13W Report Team03 Part 1
13W Report Team03 Part 1
4.
Lighthouse Project
Subject 4
Team 03
s152374
Vasile Daniel Mois
Geotechnical proposal
The basis of the current project is the design of building called Lighthouse Building T in
Arhus, Denmark. The Lighthouse is part of a bigger project which came to life with the
decision of the Arhus City Council, in 1997, when it was decided to transform the old
container harbor into a vibrant and attractive new neighborhood. In the harbor several
other buildings has been already constructed.
The Lighthouse Building it is considered a high-rise building having height of 160 m
which require and extended parking lot in the basement. In collaboration with the
architect of the project, the dimension of the basement has been established. For the
high-rise building specific types of foundation are fitted.
The site is located in manmade harbor. The site investigation of the soil has shown that
the soil profile consist of two main layers. The main layers is located at the surface and
has a thickness of 10 m. This layer is made of fill material, consisting mainly of debris
material and sand. Bellow 10m, a clay layer has been found which goes up to 70 m
depth. The clay is named Svind marl according to the Geoteknisk rapport nr. 1 and
is describe as an extreme plastic clay. This imposed the project to be treated in high
safety class.
Since the building is located on a harbor location, another important factor in the design
process is the water level at the site location. According to Geoteknisk rapport nr. 1
the water has been found at a level -1.80m bellow the ground surface, also it is
mentioned an influx of water at a level of around -20.00m to -25.00m from the ground
surface. Global warming fact is also to be considered when talking about an increase in
the level of the water. In extreme weather condition it is mentioned that water level can
increase up to 2.00m.
Other constrains to be taken into account is the site location. In the harbor area, has
been already constructed several buildings and existing underground retaining
structures are present.
The above mentioned factors, high-rise building, soil condition, water level, existing
buildings on site, are the most decisive factors in the design so far. Therefore certain
structural systems are considered for the project.
4.1 Excavation dimensions
Dimension of required excavation in order to build the basement was established in
collaboration with the architect. The requirements of the architect were that the
building required 2 level of extended basement which will be used for parking spaces.
Dimensions were established to be of 60.20m width and 79.20 m long and a depth of
10.00m from the ground surface. The depth was established by taking 4.00m for each
floor and 2.00m for the foundation system. The plan proposed for basement is presented
in Figure 4.1.
13-week report
DTU, Course 11080
Advanced Building Design
Lighthouse Project
Subject 4
Team 03
s152374
Vasile Daniel Mois
13-week report
DTU, Course 11080
Advanced Building Design
Lighthouse Project
Subject 4
Team 03
s152374
Vasile Daniel Mois
From structural point of view, diaphragm wall was chosen instead of secant pile wall,
even the second option is cheaper, the diaphragm wall provides a better waterproofing
and has better behavior in sand and gravel soil, category in which first layer of the soil
can be part of. The preliminary dimensions are presented in Table 4.1 and a sketch of
the retaining wall is presented in Figure 4.2. Material to be used for construction are
concrete C35/45 with reinforcement B550 and for anchor steel S235 is chosen.
4.3 Foundation system
The foundation system was design in collaboration with the structural engineer. In this
case two system were investigated during the design: (1) mat foundation over the entire
basement (2) pile rafted foundation for main building with isolated footings for
basement structure. The first option was to used a general mat foundation over the
entire basement. Investigation of this foundation system lead to the conclusion that a
large mat for the main building is not economical and for the basement were the loads
are much lower than for main building the design and only around 9% of the bearing
capacity of the soil was used. Therefore the second option was investigated which lead to
the use of piles. The piles were design to 20.00m long and 1.20 m diameter, a total
number of 32 piles are used. For the pile cap, dimensions are 55.80m long and 26.80m
width with a thickness of 2.00m. Isolated footing are used for the basement structural
columns. The footing are designed to 1.80m by 1.80m dimension and height of 2.00m
and achieve 75% of the bearing capacity of the soil. The material to be used are
reinforced concrete made of concrete C35/45 and reinforcement B550. Dimensions of the
foundation systems are presented in Table 4.2 and a skect is presented in Figure 4.3.
Table 4.2 Summary of foundation design
Deep foundation system - piles
Length
Diameter
[m]
[m]
Pile dimension
20.00
1.20
Length
Pile cap
[m]
Width [m]
dimension
55.80
26.80
Isolated footings
Length
Footings
[m]
Width [m]
dimensions
1.80
1.80
Note: RC - reinforced concrete
Number of
piles
32.00
Thickness
[m]
2.00
Thickness
[m]
2.00
Material
RC
Material
RC
Material
RC
13-week report
DTU, Course 11080
Advanced Building Design
Lighthouse Project
Subject 4
Team 03
s152374
Vasile Daniel Mois
The presence of the existing structure, impose safe distances from them in order to avoid
any damage or structural interference with the existing ones. Safe distances are
presented in Figure 4.4.