Set No. 1: Code No: R4203A
Set No. 1: Code No: R4203A
Set No. 1: Code No: R4203A
R10
Set No. 1
Max. Marks: 75
[8]
[7]
[8]
[7]
[8]
[7]
[8]
[7]
What is routing? What are the factors responsible for proper routing? Explain.
What is Gantt chart? Discuss the use of Gantt chart for scheduling purpose
with an example.
[15]
What is aggregate planning? What are its objectives? What is the need for
aggregate planning and explain various steps in aggregate planning?
[15]
1 of 1
[15]
[8]
[7]
Set No. 2
R10
Max. Marks: 75
1.24
1.69
1.70
3.11
[8]
[7]
[5]
[5]
[5]
[8]
[7]
[8]
[7]
[8]
[7]
[8]
[7]
[8]
[7]
1 of 1
R10
Set No. 3
Max. Marks: 75
[8]
[7]
2 a) Forecasting is essential not only in business but in our daily life alsosupport the statement with brief explanation.
b) Explain about method of least square and exponential smoothing method.
[8]
[7]
[8]
[7]
[8]
[7]
What is route sheet? How are they prepared and give factors affecting routing
procedure.
[15]
[8]
[7]
[4]
[4]
[7]
1 of 1
R10
Set No. 4
Max. Marks: 75
What are different types of forecasting? Explain their significance, merits and
demerits.
[8]
[7]
[15]
3 a) Explain about fixed order quantity system and fixed order period system.
b) Explain about ABC and VED analysis.
[8]
[7]
[8]
[7]
[6]
[9]
[8]
[7]
The precedence and the time requirements for each element are shown in
table. The line operates for 7 hrs per day and an output of 550 units per day is
desired.
a) Draw the precedence diagram for the production process.
b) Calculate i) cycle time and
ii) Theoretical minimum number of workstations required.
c) Group the tasks into number of workstations.
d) Calculate balance efficiency.
Work element
A
B
C
D
E
F
G
Precedence
A
B
C
C
D,E
F
Time(min.)
0.65 0.40 0.30 0.20 0.45 0.40 0.30
[15]
[8]
[7]