The document outlines the information and documentation required to be submitted to the Chief Controller of Explosives (CCOE) for preliminary and final approval under the Petroleum Act. For preliminary approval, details of facilities, unit plots, layouts, tank specifications and piping plans are required. For final approval, as-built versions of the same documents plus tank design details, safety certificates, and electrical installation reports must be submitted. Electrical installation approval requires comprehensive design and test reports certified by recognized bodies. All documents must be submitted in duplicate for preliminary approval and quadruplicate for final approval.

Uploaded by

prashant_dc_in
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
253 views2 pages

Cce Documents Requirementunder CCOE

The document outlines the information and documentation required to be submitted to the Chief Controller of Explosives (CCOE) for preliminary and final approval under the Petroleum Act. For preliminary approval, details of facilities, unit plots, layouts, tank specifications and piping plans are required. For final approval, as-built versions of the same documents plus tank design details, safety certificates, and electrical installation reports must be submitted. Electrical installation approval requires comprehensive design and test reports certified by recognized bodies. All documents must be submitted in duplicate for preliminary approval and quadruplicate for final approval.

Uploaded by

prashant_dc_in
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

LIST OF DOCUMENTS / INFORMATION REQUIRED TO BE SUBMITTED

FOR CCOE APPROVAL UNDER PETROLEUM ACT

For Preliminary Approval

1. Details of all facilities with process write up.

2. Unit plot plans / equipment layout, plan & elevation drawing clearly indicating
the premises proposed to be licensed, made in line with the guidelines as specified
in Petroleum rules.

3. Layout of surrounding facilities & all protected works lying within 100 mtr. of the
edge of all facilities which are proposed to be licensed.

4. Technical detail of all storage tanks including position, capacity, MOC elevation
& plan view.(Data sheets)

5. Piping plan for proposed area showing all valves, filling & discharge points, vent
pipes, dip pipes, storage & filling sheds, pumps, fire fighting facilities etc.

For Final Approval

1. Details of facilities & process write up.

2. Final as built Unit plot plans / equipment layout, plan & elevation drawing drawings
clearly indicating the premises proposed to be licensed

3. As built Layout of surrounding facilities & all protected works lying within 100 mtr.
of the edge of all facilities which are proposed to be licensed.

4. Technical details of all storage tanks including position, capacity, MOC, elevation &
plan view. (A table in a layout drawing)

5. Piping plan for proposed area showing all valves, filling & discharge points, vent
pipes, dip pipes, storage & filling sheds, pumps, fire fighting facilities etc.

6. Storage tank design details & general arrangement drawing

7. Hydro-testing reports of storage tanks certified by a competent person. (approved by


CCOE).

8. Certificate of safety by a competent person. (approved by CCOE).

9. No objection certificate from the district authority the premises proposed to be


licensed.
10. Hazardous area classification for any electrical installation in proposed licensed
premises.

For Final Approval of Electrical installation installed in the licensed premises.

1. Comprehensive report accompanied by all necessary drawings, calculations giving


reference to recognised code or codes followed, full details of design & construction
& necessary test certificates from the recognised bodies in respect of the apparatus &
its components. (Applicable for any type of electrical apparatus used in hazardous
area like MCC, substation etc.)

2. Certificate of electrical installation from any competent person.

Note : The document shall be submitted to CCOE in duplicate at the time of


preliminary approval & quadruplicate at the time of final approval.