Kaplan Turbine
Kaplan Turbine
Kaplan Turbine
CEMEL 3
Scope of supply:
Turbines
Generators
Digital and hydraulic governors
Speed increasers
Electrical equipment
Erection and commissioning
Main data:
Type: 2 x P-30,6/K139/3
Output: 2 x 2591 kW
Head: 6,32 m
Speed: 163 min-1
Year: 2014
Country: Turkey
BRUKSFORS
Scope of supply:
Turbine
Generator
Electrical equipment
Erection and commissioning
Mai data:
Type: 1 x SD-11,55/K89/3
Output: 250 kW
Head: 4,70 m
Speed: 375 min-1
Year: 2014
Country: Sweden
KUTTARI
Scope of supply:
Turbine
Generator
Hydraulic governor
Main data:
Type: 1 x Z-8,5/SR6A
Output: 497 kW
Head: 13,20 m
Speed: 600 min-1
Year: 2013
Country: Japan
TULILA
Scope of supply:
Turbines
Hydraulic governors
Erection and commissioning
Main data:
Type: 2 x Z-16,0/SR6A
Output: 2 x 2581 kW
Head: 21,70 m
Speed: 375 min-1
Year: 2013
Country: Tanzania
ZELIEZOVCE
Scope of supply:
Turbines
Generators
Digital and hydraulic governors
Electrical equipment
Erection and commissioning
Main data:
Type: 2 x RT-20,9/VK3C
Output: 2 x 1540 kW
Head: 5,75 m
Speed: 231 min-1
Year: 2013
Country: Slovakia
GRAFENBERG
Scope of supply:
Turbine
Generator
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x S-9,0/SR6A
Output: 999 kW
Head: 26,67 m
Speed: 750 min-1
Year: 2014
Country: Austria
KALLIOKOSKI
Scope of supply:
Turbine
Hydraulic governor
Electrical equipment
Erection and commissioning
Main data:
Type: 1 x S-18,0/SR6A
Output: 1203 kW
Head: 9,00 m
Speed: 230,8 min-1
Year: 2014
Country: Russia
TISLEIFJORD
Scope of supply:
Turbine
Main data:
Type: 1 x S-18,0/SR6A
Output: 1538 kW
Head: 10,73 m
Speed: 250 min-1
Year: 2014
Country: Norway
10
PRADELLA
Scope of supply:
Turbines
Generators
Hydraulic governors
Electrical equipment
Erection and commissioning
Main data:
Type: 2 x Z-10,0/SR6A
Output: 2 x 448 kW
Head: 10,13 m
Speed: 429 min-1
Year: 2013
Country: Switzerland
11
ARJEPLOG
Scope of supply:
Turbine
Generator
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x RT-22,0/VK4A
Output: 633 kW
Head: 2,94 m
Speed: 150 min-1
Year: 2013
Country: Sweden
12
URSLAU
Scope of supply:
Turbine
Generator
Inlet valve
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x S-9,0/SR6A
Output: 1028 kW
Head: 25,60 m
Speed: 750 min-1
Year: 2013
Country: Austria
13
HIIRIKOSKI
Scope of supply:
Turbine
Generator
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x AR-13,1/VK4A
Output: 375 kW
Head: 4,20 m
Speed: 275 min-1
Year: 2013
Country: Finland
14
FELSDOBSZA
Scope of supply:
Turbines
Generators
Hydraulic governors
Electrical equipment
Erection and commissioning
Main data:
Type: 2 x AR-16,95/VK4A
Output: 2 x 474 kW
Head: 3,75 m
Speed: 200 min-1
Year: 2013
Country: Hungary
15
NIKLASDORF
Scope of supply:
Turbine
Generator
Hydraulic governor
Electrical equipment
Erection and commissioning
Main data:
Type: 1 x ZE-6,7/EF3
Output: 82 kW
Head: 4,30 m
Speed: 500 - variabel min-1
Year: 2013
Country: Austria
16
STADL PAURA
Scope of supply:
Turbines
Generators
Cooling water system
Erection and commissioning
Main data:
Type: 2 x RT-26,5/VK3C
Output: 2 x 2004 kW
Head: 4,98 m
Speed: 176,47 min-1
Year: 2013
Country: Austria
17
PIPARAN
Scope of supply:
Turbine
Generator
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x S-16,0/SR6A
Output: 1234 kW
Head: 11,50 m
Speed: 300 min-1
Year: 2013
Country: Sweden
18
MOULINETS
Scope of supply:
Turbines
Generators
Hydraulic governors
Erection and commissioning
Main data:
Type: 2 x S-15,0/MR4
Output: 2 x 589 kW
Head: 6,18 m
Speed: 273 min-1
Year: 2013
Country: Switzerland
19
CEMEL 1
Scope of supply:
Turbines
Generators
Speed increasers
Digital and hydraulic governors
Electrical equipment
Erection and commissiong
Main data:
Type: 4 x P-30,6/VK3C
Output: 4 x 3620 kW
Head: 6,02 m
Speed: 163 min-1
Year: 2013
Country: Turkey
20
HAKENKRMME 2
Scope of supply:
Turbine
Main data:
Type: 1 x Z-9,0/SR6
Output: 609 kW
Head: 15,27 m
Speed: 600 min-1
Year: 2012
Country: Germany
21
SARIHIDIR
Scope of supply:
Turbines
Generators
Speed increasers
Digital and hydraulic governors
Electrical equipment
Erection and commissioning
Main data:
Type: 2 x P-30,6/VK3C
Output: 2 x 3190 kW
Head: 5,51 m
Speed: 151 min-1
Year: 2012
Country: Turkey
22
KISSAKOSKI
Scope of supply:
Turbine
Generator
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x RT-23,0/VK3C
Output: 1500 kW
Head: 4,31 m
Speed: 187,5 min-1
Year: 2012
Country: Finland
23
LAHANKOSKI
Scope of supply:
Turbine
Generator
Hydraulic governor
Electrical equipment
Erection and commissioning
Main data:
Type: 1 x S-11,2/MR4
Output: 535 kW
Head: 10,00 m
Speed: 428 min-1
Year: 2011
Country: Finland
24
GREINSFURTH
Scope of supply:
Turbine
Generator
Digital and hydraulic governor
Electrical equipment
Erection and commissioning
Main data:
Type: 1 x SZ-10,6/MR4
Output: 519 kW
Head: 7,65 m
Speed: 429 min-1
Year: 2011
Country: Austria
25
BRUNNENFELD
Scope of supply:
Turbine
Generator
Hydraulical governor
Electrical equipment
Erection and commissioning
Main data:
Type: 1 x S-11,8/MR4
Output: 321 kW
Head: 5,38 m
Speed: 333 min-1
Year: 2011
Country: Austria
26
NEUBRUCK
Scope of supply:
Turbine
Generator
Hydraulic governor
Electrical equipment
Erection and commissioning
Main data:
Type: 1 x T-16.0/MR4
Output: 1164 kW
Head: 8,71 m
Speed: 300 min-1
Year: 2010
Country: Austria
27
PRATERKRAFTWERK
Scope of supply:
Turbine
Main data:
Type: 1 x RT-22,0VK4A
Output: 2502 kW
Head: 8,07 m
Speed: 210 min-1
Year: 2010
Country: Germany
28
RENDELSTEIN
Scope of supply:
Turbine
Speed increaser
Generator
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x SZ-16,0/SR6A
Output: 1653 kW
Head: 12,25 m
Speed: 305 min-1
Year: 2010
Country: Italy
29
TIELSI
Scope of supply:
Turbine
Generator
Hydraulic governor
Electrical equipment
Main data:
Type: 1 x ZE-6,7/EF3
Output: 75 kW
Head: 4,50 m
Speed: 510min-1
Year: 2009
Country: Estonia
30
ESSLINGEN
Scope of supply:
Turbines
Generators
Hydraulic governors
Erection and commissioning
Main data:
Type: 2 x P-14,90/VK4A
Output: 2 x 674 kW
Head: 5,05 m
Speed: 250 min-1
Year: 2011
Country: Germany
31
VORSTERBACH
Scope of supply:
Turbine
Hydraulic governor
Generator
Erection and commissioning
Main data:
Type: 1 x S-10,6/SR6A
Output: 780 kW
Head: 13,70 m
Speed: 500 min-1
Year: 2011
Country: Austria
32
SCHTT
Scope of supply:
Turbines
Generators
Hydraulic governors
Erection and commissioning
Main data:
Type: 2 x S-17,0/MR4
Output: 2 x 990 kW
Head: 7,68 m
Speed: 272,7 min-1
Year: 2011
Country: Austria
33
HORB
Scope of supply:
Turbine
Main data:
Type: 1 x AR-16,5/MR3A
Output: 400 kW
Head: 3,42 m
Speed: 214 min-1
Year: 2010
Country: Germany
34
FRTUNA
Scope of supply:
Turbine
Generator
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x S-17,0/MR4
Output: 859 kW
Head: 6,47 m
Speed: 250 min-1
Year: 2009
Country: Sweden
35
LERNBO
Scope of supply:
Turbines
Generators
Hydraulic governors
Erection and commissioning
Main data:
Type: 2 x S-17,0/SR6A
Output: 2 x 3640 kW
Head: 27,00 m
Speed: 428 min-1
Year: 2009
Country: Sweden
36
GLOVA
Scope of supply:
Turbine
Generator
Digital and hydraulic governor
Erection and commissioning
Main data:
Type: 1 x S-10,6/SR6A
Output: 1000 kW
Head: 19,00 m
Speed: 500 min-1
Year: 2009
Country: Turkey
37
BURENTOBEL
Scope of supply:
Turbine
Generator
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x AR-16,5/MR3A
Output: 267 kW
Head: 2,99 m
Speed: 195 min-1
Year: 2008
Country: Switzerland
38
LUDVIKA
Scope of supply:
Turbine
Generator
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x S-21,2/SR6
Output: 3681 kW
Head: 17,00 m
Speed: 273 min-1
Year: 2007
Country: Sweden
39
YONGHUNG
Scope of supply:
Turbines
Generators
Cooling systems
Digital and hydraulic governors
Erection and commissioning
Main data:
Type: 3 x P-21,2/MR4
Output: 3 x 1070 kW
Head: 6,92 m
Speed: 188 min-1
Year: 2007
Country: South Korea
40
KHHRNDLWEHR
Scope of supply:
Turbine
Generator
Inlet valve
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x S-12,5/MR4
Output: 664 kW
Head: 8,67 m
Speed: 375 min-1
Year: 2005
Country: Austria
41
SCHALLAU
Scope of supply:
Turbine
Generator
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x AR-11,2/MR4
Output: 254 kW
Head: 4,70 m
Speed: 315 min-1
Year: 2005
Country: Austria
42
STIFTSWERK
Scope of supply:
Turbine
Generator
Hydraulic governor
Intake structure
Erection and commissioning
Main data:
Type: 1 x AR-16,5/MR3
Output: 387 kW
Head: 3,38 m
Speed: 210 min-1
Year: 2005
Country: Austria
43
CHIPOLE
Scope of supply:
Turbine
Generator
Digital and hydraulic governorr
Erection and commissioning
Main data:
Type: 1 x S-10,0/SR6
Output: 418 kW
Head: 11,83 m
Speed: 428 min-1
Year: 2003
Country: Tanzania
44
DORFMHLE
Scope of supply:
Turbines
Generators
Hydraulic governors
Erection and commissioning
Main data:
Type: 2 x S-19,0/MR4
Output: 2 x 1338 kW
Head: 7,00 m
Speed: 231 min-1
Year: 2003
Country: Austria
45
WALZWERK
Scope of supply:
Turbine
Hydraulic governor
Intake structure
Erection and commissioning
Main data:
Type: 1 x S-16,0/MR4
Output: 548 kW
Head: 5,16 m
Speed: 250 min-1
Year: 2003
Country: Austria
46
AUWEHR
Scope of supply:
Turbines
Weir equipment
Intake structure
Hydraulic governors
Erection and commissioning
Main data:
Type: 1 x SZ-12,5/MR4
1 x SZ-8,5/MR4
Output: 1 x 918 kW / 1 x 432 kW
Head: 11,14 m / 11,92 m
Speed: 428 / 600 min-1
Year: 2002
Country: Austria
47
ERLENHOLZ
Scope of supply:
Turbine
Generator
Digital and hydraulic governor
Erection and commissioning
Main data:
Type: 1 x S-9,0/SR6
Output: 494 kW
Head: 12,80 m
Speed: 500 min-1
Year: 2002
Country: Switzerland
48
Kaplan Turbine
vertical
A Voith and Siemens Company
49
MSSLACHER
Scope of supply:
Turbine
Generator
Hydraulic governor
Belt drive
Erection and commissioning
Main data:
Type: 1 x VK-7,4/VK4B
Output: 45 kW
Head: 2,93 m
Speed: 375 min-1
Year: 2014
Country: Austria
50
SCHALKMHLE
Scope of supply:
Turbine
Generator
Hydraulic governor
Belt drive
Electrical equipment
Erection and commissioning
Main data:
Type: 1 x VK-15,9/VK4B
Output: 276 kW
Head: 3,50 m
Speed: 190 min-1
Year: 2014
Country: Austria
51
PSYTTALIA
Scope of supply:
Turbine
Generator
Digital and hydraulic governor
Electrical equipment
Erection and commissioning
Main data:
Type: 1 x VK-15,9/VK4B
Output: 489 kW
Head: 5,45 m
Speed: 250 min-1
Year: 2014
Country: Greece
52
RIEDINGER
Scope of supply:
Turbine
Main data:
Type: 1 x VK-15,9/VK5E
Output: 687 kW
Head: 6,90 m
Speed: 230,77 min-1
Year: 2014
Country: Germany
53
MITTWEIDA T1 + T2
Scope of supply:
Turbines
Main data:
Type: 1 x VK-20,9/VK4B
1 x VK-14,9/VK4B
Output: 646 kW / 306 kW
Head: 4,28 m / 4,28 m
Speed: 166,67 / 230,76 min-1
Year: 2014
Country: Germany
54
OPPONITZ
Lieferumfang:
Turbine
Hydraulischer Regler
Generator
Montage und Inbetriebnahme
Hauptdaten:
Type: 1 x VK-9,55/VK4
Leistung: 186 kW
Fallhhe: 5,50 m
Drehzahl: 415 min-1
Jahr: 2014
Land: sterreich
55
POETTINGER
Scope of supply:
Turbine
Hydraulic governor
Generator
Electrical equipment
Erection and commissioning
Main data:
Type: 1 x VK-10,85/VK4
Output: 117 kW
Head: 3,36 m
Speed: 265 min-1
Year: 2014
Country: Germany
56
GARTENAU
Scope of supply:
Turbine
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x VK-14,0/VK5E
Output: 946 kW
Head: 10,54 m
Speed: 333 min-1
Year: 2013
Country: Germany
57
VERLA
Scope of supply
Turbine
Generator
Hydraulic governor
Electrical equipment
Erection and commissioning
Main data:
Type: 1 x VK-23,7/VK4B
Output: 1540 kW
Head: 6,20 m
Speed: 187,5 min-1
Year: 2013
Country: Finland
58
HGESTRM
Scope of supply:
Turbine
Generator
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x VK-14,0/VK4B
Output: 205 kW
Head: 3,30 m
Speed: 214,13 min-1
Year: 2012
Country: Sweden
59
STADTBACH
Scope of supply:
Turbines
Main data:
Type: 2 x VK-15,9/VK4B
Output: 2 x 285 kW
Head: 3,61 m
Speed: 200 min-1
Year: 2011
Country: Germany
60
PROVIANTBACH
Scope of supply:
Turbine
Main data:
Type: 1 x VK-23,0/VK4B
Output: 758 kW
Head: 4,69 m
Speed: 157,8 min-1
Year: 2011
Country: Germany
61
KEMNADE
Scope of supply:
Turbine
Main data:
Type: 1 x VK-30,6/VK4B
Output: 726 kW
Head: 2,40 m
Speed: 91 min-1
Year: 2011
Country: Germany
62
GAILITZ
Scope of supply:
Turbine
Generator
Inlet valve
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x VKS-12,5/SK5
Output: 1866 kW
Head: 25,77 m
Speed: 500 min-1
Year: 2010
Country: Austria
63
AUSLAUFTURBINE
Scope of supply:
Turbine
Generator
Speed increaser
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x VK-14,5/SK4B
Output: 384 kW
Head: 5,70 m
Speed: 220 min-1
Year: 2009
Country: Austria
64
VILLA DALME
Scope of supply:
Turbine
Generator
Intake gate
Hydraulic governor
Electrical equipment
Erection and commissioning
Main data:
Type: 1 x VK-18,0/SK4A
Output: 1020 kW
Head: 7,16 m
Speed: 231 min-1
Year: 2009
Country: Italy
65
ISARWERK 2
Scope of supply:
Turbine
Main data:
Type: 4 x VK-20,0/SK4
Output: 4 x 579 kW
Head: 4,31 m
Speed: 157 min-1
Year: 2009
Country: Germany
66
TIRINO INFERIORE
Scope of supply:
Turbine
Generator
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x VK-11,2/SK5
Output: 1205 kW
Head: 22,40 m
Speed: 500 min-1
Year: 2008
Country: Italy
67
ST. AEGYD
Scope of supply:
Turbine
Generator
Intake structure
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x VK-7,4/KR4
Output: 50 kW
Head: 3,47 m
Speed: 400 min-1
Year: 2006
Country: Austria
68
MHLTALWEHR
Scope of supply:
Turbine
Generator
Speed increaser
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x VK-19,0/SK4A
Output: 630 kW
Head: 4,75 m
Speed: 175 min-1
Year: 2005
Country: Austria
69
LOFERBACH
Scope of supply:
Turbine
Intake gate
Hydraulic governor
Erection and commissioning
Main data:
Type: 1 x VK-11,5/KR4
Output: 197 kW
Head: 4,55 m
Speed: 285 min-1
Year: 2003
Country: Austria
70
Kontakt:
Kssler GmbH & Co KG
Wasserkraftanlagen
St. Georgener Hauptstrae 122
3151 St. Georgen am Steinfeld
Tel.: +43/2742/885272
e-mail: [email protected]
71
72