battery
b) 230 V diesel generator
c) 230/110 V single phase generator
d) 230/50 V auto-transformer
18. SELV can be used as a means to meet the requirements of both basic
and fault protection. In such cases the nominal voltage must not
exceed:
a) 12 V ac
b) 25 V ac
c) 50 V ac
d) 110 V ac
20. The fault current due to an earth fault of negligible impedance in a 400
V, three phase, four wire circuit having an earth loop impedance of 0.3
ohms, is:
a) 1383 A
b) 767 A
c) 124.5A
d) 72A
25. A fault current caused by the line and neutral conductors to come in
contact with each other is referred to as:
a) an earth fault
b) an overload fault
c) a short circuit fault
d) an open circuit fault
30. When 13 A socket outlets are wired from a fused spur using 70o
thermoplastic insulated cable with copper conductors, the minimum
conductor size permissible is:
a) 1.0 mm2
b) 1.5 mm2
c) 2.5 mm2
d) 4.0 mm2
31. The correction factor for a cable surrounded by thermal insulation for a
length of 200 mm is:
a) 0.5
b) 0.63
c) 0.75
d) 1.0
36. The rating factor to be applied for eight equally loaded circuits grouped
together in conduit is:
a) 0.54
b) 0.52
c) 0.50
d) 0.71
40. Regulation 434.5.2 gives the maximum time which may be permitted
for a fault to be maintained without damaging the conductors. Assume
a prospective fault current of 1000 A with a copper 25 mm2 cable with
70o C thermoplastic insulation. The clearance time (t) is:
a) 7.2 s
b) 8.2 s
c) 5 s
d) 0.4 s
43. Heating cables laid directly in soil, roads or building structures must be
installed so that they are:
a) at least 1 m below the surface
b) fed only from an extra-low voltage supply
c) completely embedded in the substance which they are intended
to heat
d) operated at 5o C
46. The correct grouping factor for 6 circuits of three conductors per circuit,
run in the same conduit is:
a) 0.45
b) 0.54
c) 0.57
d) 0.6
47. Which one of the following does NOT determine the frequency of
periodic inspection and testing of an installation?
a) formal qualifications of the inspection and test staff
b) the type of installation
c) frequency of maintenance
d) any external influence to which it is subjected
48. Every new installation on completion and before being energised must
FIRST be:
a) subjected to a detailed inspection
b) tested for continuity of ring circuit conductors
c) tested for continuity of protective conductors
d) given a test for insulation resistance
49. Which one of the following items should be included for checking
during the initial verification of an installation?
a) site works orders and alterations
b) presence of all diagrams and instructions
c) electrical contractors site diary
d) all variations of contract
50. Which one of the following British Standards covers residual current
devices?
a) BS EN 61008
b) BS EN 60898
c) BS EN 60947
d) BS EN 60742
57. For all caravans using a mains electricity supply, an instruction notice
must be fixed:
a) at or near the main distribution point
b) under the cover of the caravan electricity inlet box
c) near the main electrical isolating switch inside the caravan
d) on the inside of the main door of the caravan
59. Which one of the following may be installed inside Zone 1 of a hot air
sauna?
a) a ceiling mounted cord operated light switch
b) a shaver socket to BS 3535
c) a thermostat attached to the side of the sauna
d) any equipment to IP2X