2008-IADC Alerts PDF
2008-IADC Alerts PDF
2008-IADC Alerts PDF
Conduct a pre-job safety meeting before starting a project. Ensure all employees know what and how it
is to be done.
All rigs should write or review a JSA for this job. Ensure all employees who are not familiar with the
operation review the JSA before starting the project.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2008 International Association of Drilling Contractors All rights reserved.
Issued January 2008
Safety Alert
From the International Association of Drilling Contractors
Since the least experienced crew member is usually the man sent to conduct work below the rotary
table, strong consideration should be given to sending a more experienced employee. If an
inexperienced crew member must be used it is critical the employee understands exactly what is to be
done and how to do it safely. Quiz the employee to ensure ALL aspects of the task are understood.
Always wear proper fall protection while working in an elevated work site.
Ensure all employees working under the rotary table are aware of the potential for some types of fall
protection to become entangled in the rotating equipment.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2008 International Association of Drilling Contractors All rights reserved.
Issued January 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 02
Standpipe receptacle
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2008 International Association of Drilling Contractors All rights reserved.
Issued January 2008
Safety Alert
From the International Association of Drilling Contractors
IADC Note: Thread Engagement per Marks Standard Handbook for Mechanical Engineers
The normal amount of thread engagement necessary to make a joint for ANSI Standard Pipe
Thread joints as recommended by Crane Co. is as follows:
Size of Pipe, inch
1/8
3/8
1
1-1/4
1-1/2
2
2-1/2
3
3-1/2
4
5
6
8
10
12
3/8
3/8
9/16
11/16
11/16
11/16
15/16
1
1-1/16
1-1/8
1-1/4
1-5/16
1-7/16
1-5/8
1-3/4
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2008 International Association of Drilling Contractors All rights reserved.
Issued January 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 03
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2008 International Association of Drilling Contractors All rights reserved.
Issued January 2008
Safety Alert
From the International Association of Drilling Contractors
Most importantly take the time to visualize the work to be done and identify the potential hazards,
and communicate them, so a control can be implemented. Think beyond the evident, adopt a
questioning attitude: What If? Remember:
Step 1: Identify the Hazard
Step 2: Assess the Risk
Step 3: Identify Controls
Step 4: Implement Controls
Step 5 Monitor the Process.
The above 5 steps are a simple and effective tool for all of us to use, whether crossing a busy street or
installing a crane.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2008 International Association of Drilling Contractors All rights reserved.
Issued January 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 04
Strained backs
Hands and arms caught under the lids
Head struck by the falling lid
CORRECTIVE ACTIONS: To address this incident, this company instructed rig personnel:
Eliminate these types of storage areas and replace with 100% polyethylene constructed storage
containers that meet the requirements in 40 CFR 264.175 (Containment), and Uniform Fire Code Article
80 (or equivalent local standard).
To prevent the lids from accidentally closing or falling shut while personnel are working in these storage
areas until they can be replaced rig personnel are to temporarily place safety bars or support legs on
these lids that can be pinned to hold the lids in place.
See the picture of the recommended storage areas to use.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2008 International Association of Drilling Contractors All rights reserved.
Issued January 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 05
Safety Alert
From the International Association of Drilling Contractors
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued February 2008
Safety Alert
From the International Association of Drilling Contractors
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued February 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 05
Safety Alert
From the International Association of Drilling Contractors
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued February 2008
Safety Alert
From the International Association of Drilling Contractors
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued February 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 06
Supervisors on the rig deviated from the agreed game plan to use the top drive system (TDS) to fill the
casing.
The casing was filled using the high pressure system instead of the low pressure mud tank system
(charge pump).
No Hazard Assessment (JSA) or pre-job safety meeting was conducted before this work started
CORRECTIVE ACTIONS: To address this incident, this company reminded rig and operations
personnel of the following:
Company policy requires that the TDS or service company, fills up machines that should be used to fill
casing whenever possible
Company procedures manual require that low pressure pumping equipment is to be used when filling
casing with a hose.
To prevent hose movement, when filling casing with a low pressure hose, the hose must be tied down
prior to starting the pump.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued February 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 07
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Immediate Actions by Contractor Resulting in Clients Follow-up
Since personnel logistics for the operation are a Client matter, the Company Man was informed. The official
document, specific for air-related near miss / incidents was completed and immediately forwarded to the
Client. An e-mail was also sent to the Client containing a video of the incident and requesting that corrective
measures be put in place. The helicopter company was contacted by the Clients Representative. The
Clients Flight Safety Officer met with the helicopter company to show the video and discuss the causes and
preventive measures. The helicopter company asked for a copy of the video to be used in pilot training in
order to minimize chances of recurrence. The Clients Contract Manager was also notified to take the
necessary administrative measures necessary to prevent recurrence by ensuring the pilots adhere to their
checklist procedures for disembarking.
Contractor Initiatives put in place:
If HLO sees he must assist a passenger or for any need for delay he is to call the pilot on the radio or
walk to front of helicopter and signal to delay lift-off. When assistance is finished, he will radio or signal all
clear for take-off.
Pilots should be trained as per the country-of-operations laws and regulations pertaining to helicopter
operations, which include offshore pilot responsibilities. Helicopter providers pilots should be trained in the
Clients General Operations Manual that includes the safety rules related to offshore landing and take off
procedures. An annual refresher training course, that includes flight simulation and HLO ops, should be
conducted.
Further Recommended Precautions
Large crew-change operations normally have a pilot and co-pilot. It is the practice of some helicopter
companies for the co-pilot (or pilot) to walk around the helicopter (not tail rotor side) to verify:
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued February 2008
Safety Alert
From the International Association of Drilling Contractors
(1)
(2)
(3)
(4)
(5)
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued February 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 08
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued February 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 09
Safety Alert
From the International Association of Drilling Contractors
7. Rig managers are to ensure this Safety Alert is reviewed with each crew member. A pre-tour safety
meeting is a good opportunity to conduct and document the review. The Safety Alert should be posted in
the top doghouse.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued March 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 10
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Short Term Actions:
Instructions were given to all rig crews to always perform as cement / casing integrity test against
blind rams.
Rig Superintendents are to provide coaching by at rig sites.
Rig supervisors are to perform proper planning of work scopes and divide them up to several suboperations with each having their own pre-job meetings.
Additional supervisory resources shall be assigned to company rigs i.e. additional field
superintendent.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued March 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 11
The elevators had to have been manually removed, turned 180 degrees and re-installed. The Driller
would then be in a position to rotate the handler 180 degrees allowing the link tilt to extend further out
(Drilling mode).
The safety system which triggers the warning alarm at 60 feet (18 meters) above the rig floor and then
triggers the braking system at 70 feet (21 meters) above the rig floor in order to prevent the TDS from
ever reaching the monkey board level when the links are in the drilling position was switched off.
In doing the above steps, the Driller knowingly violated procedures,-by-passed a safety device and put the
equipment and more importantly, the safety of the Crew at serious risk.
CORRECTIVE ACTIONS: To address this incident, this company did the following:
The job was immediately stopped by the top-drive technician. He explained again how the TDS needs to
be set up for tripping and why. He then supervised the crew to ensure that the TDS was set up properly
in the tripping mode and the safety warning device enabled.
A behavioral observation card was written and handed into the Rig Supervisor and rig Top-drive
Supervisor.
The rig Top-drive Supervisor then spoke to the Field Superintendent and explained the situation. The
Field Superintendent then immediately called the Rig Manager to ensure the proper procedures are
being maintained and enforced.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued March 2008
Safety Alert
From the International Association of Drilling Contractors
Elevator
Handles
ALWAYS
to
be
positioned pointing
to the back side of
the backup tong
Back-Up tong
Elevators
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued March 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 12
Safety Alert
From the International Association of Drilling Contractors
The unsafe hook had been identified earlier, but had not been replaced as per established procedure.
No JSA or Permit to Work was issued to perform the activity and all potential hazards had not been
identified for this task.
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Immediate action: Instructed the Rig Manager to change out the unsafe hook as soon as the mast is rigged
down.
Per the companys equipment standard, a request was made to place a dedicated man-rider winch for
the rig.
Rig personnel are to use fall protection as per company standard for personnel hoisting activities.
Rig personnel installed SRLs below rotary table that are adequate for the job.
Rig personnel were instructed that scaffolding will be erected when working in BOP area.
A third party investigation has been completed.
An inspection has been conducted of all lifting and fall protection equipment on the rig. A follow-up on its
condition has warranted several lifting equipment items to be taken out of service.
Rig supervisory personnel were instructed to reinforce company policies on following the correct safety
procedures such as, JSAs, Work Permits and use of Fall Protection Systems.
Hand-over notes and responsibilities should be identified by supervision and communicated to all
personnel.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued March 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 13
Night Pusher and Driller did not comply with the procedure for breaking out the IBOPs from the TopDrive System.
This was the first time to do the job with one tong which is a short cut for breaking out the lower and
upper IBOPs.
This shortcut was taken without authorization or advice from the Senior Toolpusher.
Incorrect securing for the intermediate tieback was made on the mast beam with the securing wire
wrapped around the intermediate tieback itself instead of being wrapped around the mast beam as was
required to prevent a dropped object.
Improper tieback allowed the tieback beam to fall from 10 meter
CORRECTIVE ACTIONS: To address this incident, this company did the following:
1. The pipe handler is to be used for breaking /making up the IBOP connection.
2. Make sure that the pipe handler clamp cylinder pressure is 2000 psi and the dies are in good condition.
3. In case of using rig tongs for breaking the IBOP or saver sub from the main shaft, its important to use a
pup joint in order to maintain it in the center and prevent the twisting motion.
4. Any non-routine job related to the TDS should be performed under the supervision of the Rig Senior
Mechanic and Senior Toolpusher.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued April 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 14
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 15
The tie back rope was cut and this allowed the diving board to free fall.
The derrickman should have been more alert to the position of the roustabout and the hazard this posed.
The roustabout should have been aware of the purpose of the secured rope.
Poor communications between both parties working.
Supervision should have provided hazard awareness and clearer work instructions.
CORRECTIVE ACTIONS: To address this incident, this company instructed rig personnel in the
following:
Follow the correct procedure in lowering the diving board and hinge up the handrail bolts back to the side
rail.
The diving board can be laid back against the back handrail and secured with a cable or safety strap.
The safety cable/safety strap keeps the board from falling when the mast is being raised or lowered.
Hold a JSA and identify hazards and job specific duties before the task is done.
Improve lines of communication from the Supervision to the employees
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued April 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 16
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued May 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 17
Incorrect positioning of crane by operator. The rigging crew failed to recognize potential lifting hazard.
Inadequate supervision and crane directives.
No JSA performed before the task.
Poor decision making by crane operator to use mobile phone during lifting/lowering operation. Very poor
supervision by allowing this practice to occur.
Miscalculation of load weight and incorrect methods of load bearing positions.
Failure to conduct pre-job safety meeting. Step Back 5x5 Safety Tool not utilized as recommended.
Senior Site Manager was not on location at time to offer expertise in lift.
Incorrect position of the employee who was knocking out the pins.
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Personnel involved in the lift are to hold a JSA and identify the hazards before the task is done.
Lift personnel are to utilize the companys pre job 3rd party equipment check list.
Site supervisors are to check crane operator certifications for competency on the operating of hire
equipment.
Because of potential injury or equipment damage site personnel are to correctly use the Permit to Work
check off list for heavy lifts.
Improve line of communications from Senior Rig Site Personnel on their responsibilities and duties when
ever Senior Site Manager is off location.
Use of competent and ticketed Dog man / Signal man for directing all loads as required on rig
construction site.
To avoid shock load the crane operator is to be sure that the package weight is taken up by the crane
prior to the pins being moved.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued May 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 18
The person in charge of the load is responsible to check that both ends are free.
When loading or unloading items from racked tubulars, all lifts will be checked for stability and correct
rigging.
Personnel shall move off the racked tubular prior to making the lift.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued May 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 19
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued June 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 20
Inadequate supervision and poor communication, as the driller gave a signal to the crane operator to
lower the V-door in, was not observing the load.
At the same time the IP was still close and installing the pin.
Driller acted as banksman (signal man) and lift supervisor, thus not giving himself full view of the work
place and he failed to see the handrail hung up on the air winch.
There was a change of design when it was decided to weld the gate support of the V-door. The
Management of Change (MOC) process was not followed.
Welding the V-door gate allowed the hand rail to get tangled with the air hoist on the rig floor.
The Safe Job Assessment (SJA) did not address the potential of the load getting hung up on the air
winch.
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Proper SJA to be issued and communicated with rig crews in the pre-job meeting.
Improve lifting competency of the crew and supervisors.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued June 2008
Safety Alert
From the International Association of Drilling Contractors
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued June 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 21
The pinch point area between the annular body and the BOP bolt where
the IP placed his left hand fingers.
WHAT CAUSED IT:
It was determined in the accident investigation that the Annular was being suspended by slings of different
length and that the crane boom was not extended far enough to have the load properly centered over the
BOP stack. Subsequently, the Annular got caught on one side of the BOP bolts and shifted at precisely the
same time the IP had his fingers in the wrong position.
CORRECTIVE ACTIONS: To address this incident, this company did the following:
1. The job was immediately stopped and the IP treated for his injuries.
2. A safety meeting was held to communicate incident with all crew members. The JSA was revised and
reviewed to include identifiable pinch point.
3. Crew and crane operator were informed to follow safe rigging/lifting procedures.
4. A Safety Bulletin was generated for circulation to other operating rigs.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued June 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 22
IADC Note: See IADC Alert 99-13. Also, note the following from the IADC HSE Reference Guide:
Employees should not attempt to tighten or loosen unions or other connections under pressure. Never
hammer on a pipe or connection that is under pressure.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued July 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 23
Ramp to be
unloaded
Stopper
being
removed
Pinch Point
Poor supervision and communication as the driller did not make sure that the IP had finished the job
assigned to him.
Change of procedure during task.
o Normal procedure is to lift off the ramp, from the trailer, high enough so that the trailer can pull
out from under the load. Then off load the ramp in place.
o The driller decided to have the IP remove the stoppers on the side opposite the forklift.
o The injured ended up being in a position where he was not full view of the driller.
o The driller decided to lift the load again without checking to determine if the injured person had
removed the pins and his hands were out of harms way.
CORRECTIVE ACTIONS: To address this incident, this company did the following:
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued July 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 24
Safety Alert
From the International Association of Drilling Contractors
3. The Driller is responsible for communicating to the Derrickman (via the hands-free communication
system), that it is clear for the Derrickman to place the rope or chain on the tubular when it has been
confirmed that rotation has been stopped, the iron roughneck or spinning wrench has been removed
from the pipe, and the pin is lifted clear of the box.
4. Length of a chain used for manually racking tubulars should be formally risk assessed, to ensure that it
does not create a potential hazard (either too long or too short).
5. All Job Risk Assessments involving manually racking tubulars are reviewed to include the previous
points.
6. Ensure that the hands-free communication systems are in good working order, as per the companys
Health and Safety Manual.
7. A plan for the rescue of personnel at elevated levels is included in the relevant Job Risk Assessment and
all necessary equipment is available [References: Company Health and Safety Manual section on Fall
Protection].
Rig Specific Corrective Action Plans are to be developed, tracked, and closed in the companys
incident closure tracking system.
Regional and Rig QHSE Managers are to follow up and report to the Director of Corporate QHSE
upon completion and close out.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued July 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 25
CORRECTIVE ACTIONS: To address this incident, this company instructed supervisors to do the
following:
Discuss with the crew, the safe handling of hand tools prior to use. Inspect before use.
Explain the importance of using the proper equipment such as tool bags and tool belts for tasks
performed in high places.
Go over with the crew, the steps in the JSA for this specific job.
Follow operational safety procedures by utilizing safety inspections.
Place Where
Hammer Fell
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued July 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 26
Position of
Floorman #1
before the fall
Original position
of Bell Nipple
Position of
Floorman #2
before fall
BOP Lifting
Bracket
Position of Floorman
#2 suspended
upside down
Bell Nipple struck
work platform
Final position of
Bell Nipple and
Floorman #1
The winch line connected to the flow line was supposed to have been disconnected.
The original plan was to use two winch lines to remove the bell nipple, one through the mouse-hole and
one through the rotary table. One line was ready and passed through the mouse hole, but not
connected. The Driller changed the plan to use only one winch.
Neither worker was connected to the Safety Retracting Life (SRL) line fall arrestors which were attached
to the underside of the rig floor on each side of the sub base.
Lanyards used were not secured above head height and in one case the lanyard was connected to an
unsecured anchor point (bell nipple).
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued August 2008
Safety Alert
From the International Association of Drilling Contractors
All four studs that attach the bell nipple to the BOP annular had been removed before it had been
secured with a hoist line.
No procedure was available for this job.
No JSA/JHA was used for this task.
Brief pre-job discussion was inadequate for the task being undertaken and potential risk
Lack of adequate and / or specific instructions during the task, particularly just before the incident.
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Procedure to be developed with sequential steps particularly the restraining of all equipment before
unbolting or removing it.
Ensure all provided safety devices are used (in this case fall arrestors)
Processes to be put in place to ensure adequate and thorough Pre Job meetings are planned as part of
the job, including the communication of hazards and why controls are necessary to prevent an accident.
Ensure all instructions given during a job are specific, understood and recorded.
Outline Supervisor expectations to ensure that jobs are undertaken safely
Reinforce to the work force that they are empowered to STOP THE JOB when safety controls or
precautions are bypassed.
Ensure fall protection lanyard is secured to a suitable (stable) anchor point.
To reduce fall distance, lanyards are to be secured to anchor points that are above head height.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued August 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 27
Although the reason for the fryer left on and temperature at max
heat setting was not determined, it is believed that:
(1) In a rush to muster for the drill, personnel simply neglected to
switch off the fryer. It is common practice to set heat at max to
heat up the oil faster. When the oil gets hot, the heat is turned
down to normal frying temperature. However, when the drill alarm
sounded, the galley was abandoned quickly leaving the fryer on
max temperature; hence, the oil ignited.
(2) Another explanation is that when the alarm sounded, in a rush
to get to the muster point, the dial was erroneously turned to
maximum heat instead of the off position.
The hood and vent above caught fire due to grease buildup.
CORRECTIVE ACTIONS: To address this incident, this company did the following:
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued August 2008
Safety Alert
From the International Association of Drilling Contractors
OIM designated a person to pass through the galley on his way to the muster point to double check that
all kitchen items (fryers, ovens, stovetops, mixers, etc) have been turned off if a kitchen monitor is not
assigned.
Installed a fire extinguishing system with a fusible link for the galley exhaust hood.
Galley crew was reminded of their duties to keep the vent hood clean and free of grease buildup.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued August 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 28
The board communication system was not functional at the time of the incident and there was no verbal
communication between the derrickman and the driller.
The driller and other employees on the rig floor were apparently not aware of the derrickmans activities.
The derrickman had the pull back rope wrapped around his arm and could not release it.
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Instructed the Rig Managers to ensure that the communication systems should be maintained in proper
working order.
Instructed rig personnel that the pull back rope should never be secured around the hand, arm or other
part of the body.
Instructed employees working on the rig floor during trips or any time personnel are in the derrick that
they should assist the driller in monitoring the derrickmans activities.
Instructed rig personnel to never stand on or in a coil of rope or line which is moving. These hazards are
present while operating the cathead line and during rig up operations.
Instructed rig personnel that under no circumstances shall a person wrap ANY rope, wire line or cable
around their hand, arm or other body part.
Instructed derrickmen that they shall use the mule line or pull back hoist whenever practical to limit the
use of the pull back rope.
Employees were instructed of other potential activities where this type injury could occur such as holding
a tag line. Being unable to release the tag line could pull a person off a platform or into harms way.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued August 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 29
Rig move preparation procedure to be followed by truck pusher(s) and rig senior toolpusher prior to
start rig move and documented by completion of the checklist.
In preparation of new location, the company Minimum Requirements for Land Rig Drilling location
procedure is to be followed by construction engineer(s).
Movement of rig move trucks is to be controlled in order to ensure proper road traffic and parking.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2008 International Association of Drilling Contractors All rights reserved.
Issued September 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 30
The injured man did not realize that he had placed his had in a pinch point.
The pre-job hazard assessment did not recognize the hazard that may result from attempting to
secure casing centralizers while making up the casing.
CORRECTIVE ACTIONS: To address this incident, this company reviewed the following lessons
learned:
Thorough pre-job hazard assessments must be held before each job. All workers involved must attend
the meetings, participate, and understand thoroughly what their roles and duties are.
During pre-job safety meetings, all pertinent guidelines, SOPs, and Hazard Recognition Worksheets
must be reviewed.
Should any scope or part of the job change, stop the job and reassess how to do the job safely
During every job it is crucial that everyone stay focused to the job at hand
Everyone must remember to stop any job that they feel is unsafe. The job must not resume until all
hazards and mitigation steps are in place, communicated, and understood by all involved.
Workers must not hold objects above the casing tong.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2008 International Association of Drilling Contractors All rights reserved.
Issued September 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 31
CORRECTIVE ACTIONS: To address this incident, this company did the following:
The following learning/corrective actions have been identified and implemented:
Awareness: All personnel will attend further refresher/awareness training on hand and finger hazards.
Communication: Effective communication is essential for safe operations. If there are any doubts or
misunderstandings, ask for clarification. ASK first, ACT later.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2008 International Association of Drilling Contractors All rights reserved.
Issued September 2008
Safety Alert
From the International Association of Drilling Contractors
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2008 International Association of Drilling Contractors All rights reserved.
Issued September 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 32
The subsequent investigation revealed that the crew assigned with the task of preparing the tensioner for
removal did not have full knowledge of the valve assembly and the necessity for completely venting
pressure on pressurized lines.
A false sense of security was created by the lack of pressure on the downstream vent valve on the
number three tensioner.
Pressure was left on the line in the event that a quick charge was needed to put the number seven
tensioner which was paired with the number three, tensioner into service.
This job was planned to be broken down into three phases. At the completion of each phase the job was
to be stopped and the next phase was to be planned before going forward. This three phase process did
not occur.
The crews were into phase two when the incident occurred and there was no stoppage of work or phase
planning between phase one and two.
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Instructed rig personnel that when they are working on pressurized lines and/or pressure vessels,
regardless of the product contained the pressure is to be vented before the work begins and isolating
valves are to be tagged-out .
Instructed supervisory personnel to discuss this alert with all employees offshore and in the various
yards.
Thee company plans to issue further recommendations in the forms of Tech Alerts, addendums to this
alert and changes to systems affected.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2008 International Association of Drilling Contractors All rights reserved.
Issued September 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 33
When the Rig Manager reached for the joystick on the control panel, the back of his right hand brushed
the rotary table speed control knob.
Due to the lack of resistance on the rotary speed control knob, the knob easily turned, causing the rotary
table to rotate in reverse.
The Stop position on the Rotary Table/Stop/Top Drive switch on the chair arm was actually a Neutral
position and does not isolate the Rotary Table throttle control.
CORRECTIVE ACTIONS: To address this incident, this company did the following:
The company requested that the manufacturer the drillers chair and control console reposition the
controls and install separation devices to prevent drillers hand from accidentally activating any controls.
This would need to be done on both the right and left sides of the chair.
Exiting chairs are to add a plexiglass / lexan cover around the rotary control knob until such time as the
control can be relocated.
Rotary table must be isolated on the touch screen when using chain tongs to manually spin-in or spin-out
tubular connections. In addition, relocate the TD lockout button to the back of the control panel to allow
room for the reconfiguration of the rotary speed control. Add a RT lockout button beside the TD lockout
button.
Change RT/Stop/TD mode selector switch to a RT/TD selector switch.
Drilling crew (including the Rig Manager, Toolpusher and Drillers) must undergo simulator training for
DDC (Digital Drilling Controller. .
Create a new JSA to include locking-out rotary table when using chain tongs for making-up or breaking
connections.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued October 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 34
Poor design of the starboard bow deck stairway, penetrating through mid-deck and creating a deck
obstruction for both load placement (constraint and space inefficiency) and personnel movements (crush
point).
Inadequate lighting
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Instituted design changes to stairway by removing and relocating the stairway to inboard side of deck
Conducted a lighting level survey for normal operations as well as during Rigged Down state.
Conducted a review of company policy regarding Heavy Lift operations during night-time hours
Conducted a review of procedures and documentation used to manage Heavy Lift operations
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued October 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 35
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Only cranes with certificates issued by a recognized certification body are to be accepted at company
work locations.
A list of recognized certification bodies is to be communicated to contractors through the companys
Transportation Superintendent.
Adequate supervision to be performed for the jobs during the rig up operation. Each group should have
an experienced and competent supervisor, and the designated site supervisor should control all
operations.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued October 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 36
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Rig personnel are to comply with all procedures. If it is not possible to comply, stop the job, contact the
Operations Manager.
In the event procedures cannot be complied with immediately, it becomes the responsibility of the
Managers, Supervisors, and Safety Supervisors to stop the job, review and modify the standards and
procedures as needed to complete the job while ensuring safety.
To assure personnel competency, personnel qualifications for all positions both permanent and relief
should be verified with the area Human Resources department.
Supervisors are to ensure that company procedures are followed regarding relief employees.
Drillers are to ensure that the crown saver device is set in the correct place so there is sufficient stopping
distance to the crown.
Drillers are to test the crown saver device system as per company procedures.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued October 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 37
Position
of
Worker
reaching
across
the
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued November 2008
Safety Alert
From the International Association of Drilling Contractors
Inadequate supervision.
o The supervisor left the work area before the task was completed as he considered this activity not
being part of his work scope.
Inadequate procedures and work instructions.
o There was no adequate method statement and Job Safety Analysis (JSA) for this activity available
as crane set up and breakdown activities were not properly addressed in the documentation
provided for this job (e.g. lift plan, permit to work, JSA, etc.)
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Several fatalities have occurred in the Group in the past involving crane operations. In general, risk
management of those activities is focused on the actual hoisting and lifting operations at the site of work.
This incident demonstrates that crane preparation or demobilization activities involve significant safety risks
as well and hence require rigorous HSE management controls.
Supervisors and Workers are to:
Assure yourself that similar activities are adequately managed in your area of operational control and
that key controls are effectively implemented when performing these activities by asking and answering
the following questions:
o Do you use similar type of equipment in your area of operation?
o Are preparation and demobilization activities treated as being part of your lifting and hoisting plan?
o Determine if clear procedures are developed and work instructions for these activities are
communicated?
o Do you supervise these activities permanently?
o How well are your workers trained in executing the emergency response plan?
o Determine how you are going to deal with language problems?
Conduct a toolbox talk prior to commencing the work.
Ensure that the work area is barricaded off to prevent access to the crane area for those not involved in
the crane operation.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued November 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 38
Impact
Point
The JSA did not point out the risk of the casing snagging the A-frame brace, although the hazard was
verbally acknowledged at pre-tour and pre-job meetings.
The lifting speed was not adjusted to allow the casing to clear the girt.
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Revise the JSA to show the danger of a joint of casing being pulled too fast up the V-door and colliding
with the top of the A-frame. Mitigate the risk by adjusting the pick-up speed.
As the joint is picked up, stop (or nearly stop) the lift before the casing enters the A-frame so there is no
chance of it colliding with the girt.
Floormen waiting on the joint--in particular the crewman with the hold-back rope--watch the joint and
signal Driller to stop if the joint gets too close to the A-frame girt or speed is not adjusted. Promote
stop-job authority to avoid release of uncontrolled killer energyfrom falling casing.
LESSONS TO LEARN for personal safety: STAY OUT OF THE DROP AND SKID ZONE UNTIL IT IS
SAFE TO ENTER. Stay alert and always be aware that lifting equipment could fail. Keep checking it.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued November 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 39
Safety Alert
From the International Association of Drilling Contractors
Ensure all items identified as potential dropped objects are either removed from the subsea tree
(preferred method) or secured in a manner approved by the subsea tree suppliers engineering
department to prevent and restrain any potential dropped object.
The Rig Manager is responsible to review and approve the subsea tree suppliers engineered solution
prior to implementing the securing method.
The motor fitted to the main block hoist is consistent with the part number specified by the crane
manufacturer manual.
The motor fitted to the whip line is consistent with the part number specified by the crane manufacturer
manual.
The motor fitted to the boom hoist is consistent with the part number specified by the crane manufacturer
manual.
The findings from the above checks must be communicated to the Rig Manager and recorded in the
installations planned maintenance system.
If additional assistance is needed to complete the required actions contact your respective Business Unit or
Division Field Support office.
For all lifts (including client and subcontractor equipment) aboard company installations:
Ensure all equipment is assessed for dropped object risk as part of the Job Risk Assessment plan.
Ensure all items identified as potential dropped objects are either removed or secured in a manner
approved by the Rig Manager.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued November 2008
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 40
FAILURE OF BACK FLOW VALVE DURING NITROGEN
FOAM FRAC RESULTS IN A FATALITY
WHAT HAPPENED:
A fatality occurred when a service company was performing a two stage nitrogen foam frac treatment. The
rig-up required four nitrogen pumps manifolded together. In the process of beginning the second stage, a
nitrogen pump failed to maintain prime on the boost pump. While attempting to regain prime, gas from the
remaining pumps back-flowed into the nitrogen pumps storage vessel. The relief system on the vessel was
not capable of venting the volume of gas entering the vessel resulting in a catastrophic failure due to overpressurization.
WHAT CAUSED IT:
A high pressure dart style check valve in the gas discharge line was modified for other than its intended
use and did not prevent the back-flow of gas from three trucks online
The pre-operation job site pressure test procedure utilized did not ensure integrity of the dart style check
valve.
CORRECTIVE ACTIONS: To address this incident, this company instructed frac personnel on the
following:
Ensure only engineered and inspected high pressure components are utilized for pressure pumping
operations.
Ensure equipment is in proper working condition prior to dispatching to job site.
Install redundant dart style check valve in gas discharge line.
Ensure pre-job pressure test procedure verifies the integrity of check valves.
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 41
The Driller was not able to see the casing on the V-door or the elevators from the drillers console. His
vision was obstructed by four stands of 8 inch Bottom Hole Assembly (BHA) and four rows of drill pipe
which was stacked in the fingers on the drillers side derrick, because the off driller side was full of drill
pipe. The driller relied on a thumbs up signal to pick up the blocks.
It is not possible for the latch to open on the casing elevators if latched and pinned correctly. It is
possible to not fully latch the casing elevators, allowing sufficient room to insert the retainer pin behind
the latch.
There was no second person assigned to check if the casing elevators were latched and pinned
correctly.
The JSA reviewed prior to commencement of the job was a generic JSA and made no reference to the
hazard of the elevators not latching, or the requirement for a second person to check for proper
attachment.
The rig was not equipped with any form of secondary safety device i.e. stopper bar at the base of the Vdoor to prevent casing etc. from sliding down the V-door through the catwalk as it did in this case.
Drillers
Console
(Station)
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued December 2009
Safety Alert
From the International Association of Drilling Contractors
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Casing elevators changed out for a type considered to have a better latching device. Pin inserted
through not in front of the latch.
Procedures to be reviewed and amended so that:
A second person is assigned to check that the elevator is latched correctly and the pin is inserted
correctly.
Driller must have a clear view to the V-door at all times. When the pipe of bottom hole assembly is
racked in the fingers, it will prevent this. The pipe should be racked differently to allow a clear view
or laid down when this is not achievable.
A rig-specific JSA is to be developed which outlines all the potential hazards identified in the
investigation report.
A stopper device design, to be agreed by Management, which when fabricated and fitted, will prevent
pipe or casing travelling down the catwalk uncontrollably if there is a elevator failure or human error
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued December 2009
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 42
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued December 2009
Safety Alert
From the International Association of Drilling Contractors
The rig was provided with a 220 ton swivel instead of 150 ton swivel. Due to this, the bail diameter of
this swivel is bigger than the hook space could accommodate. The larger bail made it difficult to close
the hook without using force. This mismatch was not assessed by the engineering team or the rig crew.
Failure to follow Management of Change (MOC) procedures.
The air hoist was attached to a whip check that was used to close the lock of the hook latch. This
resulted in bending the locking pin, preventing the pin from fully engaging. (Deviation from standard
procedure).
The driller was not paying attention to the hook load (weight indicator), so hitting the bridge caused the
kelly to bounce.
CORRECTIVE ACTIONS: To address this incident, this company did the following:
Swivel was replaced with one that fit the hook opening. In addition the kelly was replaced.
The latch lock was repaired and the hook pin was inspected.
Rig supervisors were instructed that any change in equipment shall be accompanied with a risk
assessment in order to identify hazards and consequences. Refer to the companys. Design Control and
Development, Procedures and instructions Manual.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued December 2009
Safety Alert
From the International Association of Drilling Contractors
ALERT 08 43
No JSA was written by the shipyard or the rig crew for hot work or refueling.
No lock-out or tag-out procedure applied to the fuel service line.
No verification of shipyard fire main capacity.
There was no hot work permit approved by the OIM for the job being performed by the shipyard crew.
Welding machines were left running with the live leads in the area of the fire. The welding leads were
not properly insulated with wiring exposed and were left connected to an unattended welding machine.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued December 2009
Safety Alert
From the International Association of Drilling Contractors
Unsecured fittings on the fuel line were created by the shipyard workers.
Failure to communicate the status of the work at the end of the day. No formal handover procedure was
used. (same scenario as in Piper Alpha disaster)
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued December 2009
Safety Alert
From the International Association of Drilling Contractors
CORRECTIVE ACTIONS: To address this incident, this company did the following:
The crew involved with the task along with their supervisor is to write a JSA prior to each job.
The OIM is to ensure that all work permits are approved by prior to any work with the rig crew being
informed prior to any work on any fuel lines.
Welding machines are not to be left running while unattended and welding leads are to be in good
condition.
Work site is to be checked prior to leaving the job site to ensure housekeeping and communications of
the job status with unfinished work tagged.
When work is being done on fuel lines, the fuel pumps are to be locked and tagged out.
Company personnel are to work to improve communications between the rig personnel and shipyard
construction personnel.
As part of this effort rig management is to hold morning meetings so that both rig and shipyard personnel
know what each other will be doing.
Rig supervisors are to ensure proper controls are in use when fuel is bunkered or being transferred.
Involve RSTR to verify proper controls are in place.
Rig management is to hold fire drills even when the rig is in the shipyard.
The Corrective Actions stated in this alert are one companys attempts to address the incident,
and do not necessarily reflect the position of IADC or the IADC HSE Committee.
This material is presented for information purposes only. Managers & Supervisors should
evaluate this information to determine if it can be applied to their own situations and practices
Copyright 2005 International Association of Drilling Contractors All rights reserved.
Issued December 2009