Excavation of Unsuitable Material and Back Fill With Suitable Material
Excavation of Unsuitable Material and Back Fill With Suitable Material
Excavation of Unsuitable Material and Back Fill With Suitable Material
OBJECTIVE
To outline the work instruction by which the excavation of unsuitable material and backfill with
suitable fill is carried out.
REFERENCES
WORK METHODOLOGY
1.
Prepare access to the working area and plan for the lorry and plant movements.
2.
Excavate the unsuitable material to the required depth as specified by the client / clients
representative and dispose at approved disposal area.
3.
Transport, fill and spread suitable material in layers. The loose for each layer of fill shall be
determined from the trial compaction.
4.
Repeat step 4 until the required level is achieved. Carry out necessary tests as per
inspection & test plans :
o
Compaction Trials : The BS 1377 Compaction test (4.5 kg rammer method) shall be
used in determining the moisture contest versus density relation of soil.
o
Degree of compaction : The whole of the embankment below the top 300mm of
the subgrade shall be compacted to not less than 90% (for cohesive material) or 95% (for
cohesionless material) of the maximum dry density determined in the BS 1377 Compaction
test (4.5 kg rammer method)
o
Field Density Testing : Field density tests on each layer of compacted earth fill
shall be carried out using sand replacement method in accordance with BS 1377.
o
Moisture control : - Each layer of earth fill shall be processed as necessary to bring
its moisture content to a uniform level throughout the material, suitable for compaction.
The Optimum moisture content as determined by BS 1377 compaction test (4.5 kg rammer
method) shall be used as a guide in determining the proper moisture content at which each
soil type shall be compacted.
5.
Submit request for inspection form for joint inspection and joint measurement with client /
clients representative using Earthwork Inspection checklist.
6.
Request client / clients representative to sign on checklists and maintain all inspection /
approval records as per Project Filing Index.
7.
Carry out computation and submit for claim.