Daily Report: Project Name: Hlaine Tet Hotel

1) The daily report summarizes construction progress for the Hlaine Tet Hotel project on January 13, 2017. 2) 71 workers were on site, including 1 project manager, 2 project engineers, 2 site supervisors, and trades workers conducting GI pipe fixing, formwork removal, rebar production, and sand filling. 3) Equipment on site included 2 generators and materials delivered included quantities of rebar and sand. 4) Health and safety measures were implemented including a daily toolbox talk with no lost time accidents or incidents reported that day.

Uploaded by

mcg
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
69 views1 page

Daily Report: Project Name: Hlaine Tet Hotel

1) The daily report summarizes construction progress for the Hlaine Tet Hotel project on January 13, 2017. 2) 71 workers were on site, including 1 project manager, 2 project engineers, 2 site supervisors, and trades workers conducting GI pipe fixing, formwork removal, rebar production, and sand filling. 3) Equipment on site included 2 generators and materials delivered included quantities of rebar and sand. 4) Health and safety measures were implemented including a daily toolbox talk with no lost time accidents or incidents reported that day.

Uploaded by

mcg
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Daily Report

Project Name: Hlaine Tet Hotel


Project Code: 6YG 03900 Report Date : 13.1.2017 Fri No. of Day 198 Report No. DPR-198
Proj Start Date 22.6.2016 Contract Period Calendar Day AM PM Fine
Weather
Estimate Completion Date Remain Period Calendar Day 6~8 8~10 10 ~12 12 ~1 1~3 3 ~5 Rain
Work Force
Office
Trades PM PE SSE Site Engr QA/QC QS Admin Safety Security Site Store EP Surveyor Geotech Workers Mason Carpenter Smith Welder
Staff
Today 1 2 2 1 1 2 2 1 34 6 12 7

Trades Total

Today 71

Machine & Equipments onsite


Description previous Today Cum. Remarks Description previous Today Cum. Remarks Description previous Today Cum. Remarks
Drilling Machine
Mobile Crane(Ton70)

Pile Machine

Generator (165KV, 220 KV) 1 2

Material Delivery On Site


Quantity Quantity Quantity
Description Unit Description Unit Description Unit Remarks
Today Total Today Total Today Total

QC - Test Sampling
Item Remarks

Test
Sample
Taken

LTI Free Day UA,UC Near Miss FAI MTC LTA


Daily TBT Conducted
HSE
By Safety Officer
50 - - - - -

Works Carried out Details


Trades Of Work Location Remark

1 G.I pipe fixing work for safety at 1st, 2nd and 3rd floor G/L 1 to 4, G/L A to D

2 Ground beam formwork removing work G/L 1 to 4, G/L A to C

3 Rebar production work for ground tank base slab and rebar carrying work for decking sheet slab

4 Sand filling work for ground floor slab G/L 1 to 4, G/L A to C

Special Event

Site
Visitors on
Purpose Instructio
site
n

Project Manager Project Engineer Prepare By: Site Engineer

Name Name Nyo Aung Name Zaw Myo Oo

Signature Signature Signature

FO-OP-01 REV-00