Tracking Progress Exercise
Tracking Progress Exercise
The scheduled dates in this plan match its baseline dates, so the variance values are
zero
After you record progress through a specific date, Project displays the progress bars
and, for completed tasks, the completion check marks in the Gantt Chart view
In the chart portion of the Gantt Chart view, the progress bar shows how much of
each task has been completed. Because tasks 2, 3, and 4 have been completed, a
check mark appears in the Indicators column for those tasks, and the progress bars
extend through the full length of those tasks Gantt bars. Task 5 is only partially
completed, however.
Recording 100 percent complete is a quick checklist way of recording that a task was
completed as scheduled, with no variance
Because task 6 is a milestone task with no duration, there is no change in the
appearance of its symbol in the chart portion of the Gantt Chart view as there was
for tasks 5 and 8. However, the completion check marks for all three tasks appear in
the Indicators column.
2. Set task 9, Prepare book P&L statement, to 50 percent complete, and then point to
its progress bar.
Point to the progress bar in the partially completed tasks Gantt bar to see its key
progress indicators in a ScreenTip
Note that although 50 percent of the work on task 9 is completed, the progress bar
does not span 50 percent of the length of the Gantt bar. This is because Project
measures duration in working time but draws the Gantt bars to extend over
nonworking time, which in this case includes Thursday, January 25, a nonworking
day.
When you record actual duration, the change highlighting is a great way to see what
other changes in the plan the actuals introduced
2. Use the options in the Update Tasks dialog box to record that task 10, Plan
authors travel itinerary, started one working day ahead of schedule (the Tuesday
before its scheduled start date) and required a total of seven days to complete.
When recording actual duration, you should also record the actual start date if it differs
from the scheduled start date
3. Click OK.
Project records the actual values for the task and marks it as complete. The updated
values roll up to the Internal Launch Phase summary task (task 7) and the project
summary task (task 0), as indicated by the change highlighting.
Actual values that you record at the task level roll up to the tasks summary
task and to the project summary task
4. Use the options in the Update Tasks dialog box for task 11, Channel
Sales prep. This task started on time and has three days of actual
duration but will still require five days of remaining duration to
complete. (Remember to enter the new remaining duration value after
entering the actual duration value.)
This gives the task a new total duration of eight days: three days actual
duration plus five days remaining duration.
Unless you record an actual start date, Project assumes the task started as
scheduled
Because you did not specify an actual start date, Project assumes that the
task started as scheduled. However, the actual duration and updated
remaining duration value you entered caused Project to calculate a new
finish date.