Rain Record

This document contains rain records for the months of October, November, and December 2014 from a construction project repairing and improving the KLB Prai area in Penang, Malaysia. It lists the number of work and rain days for each month, with details on start and stop times for any rain during work hours. In October there were 11 work days and 3 rain days, in November 28 work days and 10 rain days, and in December 14 work days and 3 rain days.

Uploaded by

Hazwan Nasir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
72 views3 pages

Rain Record

This document contains rain records for the months of October, November, and December 2014 from a construction project repairing and improving the KLB Prai area in Penang, Malaysia. It lists the number of work and rain days for each month, with details on start and stop times for any rain during work hours. In October there were 11 work days and 3 rain days, in November 28 work days and 10 rain days, and in December 14 work days and 3 rain days.

Uploaded by

Hazwan Nasir
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 3

JNH BINA SDN. BHD.

REPAIR & MAKE GOOD KLB PRAI, PULAU PINANG (PHASE 1)


SUB-CONTRACT FOR TARMAC, FENCING & DRAINAGE WORKS

RAIN RECORD (OCTOBER 2014)

MORNING (a.m.) EVENING (p.m.)


NUMBER OF
DATE DURATION DURATION
WORK DAY START STOP START STOP
(HOUR) (HOUR)
01-10-2014
02-10-2014
03-10-2014
04-10-2014 ###
05-10-2014 ###
06-10-2014 ###
07-10-2014
08-10-2014 ###
09-10-2014 ###
10-10-2014 ###
11-10-2014
12-10-2014 ###
13-10-2014 ###
14-10-2014 ###
15-10-2014
16-10-2014
17-10-2014
18-10-2014
19-10-2014
1 20-10-2014 ###
2 21-10-2014 4.00 9.00 5
22-10-2014
3 23-10-2014 11.00 12.00 1 ###
4 24-10-2014
5 25-10-2014
26-10-2014
7 27-10-2014
8 28-10-2014
9 29-10-2014 12.30 2.00 1.5
10 30-10-2014
11 31-10-2014
#

Total work days = 11 days


Total rain days = 3 days
JNH BINA SDN. BHD.

REPAIR & MAKE GOOD KLB PRAI, PULAU PINANG (PHASE 1)


SUB-CONTRACT FOR TARMAC, FENCING & DRAINAGE WORKS

RAIN RECORD (NOVEMBER 2014)

MORNING (a.m.) EVENING (p.m.)


NUMBER OF
DATE DURATION DURATION
WORK DAY START STOP START STOP
(HOUR) (HOUR)
1 01-11-2014 4.00 5.00 1
2 02-11-2014
3 03-11-2014 2.30 3.00 0.5
4 04-11-2014 ###
5 05-11-2014 ###
6 06-11-2014 ###
7 07-11-2014
8 08-11-2014 ###
9 09-11-2014 ###
10 10-11-2014 ###
11 11-11-2014
12 12-11-2014 2.00 5.00 3
13 13-11-2014 4.00 5.00 1
14 14-11-2014 ###
15 15-11-2014 4.00 7.00 3
16-11-2014
16 17-11-2014
17 18-11-2014 1.00 2.00 1
18 19-11-2014
19 20-11-2014 ###
20 21-11-2014
21 22-11-2014 4.00 5.00 1
22 23-11-2014 ###
23 24-11-2014
24 25-11-2014 2.00 3.30 1.5
25 26-11-2014 4.00 8.00 4
26 27-11-2014
27 28-11-2014 5.00 8.00 3
28 29-11-2014
30-11-2014
#

Total work days = 28 days


Total rain days = 10 Hari
JNH BINA SDN. BHD.

REPAIR & MAKE GOOD KLB PRAI, PULAU PINANG (PHASE 1)


SUB-CONTRACT FOR TARMAC, FENCING & DRAINAGE WORKS

RAIN RECORD (DECEMBER 2014)

MORNING (a.m.) EVENING (p.m.)


NUMBER OF
DATE DURATION DURATION
WORK DAY START STOP START STOP
(HOUR) (HOUR)
1 01-12-2014
2 02-12-2014
3 03-12-2014
4 04-12-2014 ###
5 05-12-2014 4.00 6.00 2
6 06-12-2014 ###
07-12-2014
7 08-12-2014 4.00 9.00 5
8 09-12-2014 ###
9 10-12-2014 ###
10 11-12-2014
11 12-12-2014 ###
12 13-12-2014 ###
14-12-2014 ###
13 15-12-2014
14 16-12-2014 7.30 12.00 5.5 12.00 9.00 9
17-12-2014
18-12-2014
19-12-2014
20-12-2014 ###
21-12-2014
22-12-2014
23-12-2014 ###
24-12-2014
25-12-2014
26-12-2014
27-12-2014
28-12-2014
29-12-2014
30-12-2014
31-12-2014
#

Total work days = 14 days


Total rain days = 3 days