FTA Report No. 0015 0
FTA Report No. 0015 0
FTA Report No. 0015 0
Handbook
MARCH 2012
FTA Report No. 0015
Federal Transit Administration
PREPARED BY
DISCLAIMER
This document is intended as a technical assistance product. It is disseminated under the sponsorship of the U.S. Department
of Transportation in the interest of information exchange. The United States Government assumes no liability for its contents or
use thereof. The United States Government does not endorse products of manufacturers. Trade or manufacturers names appear
herein solely because they are considered essential to the objective of this report.
This Handbook is intended to be a general reference document for use by public transportation agencies responsible for the
management of capital projects involving construction of a transit facility or system.
This document is disseminated under the sponsorship of the U.S. Department of Transportation in the interest of information
exchange. The United States Government and the Contractor, Gannett Fleming, Inc., assume no liability for the contents or use
thereof.
The United States Government does not endorse manufacturers or products. Trade or manufacturers names appear herein solely
because they are considered essential to the objective of this report.
Construction
Project
Management
Handbook
MARCH 2012
FTA Report No. 0015
PREPARED BY
http://www.gannettfleming.com
SPONSORED BY
Federal Transit Administration
Office of Research, Demonstration and Innovation
U.S. Department of Transportation
1200 New Jersey Avenue, SE
Washington, DC 20590
http://www.fta.dot.gov/research
LENGTH
VOLUME
MASS
megagrams
T short tons (2000 lb) 0.907 Mg (or "t")
(or "metric ton")
o 5 (F-32)/9 o
F Fahrenheit Celsius C
or (F-32)/1.8
1. AGENCY USE ONLY 2. REPORT DATE 3. REPORT TYPE AND DATES COVERED
March 2012 September 2008 - March 2012
4. TITLE AND SUBTITLE 5. FUNDING NUMBERS
Construction Project Management Handbook: March 2012 FL-26-7110
6. AUTHOR(S)
Kam Shadan, P.E.
13. ABSTRACT
The purpose of the FTA Construction Project Management Handbook is to provide guidelines for use by public transit agencies (Agen
cies) undertaking substantial construction projects, either for the first time or with little prior experience with construction project
management. It provides a comprehensive introduction to construction project management, including the applicability of the
principles of project management and of all phases of project developmentfrom project initiation through planning, environmental
clearance, real estate acquisition, design, construction, commissioning, and closeout. This Handbook provides guidance similar to that
in earlier documents but tailored more to agencies that are constructing maintenance and operational facilities, intermodal terminals,
park-and-ride stations, and other similar supporting transit facilities. Throughout the sections, project management concepts are il
lustrated with the use of a hypothetical example, a typical project to plan, design, and build a new bus maintenance facility.
17. SECURITY CLASSIFICATION 18. SECURITY CLASSIFICATION 19. SECURITY CLASSIFICATION 20. LIMITATION OF ABSTRACT
OF REPORT OF THIS PAGE OF ABSTRACT None
Unclassified Unclassified Unclassified
1 Section 1: Introduction
1 Purpose of the Handbook
3 What is a Project?
9 Principles of Project Management
11 Section 2: Project Development
11 Purpose of this Section
13 Integrate Agency Goals into Capital Improvement Plan
15 Evaluate and Select Capital Assets for Capital Improvement Plan
16 Fund and Authorize Projects
20 Section 3: Project Initiation
20 Purpose of this Section
21 Defining the Project
22 Planning the Project
30 Contract Management Planning
32 Section 4: Planning, Environmental Clearance, Real Estate
Acquisition
32 Purpose of this Section
34 Planning Studies
37 Environmental Compliance
41 Real Estate Acquisition and Relocation
42 Entitlement
44 Section 5: Design
44 Purpose of this Section
46 Design Phases
50 Design Management
51 Design Reviews
53 Third Party Coordination
54 Value Engineering
56 Peer Reviews
56 Constructability Reviews
57 Risk Assessment
60 Quality Assurance and Quality Control
62 Sustainability (Green Building) Standards and Design
67 LEED Certification
69 Section 6: Construction
69 Purpose of this Section
71 Construction Management
80 Third Party Coordination
81 Quality Management
83 Safety Management During Construction
ACKNOWLEDGMENTS
Rodney Dawson and Scott Zeevaart were the deputy project managers and
co-authors. Additional specialized input was provided by Michael Lee, William
Plumpton, Charles Norrish, and Mark Hollopeter of Gannett Fleming, and
Candy Spitzer of Spitzer and Associates in the areas of facilities, environmental
compliance, construction, commissioning, and real estate. Gannett Fleming staff
that assisted in editing and document preparation included Kelly Zanzinger, Mary
Kissinger, and Marlin Mann.
SECTION
Each section begins by describing the purpose of the section and includes a
checklist of important things to do. The subsections within a section include key
points of important things to know about project management that are discussed
in more detail in the text and supported by pictures, graphics, tables, and charts.
Environmental
Permitting Compliance
Utilities
Agencies
ROW
Planner
Specialist
Civil
Architect
Engineer
Landscape
Surveyor
Architect
Agency
Construction Structural
Manager Engineer
Geotechnical
Contractors Engineer
Noise Testing
Engineer Labs
Traffic Environmental
Engineer Community Engineer
Relations
Note: Depending on the project, there may be a need for a professional not listed in the chart, such as an archeologist, etc.
Characteristics of Projects
Projects are defined by their scope, budget, and schedule. For example, an
Agency is to undertake a project to design and build a new maintenance facility
for its fleet of buses (scope), at an estimate of $30 million (preliminary budget)
over a three-year period (schedule). The schedule specifies a defined beginning
and end. Projects go through a life cycle of phases between their beginnings
and ends that for construction projects are typically: initiation, planning, design,
construction, commissioning, and closeout.
Scope: Each project is unique and must have a written requirements document
that takes into consideration operational needs, level of service, regulatory
requirements such as Americans with Disabilities Act, and quality of deliverables.
The scope evolves as new information becomes available through the project
life cycle. For example, in the early planning phases of the maintenance facility
project, the scope is to have five service bays. Later, as the design progresses,
the exact location and the type of service in each bay can be determined. Scope
refinement should not be confused with scope creep. Scope creep occurs when
the Agency determines part way through the project that operational projections
now call for six rather than five service bays. Changing to six bays after the
project is underway is a serious change in scope that could impact the budget
(larger facility, more land, redesign) and delay the schedule (replan, redesign,
longer construction). Scope refinement is a necessary process in the project life
cycle while scope creep results from lack of clarity on the Agencys requirements
in the original scope for the needs, level of service, and level of quality for the
deliverables.
Schedule: All projects must have a definite beginning and end. The Agencys
Capital Improvement Plan (CIP) usually provides approximate dates for the
beginning of a project and the end date when it is due to go into operation.
Once there is a well-defined scope, the Agency needs to determine the time it
will take to complete the project by developing the project schedule. Developing
the schedule involves breaking down the work into manageable activities needed
to accomplish the scope of each deliverable, estimating the duration of each
activity, and placing them in a logical sequence. Section 9 describes useful
techniques for developing a schedule. The result is a project schedule that tells
you the expected duration of the project and the logical relationships between
the activities, including activities on the critical path, that control the end date.
budget occurs through studies and analysis in the design development process
through the preliminary engineering phase. When Agencies try to fix the budget
too early in the project life cycle, they are surprised by the significant increases
in the budget over what was set forth in the CIP. As explained later, the
budget should not be fixed as baseline until after completion of the preliminary
engineering phase. Estimating techniques for the costs of the activities needed to
accomplish the scope of each deliverable are covered in Section 9.
There are many alternative delivery methods, such as design/build (D/B) and
design/build/operate/maintain (D/B/O/M). These delivery methods assign
multiple phases of work, such as design and construction, to a single contractor.
In the D/B/O/M method the Agency also contracts out the operations and
maintenance of the completed project to the contractor.
Figure 1-3
Typical Project Life
Cycle Traditional
Design/Bid/Build
The strategic goals that relate to capital projects are summarized in CIPs. Many
times this information is in the Agencys short range and long range transit plans.
The approval of the project by the governing body will establish the project
The project manager must have prior experience (or should consult with peers
with prior experience) with the particular project type to balance the above
competing objectives in a timely manner to adequately plan the project. Lack of
prior experience will increase risks of not achieving the project objectives. In
Section 3 Project Initiation, we cover a discussion of project authorization and
the PMP. In addition to scope, budget, and schedule, it is extremely important
that the project manager facilitates a discussion of the project risk, quality, and
safety and security objectives for the project and incorporates the outcome in
the PMP.
Project Development
During project development, the Agency identifies the need for a project,
assesses the projects ranking in importance relative to other projects, analyzes
its funding requirements, and decides whether to authorize the project for
implementation. Planning how to manage an authorized project is discussed in
Section 3 Project Initiation.
The Agencys mission, vision, and resulting strategic plan govern the development
of the CIP. The strategic plan looks to the Agencys mission that in turn defines
its vision for the future and the strategies it will adopt to achieve the missions
goals and objectives. The Agency can then determine what assets it needs to
accomplish its strategies and identify any gaps between its existing and needed
assets. Simply stated, a capital project is developed as a means of filling the
gap between the needed and the existing assets. The CIP is a prioritized list of
projects to meet the Agencys capital asset needs. Figure 2-1 depicts the project
development and CIP process.
Not all projects in a CIP can be immediately implemented due to funding and
other constraints. The Agency has to rank the relative importance of the
projects and make hard choices to select which projects can be implemented,
and which must be deferred along with the strategic objectives that depend on
them. This part of the project development process requires a careful balancing
of project costs against available financing and is a complex mix of public policy,
public financing, and capital and operational budgeting.
and Capital
Improvement Plan Establish Agency Inventory Agency Establish Project Agency
Mission and Current Capital Review & Approval Funding
Process Vision Assets Framework Sources
Is
Option to
Approve & Fund
Do Asset?
Implementation
Yes
q Assess assets Go
needed to achieve to Project
Add Project
Initiation
agency goals. as Candidate for
Agency CIP
q Identify gaps
between needed
and current assets. Role of Agency and Consultant Staff in Project
Development
q Evaluate alternatives Strategic planning and the CIP process is the responsibility of the Agencys senior
to filling asset gaps. executive supported by its planning and financial staff with information input by
q Adopt a standard operating departments. Due to the long-term nature of Agency strategies and
project review/ capital projects, the FTA Guidance for Transit Financial Plans calls for a 20-year
approval CIP planning horizon. Each year the Agency re-examines the plan particularly for
framework. the near term years and also develops a budget for the upcoming financial year.
q Establish criteria
Depending on the size of the Agency, a number of new capital projects may be
to rank and select
authorized for implementation in the upcoming financial year. The budget to
projects.
complete each newly authorized project is identified and the financing needed
q Maintain a long- over the project life is committed. The budget for the upcoming year includes
term capital funding to cover new and continuing projects. Figure 2-2 shows a typical Capital
improvement plan. Improvement Plan.
q Balance capital
The Agency may choose to retain the services of qualified consultants to assist
needs to funding
sources. in: strategic planning; applying to local, state, and federal levels of government
for funding; securing funding through debt and innovative financing; and preparing
q Authorize projects a CIP. The role of the consultant is to assist the Agency planning, finance, and
in useful segments. operations staff to prepare the CIP by providing specialized expertise and
experience not available within the Agency staff.
Total Current
Prior Fiscal Future Fiscal Years Project
Yrs Yr FY1 FY2 FY3 FY4 FY5 Total
Current Projects
~~~~~~~~~~ xx xx xx
~~~~~~~~~~ xx xx xx xx xx
~~~~~~~~~~ xx xx xx xx xx xx
~~~~~~~~~~ xx xx xx xx
~~~~~~~~~~ xx xx xx xx
Total xx xx xx xx xx xx
Proposed Projects
~~~~~~~~~~ xx xx xx
~~~~~~~~~~ xx xx xx xx xx
Maintenance Facility xx xx xx xx
~~~~~~~~~~ xx xx xx
Total xx xx xx xx xx xx
If you are charged with managing the Agencys project development process, it is
important that you ensure that the resulting CIP is consistent with the Agencys
goals. Steps you should take to integrate the Agency goals into the CIP include:
Success in assessing capital resource needs requires you to first confirm that the
Agencys goals and objectives align with the Agencys mission. To do this you
will need to put in place a strategic planning process where the Agencys policy
setting executive can re-examine the Agencys mission in response to changing
needs in community requirements, government mandates, board priorities,
operations, and organizational strengths and weaknesses; and set policy goals and
objectives consistent with the mission. With the goals and objectives in place,
you can then assess what capital resources the Agency will need to accomplish
each goal and objective.
To identify any gaps between current and needed resources you will need an
inventory of current capital assets.
Comparing resources available with resources needed will enable you to identify
any gaps and begin planning to fill them.
You can create a standard review and approval framework for your Agency by
Important to establishing some form of standard Project Request Package for review by the
Know
Agencys management responsible for its CIP. The topics to be addressed in a
Projects need to be Project Request Package include:
ranked and selected
because Agencies Project overview
face funding and Benefits discussed in terms of support of Agency goals and objectives
Figure 2-3
Components of
Capital Improvement
Plan
The Agency-wide CIP allows the Agency to manage its resources and debt so as
to maintain focus on the Agencys goals and objectives to accomplish its mission.
The management of the CIP will determine the timing of when a project is to be
authorized for implementation as discussed next.
It is important that the CIP includes the full costs and funding requirement for
projects when making decisions on which projects to select for authorization
based on their ranking. Knowledge of a projects full costs and funding
requirement is necessary to assess the financial impact in future years of
implementing the project, and the Agency can verify that it has the financial
resources to complete all authorized projects. It also allows the Agencys
decision makers to compare the long-term costs and funding requirements
of alternative projects of similar ranking to better understand the financial
consequences of the CIP decisions.
The financial planning that balances the CIPs sources and uses of funds also
needs to take into account uses of funds for debt service and the balance of
funds from operations. Figure 2-4 shows a typical CIP financial plan incorporating
debt service and balance from operations.
Figure 2-4
Financial Plan - Balance Funding Sources to Capital Improvement Plan Capital Expenditures
Staged Authorization
It is frequently beneficial to manage the authorization of projects in stages.
Staged authorization is when project funding and implementation are authorized
to take the project to a certain stage of completion. On reaching this stage, the
project is re-reviewed within the context of the CIP and a further decision is
made as to whether or not to authorize the next stage of a project. Stages are
selected based on completing a useful segment of the project that either:
Provides better information on the costs, risks, and benefits of the project
before committing the Agency to the full costs and funding of the project; or
Delivers a component of the total project that itself is a useful asset that fills
an identified asset gap where the resulting benefits exceed the staged project
costs.
the example maintenance facility but defer installation of the paint booth until
additional funding became available in future years. The Agency determined that
completion of the components of the maintenance facility excluding the paint
booth resulted in operational benefits that exceeded the project costs.
the Agency.
- Description of project
(STIP)
- Environmental impact analysis under National Environmental Policy Act
(NEPA), as discussed further in Section 4
- Description of transit system in the Agencys service area.
Project Authorization Documentation
The final step in managing the project development process is to formally
document the authorization of the project using a project authorization
document. Concurrent with preparing the project authorization, it is good
practice to assign the project manager to the project so that, with the project
authorization in hand, the project manager can begin planning the management of
the projects implementation, as discussed in Section 3.
the project being selected, incorporated into the CIP, and authorized for
implementation.
Attachment or reference to Agency decision to implement the project (such
as Board action item).
Description of project.
Summary budget and funding.
Summary milestone schedule.
Assigned project manager.
Authority delegated to project manager.
Advise on project planning and delivery together with the production of the
PRD and PMP documents.
Provide project management services during the subsequent project
implementation phases.
Topic Description
Authorization Reference to project authorization that selected and authorized the project
Stakeholders Corporate sponsors, customers, third parties impacted, project team
Deliverables Products/services the project will deliver
Scope of Work Work to be done to deliver the products/services (high-level summary)
Cost Estimate Initial order of magnitude estimate of the project budget
Schedule Milestones Initial project schedule in terms of key project milestones
Finance Project financial requirements and sources of funding
Risks Threats to the project (e.g., adverse environmental factors)
Resources Resources needed to accomplish the project
Constraints Constraints such as limited resources/funding, sites available, etc.
Acceptance Criteria What determines acceptable products/services and their approval
The project manager for our example bus maintenance facility project scenario
approached the PRD as follows:
For the example bus maintenance facility project, the project manager plans a
design/bid/build (D/B/B) delivery strategy where: the project manager and other
Agency staff will manage the project; design and design management will be
contracted out to a General Engineering Consultant (GEC); and a Construction
Manager (CM) will be retained to manage construction carried out by various
construction contractors and suppliers.
For smaller Agencies it is often expedient for the project manager to choose
delivery strategies similar to the example above, that contract out the project
work rather than hire an entire project staff. It is difficult to recruit qualified
project staff for a single project. Using contracted services allows the project
manager to better match resources to project needs. A contractor can be
retained when the need arises and the project manager can immediately
terminate their involvement and expense when the project need is over.
Whatever delivery strategy the project manager selects, it is important that
the Agency, through the project manager, retains the ultimate authority and
accountability for the effective management of the project. This is the case even
where the Agencys project manager chooses to retain a Program Management
Consultant (PMC) to manage the project on behalf of the Agency.
The project manager for the example bus maintenance facility project requires
Agency procurement staff to acquire GEC and CM consultants and construction
contractors. The level of procurement effort to do this for the project is
not full-time and the staff is assigned part-time to the project on a matrix-
organization basis. The procurement staff takes project direction from the
project manager on what procurements are needed and when, while the staff
receives functional direction on how to undertake the procurements from
the functional manager of the Agencys procurement department. When not
assigned to the example project, the staff undertakes procurement activities for
operations and/or other Agency projects.
Experience has shown that a project team works better within an integrated
project office concept. This means that irrespective of the project staffs
parent organization, the Agencys organization or those of the GEC and CM
organizations, the staffs project reporting relationship with respect to project
work assignments follows the project organization chain of command reporting
to the project manager. When possible and in cases where staff is highly utilized,
co-location of project staff within a single project office facility helps foster the
integrated project office concept. Functional supervision remains the individuals
usual functional supervisor within their parent organization.
Figure 3-4
Sharing of Control and
Risk Between Owner
and Contractor for
Alternative Delivery
Strategies
In the PMP, the project manager sets out the management approach for the
project based on the decisions made with respect to the project delivery
strategy, organization and management structure, assignment of responsibilities
between the Agency and contractors, and delegation of management and
financial authority through the project team.
The projects scope, budget, and schedule are refined to establish baselines
for the projects scope of work, costs, and schedule that are documented in
the PMP (see Section 9 to learn about project control techniques used for
establishing baselines). Scope, budget, and schedule baselines are yardsticks
against which future project performance can be measured and assessed, and
changes controlled. Depending on the project phase baselines are established
for a project phase or the entire project baseline is established after completion
of preliminary engineering. A baseline remains unchanged through the project or
project phase unless a revision to the projects goals and objectives is authorized
by the Agencys executive management responsible for the project authorization.
The PMP is a living document and is updated as the project progresses, usually
as the project enters a new phase, such as moving from design into construction.
Updating and revising the PMP requires the project manager to: add management
detail on how a new phase is to be managed, note any changes to the
project scope, and forecast project costs and schedule against the baselines.
Traditionally the project is managed by personnel in the planning organization
through completion of the environmental phase. As the project moves into the
design and construction phase where engineering and construction management
skills are required, it is critical that the top management recognize and plan
for the changes in project
management leadership
necessary to successfully
make the transition from the
planning/environmental phase
to the design and construction
phase. In Section 9 we
explain some useful tools and
techniques that support the
project manager in the control
of scope, cost, and schedule.
The risk management plan describes how the project is organized and the
procedures used to manage the project risks, addressing in the plan:
It is important that the PMP and the contract management plan clearly identify
the roles and procedures to be followed by the project staff responsible for
managing the project (delivering the project scope on time and within budget)
versus the project staff responsible for administering project contracts (making
certain contract parties meet their contractual obligations and protecting the
organizations legal rights). The contract management plan sets out how this is
to be achieved, addressing:
Who has the authority to direct and approve the contractor to perform
work
How the contractors work is monitored and performance reported
Process by which changes to the contractors work are requested, approved,
and the contract modified
What inspections and audits are to be conducted of the contractors work
How the contractor requests payment and payment requests are reviewed
and approved
What financial audits are to be conducted on contractor payments
How contract documents, correspondence, and other records are managed.
(Section 9 provides additional information of what constitutes good project
documentation for handling important contract administration activities such
as contract changes and request for payment.)
planning phase activities can continue through final design and construction
Important to for assuring compliance with mitigation measures stated in the environmental
Know
compliance document and acquisition, relocation, and management of real estate.
Early role definition
for project Role of the Agency
team members
is necessary The Agencys main role is to assure that the assigned project lead person for the
to balance the planning phase has the right qualifications, responsibility, authority, and available
authority and time to steward this phase. This project lead may or may not be the assigned
responsibility. project manager and could be a consultant. Managers with current operational
or planning assignments are often tasked with the work of planning a large
Consultants who
capital project while managing many other issues. This may result in reactive
take on the planning
project management rather than proactive project management since the lack
phase and take the
project through of adequate time will result in problems getting ahead of management decisions
environmental and driving the project, rather than the Agency proactively circumventing and
compliance are solving them. This lead person will have to work closely with other functions
conflicted out of in the organization such as service planning, operations, maintenance, and
performing the final procurement. The Agency must set priorities such that adequate support is
design. provided to the lead person. For the example bus maintenance facility project,
the Agency will need to assign a qualified manager with prior maintenance facility
The Project
project management experience dedicated to thinking through the project
Management Plan
needs. This manager anticipates issues and develops plans, collaborates with
revision in this
phase will highlight all stakeholders, and brings on the necessary resources to carry the project
unique features forward to meet the budget, schedule, quality and safety requirements. If such
related to the a resource is not available or does not have the time necessary, the lead person
planning phase. will have to work with procurement to bring in consultants for this phase.
Role of Consultants/Contractors
Whether the planning phase leadership is through use of an in-house project
manager or through project management provided by a consulting firm, the
planning studies will have to be done by outside consultants for most major
projects. This is the case especially when taken on by an Agency that does not
have a large, on-going capital planning function with specialists in community
planning, NEPA, and real estate acquisitions. Real estate consultants must have
experience and a track record with the Uniform Act. The consultant team
should have expertise in environmental compliance and NEPA, transportation
planning, engineering, architecture, and community outreach. The planning
consultant team will have design experts that will take the projects through
completion of the preliminary engineering phase. There must be some
separation between the engineering team in charge of analyzing impacts and
providing mitigations, and the environmental team in charge of identifying
impacts to assure no conflict of interest exists. It is recommended that the
environmental team be a separate company from the engineering team. In any
case, the planning team will take the project through planning, environmental
Site Selection
To select a suitable site, the project manager will lead the team to determine
a general area where the facilities may be constructed. The team considers a
number of alternate sites within the general area. The project manager will lead
the team to consider site features. Once all site constraints and opportunities
have been identified, the team will undertake a more detailed study of the
preferred site with respect to fit and function for the required functions. The
team will develop a shortlist of selected sites to be studied further. The key
elements of the study are the number of people and businesses that will be
displaced, the estimated cost/time to acquire the real property for the project,
the site geotechnical characteristics and environmental impact costs, the
operational impact costs, and the estimated costs to relocate those eligible
and/or to move personal property from the property. Once these factors are
evaluated the sites will be ranked and listed in the environmental documents and
an acquisition and relocation plan is developed.
Technical Studies
The project manager must have qualified technical professionals on the team
to study the site and facilitate the technical evaluations early on and prior to
completion of site selection and acquisition. Technical evaluation of the site
includes geotechnical investigations, soil and water testing for contaminated
material, traffic studies, zoning studies, and other technical assessment that
may be applicable to the specific site. For example, the presence of hazardous
material, waste, or other contaminants on the site, and potential of undesirable
soil and geotechnical conditions can have severe cost and schedule implications
and must be studied prior to completion of site selection and acquisition.
Environmental Studies
These studies may be necessary even if the project is categorically exempt from
formal environmental review required by the federal or state governments.
These studies could include traffic and noise studies to evaluate the impact on
the neighboring homes and businesses. Federal law requires environmental
compliance, in accordance with NEPA, prior to land acquisition. The project
manager will depend heavily on the professional team with relevant experience
for this work.
Figure 4-1
The NEPA Process
Overview
or other resource; do not involve significant air, noise, or water quality impacts;
do not have significant impacts on travel patterns; or do not otherwise, either
individually or cumulatively, have any significant environmental impacts. If it is
determined that the action is categorically excluded and would not result in
significant impacts, the CE may still require supporting documentation such as
additional studies to address and clarify relatively minor impacts. Construction
of new bus storage and maintenance facilities in areas used predominantly for
industrial or transportation purposes, where such construction is consistent with
existing zoning and located on or near a street with adequate capacity to handle
anticipated bus and support vehicle traffic, is an example of an action that may
be categorically excluded from further review. A typical abbreviated checklist is
shown in Figure 4-2.
In cases where the impacts or actions are not known, a more formal study
called Environmental Assessment (EA) is performed. The purpose of an EA is
to determine if certain aspects of the proposed project have the potential for
significant adverse social, economic, or environmental impact and if present,
create the foundation for preparation of an Environmental Impact Statement
(EIS). The significance of impacts is judged on a case-by-case basis and measured
in terms of their context and intensity. The EA process may also facilitate
identification of alternatives and measures which might mitigate adverse
environmental impacts. At the conclusion of the EA study, the Agency may
receive a Finding of No Significant Impacts (FONSI). It is possible that before an
EA is completed, the Agency may be asked to expand the study to a full EIS.
Figure 4-2
Detailed Project Description
Information Required Location (Including Address)
for Probable Metropolitan Planning and Air Quality Conformity
Categorical Exclusion Zoning
Projects (23 CFR Traffic Impacts
Section 771.117(d)) Carbon Dioxide (CO) Hot Spots
Historic Resources
Noise
Vibration
Acquisitions & Relocations Required
Hazardous Materials
Community Disruption and Environmental Justice
Use of Public Parkland and Recreation Areas
Impacts on Wetlands
Floodplain Impacts
Impacts on Water Quality, Navigable Waterways, & Coastal Zones
Impacts on Ecologically-Sensitive Areas and Endangered Species
Impacts on Safety and Security
Impacts Caused by Construction
If the impacts are significant, an EIS must be prepared. The EA and EIS include
detailed environmental studies, related engineering studies, Agency coordination,
and public involvement. However, final design activities, property acquisition,
Review Process:
An Overview CE or Other
Exemption
Exclusion No
Applies
Exclusion
EA
No EIS
EIS Required
Notice of Intent
Scoping Process
DEIS
Agency/Public
Review & Comment
FEIS
FONSI
ROD
State Process
The environmental compliance process for states varies significantly from one
state to another; several states have state-specific processes similar to the
NEPA. Normally the lead Agency will process the planning applications for
approval of land use, project design, and permitting. This process is very similar,
and in some cases less stringent than the federal process. It is recommended
that the Agency contact the State Department of Transportation (DOT) in the
project state for details.
Permitting
Depending on the nature of the project, there are many permits that the project
manager will have to be concerned with and acquire prior to construction. In
this section, we cover the most commonly seen federal permits, which are
required for waterway encroachments and obstructions in conjunction with the
environmental review process. The applicable regulation is outlined in Section 404
of the Clean Water Act which requires a permit from the U.S. Army Corps of
Engineers for the discharge of dredged or fill materials into Waters of the United
States (Waters of the United States include wetlands). The Section 404 (b)(1)
Guidelines provide guidance to the Corps of Engineers and applicants for issuance
of permits. Impacts to Waters of the United States need to be avoided and
minimized to the extent practicable. Compliance with the Guidelines is required
for the issuance of a permit. The Guidelines require the selection of the Least
Environmentally Damaging Practicable Alternative (LEDPA). Some states have
similar legislation and permitting requirements for waters and wetlands.
Typically the NEPA process is completed for a project prior to applying for a
permit under Section 404 of the Clean Water Act. The goal under NEPA is to
identify and implement the environmentally preferable alternative that considers
and balances impacts on natural, cultural, economic, and social resources. An
EIS fully discloses all reasonable alternatives and their associated impacts as the
basis for selecting an alternative; however, NEPA does not contain regulatory
requirements that compel Agencies to select the LEDPA as required by the
Clean Water Act. The project manager must be careful not to be misled by
thinking that compliance with NEPA early in the transit project development
process automatically translates to compliance with the section of the Clean
Water Act. To avoid potential need for reevaluation of alternatives, the project
manager must assure that the Corps of Engineers public interest review is
integrated in the NEPA compliance process through early consultation with
the Corps. Merging NEPA and Section 404 eliminates the potential conflicts
with sequential NEPA and Section 404 processes. The Corps of Engineers
encourages applicants to request pre-application conferences when projects are
being planned that may require the discharge of dredged or fill materials into
Waters of the United States.
offer of just compensation to the property owner. The Agency, acting principally
through an acquisition agent or negotiator, should make every reasonable effort
to reach an agreement expeditiously with the property owner once it has been
approved by an Agency official. If an agreement is not reached, the Agency can
initiate condemnation proceedings as prescribed by law using legal counsel. If
there are occupants (including the property owner) or personal property on
the parcel, relocation assistance will be required. In that situation the project
manager must follow the relocation procedures associated with the Uniform Act
and its implementing regulations.
Important to Entitlement
Know Many cities and counties will enforce state laws and regulate land development
Determine and through zoning restrictions. The project manager will take the lead in
reach agreement on communicating with the cities and counties having jurisdiction to ascertain
the specific agency what steps are needed to entitle the parcel for their intended use. There are
that has jurisdiction numerous types of actions and varying procedures depending on the projects
on the project. and the jurisdictions. In the case of the example maintenance facility project,
Agency with
the project manager must assure compatible zoning and file a design review
jurisdiction over application for the intended use. In most circumstances, the project will
the project can be a go through design review before the conceptual engineering is done. Many
good resource. jurisdictions will not allow a final design review until after the project has gone
through the environmental compliance process. If the zoning is not compatible
Approval of the with the intended use, a general plan amendment or a use permit may be
project for intended
necessary.
use is provided
ACQUISITION PROCESS
NEPA PROCESS
Donation? No
Owner No
signs
waiver of Appraise In-house? No
right to
appraisal Yes
&
appraised Determine In-house
No
Counters
Receipt of Counter-offer
Accepts Internal
Rejects
Approvals
Design Phase
The design phase takes the project requirements through design criteria and
conceptual design to the final design and construction documents for a contractor
to bid on. As was discussed in Section 4 regarding the environmental clearance
process the design sub-phases, alternatives analysis, conceptual design, and
preliminary engineering are all interrelated with the environmental clearance
and process. The design phase will involve interaction with the real property
acquisition and third party coordination processes that were discussed in Section 4.
Reviews.
support of the environmental clearance documents.
q Perform Quality Control. Perform technical studies, develop engineering criteria, and
Basic elements for the example maintenance facility project to be included during
the conceptual design process include assessing the spatial area requirements
for general bus maintenance, fare removal, fueling, exterior washing, interior
cleaning, and bus storage. Additional space will be required for administrative
and operating staff offices, training rooms, lunch rooms, locker rooms, and
associated toilet facilities. Space will also be needed for parts storage, body and
paint shops, tire shops, and heavy repair areas.
On-site parking will be required for vehicles for employees and vendors who
will park on the site. Accommodations should be provided for such items as
landscaping, site security, stormwater management facilities, and potentially,
water treatment facilities.
Upon completion of site selection and acquisition, the overall site layout
considerations for daily operations at the bus maintenance facility in our example
project need to include queuing space for buses during the mid-day and evening
pull-in, bus circulation and storage space prior to maintenance and servicing, and
circulation area for buses to move to and from storage on the site. Entrance and
exit locations to and from the site to adjacent streets are also very important in
the consideration of the overall site layout.
Important to During the preliminary engineering sub-phase, the design team will finalize the
Know concept for the facility and any associated equipment, and finalize the design
Design Criteria criteria, and requirements for property/ROW and third party coordination work
that will be used for the final design sub-phase. The preliminary engineering
Codes
design should be developed to a point where the baseline capital cost and
Design Standards construction schedule can be developed.
Document Design Criteria The design team will develop the design criteria for
Standards the project based on the scope of work provided. Engineering analysis will
Drawings, establish a range of acceptable criteria or standards for the project. An
Specifications, example of an outline for the design criteria document that may be used for a
Estimate, Schedule,
project is provided in Figure 5-1. The project manager will review the service
and Calculations
characteristics and site constraints provided by the design team to make sure
Project that they satisfy the needs of the Project Requirements Definition (PRD). The
Requirements project manager will need to seek input from all stakeholders and based on their
Definition comments approve the design criteria in a timely manner. Once determined
Design Schedule the design criteria must not change unless otherwise approved by both the
project manager and the design team. A change of design criteria during either
Project Budget preliminary or final design may have significant implications on the design budget
and schedule, as well as the construction budget and schedule.
Important to
Know
Conceptual Design
Code Analysis
Zoning Analysis
Topographical
Survey
Boundary Survey
Existing Utility
Survey
Geotechnical Survey
Environmental
Alternative Analysis The design team will develop different concepts for
Survey the project within the identified design criteria. The design team will develop
attributes regarding each alternative that will allow the Agency to perform the
Space Programming analysis and prioritization of the options. This identification of the preferred
Alternative Layouts alternative will be moved forward into conceptual design by the design team.
Alternative Cost Conceptual Design The design consultant will develop graphic plans based
Analyses on functional requirements and safety as identified for the preferred alternative.
Community In addition, they will analyze the project site(s) to determine the initial "look
Outreach and feel" of the project once completed. The result of the conceptual design
is a set of architectural plans, elevations, landscaping plan, site boundary, and
Traffic Impacts
topographic surveys. Depending on the site complexity, the design may include
Noise Abatement other drawings such as grading, utility, and drainage plans.
Final Design
Federal law requires that final design cannot begin
Important to Know prior to NEPA completion as denoted by an FTA
Final Design Record of Decision (ROD), Finding of No Significant
Final Plans, Elevations, Sections, Schedules Impact (FONSI), or a Categorical Exclusion (CE)
determination. The final design team will develop
Detail Development
the construction bid package that contains the final
Final Technical Specifications drawings and specifications for the project required
Discipline Coordination to solicit and obtain construction contract bids.
The final drawings and specifications will also detail
Summary of Work Preparation
the property or ROW needed to accommodate
Temporary Facilities and Controls Defined the project, include the appropriate permits and
Federal, State, and Local Legal Requirements associated conditions from other agencies, and any
Bid Forms, Bonds, Prevailing Wages, Etc. coordination of work with or by third parties (e.g.,
utility companies) that was discussed in Section 4.
Final Design Calculations
The project manager will oversee the final design
Final Construction Schedule efforts of the design team through reviews of design
Final Construction Staging Plans drawings and specification submissions at the 60
Construction Cost Estimate Update
percent, 90 percent, and 100 percent complete
stages of design. In addition, value engineering (VE)
Environmental Permits will either be performed at the end of preliminary
engineering or early in final design. Using the various
Bid Forms, Bonds, final real property and ROW plans, design drawings, special provisions,
Plan Checks and Accept and evaluate the quality of deliverable. Verify adherence of the
Preparation
companies).
To help with the reviews, Figure 5-2 shows a typical Review Comment Register
that the project manager and the other reviewers can use to facilitate the review
during the various design reviews.
evaluation of the rejected alternatives with the design team. As such, the
The timing and duration of third party work requires careful planning,
Important to negotiation, and execution. This is due to the fact that third parties typically
Know need significant lead time to perform the necessary design and perform
Value Engineering is the relocation, or determine the interfaces of the third party that can be
a systematic, multi- incorporated into the contract provisions. Due to the limited influence
disciplined approach that an Agency has with respect to controlling the work of a third party,
designed to optimize the chance for a schedule impact on the project is likely. These risks will
the value of each
be identified as part of the risk assessment described later. Therefore,
dollar spent. To
the earlier that a third party agreement can be negotiated, the better
accomplish this goal,
understanding the project manager and the design consultant will have
an independent team
of architects/engineers of the overall schedule impact. A discussion on developing third party
identifies, analyzes, and agreements is provided in Section 9.
establishes a value for a
function of an item or Value Engineering
system.
Agencies are encouraged to apply VE techniques to all projects including bus
Value Engineering maintenance and storage facilities whose construction costs are estimated
is to satisfy the to exceed $2 million. The objective of VE is to satisfy the required
required function at functions of the project at the lowest initial total cost and cost over the life
the lowest total cost of the project. Figure 5-3 provides an overview of the VE process.
(capital, operating, and
maintenance) over When to Perform Value Engineering
the life of a project
consistent with the VE for a project should be performed early in the design process before
requirements of major decisions have been completely incorporated into the design,
performance, reliability, including civil, systems, and architectural areas. Ideally, the project manager
maintainability, safety, or the design manager will see that the VE is accomplished at or prior to the
and esthetics. end of preliminary design or before 30 percent of design.
Value Engineering on
How to Perform Value Engineering
a project should be
performed early in As the Agency's project manager, you will coordinate the VE session that
the design process will consist of a multi-disciplined team of professionals, who preferably
before major decisions are not part of the design team. VE personnel can include electrical,
have been completely mechanical, civil/structural, and construction engineers, as well as specialists
incorporated into the in architecture, cost estimation, construction management, and transit
design, at or near the O&M. The designer of record will provide support to the VE team. The
end of preliminary VE team leader could be a certified value specialist (CVS). For additional
design, or at 30 percent information on this certification visit the Society of American Value
of design. Engineers (SAVE) at www.value-eng.org.
Value Engineering
review could add
function and cost that
have not been thought
through previously.
Based on the VE proposals that will be adopted, you should consider providing
Important to
the design team with additional funds that are needed to implement the design
Know
enhancements that were identified as part of the VE.
Peer review can
Peer Reviews
be applied to any
problem or situation
where a second Peer review should be an early step in the design process that can add an
opinion can be external perspective to enhance the functionality of design, construction, and
useful. operation. Used in addition to a VE study, that is usually later in the design
Peer reviews are process, peer review is based on the question "can we do this better?" and can
intended to take be used to provide an independent critique of the design phase.
advantage of the
lessons learned Whether you or the team does or does not have previous experience with
by other agencies the overall design process, the team is encouraged to contact other transit
having done similar operations and maintenance experts, or PMCs in order to bring in and benefit
work in the past. from their experience with similar design efforts.
Although Agencies are encouraged to conduct a peer review for all capital
projects, FTA requires the peer review process for projects funded under the
Section 5309 discretionary program. These reviews are to make certain that bus
facilities are effectively designed to enhance bus operations. A review of plans
at the completion of preliminary design will be conducted using the expertise of
Important to transit operator peers who provide service under similar circumstances. The
Know FTA requires that peer reviews be coordinated with the FTAs regional engineer.
Constructability
reviews are
necessary prior
Constructability Reviews
to completion of Later in the design process, the design team will need to perform constructability
final design and reviews as part of the design process. Participants for constructability reviews
preferred at 60 can come from within your Agency, the design team, or assistance can be
percent design to obtained from other transit agencies, code officials, independent consultants, or
make certain what is contractors. The constructability reviews should be prior to completion of 90
depicted on the final percent and preferably shortly after 60 percent of the design. The purpose of
drawings, technical constructability review is to:
specifications, and
construction bid Eliminate construction requirements that are impossible or impractical to
built.
financial risks.
services, and utility connections.
- Design/construction Make certain that designs can be constructed using methods, materials,
risks include and equipment common to the construction industry.
weather conditions,
Pay attention to the requirements of the public including adjacent land
contractors' inability
use functions, existing transit patrons, and persons with disabilities.
to carry out the
project, unforeseen Make sure coordination is included with all operating elements of the
permitting delays, and Make certain adequate provisions are provided for access, staging, and
so forth. storage of waste and supplies; parking for worker and construction
- Financial risks include vehicles; and mitigation of environmental impacts during construction.
revenue shortfalls,
changes in the project Risk Assessment
cash demands, and During the design phase and preferably prior to completion of preliminary
changes in interest engineering, the project manager must facilitate performance of a risk
rates, among other
assessment to determine whether there are events or circumstances that
things.
can occur that will have a direct impact on the project's schedule and
Risk is defined in terms associated cost. As the design of the project gets more refined and nears
of an event (what may completion of the drawings and specifications, the more costly the impact of
occur to the detriment an unexpected event will have in terms of money and schedule. Therefore,
of the project), its teams risk assessment should be updated periodically through the design
probability (how likely
phase of the project, with the final update occurring prior to construction.
it is to occur), and
This risk assessment will be completed through the use of a risk register
the amount involved
process. An example of a risk register is provided in Figure 5-4.
(dollars of maximum
possible loss or number
of losses that could
occur).
A risk register will help the project team capture the risks associated with the
project and quantify the potential impacts to the project. To develop the risk
register, you should coordinate with the other key stakeholders via a meeting or
workshop to identify:
The following are a few examples of risks that may impact the development of a
project:
Budget Risks - Risk that budget elements will deviate from the estimate (e.g.,
deviations in unit prices, deviations in quantities).
Event Risks - Risk of internal or external events that force the project team
to work beyond the estimate just to meet the project scope and scope of
work (SOW) (e.g., extreme weather, contractor non-performance).
Scope Risks - Risk of significant changes to project scope due to external
pressures (e.g., community pressures for changes in bus shelter location or
increase in maintenance facility size).
Examples of risks that the Agency project manager and the design consultant
should consider for the project include:
Real Estate
- Property Acquisition
- Relocation
- Condemn
- Eminent Domain
Public Utilities
- Analysis and Coordination
- Agreements
- Relocation
Financial
Politics
- Internal/External
Environmental
Historical Significance
- Protected Lands
- Archaeological
- Structures
Contract phasing and packaging
- Scope of Work
- Bid Process/Labor
- Integrating Construction Packages
Community impacts and public perception
Public hearing
- Marketing/Communication
- Safety and Security
Material, Equipment and Construction Techniques
Once the risks for the project have been identified, they should be ranked
according to the probability of their occurring and an associated cost implication.
Then the project manager can prepare the risk management plan that will
establish and prioritize mitigation measures, allocate the risks to the appropriate
party (i.e., Agency, design consultant, contractor, third parties), and assign
mitigation and management responsibilities.
During the design phase, the project's risks can be monitored through peer
reviews, VE studies, and constructability reviews in an effort to design the
project within budget and schedule given the inevitability of unknowns.
Once the PMP is accepted, the QA/QC plan is set in place for the design portion
of the project. The plan should answer the questions of who is responsible and
when in time actions should occur. More important, the quality plan needs to
be maintained throughout the design phase so that as a new phase is initiated, it
will reflect the appropriate quality requirements. Since the primary product
Important to of the design phase is construction contract documents for construction
Know
contractors, decisions about quality requirements for construction and
Quality Control manufacturing need to be planned and included in the contract documents.
the act of taking Therefore, during the design phase of the project, you follow the design
measurements, testing, control portion of the quality management system that was put in place as
and inspecting a process
part of the PMP for the entire project.
or product to make
sure that it meets
specification. It also Quality Control in Design
includes actions by those QC during the design phase of projects is a very important part of a project-
performing the work related quality program. The design team is responsible for their own
to control the quality QC. The design team shall provide a quality management plan prior to
of the work. Products initiating design activities that identifies how they will achieve QC for the
may be design drawings project. The quality management plan describes the procedures that are
or specifications, to be followed for design changes, including sign-off and documentation. In
manufactured addition, any contract quality requirements for design reviews and sign-
equipment, or off from other departments within the Agency, such as construction and
constructed items.
operations, and other relevant Agencies must be stated. A procedure for
Quality Control also
the control of project documents should also be specified.
refers to the process of
witnessing or attesting Calculations, drawings, and specifications are checked by qualified
to, and documenting personnel not normally associated with their preparation.
such actions.
Verify the design against the scope.
Quality Assurance Constructability reviews make sure that the project includes the
making certain the application of sound construction principles consistent with operating
project requirements and maintenance requirements and accepted engineering practices for
are developed to meet safe, efficient, and economic construction.
the needs of all relevant
internal and external VE design reviews assure cost effectiveness.
agencies, planning the Design validations make certain that the project conforms to the
The LEED 2009 (V3) rating system has four levels of certification, which are
achieved by collecting design points. Certification levels and the associated point
ranges are:
Sustainable Sites
Water Efficiency
Energy & Atmosphere
Material & Resources
Indoor Environmental Quality
Innovation & Design Process
Regional Priority
Figure 5-5 is a copy of the LEED 2009 Project Scorecard for New Construction
and Major Renovations, showing the point distribution in each category, along
with identification of prerequisites required to be achieved to receive LEED
certification. The Scorecard is a checklist that can be used during initial design
activities to help establish the possible level of LEED certification for the building
project; or it can be just a guide to evaluate the types of sustainability features
that could be incorporated into the design of a new or renovated facility.
Figure 5-5
LEED 2009 Project Scorecard New Construction and Major Renovations (Pg 1 of 3)
Figure 5-5
LEED 2009 Project Scorecard New Construction and Major Renovations (Pg 2 of 3)
Figure 5-5
LEED 2009 Project Scorecard New Construction and Major Renovations (Pg 3 of 3)
Healthier and Commissioning is the Compliance Check that the design and building process
safer buildings for meets the LEED guidelines selected for the project. This is typically handled by
occupants. an outside party, independent of the design and construction teams.
Reducing harmful
Energy modeling is the comparison between the energy requirements for a
greenhouse gas
emissions. baseline version of the building in accordance to ASHRAE 90.1-2004 minimum
energy standards, and the performance of the building as designed with high
Qualifying for tax efficiency components.
rebates, zoning
allowances, and LEED certification documentation is the process of documenting compliance
other incentives in with the various LEED checklist criteria for submittal to the USGBC for review
hundreds of cities. and decision on certification. The commissioning process is executed by a
Demonstrating Commissioning Agent, who is responsible for making sure that the proper
an owner's sustainable guidelines and LEED documentation and certification requirements
commitment to are incorporated into the Contract Documents. During the value engineering
environmental studies, a Commissioning Agent makes sure that the systems are looked at as
stewardship and whole and not just pieces. When incorporating sustainable design, each system
social responsibility. affects each other and the removal of one system during value engineering can
affect other systems and actually make them cost more if you do not evaluate the
systems together. During the value engineering studies a Commissioning Agent
works with the Construction Manager to evaluate sustainable materials and their
cost impacts on the project. The sustainable design role that a Commissioning
Agent fills during the construction phase is to make sure that the contractors
understand what information they need to submit for the LEED documentation
in order for the project to receive the final LEED certification.
There is some uncertainty about how many of these costs are truly incremental
to the LEED process. Even though all the costs can be attributable to LEED;
some of these costs may also be reflected in standard construction practices
in certain regions, or in compliance with local codes and standards. Thus, they
are not necessarily an additional cost to the project due to the decision to seek
LEED certification.
- Lighting Systems
Construction Phase
In the construction phase contractors, procured by the Agency, combined
with the Agencys own forces, construct the projects facilities, and fabricate
and install equipment. The work is done in accordance with the plans and
specifications developed during the design phase. Following construction the
facilities and equipment are integrated and tested in the commissioning phase.
out and replacing construction. Delaying one contractor may delay other
Important to contractors resulting in further claims.
Know
q Make timely and decisive Role of the Consultant Construction Manager
decisions.
For all but the simplest project, you will need project staff with expertise and
q Acquire project experience in construction management beyond the capability and capacity
staff with expertise/ of the Agencys regular employees, for which the Agency will need to retain
experience in a construction manager (CM) consultant. The CM acts as the Agencys
construction representative with the contractors, oversees what work the contractors
management. perform pursuant to the contract drawings and specifications, inspects the
q Retain a Construction work as acceptable, and recommends payment of contractor invoices. The
Manager consultant if key CM staff is the resident engineer (RE) who is principal point of contact
Agency does not have with the contractor and is stationed at the site for larger projects and for
qualified staff. smaller projects visits the construction site one or more days a week.
q Delegate levels of
authority through the Role of the Design Consultant(s) in Construction
project team to handle Design consultant(s) who produced the contract drawings and specifications
construction issues such and sealed them with their professional engineering seal, are referred to as
as contractor change the designer(s) of record; and will continue to provide the following design
requests. services during construction:
q Continue the services of
Receive and respond to construction contractor Requests for
the designer of record to
Information (RFI), communicated from the contractor to the designer
respond to contractor
through the CM. An RFI is a request by the contractor for clarification
requests for information
of the design intent of the drawings and specifications.
and review change
requests that impact Review and recommend acceptance of contractor submittals called
design. for in the drawings and specifications with respect to the construction
deliverables.
q Complete third party
Review change requests and estimate costs for change orders.
work early in the project
so as to avoid delaying Make periodic visits to the site to assure design compliance and provide
follow on contractors. certification efforts as required by the permitting agency.
Assurance/Quality specifications using means and methods that are the contractors
Construction Management
proposals.
Construction
schedule control Project Organization for Construction
should focus on Figure 6-1 illustrates a project organization structure for construction for a
the high-level project with three construction contracts (yellow boxes), where the Agency
management of (blue boxes) has retained the services of a CM and a general engineering
interfaces between consultant (GEC) who is the designer of record (tan boxes). Delegation of
contractors, third
authority for RFCs is illustrated by the red arrows and lines of communication
parties, and other
for RFIs by green arrows.
construction
activities.
PROJECT ORGANIZATION, ASSIGNED AUTHORITIES
The RE and CA meet with the contractor on a regular basis to assess the
contractors progress. At these meetings the contractor reports on progress,
issues that arise in the field are addressed, and any disputes resolved. If disputes
cannot be resolved between the RE and contractor they are passed up the
project management chain of command as delineated in the PMP.
Partnering
As project manager you can use partnering to demonstrate leadership, build
positive working relationships between project parties, and help avoid and
resolve disputes.
Partnering is incorporated into the contract provisions and begins with a half-
day to two-day workshop held at the start of the contract facilitated by an
independent partnering consultant. Workshop participants are the contract
stakeholders including representatives from the Agency, CM, contractor, sub
contractors, suppliers, government agencies and third parties, design consultants,
special interest groups such as community and local business leaders, and local
fire/life safety officers. The workshop sets contract goals, identifies stakeholder
expectations, establishes lines of communication, and anticipates potential issues
and the means for their resolution.
Permitting
While the Agency is responsible for obtaining project clearances, environmental
permits, and plan checks by the construction permitting agencies (see sections
4 and 5), the contractor is responsible for obtaining permits related to the
contractors work. The cost and time involved are the contractors responsibility
and should be included in the contract price and schedule.
Schedule Control
Construction contractors control their contracts detailed schedule progress. As
project manager your focus is the big picture, the master schedule, to manage
interfaces between contractor, third party, and Agency construction activities.
Your approach to master schedule control depends on the projects size and
complexity:
For larger and more complex projects you will require the CM to provide
a scheduler to monitor construction progress using scheduling software to
maintain a master schedule of construction activities.
For smaller projects the use of hand drawn bar charts worked out directly
with the RE(s) should be adequate to serve as a master schedule for you to
oversee construction progress.
Large or small, to control the project schedule as project manager you should:
Figure 6-3 below describes the types of changes that occur during construction
and indicates whether the contractor is entitled to receive additional
compensation for the change.
discussed below.
Configuration Management
The project manager should put in place procedures to provide for the
configuration management of (i) Contractor RFCs, red arrows in Figure 6-1, to:
describe the changes nature and justification, and indicate whether the
The project manager should put in place procedures to provide for the
configuration management of Contractor RFIs and submittals, green arrows in
Figure 6-1, to:
Document the CMs receipt of RFIs from the contractor, track and expedite
the CMs response, and coordinate information from the designer of record
where design issues are involved.
Document the timely receipt of contractor submittals called for in the
contract specifications and track their review/acceptance. Submittals include:
contractors schedule, safety plan, quality plan, shop drawings, progress
reports, invoices, record drawings and documents, and operations and
maintenance manuals.
Document Control
Document control is the management of records generated during construction.
In addition to the records associated with changes, RFIs, and submittals discussed
above, document control procedures are needed to handle reporting of
construction progress including:
Site records that include a daily log of site activities, occurrences, weather,
equipment, personnel, and communications.
Inspection Report of contractors work and practices observed by the CMs
construction inspectors covering construction work performed, instructions
given or received, unsatisfactory conditions, delays encountered, manpower
and equipment, or other problems.
REs weekly Construction Report of all items of importance, conferences
with the contractor or other parties, agreements made, special notes
regarding equipment or organization, labor conditions, weather or other
causes of possible delays, and other matters that have a bearing on the
history of the job.
Safety management and accident reports.
QA/QC reports.
Progress Payments
Management of progress payments begins with the contract specifications clearly
stating how the contractors work progress is to be measured, how payments are
determined based on the measured progress, and what documents and reports
are required to be submitted by the contractor to justify the payment request.
The project manager should authorize payment only when the contractors
progress payment request is in full compliance with the contract requirements
and the progress claimed has been independently verified by the CM.
of the relocation to upgrade the relocated facility. The project manager should
agree to reimburse the third party only for the cost of relocating the equivalent
facility and any additional costs for upgrades should be borne by the third party.
The Agency performs scheduled audits and periodic oversight reviews to ensure
contractors comply with their quality plans and overall Agency QA policies. To
avoid conflicts of interest between project progress and quality management
the Agencys quality manager should report outside of the project managers
chain of command. The project manager should set a tone for the project that
emphasizes quality management and supports the Agencys independent quality
manager.
Audits
The Agencys quality management plan should include a comprehensive program
of periodic audits. The audits are to verify that the CM and contractors have
effectively implemented and are in compliance with, applicable elements of the
quality management plan. Follow-up audits, including re-audit of deficient areas
will be conducted to assure that effective corrective action has been taken.
Enforcement
Contractors enforce safety by developing a Job Hazard Analysis for the work to
be undertaken and discussing actions needed to provide safety at jobsite planning
meetings. Supervisors draw on their safety experience to direct the actions of
those under their direction. Contractor staff should include a safety professional
Education
Contractors give newly employed, promoted, and/or transferred personnel
comprehensive safety indoctrination on topics such as: workplace hazards,
required protective equipment, procedures for reporting unsafe job conditions,
procedures for reporting accidents, contractor job rules, location of first-aid
and medical facilities, and tool box safety meeting requirements. Safety should
be a standing item at site meetings. Foremen or shift supervisors should also
hold regular crew training (toolbox) meetings to cover specific safety procedures
pertinent to the crews on-going activity.
Incentives
Contractors should display signs and posters at the job site to reinforce safety
training and as an incentive to maintain interest in job safety with the changing
work assignments and jobsite conditions. The Agency should encourage
contractors to introduce employee incentive programs that reward safe work
performance through personal recognition and prizes such as belt buckles, pins,
or lunch boxes.
Audits
The Agency through the CM monitors and conducts regular audits of contractor
safety performance and notifies the contractor in writing of unsafe practices
observed. Should a contractor fail to correct an unsafe condition or practice,
the CM may recommend that the Agency issue a stop work order until the
condition is corrected.
Figure 7-1 below is a typical responsibility matrix that shows the lead personnel commissioning tasks including testing.
Submittals:
Prepare Equipment, O&M Proof of design, Prepare Perform
Team plans and Manuals, and construction and integrated test integrated Safety As-built Warranty Team
Members specifications Warranties manufacturing tests procedures tests Training Certification drawings Administration Management
Designer of
Lead Support Support Support
record
Construction
Support Support
Manager
Construction
Lead Lead Lead Lead Support
Contractor
Project
Lead
Manager
Commissioning
Lead Lead Support
Team
Operations Support Support Support Support Support
Safety and
Security Lead Support
Department
Procurement
Lead Support
Department
Agency top
Support
management
Figure 7-1 Typical Responsibility Matrix for Commissioning Tasks (Design-Bid-Build Delivery)
SECTION 7: COMMISSIONING
Figure 7-2 LEED ITEM HVAC System (and all integral equipment controls):
Typical Equipment X 1. Pumps (chilled water) if required
Commissioning List X 2. Chillers if required
X 3. Piping, cleaning, and purging
X 4. Chemical treatment
X 5. Ductwork
X 6. Air handling units
Heating/A.C (including controls, piping, pumps, compressors) recovery &
X 7.
ventilating units
X 8. Split systems
X 9. Air terminal units
X 10. Testing, adjusting, and balancing work (TAB)
X 11. Unit heaters (area, cabinet)
Building automation system (controlled devices, control loops, and
X 12.
system integration)
X 13. Fans & ventilation systems including fume and exhaust evacuation systems
X 14. Variable frequency drives
X 15. Humidifiers
The project manager, with support from the commissioning manager and led by
the safety and security personnel, should consider self-certification of the project
for satisfactory compliance with a formal list of hazards and applicable safety
and security requirements. The self-certification will document all actions taken,
identify and close gaps, and assure the stakeholders of the Agencys commitment
to safety and security. The responsible parties self-certify by signing off on this
document.
In addition, the Agency should establish strong ties with emergency response
agencies and resources to provide mutual assistance in an event of major
emergencies on or near the project. Emergency preparedness requires
working with local emergency management groups to develop procedures and
contingency plans specific to the location and the nature of the project, and
perform specific drills to simulate emergencies.
As-Built Documentation
The project manager should assure
Important to the construction contract calls for the
Know
contractor to mark up the changes
The construction on the drawings and specifications as
contractor should they occur during construction and
mark up the
turn in a set of marked up drawings
drawing as changes
and specifications. Under general
occur.
direction of the project manager, the
The designer of the construction manager verifies the
record reviews, construction contractor is keeping
approves, and the drawings up to date. The project
documents the manager should provide in the agreement with the designer of record scope for
changes into final the designer to review, approve, and produce the final as-built drawings.
as-built drawings
and conformed The commissioning manager will use the as-built documentation as necessary to
specifications. commission the project. As-built drawings will save significant life cycle costs
and avoid potential safety hazards during operations and life of the facilities. The
commissioning manager will review the final as-built drawings and assure they are
a part of the final commissioning report.
from principal maintenance (O&M) manuals for the facilities constructed and equipment
stakeholders.
installed and provides any associated training of Agency staff in their use.
q Celebrate project
completion. Beneficial Occupancy A contract is substantially complete when the
permitting authority issues a Certificate of Beneficial Occupancy to the
Agency and then the Agency can occupy and begin use of the facility and
equipment. It is important on taking beneficial occupancy that you ensure
the construction manager/resident engineer prepares a punch list of open
items for the contractor to complete.
Contract Audit Where contract payments are on a cost plus fee basis,
the contract provisions should give the Agency the right to audit the
contractors costs. The audit should verify items such as direct labor rates,
support for time charges, support for other direct costs, and justification
for overhead rates.
out. difficult to relocate off the project because there is no immediate position
Project Evaluation
Before the project is over and key project staff has dispersed, it is desirable
for the project manager to hold a lessons learned session. The lessons
learned should focus on identifying project strengths and weaknesses with
recommendations on how to improve future performance on projects. To
be most effective the project manager should encourage the project team to
identify and document lessons learned through the project life cycle so that a
database of lessons learned experience is built up for consideration at the final
lessons learned session. Lessons learned can consider technical, managerial, and
process aspects of the project.
Stakeholder Closure
Perhaps the most important aspect of completing the project is to achieve
acceptance and closure of the project by the projects principal stakeholders,
those who sponsored the project, and those that are to use the facilities and
equipment delivered by the project. The Project Authorization and PRD
documents formally set out the expectations for the project. The project
manager should now receive formal confirmation that with the handover of the
project deliverables from the project team to the operational users, the project
sponsors and users have officially accepted the project deliverables.
This formal acceptance is also the opportunity to celebrate project success with
some ceremony to mark the opening of the new facility and equipment into
operations.
Scope
The work package elements are assigned to the design consultants, contractors,
third parties, and the Agencys own forces. In addition to using the WBS to
define scope, budgets and cost estimates are developed for each WBS work
package element and the activities of the WBS work packages are scheduled to
define and control the projects cost and schedule as discussed below.
Often the scope changes also result in changes to the scopes of work of the
design consultant and/or construction contracts, in which case the projects
change control processes should be used to process the associated contract
changes. Additionally, the impact on the projects cost and schedule needs to be
assessed with corresponding updates to cost and schedule as discussed below.
Cost Control
Cost control is based on continually refining the projects cost estimate at
completion as the project progresses and taking management action to address
adverse variances in the cost estimate compared to the baseline budget. As
with the scope baseline, the cost baseline is developed at the conclusion of
preliminary engineering. You should manage the preliminary engineering so that
the baseline cost estimate for the selected scope configuration is in an acceptable
range of the estimated project cost at the time the project was authorized and
the project requirements definition prepared.
The baseline cost estimate must include allocated and overall unallocated
contingency funds that are established based on deterministic or probablistic risk
assessment.
You should track the projects cost performance against the baseline budget as
design and construction progresses and contracts are awarded, costs incurred,
project changes identified, and cost trends forecasted based on expected future
scope and/or contract changes. The projects cost at completion should be
continually reforecast and management action taken to address adverse cost
variances.
The WBS is again the key control tool. The baseline budget and cost estimates
are developed for the WBS work package elements. The assignment of the
elements to design and construction work packages provide the means to track
the costs as they develop by the same categories as the work is performed. In
addition, as the scope control is also by the same work package elements, the
WBS provides for consistency in assessing changes in scope and assessing the
corresponding impact on costs for the affected WBS work package elements.
Figure 9-3 provides an example format for a WBS cost control report for the bus
maintenance facility project.
2 Design
---
3 Construction
---
4 Commissioning
---
9 Contingency
Total Project
Notes:
(a) Baseline Budget: Control budget against which project cost performance is measured and controlled
(b) Committed: Value of project contractual commitments to contractors and/or internal work orders to Agency's own forces
(c) Incurred: Project costs to date incurred by contractors and/or Agency's own forces
(d) Estimate to Complete: Forecast of estimated costs to go in order to finish the remaining work on the WBS element/package:
for construction in design - the forecast is based on the current capital cost estimate for the construction package; for contract
work in progress - the forecast is based on the outstanding commitment (b - c) plus the forecast value of any pending and/or
expected contract changes; for Agency own forces work - the forecast is based on the expected cost of the remaining work.
(e) Estimate at Completion: Forecast of the final cost of the work element/package (c + d)
(f) Variance: Comparison of the Estimate at Completion to the Baseline Budget (a - e): positive variance indicate forecast project
costs better than budget; negative variances are forecast to be worse than budget and indicate to the project manager where
action needs to be taken to address forecast adverse project cost performance.
You should include formal cost reviews at the following project milestones and
major events:
that remain with the Agency and could result in contract changes. Where major
contract changes have occurred, are pending, or forecast, the expected final
contract cost should be updated. At each of these types of review, management
action should be taken to address adverse cost trends so that the final cost of
the project can be maintained within the cost baseline.
You should have in place cost control procedures to provide for transfers in
budget between WBS elements as the project evolves so that, for example,
cost savings in one area can be used to offset overruns elsewhere, or scope is
transferred along with budget from one area of the project to another. The
procedures should provide for the appropriate levels of management approval to
transfer budget and the maintenance of an audit trail of budget transfers so the
current budget can be tied back to the original baseline.
Unforeseen events may result in the need to make hard trade-off decisions
between scope, budget, and schedule. For example a part of the projects
scope may have to be reduced in order to keep costs within budget following
an unforeseen change that exceeds the outstanding contingency. Alternatively,
an increase in the projects final cost may be agreed to in order to keep the
project on schedule following delays in progress due to unforeseen construction
conditions. Project procedures should require that significant changes in scope,
schedule, or budget from the baseline receive the approval of the projects
sponsors, which in our example maintenance facility project would be the
Agencys board.
Schedule Control
The WBS is again the starting point for schedule control. Work activities are
identified for each of the WBS work package elements and form the building
blocks of the project schedule. For relatively simple projects you can represent
the activities using a bar chart schedule and the time from the beginning of the
first bar (start) and the end of the last bar (finish) is the duration of the project.
More complex projects, such as our example maintenance facility project require
a critical path method (CPM) schedule.
precedence diagram and activity durations is then input into a CPM software
scheduling program that calculates the projects critical path. The critical path
is the path through the network that has the longest duration and therefore
determines the duration of the project. The sums of the durations along all
other paths through the network are shorter than the critical path. Figure
9-4 shows a simplified precedence and critical path for the maintenance facility
project.
As with the scope and cost baseline, the schedule baseline should be developed
at the close of conceptual design/preliminary engineering. As the project
progresses through final design and construction the schedule performance
is monitored, the outstanding durations of incomplete activities estimated,
the critical path updated and compared to baseline. You should then take
management action to address schedule slippages of critical and near critical
activities.
Project Administration
Project Accounting
Important to
Know The Agencys accounting department performs accounting functions for the
project including:
Project accounting
reports project Developing the fiscal year budgets for the project
expenditures in
compliance with Recording and reporting expenditures in the Agencys accounts
generally accepted Review and payment of contractor invoices
accounting practice, Management of project cash flow.
administers the
projects accounts The total project budget typically spans multiple project years. Agency
payables, and accounting works with project staff to develop the fiscal year budgets as part of
manages the project the Agencys annual budget. In addition to being by fiscal year, the accounting
cash flow. project budget is broken down by the Agencys chart of accounts as opposed to
the WBS breakdown used for project control. For these reasons an Agency that
Grants management
applies for project relies only on accounting information to manage project costs (that is fiscal year
funding from and chart of account based) and does not create a project cost control system
federal, state, and (that is project-to-date and WBS based) finds that cost data appropriate for
local agencies, accounting controls is not helpful from a project cost management point of view.
draws down funds
to meet project Similarly, accounting records project expenditures by the Agencys chart of
expenditures, and accounts and report the results against the fiscal year budgets. In setting up
reports project procedures to process project transactions you should give careful consideration
status to funding to ensuring that costs are coded by both their WBS and accounting codes so that
agencies. they can be processed through both the cost control and accounting systems.
Administrative The project team is responsible for reviewing consultant and contractor invoices
support provides to confirm that the services or work invoiced has been acceptably completed.
for the project Accountings role is to review the invoices to confirm that they are computed
office facilities
accurately, that the charges billed are contractually eligible, and that the charge
and clerical and
rates and/or prices are consistent with the contract terms. Following review,
administrative staff.
accounting is responsible for paying the invoice having made adjustments for
retainage and any disallowed charges.
Accounting, through its treasury function, manages the cash flow for the project.
Accounting works with the project team to project both the near and long term
cash flow requirements for the project so that funds are made available for
project expenditures without tying up the Agencys cash. Accounting invests
funds raised for the project that are not immediately required in a mix of short
and long term investments based on the cash flow projections.
Grant Management
Grant management involves:
Application for grant funding from the FTA and/or state and local funding
agencies
Reporting of project progress
Drawing down and management of grant funds during project
implementation.
Once a grant has been approved the regional engineer will monitor project
milestones and progress reports that the grantee submits through the TEAM
system. After a grant has been awarded the Agency will draw down funds for
reimbursement of project expenses using the FTA Electronic Clearing House
Operation (ECHO) system.
Administrative Support
Administrative support involves providing the project office facilities and clerical/
administrative staff. Wherever possible a project team works most effectively
when the team members, including both Agency staff and their consultants, can
be co-located in the same project office. Large projects can justify the cost of
setting up a special project office for this purpose. An effective compromise for
mid size and smaller projects, such as our example maintenance facility project, is
to set aside workspace in the Agencys office and require the projects principal
consultants to use this space when working on the project.
As the demands of a project change as the project moves through its phases, it
is desirable to select administrative support staff who thrive on variety and are
flexible to take on a range of administrative tasks where the workloads can vary
from day to day.
description.
- The procurement lends itself to a firm fixed price contract and the
State law usually restricts the method of procurement more tightly than these
federal requirements.
Professional Services
Contract Types
To contract for professional services, you have two main methods:
contracting for A&E services, you will need to use competitive proposal
For further details regarding each selection method, you should refer to FTA
Circular 4220.1E, Section 9, Procurement Methods.
Contract Provisions
When procuring for professional services, you will need to coordinate with
your Agency's contracting officer. When developing the contract provisions
you and the contracting officer should review the 54 mandatory procurement
standards listed in Appendix B.19 of FTA Circular 4220.1E and determine the
provisions that apply to the particular procurement. In addition, to receive
federal funds, you will need to determine which of the 31 federal statutes and
regulations presented in Appendix A.1 of the FTA Best Practices Procurement
Manual (BPPM) applies to the project. Finally, you will also need to make sure
your Agencys required terms and conditions (clauses, etc.) are included in
the advertisement. This will allow the A&E firm to address these terms and
conditions as part of the proposal. Any exceptions taken by the A&E firm
to terms and conditions should be included in the price proposal only, as this
recognizes that contract terms involve risk allocation and therefore cost.
Procurement Process
The procurement process for professional services is a multi-step process. The
following are the key steps that occur in the process. For additional information,
refer to Section 6.5 of the BPPM.
of getting the award. You should check your state laws to determine if a
minimum number of firms are required to be short-listed.
Request technical proposals. If you determine to require detailed technical
proposals after the short-list has been determined, you will need to establish
the evaluation criteria to be used in selecting the successful contractor and
to advise the firms of the criteria in your RFP. Criteria would normally
involve past performance, technical criteria, and key personnel.
Evaluate the technical proposals. The selection committee will review the
submitted technical proposals within the criteria that were set forth in the
RFP.
Oral presentations by A&E firms. If the selection committee feels that oral
presentations are needed, they should be scheduled with the short-listed
firms. It is important that the actual project managers are being proposed by
the short-listed firms assigned to the project.
Final rank of firms. After the technical evaluation and oral presentations (if
held), the selection committee will finalize the ranking of the firms.
Once an agreement is reached on the highest qualified firm, that firm is then
requested to submit a cost proposal for negotiation of a contract.
Contract Negotiations - The Brooks Act requires a qualifications based
procurement method for the selection of A&E firms. Price is excluded as
an evaluation factor, and negotiations are conducted with the most qualified
firm only.
Construction Contracts
The traditional approach has been to have a detailed design completed for the
entire project prior to soliciting bids from construction contractors. This is
known as design/bid/build (D/B/B). This D/B/B approach requires that a detailed
design package of the entire project be complete before bids are solicited from
construction contractors. For the procurement of contractors, the most
common method of procurement is Procurement by Sealed Bids/Invitation
for Bid. Bids are publicly solicited and a firm-fixed-price contract (lump sum
or unit price) is awarded to the responsible bidder whose bid, conforming to
all the material terms and conditions of the bids, is the lowest in price. These
services must be procured in a manner that conforms to applicable state and
local law, the requirements of FTA Circular 4220.1E relative to the method of
procurement used, and all other applicable federal requirements.
Contract Provisions
Construction contracts require certain provisions which are unique to that
activity. These provisions are discussed in detail Chapter 6 of the BPPM.
Following is a summary of the special provisions and the BPPM sections where
they are discussed.
Labor The three wage and hour laws governing federally assisted
construction are the Davis-Bacon Act, the Contract Work-Hours and Safety
Standards Act, and the Copeland Anti-Kickback Act.
Bonding Construction contracts require contractors to furnish three
Closeout.
When developing the contract provisions for sealed bid procurement, you
along with the Agency's contracting officer should review the 54 mandatory
procurement standards listed in Appendix B.19 of FTA Circular 4220.1E and
determine the provisions that apply to the particular procurement. In addition,
to receive federal funds, you will need to determine which of the 31 federal
statutes and regulations presented in Appendix A.1 of the FTA BPPM applies to
the sealed bid document.
Procurement Process
The procurement process for construction is a multi-step process. The following
are the key steps that occur in the process. For additional information, refer to
Chapter 6.5 of the BPPM.
Contract Types
For the procurement of equipment, you will need to perform a lease versus
purchase analysis to determine the most economical approach. The analysis
should be appropriate to the size and complexity of the procurement. While
it is usually more economical to purchase equipment than to lease it, this is not
always true, however, especially when highly complex equipment is involved and
there are issues of maintaining the equipment or having trained personnel who
are competent to operate the equipment. The factors that must be considered
when performing a lease versus purchase analysis are discussed in detail in
Chapter 6.2 of the BPPM.
Contract Provisions
When developing procurements for equipment and supplies, you along with
the contracting officer must be aware of local or state labor laws, as well as
federal laws if construction is involved (e.g., Davis-Bacon Act), when developing
the solicitation document and contract. In addition, the contract officer should
carefully coordinate the insurance provisions with their insurance department or
legal specialists. Requirements might include coverage for commercial general
liability, auto vehicle insurance, workers compensation, and perhaps, a special
railway protective policy. The Agencys insurance specialists should determine
specific coverage requirements and amounts.
Once the preliminary initial utility alignments have been identified, you should
initiate discussions with the utility regarding the development of the utility
agreement. The scope of the utility relocation must be determined as well as the
responsibility for costs of the relocation. As part of this discussion, determine:
The utility's policy for relocating its own utilities or if it wants the relocation
performed under the relocation activities of the project.
Who is responsible for the relocation costs. Only actual allowable, allocable,
Important to and reasonable costs are reimbursable. If costs are to be covered by the
Know Agency, determine what these costs are up front, and begin negotiations.
A Disadvantaged The costs of the relocation are not always borne by the Agency. Cost
Business Enterprise sharing must always be considered as a feasible alternative.
or DBE means a If a utility elects to improve, change, rearrange, or otherwise enhance its
for-profit small facilities beyond that which currently exists, you should obtain separate
business concern estimates to identify the cost difference between the improved adjustment
that is at least 51 and the adjustment that is comparable to the existing facility.
percent owned
by one or more The ideal situation is to have signed agreements and all utilities relocated prior
individuals who to the general contractor receiving a notice-to-proceed on the main project. If
are both socially this is not possible, all affected utility facilities need to be shown in the project
and economically documents and relocation will be made concurrent with the construction
disadvantaged, activities. Coordinating the availability of the project site with the project's
or, in the case of general contractor and the utility will be very important. Once the utility
a corporation, 51 agreement is in place, you will need to oversee or perform the following as part
percent of the stock of administering the utility agreement:
of which is owned
by one or more Conduct a utility pre-construction meeting.
such individuals; and Monitor the relocation work.
whose management
and daily business Provide oversight of progress. Any slip in the schedule of the utility
operations are relocation will have an effect on main construction project's schedule.
controlled by Inspect the utility relocations to ensure that all work is performed according
one or more of to the Agency's expectations.
the socially and
economically DBE Requirements
disadvantaged Any third party contract that you award, funded in whole or in part with Federal
individuals who Department of Transportation (DOT) funds, is subject to the DBE regulations
own it. in 49 CFR Part 26. It does not matter whether the federal funds are for
planning, capital, or operating assistance, the DBE rules apply. This does not
mean, however, that every procurement or contract must be reviewed for DBE
participation. The rules give you the flexibility regarding how and when they
establish individual contract goals. Certain types of procurements (e.g., off-the-
shelf commodities) may not have subcontracting opportunities or be appropriate
for DBE goal setting.
While the U.S. DOT has a national goal of 10 percent, this goal does not apply to
individual Agencies or their contractors. Therefore, Agencies are not required
to set their overall or contract goals at 10 percent or any other particular level.
Agencies are to set goals based on what will achieve a level playing field for DBEs
in their own programs, without regard to the national DOT goal.
It should also be noted that a contract that is funded entirely with local funds,
without any federal funds, is not subject to the DBE requirements under this rule.
Project Communications
In accordance to the Project Management Plan, the project manager or delegated
personnel should prepare a communication plan for the project that addresses
the following:
Community Relations
Important to
Know Most transit-related projects have an impact on the community. The project
manager should inform the general public, business groups, and civic associations
Most transit
as to the goals, facts, and progress of the project. The Agency through the
projects impact
the community project manager should encourage community input and comments during
and therefore need the project design and adhere to any local, state, or federal comment period
informing. regulations that apply to the project.
Every media contact You should pay special attention to making certain that the residents, businesses,
is an opportunity to and general public in the vicinity of project construction are kept informed of
communicate your the status of construction and its possible impact on the community. To assist
project message. in this effort on larger projects it is beneficial to open a local store front office
Good conveniently accessible to the community, hold community meetings, and visit
communications local schools.
with government
stakeholders means Public Agencies have the policy and obligation to ensure that DBEs have the
no surprises. opportunity to compete for contracts and perform work on Agency projects.
The project manager should communicate with the DBE community to make
Regular certain that they are informed on project contracting opportunities. You should
project team refer to Agency records of DBE firms interested in performing project work
communications
as subcontractors and make this available to principal professional service and
maintain
contracting firms competing for project contracts.
Media Communications
Project managers should be accessible and responsive to media requests for
information and comment. However, communication with the media needs to
be coordinated by and channeled through the Agencys media communications
personnel. The project manager should make certain that project staff,
consultants, and contractors do not contact or respond to the media unless
requested to do so by the Agencys communications personnel. Contacts by the
media to project personnel, consultants, or contractors should be immediately
referred to the Agency communications personnel.
All contacts with the media should be viewed as opportunities to get the
Agencys message out on the status of the project through briefings and press
releases covering project facts, events, and progress of interest to the media.
Special events are a particularly good time for messages to the media, e.g.,
ceremonies to mark groundbreaking, significant project achievements, dedication
ceremonies upon the completion of project facilities, tours of the project, and
local community events.
Government Relations
The most important principle the project manager needs to remember with
respect to government relations is no surprises. Whatever developments
take place on the project, good or bad, it is critical that you make certain that
the government stakeholders are kept informed and do not learn of events from
other sources, particularly the media. You should make full use of your Agencys
government relations staff to help you keep government stakeholders fully
informed. To do this you need to keep the government relations staff informed
on project issues and status, and give priority to responding to requests from
government relations staff on project issues.
The project manager should ensure that incoming and outgoing correspondence
and documents are transmitted through the projects records management
specialist, who can use records database software to computer index the
records. Working copies of records can be retrieved by records management
for use by project staff. Records management should securely store original
copies and ultimately dispose of the records according to the Agencys and the
projects records retention schedule.
The project manager should not allow project staff to keep their own files of
original project documents or correspondence. Records management should
maintain the projects active and historical records and files in order to provide
efficient access and complete audit trails of the current status and record of
revisions to the project design and baseline documentation and associated
correspondence.
FTA HEADQUARTERS
Federal Transit Administration
1200 New Jersey Avenue, SE
East Building, 4th and 5th Floors
Washington, DC 20590
Office of Communications and
Congressional Affairs
Telephone: (202) 366-4043
REGION 1
Transportation Systems Center
Kendall Square
55 Broadway, Suite 920
Cambridge, MA 02142-1093
Telephone: (617) 494-2055
Fax: (617) 494-2865
Areas served: Connecticut, Maine, Massachusetts, New Hampshire, Rhode
Island, and Vermont
REGION 2
One Bowling Green
Room 429
New York, NY 10004-1415
Telephone: (212) 668-2170
Fax: (212) 668-2136
Areas served: New Jersey, New York, and U.S. Virgin Islands
REGION 3
1760 Market Street
Suite 500
Philadelphia, PA 19103-4124
Telephone: (215) 656-7100
Fax: (215) 656-7260
Areas served: Delaware, District of Columbia, Maryland, Pennsylvania, Virginia,
and West Virginia
REGION 5
REGION 6
819 Taylor Street
Room 8A36
Fort Worth, TX 76102
Telephone: (817) 978-0550
Fax: (817) 978-0575
Areas served: Arkansas, Louisiana, New Mexico, Oklahoma, and Texas
REGION 7
901 Locust Street
Suite 404
Kansas City, MO 64106
Telephone: (816) 329-3920
Fax: (816) 329-3921
Areas served: Iowa, Kansas, Missouri, and Nebraska
REGION 8
12300 West Dakota Ave., Suite 310
Lakewood, CO 80228-2583
Telephone: (720) 963-3300
Fax: (720) 963-3333
Areas served: Colorado, Montana, North Dakota, South Dakota, Utah, and
Wyoming
REGION 10
Jackson Federal Building
915 Second Avenue, Suite 3142
Seattle, WA 98174-1002
Telephone: (206) 220-7954
Fax: (206) 220-7959
Areas served: Alaska, Idaho, Oregon, and Washington
Section 1
Federal Transit Administration: www.fta.dot.gov
49 CFR Part 611-Major Capital Investment Projects http://www.access.gpo.
gov/nara/cfr/waisidx_03/49cfr611_03.html
Project and Construction Management Guidelines, 2003 Update. http://
www.fta.dot.gov/publications/reports/publications_3875.html
Best Practices Procurement Manual http://www.fta.dot.gov/library/admin/
BPPM/
FTA Circulars, http://www.fta.dot.gov/laws/leg_reg_circulars_guidance.html
SAFETEA-LU Federal Register Notices, http://www.fta.dot.gov/index_6533.
html
National Transit Institute: www.ntionline.com
American Public Transportation Association: www.apta.com
Transportation Research Board: www.trb.org
International Association of Public Transport: www.uitp.com
Project Management Institute: www.pmi.org
A Guide to the Project Management Body of Knowledge (PMBOK Guide)
Section 2
United States General Accounting Office, Leading Practices in Capital Decision-
Making, Accounting and Information Management Division GAO, December
1989.
Section 3
Federal Transit Administration,
Project and Construction Management Guidelines," 2003 Update. http://
www.fta.dot.gov/publications/publications_3875.html .
Best Practices Procurement Manual www.fta.dot.gov/library/admin/BPPM
Section 4
Environmental Impact and Related Procedures (23 CFR part 771), http://www.fta.
dot.gov/documents/NEPA_reg_clean.pdf
The National Environmental Policy Act of 1969, http://www.fhwa.dot.gov/
environment/nepatxt.htm
Real Estate Acquisition Guide for Local Public Agencies, http://www.fhwa.dot.
gov/realestate/lpaguide/
The Uniform Relocation Assistance and Real Property Acquisition Policies Act of
1970 (Uniform Act), http://www.fhwa.dot.gov/realestate/ua/
Land Acquisition Guidelines, http://fast.faa.gov/realestate/land/l-land.htm
Federal Transit Administration,
Planning & Environment Website, http://www.fta.dot.gov/planning_environment.
html
General Acquisition & Relocation Information, http://www.fta.dot.gov/
documents/FTA_Trifold.pdf
Real Estate, http://www.fta.dot.gov/region5_5937.html
Section 5
Federal Transit Administration,
Project and Construction Management Guidelines," (2003 Update).
"Third-Party Contracting Requirements," C 4220.1F, (November 1, 2008).
Quality Assurance and Quality Control Guidelines," FTA-IT-90-5001-02.1,
(February 2002).
Section 6
Project Management Institute, Construction Extension to A Guide to the Project
Management Body of Knowledge (PMBOK Guide) Project Management
Institute, 2003.
Federal Transit Administration
C 4220.1F., "Third-Party Contracting Requirements," (November 1, 2008).
Project and Construction Management Guidelines," 2003 Update.
Crowell, R.D., and Dixon, S.A., DPICs Contract Guide. DPIC Companies, Inc.,
1999.
Section 7
American Society of Heating, Refrigerating, and Air Conditioning Engineers
(ASHRAE), http://www.ashrae.org/
Institute of Electrical and Electronics Engineers, http://www.ieee.org/index.html
Federal Motor Carrier Safety Administration Regulations, http://www.fmcsa.dot.
gov/rules-regulations/administration/fmcsr/fmcsrguide.aspx?Section_type=A.
htm
Occupational Safety and Health Administration, http://www.osha.gov/
Section 8
Federal Transit Administration
Circular 5010.1D Grant Management Requirements http://www.fta.dot.gov/
laws/circulars/leg_reg_8640.html
PMO Lessons Learned references in Guidelines, September 11, 2003
Project and Construction Management Guidelines, 2003 Update.
Project Management Institute, A Guide to the Project Management Body of
Knowledge (PMBOK Guide) -Third Edition Project Management Institute.
2004.
United States General Accounting Office, Leading Practices in Capital Decision-
Making, Accounting and Information Management Division GAO, December
1989.
Section 9
Federal Transit Administration
Best Practices Procurement Manual, (October 2005).
Sample Master Agreement, Section 15, Procurement, FTA MA(17),
(October 1. 2010 Version).
Sample Master Agreement, Section 16, Leases, FTA MA(17), (October 1,
2010 Version).
Project and Construction Management Guidelines, (2003 Update),
Appendix C, Utility Agreements.
Third-Party Contracting Guidance, C4220.1 F, (November 1, 2008) http://
www.fta.dot.gov/laws/circulars/leg_reg_8641.html
Project Management Institute, A Guide to the Project Management Body of
Knowledge. (PMBOK Guide) Third Edition Project Management Institute,
2004.
Kerzner, H. Project Management: A Systems Approach to Planning, Scheduling and
Controlling. 9th Ed, John Wiley, 2005.
A
A&E. See Architectural and Engineering Services.
acceptance criteria, 21, 22, 50, 70, 73, 78, 92, 94, 95, 96, 99, 113
accessibility, 34
accident investigation, 84
accounting, 23, 28, 108
acquisition process, 43
acquisitions
real estate, 1, 2, 23, 32, 33, 37, 41, 59
right-of-way, 49, 73
ADA. See Americans with Disabilities Act.
administration, project, 46, 74, 108, 110
administrative closeout, 96
administrative support, 108
adverse cost trends, 104, 106
advertising, 34
agency goals
integrating in CIP, 12
agency oversight, 60
agency role
commissioning phase, 87
construction phase, 69
construction quality management, 81
design phase, 44
planning phase, 32
B
baseline
budget, 103, 104
cost, 103
documents, 118, 119
schedule, 76
scope, 102
technical, 102
beneficial occupancy, 97
benefits, project, 15
Best Practices Procurement Manual, 1, 111
bid bonds, 123
bid document verification, 52
bid phase, document control, 78
bids submission, 114
bids, sealed, 112
bonding, 113
bonds
bid bonds, 113
payment, 113
performance, 113
boundary survey, 48
BPPM. See Best Practices Procurement Manual.
Brooks Act, 111
budget, 1, 2, 6, 9, 11, 12, 15, 21, 28, 100, 101, 103, 104, 105, 108
estimating, 7
refining, 6
risks, 59
building codes, 34, 51, 92
C
capability assessment, 20, 12, 66
capacity assessment, 24, 28, 50
capital assets
evaluation, 15
inventory, 12
needs assessment, 11
selection, 15
capital cost, 42, 45, 47, 50, 105
Capital Improvement Plan, 6, 7, 11, 12, 13, 14, 15, 17
components, 16
capital resources, 13
cash flow, 108
Categorical Exclusion, 37, 38, 59
park-and-ride stations, 1
project management, 1, 33
project organization, 69, 71
safety management, 78
supporting transit facilities, 1
construction bid package, 45, 46, 49, 50
construction capital cost estimates, 46, 49, 50, 51
consultants, 12
contacting FTA, 2
contract
administration planning, 31, 102
audit, 97
award, 105
performance, 104
D
damages, liquidated, 76, 93
Davis-Bacon Act, 113, 114
D/B. See design/build.
D/B/B. See design/bid/build.
DBE. See Disadvantaged Business Enterprise.
D/B/O/M. See design/build/operate/maintain.
debt service, 17, 18
definition, project, 3, 21
deliverables, 21, 22, 23, 82, 96, 99, 101, 102
delivery method, 20
delivery strategy, 20, 13, 24, 26, 27, 28, 29
construction manager at risk, 25
design/bid/build, 25
design/build, 25
design/build/operate/maintain, 25
own forces, 25
turnkey, 25
DEIS. See Draft Environmental Impact Statement.
Department of Motor Vehicle regulations, 92
Department of Transportation, 40
design
charrette, 34, 67, 68
quality assurance, 61
quality control, 61
design/bid/build, 7, 8, 24, 25, 51, 69, 102
design/build, 8, 25
design/build/operate/maintain, 8, 25
design consultants role, 44, 46, 70
design criteria, 44, 45, 47, 48, 51
design phase, 3, 7, 28, 45, 42, 46, 88
agency role, 44
document control, 118
management, 44
project scope, 46
design, projects, 1
design review comment register, 52
design reviews, 46, 51, 61
differing site conditions, 77, 113
document control, 78, 128
Disadvantaged Business Enterprise, 18, 115, 116
E
EA. See environmental assessment.
easements, 53
ECHO. See Electronic Clearing House Operation.
economic assessment, 15
Electronic Clearing House Operation, 18, 109
elevations, 48, 49
emergency preparedness, 86, 89, 92, 93
energy modeling, 67, 68
engineering, preliminary, 7, 17, 25, 27, 28, 32, 33, 34, 4251, 101, 107
entitlement, 42
environment personnel, FTA, 1
environmental assessment, 37, 38
environmental checklist, 37
environmental clearance, 1, 2, 22, 32
environmental compliance, 37
environmental compliance process, federal, 37
environmental compliance process, state, 39, 40
environmental design, 87
Environmental Impact Statement, 37, 38, 39
environmental review process, 40
environmental review requirements, 49
environmental studies, 36
equipment, 114
contract provisions, 114
lease, 114
procurement, 114
requirements, 34
estimated costs, 35, 105, 106
equipment commissioning list, 89
event risks, 59
F
facilities, lease, 14
federal building codes, 92
Federal Motor Carrier Safety Administration, 92
Federal Transit Administration, 1
FEIS. See Final Environmental Impact statement.
final cost, 50, 105, 106
final design, 44, 45, 80
final engineering, 44
legal personnel, 2
locating offices, 3
planning personnel, 2
procurement personnel, 2
program management personnel, 2
working with, 2
FTA Annual Certifications and Assurances, 18
FTA Drug and Alcohol, 92
FTA Electronic Clearing House Operation, 18, 109
FTA Guidance for Transit Financial Plans, 12, 15
FTA personnel, 1
FTA Transportation Electronic Award Management, 18
functional studies, 34
funding requirements, 11, 16, 18
G
gap assessment, assets, 12
GEC. See General Engineering Consultant.
General Engineering Consultant, 24, 25, 72
geotechnical investigations, 32, 34, 431, 46
government relations, 117
government stakeholders, 117
Grant Management Guidelines, 98, 109
grants
administration, 11
applications, 18, 109
funding, 27, 109
management, 1, 98, 100, 109
personnel, FTA, 1
graphic plans, 48
green building design, 62, 57
guaranties, 106
Guidance for Transit Financial Plans, 13, 15
guidelines
public transit agencies, 1
H
handbook, how to use, 2
help, 122
IEEE. See Institute of Electrical and Electronics Engineers.
I
incentives, safety, 84
initiation phase, 20
in-progress preliminary submittal, 52
inspection, final, 97
Institute of Electrical and Electronics Engineers, 92
insurance, 114
integrated project office concept, 26
integrated testing, 86, 89, 92
intermodal terminals, construction, 1
inventory, capital assets, 12, 14
Invitation for Bid, 112
invoices, 70, 108
J
Job Hazard Analysis, 83
L
labor, 113
landscaping plan, 48
Leadership in Energy and Environmental Design, 63, 87
certification, 87
commissioning, 67, 87
Project Scorecard, 63, 64
Least Environmentally Damaging Practicable Alternative, 40
LEDPA. See Least Environmentally Damaging Practicable Alternative.
LEED. See Leadership in Energy and Environmental Design.
legal personnel, FTA, 2
level of service, 6
life cycle costs, 86
life cycle, projects, 3, 68
lighting, 34, 68, 90
liquidated damages, 93
locating FTA offices, 2
M
maintenance and operational facilities, construction, 1
maintenance needs assessment, 14
manage work activities, 3
management, design phase, 44
N
National Environmental Policy Act of 1969, 18, 32, 36, 37, 39, 43, 49
National Transit Institute course manual, 1
NCRs. See non-conformance reports.
NEPA. See National Environmental Policy Act of 1969.
NEPA Environmental Review Process, 37
net present value, 15
New Starts, 109
noncompetitive proposals, 110
non-conformance reports, 82
non-conforming work, 82
notice, preparing/publicizing, 114
O
O&M. See Operations and Maintenance Manuals.
objectives, project, 21
Occupational Safety and Health Administration, 83, 92
OFE. See owner furnished equipment.
operational interference, 53
operational needs, 6, 34
Operations and Maintenance Manuals, 50, 71, 86, 88, 89, 93
organization structure, 20, 26, 71
OSHA. See Occupational Safety and Health Administration.
outsourcing, 3, 14, 34
outreach, community, 33, 48, 79
overview, project, 15
own forces strategy, 25
Owner Controlled Insurance Programs, 113
owner furnished equipment, 86, 91
P
park-and-ride stations, construction, 1
partnering, construction phase, 74
payment bonds, 113
payment, final, 97, 98
peer reviews, 44, 46, 56, 60
planning, 30
standards, 111
constraints, 21
construction phase, 1, 3, 9, 69
contracting out, 24, 35
control process, 100
costs and control of, 23, 71, 85, 101, 103, 105, 106
definition of, 3, 21
deliverables, 21, 22, 23, 82, 96, 99, 101, 102
delivery methods, 20
delivery strategies, 20, 23, 24, 2730
demobilization, 98
design criteria, 44, 45, 47, 48, 51
design management, 44
design phase, 3, 7, 28, 34, 44, 46, 97
design review, 46, 51, 61
development, agency role, 32
development of, 3, 32
environmental clearance, 1, 2, 22, 32
evaluation of, 99
final design, 44, 45, 49
financial planning, 11, 17, 18
financing closeout, 97
funding, 11, 14, 18
funding closeout, 98, 109
initiation, 3, 20
implementation, 1
importance, 1
milestones, 15, 21, 22, 57, 73, 76, 97, 105, 109
objectives, 21
organization structure, 20, 26, 71
overview, 15
phases, 3
planning, 1, 20
preliminary engineering, 7, 17, 25, 47, 28, 32, 33, 34, 4451, 109, 107
procurement, 21
ranking, 11, 15, 112
records disposition, 96
records management, 23, 118
requirements definition, 21, 22
resources, 20, 33
review, 12, 21
risk assessment, 15, 45, 52, 54, 57, 103
schedule, 6, 32, 22, 30, 44, 50, 51, 73, 75, 100
scope, 9, 23, 25, 37, 41, 46, 50, 52, 59, 67, 100, 101, 103
stakeholders, 21, 22
with manager, 4
without manager, 5
project control, 100
documents, 98
process, 102
triangle, 101
Project Management Plan, 9, 20, 23, 27, 33, 45, 69, 87, 89, 101, 117, 118
Project Request Package, 15, 19
Project Requirements Definition, 20, 21, 47, 95, 103
Project Requirements Document, 20, 101
project support, 100
proposals
competitive, 110
noncompetitive, 110
public infrastructure, 53, 80
public transit agencies, guidelines, 1
Q
QA/QC See quality assurance/quality control.
Quality Assurance and Quality Control Guidelines, 1
quality assurance, design, 69, 81, 102
quality assurance/quality control, 1, 112
quality management, 20, 28, 29, 45, 60, 61, 70, 81
R
real estate acquisition, 1, 2, 32, 37, 41
Record of Decision, 39, 43, 49
regulation 23 CFR, 36, 37, 114
regulation 49 CFR, 41, 115
regulatory requirements, 6, 7, 40
release of retention, 97
Requests for Change, 71
Requests for Information, 70, 117
Request for Proposals, 110
review, constructability, 44, 45, 50, 53, 56
RFI. See Requests for Information.
RFP. See Request for Proposals.
right-of-way acquisitions, 46
risk management, 20, 28, 29, 30, 60
risk register, 57, 58
ROD. See Record of Decision
ROW acquisitions. See right-of-way.
S
safety, 9, 83
safety audits, 83
safety certification, 88
safety education, 83
safety enforcement, 83
SAVE. See Society of American Value Engineers.
sealed bids, 110, 112, 114
Section 404 (b)(1) Guidelines, 40
U
U.S. Army Corps of Engineers, 40
Uniform Act of 1970, 32
United States Fish and Wildlife Service, 37
United States Green Building Council, 63, 87
USGBC. See United States Green Building Council.
utilities, 36, 53, 73, 80
utility agreements, 114V
V
value engineering, 45, 49, 54, 55, 67, 71, 75
VE. See value engineering.
verification, bid document, 52
verification, scope completion, 98W
Z
zoning restrictions, 42
zoning studies, 35