Plant Design PDF
Plant Design PDF
Plant Design PDF
INSTITUTE OF
TECHNOLOGY
FACULTY OF
CHEMICAL AND
FOOD ENGINEERING
Identification
Function
Operation
Materials handled
Essentials controls
Insulation requirements
Allowable tolerances
Materials of constructions
3
Plant design
The general term plant design includes all engineering aspects involved in the development
of either a
new
modified, or
expanded industrial plant.
In this development, the chemical engineer will be making economic evaluations of new
processes, designing individual pieces of equipment, or developing a plant layout.
What is Design?
Design is a creative activity, and as such can be one of the most rewarding and satisfying
activities undertaken by an engineer.
It is the synthesis, the putting together, of ideas to achieve a desired purpose.
The design does not exist at the commencement of the project.
The designer starts with a specific objective in mind, a need, and by developing and
evaluating possible designs, arrives at what he considers the best way of achieving that
objective; be it a better chair, a new bridge, or for the chemical engineer, a new chemical
product or a stage in the design of a production process.
Nature Of Design
All design starts with a perceived need. In the design of a chemical process, the need is the
public need for the product, creating a commercial opportunity, as foreseen by the sales and
marketing organization.
Within this overall objective, the designer will recognize sub-objectives, the requirements of
the various units that make up the overall process.
process
Before starting work, the designer should obtain as complete, and as unambiguous, a
statement of the requirements as possible.
If the requirement (need) arises from outside the design group, from a customer or from
another department, then the designer will have to elucidate the real requirements through
discussion.
6
Objective(design specification)
The
The creative part of the design process
The
The designer will largely rely on previous experience
Selection and
evaluation(optimization)
The designer starts with the set of all possible solutions bounded by the
external constraints, and by A process of progressive evaluation and
selection, narrows down the Range of candidates to find the best design for
Final design
the purpose
Final design
7
Selection
The designer starts with the set of all possible solutions bounded by the external
constraints, and by a process
Of progressive evaluation and selection, narrows down the range of candidates to
find the best design for the purpose.
The selection process can be considered to go through the following stages:
Possible designs(credible)- within the external constraints.
Plausible designs(feasible)-within
within the internal constraints.
Probable designs- likely candidates
Best design(optimum)- judged the best solution to the problem
11
Design constraints
12
Cont.
When considering possible ways to achieve the objective constrained by several factors
that will down the number of possible designs.
designs
Some constraints will be fixed, invariable that arise from physical laws, government
regulations, and standards.
External constraints- arise outside the designers influence
Economics and time are main constraints
13
14
Descriptions
Stage 1. Raw material storage: The storage required depends on the nature of the raw materials, the method of
delivery, and what assurance can be placed on the continuity of supply.
Stage 2. Feed preparation: Some purification and preparation of the raw materials will usually be necessary
before they are sufficiently pure, or in the right form, to be fed to the reactor.
Stage 3. Reaction: The reaction stage is the heart of a chemical manufacturing process.
Stage 4. Product separation: After the reactor(s) the products and byproducts are separated from any
unreacted material.
Stage 5. Purification: Before sale, the main product will often need purification to meet the product
specifications.
Stage 6. Product storage: Some inventory of finished product must be held to match production with sales.
Liquids are normally dispatched in drums and in bulk tankers (road, rail, and sea); solids in sacks, cartons, or
bales
15
Types Of Designs
The methods for carrying out a design project may be divided into the following
classifications, depending on the accuracy and detail required:
1. Preliminary or quick-estimate designs
2. Detailed-estimate designs
3. Firm process designs or detailed designs
1. PRELIMINARY DESIGNS
Are ordinarily used as a basis for determining whether further work should be done on
the proposed process.
The design is based on approximate process methods, and rough cost estimates are
prepared.
Few details are included, and the time spent on calculations is kept at a minimum.
16
2. DETAILED-ESTIMATE
ESTIMATE DESIGN
If the results of the preliminary design show that further work is justified, the detail estimate
design will be implemented.
Profit potential of an established process is determined by detailed analyses and calculations.
However, exact specifications are not given for the equipment, and drafting-room work is
minimized.
Things to be included
When the preceding information is included in the design, the result permits accurate
estimation of required capital investment, manufacturing costs, and potential profits.
Consideration should be given to the types of buildings, heating, ventilating, lighting, power,
drainage, waste disposal, safety facilities, instrumentation, etc.
18
Cont.
Before any detailed work is done on the design, the technical and economic
factors of the proposed process should be examined. The various reactions and
physical processes involved must be considered, along with the existing and
potential market conditions for the particular product. A preliminary survey of
this type gives an indication of the probable success of the project and also
shows what additional information is necessary to make a complete evaluation.
Following is a list of items that should be considered in making a feasibility
survey:
22
Cont.
1.
2.
9.
Markets (present and future supply and demand, present uses, new
uses,
3.
4.
5.
6.
8.
12.
13.
14.
Plant location
15.
Materials of construction
Safety considerations
23
B. Time Management
An essential ingredient of all successful projects is realistic time management.
Once a project is defined it is necessary to identify the associated tasks, the required deadlines,
and the resources available.
It is necessary to look to the end of a project at the beginning of the work, rather than focusing on
the day-by-day or week-by week tasks.
An overall view is required in the early stages of a project proposal, and the essential/key tasks,
decisions and bottlenecks need to be identified.
Appropriate actions and planning can then be incorporated in the time-plan for the project.
It is also necessary to be flexible and to modify the timing of the project stages as the work
proceeds.
24
construction and
of chemical plants.
Operation
Evaluating the Alternatives - Making Decisions
Probably by the end of the first (or second) week of a project a wide range of options and alternatives will have been
considered & decisions has to be made based on the questions below:
27
28
Cont.
Once you decide on the chemical to be produced then the selection of a process route for production of a
chemical will depend upon the following factors/considerations:
factors/considerations
a.
b.
c.
The necessary design data, technology, fabrication methods and materials, raw materials, etc., must be
available.
d.
The plant must operate in a safe manner, providing an acceptable hazard risk to the plant employees and the
public.
e.
f.
g.
Cont.
h. The plant should be designed to operate adequately under conditions of reduced throughput (say
by 50%), and for increased production (say 25%).
i.
j.
All necessary utilities should be available, e.g. electricity, cooling water, etc. The utilities
specifications must be established, these are dependent upon whether a grass-roots plant is to be
built or the plant situated in an existing chemical complex. These specifications plant situated in
an existing chemical complex. These specifications include the steam-pressure levels, cooling
water and/or refrigerants available, etc. The unit costs must also be determined.
k. Etc.
30
31
optimization
Design is optimization: the designer seeks the best, the optimum, solution to a problem.
Much of the selection and choice in the design process will depend on the intuitive
judgement of the designer; who must decide when more formal optimization techniques can
be used to advantage.
The task of formally optimizing the design of a complex processing plant involving several
hundred variables, with complex interactions, is formidable, if not impossible.
The task can be reduced by dividing the process into more manageable units, identifying the
key variables and concentrating work where the effort involved will give the greatest
benefit.
32
General procedure
When setting out to optimize any system, the first step is clearly to identify
the objective: the criterion to be used to judge the system performance. In
engineering design the objective will invariably be an economic one. For a
chemical process, the overall objective for the operating company will be to
maximize profits. This will give rise to sub-objectives, which the designer
will work to achieve. The main sub--objective will usually be to minimize
operating costs. Other sub-objectives may be to reduce investment, maximize
yield, reduce labor requirements, reduce maintenance, operate safely
33
Cont.
The second step is to determine the objective function; the system of equations, and other
relationships, which relate the objective with the variables to be manipulated to optimize the
function. If the objective is economic, it will be necessary to express the objective function in
economic terms (costs).
The third step is to find the values of the variables that give the optimum value of the objective
function (maximum or minimum). The best techniques to be used for this step will depend on the
complexity of the system and on the particular mathematical model used to represent the system.
A mathematical model represents the design as a set of equations (relationships) and it will only be
possible to optimize the design if the number of variables exceeds the number of relationships; there
is some degree of freedom in the system.
34
Cont..
Simple models
If the objective function can be expressed as a function of one variable (single degree of freedom) the function can be differentiated, or
plotted, to find the maximum or minimum.
Example
Analytical methods
If the objective function can be expressed as a mathematical function the classical methods of calculus can be used to find the maximum
or minimum.
Setting the partial derivatives to zero will produce a set of simultaneous equations that can be solved to find the optimum Values
Search methods
35
Cont.
Linear programming
36
Qualitative:
indicates the flow of materials, unit operations involved, equipment necessary & special information on operating temperature & pressure.
Quantitative:
shows the quantities of material required for operation.
Combined detail:
qualitative information & quantitative data are combined on the basis of one flow diagram.
Contains detail information on the flow quantities and equipment specifications.
specifications
Contain the location of temp., pressure regulators & indicators as well as the location of critical control valves & special instruments.
37
38
39
40
Pictorial Diagram
On the detailed flow-sheets used for design and operation, the equipment is normally drawn in a
stylized pictorial form.
The symbols given in British Standard, BS 1553 (1977) "Graphical Symbols for General
Engineering" Part 1, "Piping Systems and Plant are recommended; though most design offices use
their own standard symbols.
A selection of symbols from BS 1553 is given in Appendix A of the book Coulson and Richardson,
V6.
The American National Standards Institute (ANSI) has also published a set of symbols for use on
flow-sheets.
In Europe, the German standards organization has published a set of guide rules and symbols for
flow-sheet presentation, DIN 28004 (1988).
42
43
44
46
47
Information To Be Included
Essential information
Stream composition, either:
I. The flow-rate of each individual component, kg/h, which is preferred,
preferred or
II. the stream composition as a weight fraction.
Optional information
Molar percentages composition.
Physical property data, such as: density, kg/m3, viscosity, mN s/m2.
Stream name, a brief, one or two-word,
word, description of the nature of the stream, for example "ACETONE COLUMN BOTTOMS".
Stream enthalpy, kJ/h.
48
49
Cont.
Its purpose is:
To have a common language for instrument technicians, process engineers
and suppliers.
To properly document plant designs for installation
To properly document plant designs for installation in graphical form.
To help in maintenance, failure analysis & troubleshooting.
50
Cont.
The P & ID should include:
1) All process equipment identified by an equipment number. The equipment should be drawn roughly in
proportion, and the location of nozzles shown.
2) All pipes, identified by a line number. The pipe size and material of construction should be shown.
3) All valves, control and block valves, with an identification number.
The type and size should be shown. The type may be shown by the symbol used for the valve or included in
the code used for the valve number.
4) Ancillary fittings that are part of the piping system, such as inline sight-glasses, strainers and steam traps;
with an identification number.
5) Pumps, identified by a suitable code number.
6) All control loops and instruments, with an identification number.
51
Material balance
Material balances are the basis of process design. A material balance taken over the complete process will
determine the quantities of raw materials required and products produced.
Balances over individual process units set the process stream flows and compositions.
Chemical processes may be classified into as batch, continuous, or semi batch, or either steady state or
transient.
Batch process: the feed is charged (fed) into a vessel at the beginning of the process & the vessel content are
removed sometimes later.
Continuous process: the inputs and outputs flow continuously throughout the duration of the process.
Semi-batch process: any process that is neither batch nor continuous.
53
Cont.
If the values of all variables in the process do not change with time, Steady state process.
If any of the process variables change with time, transient or unsteady state.
A balance on a certain conserved quantity can be written as: Material out=Material in + Generation
- Consumption Accumulation
For a steady-state process the accumulation term will be zero.
If the balanced quantity is total mass (or if there is no reaction), set generation and accumulation = 0
If there is no chemical reaction the steady-state balance reduces to
Material in = Material out
A balance equation can be written for each separately identifiable species present, elements,
compounds or radicals; and for the total material.
54
Cont.
The standard procedures for material balances are:
1) Make any necessary assumptions (E.g. steady state, no rxn, etc.)
2) Draw a flowchart for the process & fill in all known variables and values. Label unknown stream variables on the chart. Include either:
3) Choose as a basis of calculation an amount or flow rate of one of the process stream.
4) Express what the problem statement asks you to determine in terms of the labeled variables.
5) If you are given mixed mass and mole units for a stream, convert all quantities to one basis.
6) Do the degree of freedom analysis. Count the unknowns and identify equations
Ndf = unknown-independent equations
55
Cont.
1. If ndf=0, there are n independent equations in n unknowns and the problem can in
principle be solved.
2. if ndf>0, there are more unknowns than independent equations relating them and
at least ndf additional variable values must be specified before the remaining
variable values can be determined. Either relations have been overlooked or the
problem is underspecified and has infinitely many solutions; in either case, plunging
into calculations is likely to be a waste of time.
3. if ndf<0, there are more independent equations than unknowns. Either the
flowchart is incompletely labeled or the problem is over specified with redundant
and possibly inconsistent relations. Again there is little point wasting time trying to
solve it until the equations and unknowns are brought into balance.
56
Cont..
Sources of equations relating unknown process stream variables include the
following:
Material balances
Energy balances
Process specifications
Physical properties and laws
Physical constraints
Stoichiometric relations
recycle
It is rare that a chemical reaction A B
B proceeds to completion in a reactor.
No mater how A is present in the feed or how long the reaction mixture
remains in the reactor, some A is normally found in the products.
Recycling diagram
Recycle stream
Unit 1
Unit 2
Unit 3
58
Cont.
1. recovery of catalyst. Many reactors use catalysts to increase the rate of reaction. Catalysts are usually expensive, and the processes
generally include provisions for recovering them from the product stream and recycling them to the recovered separately in special
facilities designed for this purpose.
2. dilution of a process stream. Suppose a slurry( a suspension of solids in a liquid) is fed to a filter. If the concentration of solids in the
slurry is too high, the slurry is difficult to handle and the filter will not operate properly. Rather than diluting the feed with fresh liquid,
a portion of the filtrate can be recycled to dilute the feed to the desired solids concentration
3. control of a process variable. Suppose a reaction releases an extremely large amount of heat, making the reactor difficult and
expensive to control. The rate of heat generation can be reduced be lowering the reactant concentration, which can in turn be
accomplished by recycling a portion of the reactor effluent to the inlet.
inlet In addition to acting as a diluent for the reactants, the recycled
material also serves as a capacitance for the heat released: the greater the mass of the reaction mixture, the lower the temperature to
which that mass will be raised by a fixed amount of heat.
4. Circulation of a working fluid. The most common example of this application is the refrigeration cycle used in household
refrigerators and air conditioners. In these devices, a single material is reused indefinitely, with only small makeup quantities being
added to the system replenish working fluid that may be lost through leaks.
59
purge
It is usually necessary to bleed off a portion of a recycle stream to prevent the
build-up of unwanted material.
For example, if a reactor feed contains inert components that are not separated
from the recycle stream in the separation units these inert would accumulate in
the recycle stream until the stream eventually consisted entirely of inert.
So the required purge rate can be determined from the following relationship:
[Feed stream flow-rate]
rate] x [Feed stream inert concentration] = [Purge stream
flow-rate]
rate] x [Specified (desired) recycle inert concentration]
60
Energy balance
Process industries have always recognized that wasting energy leads to reduced profits.
If a plant uses more energy than its competitors, its product could be priced out of the
marketplace.
A chemical process may consists of reactors, pumps, compressors, distillation columns,
mixing tanks, evaporators, filter presses, particle size reduction and transportation filter
presses, particle size reduction and transportation apparatuses.
apparatuses Each of these units either
requires or releases energy.
So,, the total amount of energy required in the plant should be estimated and we always need
to design and operate each unit operations in such a way that the energy requirement is
minimum.
61
Cont.
As with mass, energy can be considered to be separately conserved in all but nuclear
processes.
The conservation of energy differs from that of mass in that energy can be generated
(or consumed) in a chemical process.
Material can change form, new molecular species can be formed by chemical
reaction, but the total mass flow into a process unit must be equal to the flow out at
the steady state.
The same is not true of energy. The total enthalpy of the outlet streams will not equal
that of the inlet streams if energy is generated or consumed in the processes; such as
that due to heat of reaction.
62
Cont.
Energy can exist in several forms: heat, mechanical energy, electrical energy,
and it is the total energy that is conserved.
conserved
In process design, energy balances are made to determine the energy
requirements of the process: the heating, cooling and power required.
In plant operation, an energy balance(energy audit) on the plant will show the
pattern of energy usage, and suggest areas for conservation and savings.
63
Cont..
A general equation can be written for conservation of energy
Energy out= energy in+ generation- consumptionconsumption accumulation
This is a statement of the first law of thermodynamics.
thermodynamics
an energy balance can be written for any process step
Chemical
reaction
will
evolve
energy
(exothermic)
or
consume
Cont.
Energy can be transferred between a system and the surrounding as
Kinetic energy: energy due to the translational motion of the system as a whole relative to
some frame of reference(usually the earths surface) or to rotation of the system about some
axis.
Potential energy: energy due to the position of the system in a potential field (such as a
gravitational or electromagnetic field).
Internal energy: all energy possessed by a system other than kinetic and potential energy,
such as energy due to the motion of molecules relative to the center of mass of the system, to
the rotational and vibrational motion and the electromagnetic interactions of the molecules,
and the motion and interactions of the atomic and subatomic constituents of the molecules.
65
Cont.
As heat or energy that flows as a result of temperature difference between a system and its
surroundings.
The direction of flow is always from a higher temperature to a lower one Heat is defined
as positive when it is transferred to the system from the surroundings.
As work, or energy that flows in response to any driving force other than a temperature
difference, such as a force, a torque or a voltage.
voltage
For example, if a gas in a cylinder expands and moves a piston against a restraining force,
the gas does work on he piston( energy is transferred as work from the gas to its surrounds,
which include the piston).
66
project
Your project must include the following tasks
Take any chemical processing plant
Put your objective on the plant and determine design variables, put flow sheet and process
diagram
Do necessary plant design steps and bring your result weekly
Do material balance , energy balance, economic analysis,
Select site for your plant
Put reasonable plant lay out
Do analysis on waste minimization for your plant
67
68
introduction
Even if insufficient technical information is available to design a plant completely, we
must still make an economical evaluation to determine if it is economically and financially
feasible.
A project is economically feasible when it is more profitable than other competing
projects, and financially feasible when management can raise the capital for its
implementation.
Although calculations may show that a given project could be extremely profitable, the
capital requirements may strain the financial capabilities of the organization.
In this case, the project may be abandoned unless partners can be found to share the risk.
69
Introduction(cont..)
The economic evaluation of a process proceeds in several steps. These are:
1. Preparing A Process Flow Diagram
2. Calculating Mass And Energy Flows
3. Sizing Major Equipment
4. Estimating The Capital Cost
5. Estimating The Production Cost
6. Forecasting The Product Sales Price
7. Estimating The Return On Investment or other profitability measurements.
70
71
Cont.
An understanding of engineering and economics principles is a prerequisite for direct Plant
design work as well as plant operation.
The expression plant design always aimed at industrial applications; consequently, the Birr
flow & balance must always be kept in mind when carrying out the design of a plant and its
operation.
The theoretical and practical aspects of plant engineering are important, but, in the final
analysis, the answer to the question Will we realize a profit from this venture? almost
always determines the fate and true value of design.
The engineer, therefore, should know that the fate of his plant design is determined by the
financial & economic return and viability.
72
73
TCI=FCI+ WC
Where TCI is total capital Investment
FCI is fixed capital investment and
WC is working capital
76
Direct Costs
Direct costs is the cost of material and labor involved in actual installation of complete
facility(70-85% of fixed capital investment)
1. Purchased equipment (15-40% of fixed capital investment)
All equipment listed on a complete flow sheet, Spare parts and non-installed equipment spares supplies, and
equipment allowance. Inflation cost allowance, Freight charges, Taxes, insurance, duties. Allowance for
modifications during startup.
Cont..
3. Instrumentation and controls: installed (6-30% of purchased equipment cost)
Purchase, installation, calibration, computer tie-in.
tie
Cont..
6. Buildings (including services)
Process buildings-substructures, superstructures,
superstructures platforms, supports, stairways, ladders, access
ways, cranes, monorails, hoists, elevators
Auxiliary buildings-administration and office, medical or dispensary, cafeteria, garage, product
warehouse, parts warehouse, guard and safety, fire station, change house, personnel building,
shipping office and platform, research personnel building, shipping office and platform, research
laboratory, control laboratory Maintenance shops-electric,
shops
piping, sheet metal, machine, welding,
carpentry, instrument Building services-plumbing,
plumbing, heating, ventilation, dust collection, air
conditioning, building
lighting, escalators, telephones, intercommunication systems, painting, sprinkler systems, file
alarm.
80
Cont..
7 Yard improvements
Site development-site clearing, grading, roads, walkways, railroads, fences,
fences parking areas, wharves and piers, recreational facilities, landscaping
8. Service facilities
Utilities-steam, water, power, refrigeration, compressed air, fuel, waste disposal
Facilities-boiler plant incinerator, wells, river intake, water treatment,
treatment cooling towers, water storage, electric substation, refrigeration plant, air
cooling towers, water storage, electric substation, refrigeration plant, air plant, fuel storage, waste disposal plant, environmental controls, fine
protection
Non process equipment-office furniture and equipment, cafeteria equipment, safety and medical equipment, shop equipment, automotive
equipment, yard material-handling equipment, laboratory equipment,
equipment locker-room equipment, garage equipment, shelves, bins, pallets, hand
trucks, housekeeping equipment, fire extinguishers, hoses, fire engines, loading stations
Distribution and packaging-raw-material and product storage and handling equipment, product packaging equipment, blending facilities, loading
stations
81
82
Indirect costs
Expenses which are not directly involved with material and labor of actual installation of complete facility (15-30% of fixed
capital investment)
1. Engineering and supervision ( 5-30% of direct cost)
Safety, medical
Use previous cost on similar equipment and scale for time and size
Reasonably accurate
Corrected to the current cost index
Beware of large extrapolation
Beware of foreign currency
85
87
91
Turnover ratio
Turnover ratio= gross annual sales/fixed--capital investment
Turnover ratios range from 0.2 to 4 (rule of thumb for chemical industry: turnover
ratio=1)
The reciprocal of this ratio is the so-called
called capital ratio or the investment ratio
92
Working Capital(WC)
Total amount of money invested in:
1. Raw materials and supplies carried in stock(usually 1 month supplies valued at delivery prices)
2. 2. finished products in stock
3. Semi-finished products being manufactured
4. Accounts receivable
5. Cash kept on hand for monthly payment of operating expenses(salaries, wages and raw
materials purchases
6. Accounts payable
7. Taxes payable
93
Cost indexes
Time increase- cost increase (inflation)
Inflation is measured by cost indexes
Cost indexes can be used to give a general estimate, but no index can take into account all factors, such as special technological advancements or
local conditions.
An index value for a given time showing the cost at that time relative to a certain base time.
Present cost= original cost* index value at present time/ index value at time original cost was obtained
Valid the period less than 10 years
We can project costs forward by using extrapolated values of an index or an expected inflation rate.
Most common indexes: ( some of these can be used for estimating equipment costs; others apply specifically to labour, construction, materials or
other specialized fields)
Marshall and swift all industry
Process-industry equipment indexes
Engineering news-record construction index
Nelson-Farrar refinery construction index
Chemical engineering plant cost index
94
Cont.
Marshall & Swift Equipment Cost Indexes
All-industry equipment index is the arithmetic average of indexes for 47 different types of industrial, commercial, and housing
equipment based on an index value of 100 for the year 1926..
Account for cost of machinery and major equipment plus costs for installation, fixtures, tools, office, and minor equipment.
Cont.
CHEM.ENGR. PLANT COST INDEX (CEPCI)
Construction costs for chemical plants.
The four major components are: equipment, machinery and supports, 61%; erection and
installation labor, 22%; buildings, materials, and labor, 7%; engineering and supervision,
10%
Major components subdivided as: fabricated equipment 37%; process machinery, 14%; pipe,
valves, and fittings, 20%; process instruments and controls, 7%; fittings, 20%; process
instruments and controls, 7%; pumps and compressors, 7%; electrical equipment and
materials, 5%; structural supports, insulation and paint, 10%
basis - 100 for 1957-1959
96
Cont.
Unfortunately, all cost indexes are rather artificial; two indexes covering the
same types of projects may give results that differ considerably.
The most that any index can hope to do is to reflect average changes.
For use with process-equipment estimates and chemical plant investment
estimates, The Marshall and Swift equipment Cost indexes and the Chemical
Engineering plant cost indexes are recommended.
recommended
97