Boiler C&I
PART 2 - INSTRUMENTATION
PART 3 - CONTROLS
BOILER BASICS
K Karthikeyan
Manager/C&I
a age /C&
BHEL Trichy
BOILER CLASSIFICATION
BHEL BOILERS
Power Boilers
Up to 600 MW rating(Coal, oil and gas fired - Subcritical)
Up to 800 MW - Supercritical
Industrial boilers
Up to 450 Tonnes/hour rating
Fertilisers,, Petrochemical,, Steel & Paper
p industries
Wide range of fuels- Oil, Gas, BFG, Bagasse, Black liquor.
Circulation ratio :
Mass rate of water fed to the steam generating tubes
to the mass rate of steam generated.
Natural circulation 6
Controlled circ 4
Once through 1
Fans
Types
1. Axial
Impulse type - IGV Control.
Reaction type - Blade pitch Control.
2. Radial
Inlet damper control, Variable speed control;
Variable speed control by two speed motor,
Hydraulic coupling or Variable frequency drive.
etc.-
t 50 tto 100 RPM)
AIRHEATER
H t recovery equipment
Heat i t
Extract heat from Flue gas to heat primary & secy. Air
Types :
Tubular type
Types
Tangential Firing
Assembly
sse b y
Windbox
C l Pi
Coal Pipes
From Mills
to Windbox
Radial Fan
Axial Fan
Pulveriser
Pulveriser
BOILER CONTROLS
K Karthikeyan
y
Manager/C&I
BHEL Trichy
Mail: [email protected]
BOILER CONTROLS
Continuous control :
Objective
Enabling
E bli Automatic
A t ti Operation.
O ti
Optimising operating performance.
On-Off control :
Objective
Supervise process operation for safety
P
Prevent
t process from
f entering
t i hazardous
h d region.
i
BOILER CONTROLS
Boiler A
Auxiliaries
iliaries interlocks & protection s
system
stem
Master demand
Feed-water control
Steam
Steam-temperature
temperature control
Water
W t mustt be
b fed
f d into
i t boiler
b il to
t match
t h steam
t production.
d ti
Functions of Master
Master demand
demand :
Power Demand.
..Fed directly
y to boiler ((Turbine-following
g control))
Objective :
Fuel is consumed at a rate that exactly matches the
Steam demand.
ota co
Total corrected
ected Fuel
ue flow
o s signal
g a is
s obta
obtained
ed by su
summing
g
up individual fuel flow signals
Bharat Heavy Electricals Limited - Tiruchirappalli
Boiler C&I
So steam-temperature/steam-flow
p profile for radiant
p
zone shows a decline as steam flow increases.
Bharat Heavy Electricals Limited - Tiruchirappalli
Boiler C&I
Steam temperature control
St
Steam t
temperature
t control
t l
St
Steam t
temperature
t control
t l
Scope :
Sequence control of starting and Protection &
interlocking of boiler auxiliaries like
FD fans,
ID ffans,
PA fans,
Airheaters,
Dampers,
Valves, etc.
Wh ID fan
When f 'A' is
i started
t t d (ID Fan
F B is i off),
ff) impulses
i l shall
h ll be
b
given for:
When ID fan A trips (ID fan B is off) impulses shall be given for:
When FD Fan A trips (FD fan B is off) impulses shall be given for:
Wh PA fan
When f A is
i started
t t d (PA fan
f B is i off),
ff) iimpulses
l shall
h ll be
b
given for:
PA fan
f A shall
h ll trip
t i (PA fan
f B isi off)
ff) under
d ththe ffollowing
ll i
conditions:
When PA fan A trips (PA fan B is off), impulses shall be given for:
The gas inlet damper, the secondary air outlet damper and primary
air outlet damper of the tripped AH shall automatically closed.
The gas outlet damper, the secondary air inlet damper and PA fan
inlet damper (if provided) of the tripped AH need not be closed.
However, if the operator wants to manually close these dampers
they can be closed.
If both AHs A & B trip the operator may try for restarting the AHs.
When drum water level rises to 125mm above normal water level
an annunciation
i ti 'D
'Drum l
level
l high
hi h shall
h ll be
b given
i i UCB.
in UCB
When drum level rises to 125mm above normal water level, blow
down valves BD-8 and BD-9 shall open and this condition shall be
annunciated.
Blow down valves shall close automatically when the water level
falls down to NWL. One de-interlock switch shall be provided for
both the valves for manual operation
operation.
(ii) HP Bypass
B or LP Bypass
B valves
l remain
i closed
l d less
l th 2%
than
Tangential Windbox
NDARY AIR
NDARY AIR
SECON
SECON
FUNCTIONS OF FSSS
F - FURNACE
S - SAFEGUARD
S - SUPERVISORY
S - -SYSTEM
START UP
LOW LOAD OPERATION
SHUT DOWN.
FSSS
FSSS
UNIT LOGIC
ELEVATION LOGIC
CORNER LOGIC
COMPUTE MONITOR
MONITOR COMPUTE
ELEVATION A LOGIC
MONITOR
CONTROL
CORNER 4 LOGIC
COMPUTE CONTROL
COMPUTE
MONITOR
MONITOR
FSSS
UNIT LOGIC
Scope :
SUPERVISION OF OVERALL FURNACE CONDITIONS
FSSS
ELEVATION LOGIC
FSSS
CORNER LOGIC
FSSS
ARRANGEMENT OF SYSTEM
LOGIC CABINET
CONSOLE INSERT
SECONDARY AIR DAMPER PANEL
MILL PANEL
FIELD EQUIPMENTS
CUSTOMER SUPPLIED INTERFACE
EQUIPMENT.
FSSS
FSSS NET
CABI
LO GIC
Y
RELA
L
PANE
ES MILL
CABL THER MENT
S
UG-I
N TO O QUIP
ATED PL FIEL
D E
BRIC
. FA AIR
PREE SEC.
ANEL
OM
ROL P
RO
CO NT
L
RO
NT
CO
D
EL
OLE
FI
CONS RT
IN E
S
LOCAL GUN MAINT.
SWITCH
ARRANGEMENT OF
FURNACE SAGEGUARD SUPERVISORY SYSTEM
FSSS
BOILER TRIP COMMAND IS INITIATED BY
FSSS
BOILER TRIP COMMAND RESULTS IN
1. ALL PULVERIZERS
2
2. ALL FEEDERS
3. ALL OIL GUNS
4. ALL IGNITORS
IT CLOSES
1. IGNITOR
2. LIGHT OIL
3. HEAVY OIL
TRIP VALVES
FSSS
FSSS
FSSS
FEEDER CONTROL
FSSS
BOILER TRIP
FSSS
PULVERIZER STARTING PROCEDURE
} START
< PULVERIZER ON LIGHT
} OPEN HOT AIR GATE
< WAIT TILL PULVERIZER COMES TO TEMPERATURE
( 140F )
} START FEEDER ( AT MINIMUM FEEDER SPEED )
< COAL FLOW INDICATOR OR PULVERIZER AMPERE (
( WITH IN 5 SECONDS )
< FIFTY SECONDS
} FEEDER SPEED RELEASED TO AUTOMATIC CONTROL
FUEL AIR DAMPER OPENED
FUEL AIR DAMPER MODULATED TO AUTOMATIC
CONTROL.
FSSS
PULVERIZER START REQUIREMENTS
FSSS
CONDITIONS ( LOCAL ) TO BE SATISFIED TO START
RESPECTIVE PULVERIZER
FSSS
FSSS
OR
FSSS
FUNCTIONS OF FURNACE SAFEGUARD SUPERVISORY SYSTEMS
FSSS
NO COAL FLOW ALARM SYSTEM
1 PICKUP UNIT
1.
a) SOUNDING ROD
b)) RUBBER MOUNTING
c) MICRO PHONE
FSSS
PULVERIZER SHUT DOWN
HFO RECIRCULATION :
3 HEAVY FUEL OIL (HFO) RECIRCULATION DONE TO HEAT HFO TO
REQUIRED TEMPERATURE BEFORE FIRING IN BOILER.
3 HFO RECIRC. VALVE CAN BE OPENED WHEN ALL HFO NOZZLE
VALVES ARE CLOSED.
3 HFO RECIRC. VALVE AUTOMATICALLY CLOSES IF ANY HFO NOZZLE
VALVE IS OPENED.
CORNER TRIP
ELEVATION TRIP :
1. STARTING OF CORNER-1.
2 STARTING OF CORNER-3 AFTER 15 SECS.
2. SECS DELAY.
DELAY
3. STARTING OF CORNER-2 AFTER 25 SECS. DELAY.
4. STARTING OF CORNER-4 AFTER 40 SECS. DELAY.
AN UNSUCCESSFULL START ALARM IS GIVEN AND THE BURNERS IN
SERVICE WILL BE SHUT DOWN IF AFTER THE EXPIRY OF START TIME
IS ATLEAST 3 BURNERS ARE NOT IN SERVICE.
3 CORNER-3
3. CORNER 3 RECEIVES STOP COMMAND 15 SECS.
SECS LATER.
LATER
PAIR 2-4 SHUT DOWN SEQUENCE IS SIMILAR TO PAIR 1-3 SHUT
DOWN SEQUENCE.
BOILER
INSTRUMENTATION
K Karthikeyan
M
Manager/C&I
/C&I
BHEL Trichy
Mail: [email protected]
Why
h Instruments?
To measure the actual values of
different p
parameters for which the
boiler is designed.
Safe working range of the different
parameters are maintained.
To monitor one or more variables at
a time and provide input for
automatic control.
control
Bharat Heavy Electricals Limited - Tiruchirappalli
Boiler C&I
Why Instruments?
In case of operator failure to take
p
remedial action for an upset
condition, it protects the boiler by
pp g
alarms and trippings.
To provide data on operating
conditions before failure of the
equipment for analysing the failure.
Boiler measurements
Pressure Flue gas analysis(O2,
Differential
ff pressure CO, SOx, NOx,
Temperature Opacity)
Differential SWAS(Conductivity,
SWAS(Conductivity
temperature(heat flux) pH, Silica, Dissilved
Flow O2, Hydazine)
Level Image
I sensing(CCTV)
i (CCTV)
Vibration (rotating
Sound(steam leak)
device)
S
Speed d (rotating
( t ti Viscosity (fuel oil)
device) Calorific value
Position
Weight
Instrumentation
representation- ISA
First letter Succeeding letters
A- Alarm
P-Pressure
I Indicate
I-
T-temperature
R- Record
F- Flow
g
Q- Integrate
A- Analytical C- Control
S- Switch
T tansmitter
T- t itt
E- Element
P- Pocket
P
W- Well
Bharat Heavy Electricals Limited - Tiruchirappalli
Boiler C&I
LAB- FW piping
LAC-BFP
LAD- HP heater
p y
LAE- HP DESH spray
LAF- IP DESH spray
LBA- MS piping
LBA
LBB-HRH piping
LBC-CRH Piping
TO SHH1
TO DRUM LEVEL TO DRUM LEVEL
CONTROL CONTROL
OR
D FIREMANS FLOO
EWLI
DWLG
DWLG
EWLI
AT UCB AND
AT UCB AN
CHEMICAL DOSING
TO SAMPLE
COOLER
FROM ECONOMISER
TO SUCTION MANIFOLD
TO CBDT
TO DRUM TO DRUM
ECONOMISER
TO DRAIN HEADER
TO SAMPLE COOLER
FEED CONTROL
STATION
( LEFT )
MAIN STEAM LINE
( RIGHT )
MAIN STEAM LINE
SH OUTLET HDR