Check List for Installation of AHUs, FCUs And Fans

Ref. No. : MAP/CL-003


Rev No. : 00
End
Contracto
Al Shifaa Hospital, Khalifa City,
:
:
Abu Dhabi
User
r
Project
The
Dar Al Shifaa Hospital LLC
Name :
Employer :
Engineer
:
Society Technical House(STH)
Drawing(s) No. :
Works Location:

SECTION OF WORK
:
Level

N/A

S/N
1

AHUs, FCUs And Fans

Date:
23/8/2015
Vamed Emirates LLC/Vamed Engineering
Gmbh & Co KG
Al Shifaa Hospital, Khalifa City, Abu
Dhabi
Date
:
Checklist N: MAP/CL-003
LOCATIO
ITP
No
: MAP/ITP-003

N:

Checked By Checked& Remarks


By The Engineer
Contractor

Item
Installation Checks For (FCUs/AHUs)

1.1

Units are factory assembled as per specification and no damage.


Assembly is correct.

1.2

Equipment installation and general arrangement, correct and as per


approved drawings

1.3

Equipment supports and location correct as per approved drawing.

1.4

Water /Air Flow rate is correct as per design flow

1.5

Entering/Leaving water temperature rating is correct

1.6

Supply Power Cable size and type, connected.

1.7

Supply Power Cable size and type, connected.

2
2.1

All the Project

Installation Checks For (EXHAUST FANS)


Units are factory assembled as per specification and no damage.

2.2

Equipment installation and general arrangement, correct and as per


approved drawings.

2.3

Exhaust Fans type & characteristic correct

Material Checks
1. FAN COIL UNITS
1
Manufacturer
1.1 Cooling Capacity
1.2 Temp. Range/flow
1.3 Kw/hz/ph
1.4 Pressure drop
1.5 Type/shape/Wt
1.6 Dimension
1.7 Serial No./location
1.8 Drawing No.
2. AIR HANDLING UNITS
2.1 Manufacturer
2.2 Cooling Capacity
2.3 Temp. Range/flow
2.4 Kw/hz/ph
2.5 Pressure drop
2.6 Type/shape/Wt
2.7 Dimension
2.8 Serial No./location

Page 1 of 2

2.9
3.
3.1
3.2
3.3
3.4
3.5

Drawing No.
FANS
Motor Power input
Motor Power input
Manufacturer
Serial No./location
Drawing No.

Remarks

Accompanying Documents
Contractor
Mapco QA/QC

Main Contractor

Name
Signature
Date

Page 2 of 2

Client
Engineer(Consultant)