Project Handover Guidelines
Project Handover Guidelines
Version 4.2
Last updated: 12/5/2016
Version 4.2
Last Updated: 16/05/2016
Page 1
Revision history
Version
4.2
Version 4.2
Date
Author
May 2016
Mark White
Reason
Sections
Page | 2
Contents
Background ................................................................................... 5
Pre-project Handover Site Meeting ................................................... 5
Requirement Overview .................................................................... 6
1.
2.
3.
4.
5.
Appendix A
Appendix B
Appendix C
Appendix D
Appendix E
Version 4.2
Page | 3
Version 4.2
Page | 4
Background
The handover of a project to the client at the end of construction is a very important stage of the
project procurement process and facility operation success. A well organised, efficient and effective
transfer of information from project works to the University is essential.
The transfer of ownership of the project from contractor to client can have an effect on health and
safety, reliability, standards of operation, maintenance and operational cost efficiencies to the
University. The transfer/handover period can be a very stressful time for contractors staff, and
building owners and occupants alike as spaces become occupied and operation of the facility starts.
The commissioning and fine tuning operations during handover can impact heavily on core business
of the University if not managed in a structured manner. The University capital works project
management process identifies broad activities of the project handover stage.
The following sections of this document detail the requirements and actions required to be
undertaken during any project handover.
The handover program shall be organised by the project manager in conjunction with the head
contractor and subcontractors.
CAD information
maintenance manuals
prescribed essential safety and health features and measures (PESHFM) maintenance during
the defects liability period (DLP) - Understanding and process development
The project manager will arrange this meeting with all stakeholders (architects, engineers, head
contractor, major subcontractors and University facilities staff).
University staff members will be nominated to attend various elements of project handovers, meetings
and operational training sessions.
Version 4.2
Page | 5
Requirement Overview
A certificate of practical completion shall not be issued and the project will not be handed over (for
occupation and use) until the following five important contracted activities have been undertaken or
fulfilled:
1.
Connection and commissioning of all systems, plant and equipment shall be complete and
all testing data and reports made available (as part of the maintenance manuals to be
supplied).
2.
3.
Defect liability period (DLP) maintenance management processes shall be in place and
4.
5.
The above task details and requirements are expanded in the subsequent pages and support
information is offered in appendices:
Appendix A Maintainable Assets Description Hierarchy
Appendix B Data and Information Requirements from Projects
Appendix C Maintenance Manuals
Appendix D Spatial Data Collection / Verification
Appendix E After Hours Call Out Protocols
1.
Policy Statement
Specific testing and commissioning requirements and programs for individual projects will be those
that are agreed at a pre-commissioning meeting attended by the contractor, project management,
and University staff. Connection testing and commissioning of all systems, plant and equipment shall
be complete to the satisfaction of the Consulting Engineer/s and UTAS.
Requirement
Provide testing and commissioning procedures at least a week in advance of the event that
the University staff will witness.
Label all equipment, switches and controls eligibly in accordance with UTAS requirements.
Version 4.2
Page | 6
Security surveillance systems o Door access control systems o Alarm monitoring systems
Connection and commissioning of specialised and restricted systems shall be completed by joint
actions of the contractor and nominated University staff members. In most cases these connections
will be extensions to existing operational systems.
Existing contracts for management and operation of these systems may already exist. These contracts
specify responsibility for the operation, data configuration integrity and the ongoing maintenance of
the system data by the contracted company.
2.
Policy Statement
All licences, certifications and documentation required by Workplace Standards or by any other
specialised legislation such as the Tasmanian Building Act or Building Code of Australia or other
certifying agency shall be provided prior to taking occupancy or accepting the project as being
handed over.
Requirement
The following are items that could have be installed or constructed during the project that fall
under this category:
o Hazardous plant and equipment
o
Registered equipment
o
o
Chemical stores
Specialised facilities e.g. PC2 / PC3 / radiation, or
Follow all UTAS policy and procedures for procuring or constructing these items/facilities.
Provide relevant authorities inspection reports, certificates and registrations as part of the asconstructed information documentation.
Provide evidence of facility functionality compliant and consistent with the designed
specification.
Ensure all chemical or hazardous substance purchases are referred to the UTAS Work Health
and Safety Unit.
Version 4.2
Page | 7
3.
Policy Statement
Maintenance does not include construction defect repairs. Defects are dealt with separately under the
construction contract.
The Tasmanian Building Act and Building Regulations require UTAS (as the building owner or
occupier) to certify all prescribed essential safety and health features and measures (PESHFM)
maintenance and other tasks have been undertaken as defined in Form 46 and finally manage the
displaying of a Form 56.
Form 56 is the Annual Maintenance Statement and shows confirmation from the Building
Owner or Occupier that all required Form 46 specified requirements have been undertaken
during the preceding year.
The Form 56 must be renewed and re-displayed annually by UTAS on or before the 15 July
each year.
Requirement
UTAS will take the lead in arranging and displaying Form 56 certificates but requires the
unmitigated assistance of the contractor(s) to achieve this as the Form 56 must list all new
occupancy certificates for that facility that have occurred since the displaying of the previous
certificate was displayed.
All maintenance activities undertaken during the defects liability period (DLP) must be
undertaken by the construction project contracted providers/installers.
To ensure the required maintenance activities are actioned during the DLP, maintenance
schedules for all essential services assets shall be in place and confirmed by the Universitys
facilities manager prior to a project being handed over.
The maintenance program will be recorded in the UTAS asset management system.
The UTAS general maintenance service provider will assist the project management team by
ensuring all required maintenance and activities have been undertaken.
Contractors DLP maintenance service reports must be supplied to the UTAS general
maintenance service provider by either the construction contractor of the project manager as
evidence of compliance.
Maintenance activity will be monitored through the UTAS general maintenance service
provider and compliance reports will be provided to the project manager. Non- compliance of
maintenance tasks must be remedied by the construction/installation contractor immediately.
A separate process for management of contract related building defects shall be organised by
the project manager.
Submit reports to the project manager certifying that all engineering infrastructure has been
designed, installed and commissioned in accordance with legislated requirements and the
Version 4.2
Page | 8
UTAS design requirements and that they are in full operational modes, before the installations
are deem to be practically completed.
During the month prior to the end of the DLP, a report must be submitted to the project
manager from the various engineering consultants identifying how the various engineering
systems/installations/works actually performed as compared to the design criteria;
achievement of environmental targets including energy and water consumptions; quality of
the indoor environment; and outline any inadequacies and adjustments made.
At the conclusion of the DLP, final inspections must be certified, including final seasonal
adjustments undertaken to ensure proper operation of all systems.
4.
Policy Statement
Successful operational, familiarisation and maintenance training sessions will have been held to the
satisfaction of UTAS managers in each field of expertise prior to handing over the works for
occupation or use.
Requirement
The contractor shall submit a draft training program to the project manager for each system
or specialised item of plant for approval based on the commissioning program and where
possible prior to the pre project handover meeting held at least four weeks prior to the
proposed handover date.
Sample training information documentation shall be submitted with the above mentioned
proposed program. Ensure adequate and appropriate training materials inclusive of asinstalled drawings and operation and maintenance manuals as the basis for training
Final dates for training sessions shall be scheduled and agreed with the project manager and
other stakeholders to ensure adequate contractor and UTAS staff availability.
Use only qualified and competent trainers. These shall be people like the manufacturers
representatives or others duly trained by the manufacturers who are knowledgeable about the
installations/systems.
Adequate and effective training must be arranged for early, partial or staged handovers. These
early handovers must be reviewed and reinforced during final project handover training
program development. This is of particular importance to building evacuation procedures and
plant and equipment installations that serve more than the area of defined project works (i.e.
new fire indicator panel installed as part of partial building refurbishment but services the
building as a whole).
5.
Policy Statement
As-constructed information is required by the University to allow a smooth transition from project to
actual use or occupation. As-constructed information includes schedules of equipment, technical data
and manufacturers technical literature including performance information on individual plant and
equipment; original software programmes and all passwords; copies of certifications and warranties;
Version 4.2
Page | 9
all test results, maintenance schedules and complete as-built drawings in CAD format; list of suppliers;
list of programmed operational time periods, thermostatic settings, etc.
See Appendix B and C for a detailed list of information required.
Requirement
It is recognised that it is very difficult to gather all as-constructed information prior to project
handover due to the busyness of completing projects in the final stages and also the process
of commissioning plant during the same period. Submit progressive as- installed drawings
especially for those concealed/ underground cable and piping routes shall be provided prior
to backfilling of excavation or concreting of floor slab or installation of non removable ceiling.
Provide critical dimensions and access points.
All other listed items (if included in the project) must be provided within four weeks after the
date of issue of a Certificate of Practical Completion.
Appendix C identifies various information that must be supplied as maintenance manuals. All
information shall be provided in duplicate (1 x original and 1 x copy) hard copy, bound into 3or 4-ring folders. These folders shall contain a compact disk or disks of electronic copies of
the information supplied in the folders.
Manuals shall be sectioned and indexed. Indexing and labelling shall be to the UTAS standard.
Manuals must not contain superfluous information such as product catalogues that add bulk
and make it look a healthy presentation. Only useful information shall be provided such as
instructions, schedules, and maintenance plans etc covering the information identified in
Appendix B or C.
For small projects, the UTAS project manager may approve an alternative to providing the
information in 3-ring folders. As an example the information required for the installation of a
split system air conditioner may take the form of operational instructions, schematic updates,
warranties and appropriate asset detail forms. These could all be supplied on a CD.
Update existing UTAS maintenance manuals information as required with details such as
system schematics and schedules for works that shave been undertaken in existing buildings.
Version 4.2
Page | 10
Appendix A
Assets
Refer to Maintainable Asset Forms document, for maintainable asset forms. Available at:
www.utas.edu.au/commercial-services-development/asset-data/asset-management
Version 4.2
Page | 11
Received
Required
Appendix B
Projects
General Items
As-built plans including services (CAD format to UTAS layering standards
See document titled CAD Standards). These are to be a measured full set
at completion of the building works
Asset forms for fixed plant and equipment maintainable assets (See
document titled Maintainable Assets Description Hierarchy
identifying asset groups, types and descriptions);
o
o
o
o
o
Finishes schedule
Products schedule
Hardware schedule (installed) including master keying system and key
allocations
Version 4.2
Page | 12
Warranties
Version 4.2
o
o
o
o
o
o
o
o
o
Paint systems
Carpets
Suspended ceiling systems
Access ladders and platforms
Vehicle access control devices
Roller shutters and operating equipment
Page | 13
Maintenance Manuals
(to include CDs of data)
Received
Required
Appendix C
3-ring folder
loose leaf
o
o
o
o
Smoke vents
Fire dampers
Electrical Information
3-ring folder
loose leaf
3-ring folder
loose leaf
Version 4.2
Page | 14
3-ring folder
loose leaf
o
o
Certification of installation
Version 4.2
o
o
Page | 15
Appendix D
Policy Statement
Spatial information is very important to the University for strategic planning purposes.
Space type information is agreed at the project initiation phase by the UTAS space planner and the
client.
Requirement
Project managers will confirm the space information provided on the as-built plans to ensure
that it matches which was actually built.
Prior to project handover, the contractor/designer may be required to assist the project
manager in confirming the originally agreed space allocations.
Space type information used on plans should match that used in the UTAS space
management database.
Version 4.2
Page | 16
Appendix E
After-hours call outs will vary for each project. Two types of works are encountered.
Version 4.2
Page | 17