Hid QQ Survey
Hid QQ Survey
Hid QQ Survey
HARAMAYA
NASIR SIRAJ
HARAMAYA UNIVERSIY
UNIVERSITY
TURA MASKALA
2. What is necessary?
In order to have reliable estimate of building, the following are critically necessary
complete and detailed drawings of the building are necessary with all the necessary
dimensions and descriptions include
1. Market price of construction materials at site of construction is necessary
2. Current labor cost at site of construction is necessary
3. How do we estimate?
To provide an estimate very close to an actual work, we need have to good knowledge on
blue print reading, once we understand the entire nature of the building, we can take
dimensions of items from the drawing and calculate for their quantity. The calculated amount
of work is then multiplied by the current market price of all materials and labor to complete
the work
CIVIL
HARAMAYA
UNIVERSITY
4. Works to be established
The works incorporated in all buildings are not the same. They vary depending on their type .
But most buildings have similar works, and the most widely expected are out lined below in
two categories
A. SUBSTRUCTURE
This part of building which is located below the grade beam or the ground floor level. It is
usually assumed as foundation work. Some times in small construction projects, it is
customary to classify works in phases. In a two- phase construction, the substructure is
regarded as phase one construction, and every evaluation of profits and loss is made at the
end of this phase
B. SUPER STRUCTURE
This is part of the building, which is located above the grade beam, or the ground floor level.
It is part of the building that is giving the service the building is designed for. In most
buildings the super structure starts by constructing the ground floor columns after the ground
floor slab is casted.
1cm
1cm
clearance gap
1cm
W
1cm
-fig 1.
1.2 Deep excavation: this excavation is made for foundation. It may different for the
different types of foundation, but the most popular types are:
a. Pit excavation: which is made for footings
b. Trench excavation: which is made for foundation walls
such excavation have their depth greater than their width that is why they are called deep
excavations. The method of calculation is by taking the exact geometric figure of the
foundations. No working allowance is made during estimations. The allowance which is
made at construction sites is paid for based on measured amounts.
6. Units: the unit of measurement for deep excavation is cubic meter (m3)
Illustration:
CIVIL
HARAMAYA
UNIVERSITY
1.5m
2m
2m
V= volume of pit
excavation
V= L*e*h
V=2m*2m*1.5m
V= 6m
fig 2
0.5m
4m
1m
V= volume of trench
excavation
l is the length of
foundation wall
l= 2*6m + 2*4m = 20m
V= 20m*0.5m*1m
v= 10m
0.5m
5m
0.5m
0.5m
fig. 3
1.2. Bulk excavation: this excavation is made in larger horizontal size than its vertical depth.
It is usually made for:
a. removal of poor soil from the site of replace with selected material
b. mat foundations
c. allowing hard core under ground floor slab
* units: the unit of bulk excavation is:
- square meter (m2) if the depth is less than 30m
- cubic meter (m3) if the depth is greater than 30cm
1.4 Back fill: this is soil that is filled back to an extra excavated space in the foundation.
Sometimes, when the soil at construction site is very poor, it is dangerous to fill back the
excavated soil. Therefore filling selected material is recommended. In both cases the volume
of open spaces around footings and trenches is calculated.
Units: the unit of measurement for back fill is cubic meter (m3)
HARAMAYA UNIVERSIY
Illustration:
20
20
2m
1.2m
0.3m
2m
fig. 4
1.5. Cart away: is take out the material from the construction site. Cart away is calculated by
deducting the back fill from the total volume of soil excavated.
* Unit: the unit of measurement for cart away is cubic meter (m3)
V = T.S B.F
2. Concrete work
This work incorporates all items related with concrete.
CIVIL
HARAMAYA
UNIVERSITY
V= V1+V2
V1 = 2m*2m*0.3m
= 1.2m3
V2 = 0.2m*0.2m*1.2m
= 0.05m3
V= 1.2m3 + 0.05m3
= 1.25m3
2.3. Grade beam: the grade beam is a line of reinforced concrete member constructed round
the ground floor slab of the building.
Unit: the unit of measurement for grade beam is cubic meter (m3)
HARAMAYA UNIVERSIY
CIVIL
HARAMAYA
UNIVERSITY
V= l*w*h
V= 20m*0.5m*0.95m
V= 9.5m3
3.2. Hard core: the hard core is crushed stone provided under ground floor slab to give
uniform support for the slab. It is usually constructed in 25cm thickness.
Unit: the unit of measurement for hard core is square meter (m2)
Refer back to fig.3 the area of hard core is just equal to area of ground floor slab.
A=l*w
A= 5m*4m
A= 20m2
600
30
530
fig.5
1.2. Beams
Clear distinction, during estimation, shall be made for intermediate and top tie beams.
9. Unit: the unit of measurement for beams is cubic meter (m3)
Note: great care is taken not to repeatedly calculate the volume of concrete at intersection
points of the beams.
HARAMAYA UNIVERSIY
L= 2*6m + 2*5.6m
v = l*w*h
L= 23.2m
v= 23.3m*0.3m*0.4m = 2.78m3
1.3. Slabs
Concrete slabs may be of two types as floor slab and roof slab. The volume of concrete for
slab of each floor is estimated separately. The clear length of slab in between beams is
multiplied with the clear width of the slab and its thickness.
10. Unit: the unit of measurement for slab is
- cubic meter (m3) for thickness greater than 10cm
- square meter (m2) for thickness less than 10cm
Refer back to fig.5
The rectangular surrounded by beams is the area of the slab. Lets assume a thickness of
10cm for the slab, and therefore, the volume of the concrete is v
V= l*w*h
V= 6m*5m*0.1m
= 0.3m3
10
CIVIL
HARAMAYA
g
r
r
r
g
g
UNIVERSITY
fig.6
b. Landing
The volume of concrete for the landing is calculated just like the slabs. The length of the
landing is multiplied with the width and the thickness.
Refer back to fig.6
Assume thickness of the landing is t
V= l*w*h => l*w*t
Notice: the beam supporting the landing is categorized in beams, not in the staircase.
1.5 slab
The slab is the soffit of the staircase. It is sometimes called as the waist of the staircase. It
is wisely calculated because it has inclined length. Pythagoras theorem is used to find the
actual length of the slab under the steps.
HARAMAYA UNIVERSIY
11
r
g
a
b
r
r
5r
BY pythagoras
theorem
c= a + b
r
5g
fig.7
2. Masonry work
This work incorporates all works related with construction of walls for super structure part.
There are many types of masonry works classified based on the types of masonry unit used.
Some of the most widely used are:
a. Block masonry:
Concrete blocks are used for these walls. Hollow concrete blocks (HCB) or solid
concrete blocks (SCB) are usually used in various sizes such as 40cm*20cm*20cm,
40cm*15cm*20cm, 40cm*10cm*20cm and others. In any case, concrete block
masonry is measured by square meter (m2)
b. Brick masonry:
Clay brick are used for these walls. Standard sizes of bricks, 25cm*12cm*6cm are
used in various bonds to construct boundary and partition walls. The wall may be
constructed in 12cm for stretcher bond, 25cm in Flemish or header bond and so on.
The masonry is measured by square meter (m2)
c. Stone masonry:
Stone of various patterns are used for these walls. Stone masonry is usually measured
by cubic meter (m3) unless it is used as facing work in thin layers over boundary
walls.
3. Roof work
This incorporates the upper cover of the building in any form (CIS, asbestos, tiles, concrete).
The most widely used roofing materials is the corrugated iron sheet (CIS). It is measured by
square meter (m2). Mostly CIS roofs are inclined at some slope. And hence it is necessary to
calculate the actual length of the sloped roof by using Pythagoras theorem
12
CIVIL
HARAMAYA
UNIVERSITY
500cm
1.2m
l=
60cm
5.6m
fig.8
600cm
4. Skirting
Skirting is the line of tile or timber provided at the junction point of a floor and a wall to
protect the wall from splash of water and deterioration of the paints near the floors. It is
measured by meter length by taking the internal perimeter of the building.
l= length of internal perimeter of the room
l= 2*5m+2*4m
l= 10m+8m
l= 18m
there is no skirting on the door. therefore the
width of the door should be deducted
l= 18m-0.8m
l= 17.2m
400
20
20
500
20
20
fig.9
5. Floor finish
This incorporates the finishing provided to the floors, such as terrazzo tiles, ceramic tiles,
poly vinyl chloride (PVC) tiles or rubber. The total area of the room is calculated, and the
deduction is made for partition walls. It is measured by square meter (m2)
Refer back to fig.9
A= area of floor finish
A= l*w
a= l*w
A= 5m*4m
a= 0.8m*0.2m
A= 20m2
a= 0.16m2
HARAMAYA UNIVERSIY
13
14
CIVIL
HARAMAYA
UNIVERSITY
B. standard formats
there are many standard formats in quantity surveying that are used for simple
communication among all parties involved in the construction world.
The standard formats are not the same throughout the world, but Ethiopian papers are more
or less the same. By these formats we can communicate without meeting in person.
Some of these papers are:
a.
b.
c.
d.
15
3.squaring column:
In this column, the product of the dimensions is written. The columns contains the area or
volume of an item of work.
12. Rules: the squaring column is used with the following rules.
- underline once for incomplete items, and twice for complete items.
- never overwrite numbers when mistaken. Cancel the wrong number and write
the correct number on top of the wrong one.
- addition and subtraction are possible here. Never divide or multiply any
number in the squaring column.
- dont forget to write units of items
- numbers are rounded off to the next significant digit.
4. Description column:
In this column the description of the item in the squaring column is written. Ordinally English
is used to describe the works, the amount of which is written in the squaring column.
13. Rules: The description column is used with the following rules.
all mathematical operations are allowed here
some procedures, which are very difficult to write in the remaining columns are
written here.
Some assumptions on missing dimensions are written here
Sketches (if any) are shown here
Sine, cosine, log, square root and others are worked here
Generally, the above columns are properly filled by the necessary numbers to prevent
misunderstanding among the parties using the take off sheet for works control and evaluation.
HARAMAYA UNIVERSITY CIVIL ENGINEERING DEPARTMENT
16
CIVIL
HARAMAYA
UNIVERSITY
Paper management
Usually A4 papers (210mm x 297mm) are used for takeoff sheets. A4 paper is what you are
reading now. The paper is classified in to three sections.
-
Header section
Body
Footer section
Look at the attached take off sheet. It is a complete sheet that is widely used in many
engineering offices and construction sites.
Sometimes, two take off sheet tables may be drawn on a single paper to save economy of
paper. But this is not a good practice as it results in confined arrangement of dimensions and
reading such papers is usually hectic!!
Project
: ----------------------------------------
Location : ----------------------------------------Owner
: -----------------------------------------
description
--------------------------Sign by estimator
We have put every step in detail. You will then see how the calculated quantities is written in
the standard take off sheet. Try your best to understand the following drawings of the simple
building before you going to the calculations. Or you can watch the take off sheet table along
with the drawings so that you can get the dimensions as per their appearance in the take off
sheet.
HARAMAYA UNIVERSIY
17
+460
20
+360
floor plan
500
520
540
100
20
+280
+180
80/210
+330
20
20
400
20
+0.00
+30
NGL
420
440
150
Side elevation
F1
F1
520
footing
lay out
F1
4 Pcs
150
50cm x 30cm Grade beam
0.00 NGL
-200
F1
420
F1
Drawing 1
-230
NGL
-150
5cm lean concrete
- 10cm RC slab
- 25cm Hard core
- compacted soil
The following listed works are incorporated in the construction of the building shown above.
A. Substructure
1. Earth work
1.1.Site excavation
1.2.Deep excavation
1.3.Bulk excavation
1.4.Back fill
1.5.Cart away
2. Concrete work
2.1. lean concrete
2.2. Footing
2.3. Grade beam
2.4. Ground Floor Slab
3.Stone work
3.1. foundation wall
3.2. Hard core
B. Super structure
1. Concrete work
1.1.Column
1.2.Beam
2. Masonry work
2.1.20cm HCB
2.2.15cm HCB
HARAMAYA UNIVERSITY CIVIL ENGINEERING DEPARTMENT
18
CIVIL
3.
4.
5.
6.
HARAMAYA
UNIVERSITY
Roof work
Floor finish
Skirting
Plastering
6.1.Internal plastering
6.2.External plastering
A. Substructure
1. Earth work
1.1 site excavation: the site is cleared with a minimum of 1m extra spaces around the
perimeter of the building. The building touches the ground with its footings extending
75cm off from the centers of the columns. Therefore, the total contact area of the building
and the ground is 6.70m x 5.70m. by adding the extra 1m we will have 8.70m x 7.70m.
hence the area of site excavation will be A
A=LXW
A = 8.70m x 7.70m
A = 66.99m
Plinth area
6.70
5.70
7.70
Total clearance
area
8.70
1.2. Deep excavation: there are two excavations. Pit and trench excavation
1.2.1. pit excavation:
Pit excavations are made for footings, we have four identical footings of size 1.50m x 1.50m.
Depth of excavation from NGL is 2.30m. let us say this depth includes the lean concrete
under the footing pad. The volume of pit excavation for one footing is v
V = l*w*h
V = 1.50m x 1.50m x 2.30m
V = 5.18m3
Then the total volume of pit excavation for all footings will be
V = 4 x 5.18m3
20.72m3
Note: no working space is considered during estimation. But payment is made at construction
site for the extra excavations the contractor makes.
1.2.2. Trench excavation:
Trench is excavated for foundation walls. Find the length of wall from the foundation plane.
HARAMAYA UNIVERSIY
19
50
fig.10
440
50
50
340
50
The columns are already constructed and therefore, there is no excavations on their point.
Hence the volumes of the columns should be deducted from the total volume.
1.3. Bulk excavation:
The thickness of the beam is 30cm. whereas the total thickness of the ground slab and the
hard core is 35cm. this implies that there is 5cm down bulk excavation for the hard core.
Therefore we estimate this excavation by using the area of the hard core.
Since the depth of the excavation is less than 30cm, we measure by its area (m2).
A= l*w
A= 4.40*3.40
A= 14.96m2
1.4. Back fill:
There is back fill around column footing. The volume of soil, which is required to fill the
void, is equal to the volume of void around the footing.
Refer to drawing 1
20
CIVIL
HARAMAYA
65
20
65
65
20
65
UNIVERSITY
To find the volume of the soil to be disposed of the site, deduct the back fill from the total
volume of excavated. This is true only when the soil excavated is not expansive soil.
We have soils from site excavations, deep excavation and bulk excavation. All these should
changes ti volume by multiplying by their respective thickness.
C.A = T.S- B.F
= (S.E + D.E +B.E)-B.F
= ((66.99m2 *0.25m) +(20.72m3 + 17.6m3)+(14.96m2 *0.5m)) -17.68m3
= 33.5m3 is the total volume of the soil to be disposed off the construction site.
2. Stone work
2.1 Foundation wall: the stone for the foundation wall is measured by its volume.The
volume is then calculated by the product of the length, the width and the height. From
the given drawing the depth of the foundation wall is 50cm, and its depth is 145cm
after deducting 5cm for the lean concrete. The length of the foundation is already
calculated in the trench excavation. It is 16.7m. this length is calculated including the
four columns that have already been put in place. Lts use it and finally we will
deduct the columns.
V= l*w*h
V= 17.6m*0.50m*1.45m
V= 12.76m2
V is total volume of the columns to be deducted from the volume of the stone.
V= 4(0.20m*0.20m*1.45m)
V= 0.23m3
The actual volume of the stone in the foundation wall will be 12.76m3 0.23m3 = 12.53m3
HARAMAYA UNIVERSIY
21
3. Concrete work
3.1.Lean concrete: we have lean concrete in two places. It is found under the
Footing pad, and under the foundation wall. In both places it is measured by its area. The area
of the lean concrete is made just equal to the area of the element above it.
14. Under footing: there are four footing equal in size with the size of footings.
Therefore the area of lean concrete is A
A= l*w
A= 4(1.50m*1.50m)
A= 9.00m2
15. Under foundation wall: the length of the foundation wall is calculated as17.60m
including the columns. Lets use this length and we will deduct the columns.
A= l*w
A= 17.60m*0.50m
A= 8.80m2
The area of the columns should be deducted a= 4(0.20m*0.20m) = 0.16m2
Therefore, the area of lean concrete under the foundation wall is 8.80m2 0.16m2 = 8.64m2
The total area of the lean concrete then will be A
A= 9.00m2 + 8.64m2
A = 17.64m2
3.2.Footing: we have four footings of the same size. The footing is the
summation of the footing pad and the footing column. The footing column
is the column that is constructed from the footing pad to the grade beam.
a. Footing pad: volume of the concrete for footing pad is V
V= 4(1.50m*1.50m*0.25m) 5cm is deducted for lean concrete
V = 2.25m3
b. Footing column: volume of concrete for the footing of column is v
V= 4(0.20m*0.20m*2.00m)
V= 0.32m3
HARAMAYA UNIVERSITY CIVIL ENGINEERING DEPARTMENT
22
CIVIL
HARAMAYA
UNIVERSITY
The total volume of concrete for the footing will be 2.25m3 + 0.32m3 = 2.57m3
3.3.Grade beam: grade beam is measured by the volume. The length of the
Grade beam is equal to the length of the foundation wall without any deduction. Because, the
grade beam runs on the top of the columns, and therefore, the full length is taken.
V= l*w*h
V= 17.60m*0.50m*0.30m
V= 2.64m3
3.4.Ground floor slab: ground floor slab is measured by the volume. Because
its thickness is 10cm. the size of the slab is just equal to the size of hard
core.
Refer back to fig.10
The volume of the concrete the slab is v
V= l*w*h
V= 4.40m*3.40m*0.10m
V= 1.50m3
B. superstructure
1. Concrete work
1.1. Columns: there are four columns of identical size. There volume will be v
V= l*w*h
V= 0.20m*0.20m*3.00m
V= 0.12m3
Total volume of the column will be v= 0.12m3*4 = 0.48m3
1.2. Beams: the length of the tie beam is calculated from the floor plan of the building.
L= 2*5.40m + 2*4.00m = 18.80m
The volume of concrete for tie beam is,
V= l*w*h
= 18.80m*0.20m*0.30m
HARAMAYA UNIVERSIY
23
80
take 25cm
space from the
side walls
20
525
440
525
24
CIVIL
HARAMAYA
UNIVERSITY
80
600
4. Floor finish
floor finish is measured by area of the room. A= 4.00m*5.00m = 20.00m2 and the area of the
floor finish under the door is A= 0.80m*0.20m = 0.16m2. therefore the total area of the floor
finish will be A= 20.00m2 + 0.16m2 = 20.16m2
5. Ceiling
The area of the ceiling is similar with the area of floor finish except that under the door.
Therefore the area of the ceiling will be A= 4.00m*5.00m = 20.00m2
6. Skirting
The length of the skirting is equal to the internal perimeter of the room except the door
2/4.00m+2/5.00m = 8.00m+10.00m = 18.00m is internal perimeter of the room.
L= 18.00m- 0.80m = 17.20m is the total length of the skirting.
7. Plastering
we have internal and external plastering
HARAMAYA UNIVERSIY
25
Total area of plastering for the tie beam and the grade beam will be A.
A= 39.20m * 0.30m = 11.76m2
8. Rendering
As assumed before, the external walls, except the beam and the column, are all rendered.
Rendering is measured by area (m2). The height of the front, rare and side walls is the same
below the tie beam, i.e. 3m. therefore, lets first find the length of the walls.
L= 2/5.00m + 2/4.00m = 18.00m
Area of rendering under tie beam is A
A= l*w
A= 18.00m*3.00m
HARAMAYA UNIVERSITY CIVIL ENGINEERING DEPARTMENT
26
CIVIL
HARAMAYA
UNIVERSITY
A= 54.00m2
Area of rendering for the parapet is : Rare parapet = 4.40m*1.00m = 4.40m2
Side parapet = 2(1/2(0.20m+ 1.00m) 5.40m)
= 6.48m2
The total area of rendering for parapet is 10.88m2
Therefore, the total area of rendering for the walls will be 54.00 m2 + 10.88 m2 = 64.88 m2.
Now look at the following take off sheet. It shows how the above estimated quantities are
written in the take off sheet. Read carefully, and try to miss nothing!!
Project
: construction of a residence
Location
: CMC, Ambo
Owner
description
A. SUBSTRUCTURE
1. Earth work
1.1.Site excavation
8.70m
7.70m
1.50m
1.50m
2.30m
20.70m
17.60m
0.50m
1.50m
0.20m
0.20m
1.50m
0.24m3 Ddt. Ditto. For columns
HARAMAYA UNIVERSIY
27
1.50m
1.50m
2.00m
4/
18.00m3
0.20m
0.20m
2.00m
4/
0.32m3
Total volume of net soil to be back filled
17.68m3
around the footing pads.
description
1.5 cart away
C.A = T.S B.F
C.A = (S.E+ D.E + B.E) B.F
C.A = (66.99m2*0.25m + 20.70m3
+12.96m3 + 14.96m2* 0.05m)- 17.68m3
C.A = 33.48m3
17.60m
0.50m
1.45m
12.76m3
4/
0.20m
0.20m
1.45m
4.40m
3.40m
14.96m2
4/
2. stone work
2.1.foundation wall
l= length of foundation wall
l= 17.60m(see trench excavation)
volume of foundation wall including
columns
1.50m
1.50m
9.00m2
28
CIVIL
HARAMAYA
UNIVERSITY
3.1.2. under foundation wall
17.60m
0.50m
0.20m
0.20m
4/
3.2.
2.25m3
4/
0.20m
0.20m
2.00m
2
3
17.60m
0.50m
0.30m
4.40m
3.40m
0.10m
footing
Note: Ddt. Means deduct. That is to mean you have to subtract the said amount.
Ditto. Means from the above or just like the above
Ddt.Ditto. means subtract the said amount from the one stated above
HARAMAYA UNIVERSIY
29
2
4/
3
0.20m
0.20m
3.00m
0.48m3
18.80m
0.20m
0.30m
18.00m
3.00m
Description
A. SUPER STRUCTURE
1. Concrete work
1.1. Column
Total volume of concrete for the columns
1.2.Tie beams
L=length of tie beam
L=2/5.40m + 2/4.00m
L= 10.80m+8.00m
L= 18.80m
0.80m
2.10m
1.68m2 Ddt. Ditto. For door
1.00m
1.00m
1.00m2 Ditto but for the window
51.32m2 Total area of 20cm HCB
30
CIVIL
HARAMAYA
UNIVERSITY
Rare wall
100
20
4.40m
1.00m
440
525
2/ /
5.25m
0.80m
8.40m2 Ditto. But for the triangular
17.00m2 Total area of 15cm HCB for parapet wall
3. Roof work
l
0.8m
6.00m
l is actua length of the roof
l = 6m + 0.8m
l = 6.05m
6.05m
4.00m
0.80m
0.20m
2
0.16m
20.16m2
5.00m
4.00m
20.00m
6. Skirting
L= length of skirting
L= 2/5.00m + 2/4.00m = 18.00m
18.00m
HARAMAYA UNIVERSIY
31
0.80m
2.10m
1.68m2
1.00m
1.00m
1.00m2
51.32m2
1.60m
3.06m
4.80m2
19.60m
0.3m
5.88m2
19.60m
0.30m
7.2.External plastering
a. Columns
L= 8/0.20m = 1.60m
Area of plastering to columns
b. Grade beam
L= length of grade beam
L= 2/5.40m + 2/4.4m = 19.60m
Area of plastering to grade beams
c. Tie beam
L= length of Tie beam
L= 19.60m
Ditto but Tie beams
Total area of external plastering
5.88m2
16.56m2
1
18.00m
3.00m
54.00m2
Description
8. Rendering
8.1.Below tie beam
L= length of the wall to be rendered
L=2/4.00m + 2/5.00m= 18.00m
Area of external wall
0.80m
2.10m
1.68m2 Ddt. Ditto. For the door
1.00m
1.00m
4.40m
1.00m
2/ /
5/
5.40m
0.80m
4.32m2 Ditto. But for the side parapet (triangular part)
5.40m
0.20m
2.16m2 Ditto. But for the rectangular part
62.20m2 Total area of rendering for external walls
9. Gutter
HARAMAYA UNIVERSITY CIVIL ENGINEERING DEPARTMENT
32
CIVIL
HARAMAYA
UNIVERSITY
HARAMAYA UNIVERSIY
33
Description
A. Substructure
1. Earth work
1.1 site excavation
x
A=12bh
= 12(x)(4.40m)
4.40m
30
3.40m
x= tan 30 x 4.40m
= 2.55m
4.40m 30
2.55m
12/ /
A= 12bh
= 0.5(2.55m*4.40m)
we have 12 triangles
of this size
4.40m
2.55m
4.40m
67.32m2
A=12bh
= 12(x)(4.40m)
4.40m
30
3.40m
x= tan 30 x 4.40m
= 2.55m
4.40m 30
12/ /
2.55m
21.96m
0.50m
0.90m
A= 12bh
= 0.5(2.55m*4.40m)
we have 12 triangles
of this size
4.40m
3
9.88m
1.68m
2.90m
0.05m
2.9m
30
x= 0.58*2.90m
= 1.68m
---------------------------Sign by contractor
----------------------------------sign by supervisor
34
CIVIL
HARAMAYA
21.96m
0.50m
UNIVERSITY
Description
4.4. cart away
C.A. = T.S. B.F
S.E = 67.32m2 * 0.25m
= 16.83m3
T.S = S.E + D.E
= 16.83m3 + 9.88m3
= 26.71m3
C.A = 26.71m3 1.46m3
= 25.25m3
21.96m
0.30m
0.20m
12/ /
12/ /
3m 30
1.74m
3.00m
0.10m
x=3*tan30
=0.58*3
= 1.74m
HARAMAYA UNIVERSIY
35
3
21.96m
0.30m
2.80m
18.45m3
Description
B. superstructure
1. stone work
l= 21.96m (see trench excavation)
volume of wall including door
1.20m
0.30m
2.10m
0.76m3 Ddt. Ditto. For door
2/
1.00m
0.30m
1.00m
21.96m
0.30m
0.20m
pitch = 1.2cm
c
r
30
33
tan30= 0.58
12/ /
2.37m
4.08m
r= 3.90m
58.02m2
3m
12/ / 1.74m
3.00m
31.32m2
1.20m
0.30m
12/ /
a= 0.58*c
a= 0.58*4.08m
a= 2.37m
30
=0.58*3
= 1.74m
1.74m
3.00m
31.32m
36
CIVIL
HARAMAYA
12/ /
UNIVERSITY
20.88m
3.00m
62.64m2
Description
6.plastering
6.1. internal plastering
L= internal perimeter of the wall
L= 12*1.74m= 20.88m
Internal wall area
1.20m
2.10m
2.52m2 Ddt. Ditto for door
1.00m
1.00m
22.92m
3.00m
2/
1.00m
1.00m
HARAMAYA UNIVERSIY
37
150 W2
150
Dinning Room
150 W2
2520
175
Toilet
D2
scale 1:50
38
D1
Kitchen
305
660
2085 40
D6
15
40
55
175
55
20
60
3030110
D5
120 120
300
320
340
20
221
3 3 9 ,4 8
20
Living Room
W4
300
320
340
660
30
3 03 0
20
15
20
33 86 66
346
798
20
432
34 91 22
HARAMAYA
3
20
15
15
495
w1
15
90
D2
45
175
D1
90
bath room
184,84
70
392
D2
D1
90
63,83
115
300
bed room 1
w3
110
15
190,07
305
3030
216
150 320
300
w2
UNIVERSITY
412
D1
660
B
bed room 2
320
150
w
2
25
20
366
scale 1:50
247
221
120
20
130
CIVIL
90
201
99
20cm HCB
Rendered wall
120
90
10cm HCB
rendered wall
25
210
Rendered wall
210
scale 1:50
25
90
FRONT ELEVATION
120
Front Elevation
25
80
20cm HCB
Rendered wall
Rendered wall
120
210
300
120
Rendered wall
25
90
100
120
90
10cm HCB
rendered wall
scale 1:50
25
REAR ELEVATION
Rear Elevation
HARAMAYA UNIVERSIY
39
25
200
300
10
NGL
10
Footing 1 (9 pcs)
90
30
300
25
25
20
200
20
40
CIVIL
HARAMAYA
UNIVERSITY
Description
A. Substructure
1. Earth work
1.1. Site excavation
8.40m
plinth area
9.78m
11.78m
10.40m
11.78m
10.40m
9/
2.00m
2.00m
1.85m
50
301
798
39.24m
0.50m
0.95m
50
l= length of trench
l= 3/7.98m + 6/2.55m
l= 39.24m
347
50
50
255
50
255
50
0.20m
0.20m
0.95m
3.01m
2.55m
0.10m
3.47m
2.55m
0.10m
1.77m3 Ditto but in bay C and D
3.31m3 Total volume of both excavation under hard core
HARAMAYA UNIVERSIY
41
Description
1.5. Back fill
2.00m
2.00m
1.50m
35
9/
150
20
20
200
200
0.20m
0.20m
1.50m
0.54m3 Ddt. Ditto for column
53.46m3 Total volume of back fill around footing column
1.6. Cart away
C.A = T.S B.F
T.S = S.E + D.E + T.E+ B.E
= (122.51m2 x 0.25m) 66.60m3 + 18.30m3 3.31m3
= 115.53m3
C.A = 155.53m3 53.46m3
= 65.38m3
9/
2.00m
2.00m
39.24m
0.50m
9/
0.20m
0.20m
9/
0.20m
0.20m
1.50m
9/
2.00m
2.00m
0.30m
39.24m
0.50m
0.25m
42
CIVIL
HARAMAYA
UNIVERSITY
2
2/
Description
2.4. Ground floor slab
See fig. 1
3.01m
2.55m
0.10m
3.47m
2.55m
0.10m
1.77m3 Ditto but in bay C and D
3.31m3 Total volume of concrete for slab
39.24m
0.50m
0.90m
17.66m3
9/
3. STONE WORK
3.1. Foundation wall
L= 39.24m (see trench)
Volume of stone including columns
0.20m
0.20m
0.90m
2/
3.01m
2.55m
2/
3.47m
2.55m
HARAMAYA UNIVERSIY
43
2
9/
3
0.20m
0.20m
3.00m
1.08m3
1.08m3
Description
B. SUPER STRUCTURE
1. Concrete work
1.1. Columns
Volume of concrete for ground floor columns
Ditto but for 1st floor columns
1.2. beams
20
346
fig.2
20
l= 3/7.98m + 6/3.00m
= 23.94m + 18.00m
= 41.94m
392
41.94m
0.20m
0.25m
20
20
300
20
300
20
2/
3.46m
3.00m
0.10m
2/
18/ /
3.92m
3.00m
0.10m
0.30m
0.18m
0.10m
1.10m
1.10m
0.15m
44
CIVIL
HARAMAYA
1.04m3
1.76m3
18 x 18
18 x 30
53.52m
3.00m
160.56m2
3.00m
3.00m
2/
4/
0.60m
2.10m
1.50m
1.20m
1.20m
2.10m
0.85m
2.10m
31.32m
3.15m
4/
2/
UNIVERSITY
18 x 18 = 324
18 x 30 = 540
c = a + b
= 324 + 540
= 629.72
= 630
0.90m
2.10m
7.56m2
2.94m2
0.70m
2.10m
88.16m2
HARAMAYA UNIVERSIY
45
3.30m
1.20m
4/ /
1
330
330
798
120
330
60
2/
3.51m
7.98m
330
330
798
60
45.87m
3.15m
46
CIVIL
HARAMAYA
2/
1.50m
1.20m
0.85m
2.10m
1.79m2
0.60m
2.01m
1.21m2
1
2
2/
3
0.90m
2.10m
59.00m
3.25m
2/
6/
4/
UNIVERSITY
1.50m
1.20m
0.90m
2.10m
0.70m
2.10m
3.00m
1.20m
87.48m
0.25m
Description
3.78m2 Ditto but for D1
134.11m2 Total area of internal wall plastering and painting to
ground floor.
b. Upper floor
L= 59m (see skirting)
2 Total area of internal wall in upper floor.
191.75m
3.60m2 Ddt. Ditto for W2
11.34m2 Ditto but for D1
5.88m2 Ditto but for D2
3.60m2 Ditto but for W4
167.33m2 Total area of internal plastering and painting to upper
floor.
5.2. External plastering
a. Beams
L= (2/660+2/790)x3
= 87.48m
21.87m2
4.80m
6.00m
28.80m2
50.67m2
53.52m
HARAMAYA UNIVERSIY
47
= 53.52m
160.50m
2/
2.41m2
Ditto but for W3
1
Description
3.10m
1.20m
3.60m2 Ditto but for W1
4/
1.50m
1.20m
7.20m2 Ditto but for W2
1.20m
2.10m
2.52m2 Ditto but for D5
135.77m2 Total area of rendering for wall below the beam
6.2. Above Tie beam
4/ /
3.30m
1.20m
7.58m
3.00m
330
3.92m
1.40m
5.49m2 Ditto but in living room
0.90m
2.67m
2.40m2 Ditto but in living room
1.10m
1.60m
1.76m2 Ditto but in stair case
2.82m
1.10m
3.10m2 Ditto but in stair case
1.10m
HARAMAYA UNIVERSITY CIVIL ENGINEERING DEPARTMENT
48
CIVIL
HARAMAYA
UNIVERSITY
1.75m
1.93m2 Ditto but in corridor
1.10m
1.10m
1.21m2 Ditto in Toilet
3.05m
2.21m
6.74m2 Ditto but in kitchen
0.85m
0.20m
0.17m2 Ditto but in D6
0.90m
0.15m
1
0.70m
0.15m
3.00m
2.21m
3.05m
2.21m
6.74m2 Ditto but in bed room 2
1.15m
1.71m
1.97m2 Ditto but in Bath room 1
1.30m
1.71m
2.23m2 Ditto but in bath room 2
4.54m
1.15m
5.22m2 Ditto but in corridor
2.47m
4.95m
3.09m
1.45m
4.48m2
3/
2/
0.90m
0.15m
0.70m
0.15m
HARAMAYA UNIVERSIY
49
FORM WORK
Form work is a temporary supporting structure for concrete and other works. The estimation
of form work is conducted by taking the area of the member covered by the form work. After
the area of the form work is calculated it is changed to volume by multiplying with the
thickness of the board for purchasing purposes. The normal take off sheet paper can be used
for estimation of form work. The dimensions will be written in the dimension column, and
proper description shall be given in the description column.
For instance, look at the following method of writing in the take off sheet.
Lets say we have eight columns of size 30cm by 30cm and the height for all columns is
300cm.
Timesing Dimension Squaring
8/
1.30m
3.00m
Description
A. Super structure
1. Form work
1.1. Column
L= the developed length of the side of the column
L= 4/32.5cm=> 2.5cm is given for the thickness of
the board.
L= 130cm
The same way the area of form work for all concrete members of the building is calculated.
The thickness of the form work board is added to one side of the concrete member.
50
CIVIL
HARAMAYA
UNIVERSITY
Experienced site carpenters can estimate the quantity of other struts. Braces and ties
roughly. There is no hard and fast rule for the estimation of such members as there number
cannot be clearly stated.
BAR SCHEDULE
The take off sheet has no room for estimation of reinforcement bars. Therefore, an other
separate sheet of paper is necessary.
Bar schedule is a tabular format that is specially used for estimating the quantity of
reinforcement bars required for a given project. A complete set of structural drawings is
necessary to take sizes and shapes of bars of different members of RC structures.
The bar schedule consists of around 8 column and sometimes the columns may even be
more. In many construction sites and engineering offices the following table is used.
Bar
Dia.
mark (mm)
Shape of
bending
Length
(m)
No
Total
length
Unit
weight
Total
weight
Location remark
1.Bar mark: in this column the mark of the bar is written. It is customary to mark bars or
Structural drawings for identification purposes.The marks may be given by English
Alphabets, numbers or symbols in circles.
Eg.
2. Diameter: in this column the diameter of the bar is written in mm eg. 12mm
3. Shape of bending: in this column the shape of the bar with its bending dimensions
Sketched. this will help the bar bender to prepare the bars according to the
specifications.
Eg.
20
470
20
HARAMAYA UNIVERSIY
51
52
CIVIL
HARAMAYA
UNIVERSITY
F1
C1
F1
C1
20
120
20
115
120
NGL
600
25
120
F1
600
F1
C1
25
-20-
+ 325
A
412mm L = 342
-322-
F1 (4 Pcs)
A
C
412
D 8mm c/c 200mm
- 145
210mm
20
20
210mm
210mm
312mm A
F
G
20
20
210mm
25
200
210mm L= 220
5
5
-575-
20
20
-30-
210mm A F 210mm
I
25
- 120
-217412mm
L = 247
0.00
25
50
+25
25
200
20
210mm L= 220
310mm L= 620
-620Beam on Axis 1,2,A,B at level 0.00 (GB) and +3.25 (TB)
H
HARAMAYA UNIVERSIY
20
20
20
312mm
Sec. B-B
Sec. A-A
210mm L= 660
-620-
312mm
5
5
20
20
53
54
CIVIL
HARAMAYA
Bar
Dia.
mark (mm)
A
12
Shape of
bending
20
20
Length
(m)
1.55
No
UNIVERSITY
Weight
(kg/m)
0.888
Total
weight
77.08
location
56
Total
length
86.8
remark
F1
Mesh
2.47
16
39.52
0.888
35.09
C1
Main
3.42
16
54.72
0.888
48.59
C1
Main
0.9
92
82.8
0.395
32.71
C1
Stirrup
5.7
60
342
0.395
135.09
Slab
Mesh
2.2
32
70.4
0.617
43.44
Beam
Negative
6.6
16
105.6
0.617
65.16
Beam
Top
6.2
24
148.8
0.888
132.23
Beam
Bottom
0.9
240 216
0.395
85.32
Beam
stirrup
115
12
12
247
322
5
5
8
20
10
20
20
10
620
20
12
620
5
5
20
20
20
HARAMAYA UNIVERSIY
55
56
CIVIL
HARAMAYA
UNIVERSITY
Clear the site to an average b/n depth of 25cm from NGL with all trees, bushes and
dirt collections and other organic materials completely removed from the
constructions site.
.2 trench excavations
Details shall be given on the following conditions
eg. Use one of the following words to specify the depth of the trench
-
n/e 1cm
n/e 1.5cm
n/e 2cm
Sample specification
Trench excavation for 50cm thick foundation wall on ordinary soil to a depth
n/e 1.5cm from NGL
1.3. Pit excavation
Details shall be given on the following words to specify the depth of the pit
- n/e 1.5cm
- n/e 2.5cm
- n/e 3.5cm
Nature of the soil or the ground
Possible presence of timbering
Sample specifications
Pit excavation for isolated footing on soft soil to a depth n/e 2.5cm from NGL. Timbering
may be necessary to prevent collapse of pit.
1.4. Bulk excavation
Details shall be given on the following conditions.
HARAMAYA UNIVERSIY
57
Depth of excavation
Eg . 40cm
Purpose of excavation
Eg. To remove black cotton soil out from the foundation
Sample specification
Bulk excavation under hard core to remove black cotton soil to an average depth of 40cm
from NGL.
1.5. Back filling
Details shall be given on the following conditions
-
Sample specification
Backfill around footing pad and foundation wall by using selected material of trusted quality
compacted in 2.5cm layer.
1.6
Cart Away
Sample specification
Dispose off surplus excavated material 2km away from the construction site. Any social or
Environmental complaints are borne by the contractor.
2. Concrete work
58
CIVIL
HARAMAYA
UNIVERSITY
Grade of concrete
E.g. C-5
Mix ratio of concrete
E.g. 1:4:8
Thickness of lean concrete
Eg.5cm
Location of lean concrete
E.g. Under footing pad
Sample specification
Discharge 5cm thick lean concrete in C-5 grade or 1:4:8 ratio under footing pad.
2.2 . Footing
2.3. Grade bean
2.4.Ground floor slab
For all the above concrete members of building the same class concrete can be used , and
Details shall be given on the following conditions.
-
Grade of concrete
Eg. C-25
Mix ratio
Eg. 1:2:3
Thickness of concrete members
Eg .10cm thick concrete slab
Minimum cement content
Eg. 300kg/
Maximum size of course aggregate
Eg. 20mm
Sample specifications
Provide C -25 concrete in 1:2:3 ratio with minimum cement content of 300kg/
. The
maximum size of coarse aggregate shall be 20mm , and the concrete shall be thoroughly
compacted around reinforcing bars.
3 .stone work
3.1 .Foundation wall
HARAMAYA UNIVERSIY
59
Sample specification
Supply and construct 50cm thick foundation wall with dressed basaltic or equivalent stone
bedded in cement mortar of 1:4 mix ratio.
3.2 Hard core
Details shall be given on the following conditions.
-
Sample specifications
supply and construct 25cm thick basaltic or equivalent stone hard core blinded with red ash
and scoria.
1. Concrete work
1.1. Columns
1.2 . Floor Beams
1.3. Tie beams
1.4. Floor Slabs
1.5. Roof slabs
HARAMAYA UNIVERSITY CIVIL ENGINEERING DEPARTMENT
60
CIVIL
HARAMAYA
UNIVERSITY
Grade of concrete
Minimum cement content of concrete
Maximum size of coarse aggregate
Size of member
Sample specifications
Refer back to substructure
2. Masonry Work
2.1. Brick masonry
Details shall be given on the following conditions.
Type of bond
Eg. English or Flemish Bond
Thickness of wall
Eg.25cm
Mortar mix ratio
Eg. 1:4
Sample specifications
Supply and construct 25cm thick well burnt sound brick wall in header bond
bedded in cement mortar of 1:4 mix ratio both sides left for plastering.
2.2.
Sample specification
HARAMAYA UNIVERSIY
61
Stone masonry
Sample specification
Supply and construct 30cm thick fully dressed Ashlar masonry super structure wall
bedded in cement mortar of 1:4 mix ratio.
3. Roof work
Details shall be given on the following conditions.
Sample specifications
Supply and construct G-28 well galvanized corrugated sheet of iron of Akaki brand: price
includes all accessories.
4. Floor finish
Details shall be given on the following conditions
62
CIVIL
HARAMAYA
UNIVERSITY
Sample specifications
Construct 20vm x20cmx 2cm terrazzo tile finishing bedded in cement mortar of 1:3 mix
ratio.
5. Plastering
Details shall be given on the following conditions.
Thickness of plaster
Eg. 25cm
Number of coats
Eg. 3
Grade of mortar
Eg . 1:3
Location of plaster
Eg. Internal wall
Type of mortar
Eg . Line mortar
Sample specification
Apply three coats of cement mortar plastering in 1:3 ratio to internal walls and ceiling
6. Ceiling
Details shall be given on the following conditions.
Sample specifications
Supply and fix 60cm x60cm x 8mm chip wood ceiling on 7cm x 5cm zigba ceiling batten
spaced 60cm on centers. Price includes ceiling battens.
7. Skirting
Details shall be given on the following conditions.
Type of materials for skirting
Eg. Terrazzo tile skirting
HARAMAYA UNIVERSIY
63
Sample specifications
Supply and construct 10cm high terrazzo tile skirting with 2cm thick tiles bedded in cement
mortar of 1:3 ratio
8. Rendering
Details shall be given on the following conditions.
Sample specifications
Apply 25mm thick 1:2:9 compo mortar rendering to external wall of main building
9. Glazing
Details shall be given on the following conditions.
Type of glass
Eg. Clear glass
Thickness of glass
Eg.3mm
Brand( if necessary)
Sample specifications
Supply and fix 3mm thick clear glass to all opening.
10. Metal work
Details shall be given on the following conditions
Type of metal
Eg.LTZor RHS
Thickness of metals
Eg. 4mm
HARAMAYA UNIVERSITY CIVIL ENGINEERING DEPARTMENT
64
CIVIL
HARAMAYA
UNIVERSITY
Sample specifications
Supply and fix AKaki made LTZ steel door and window frames coated with antirust
paints.
Bill of quantity
Bill of quantities is a table with 5 columns that specially contains the specifications of all
works in a project along with their amount. It is sold to contractors for non-refundable
money. The contractors read the specifications of the work in the bill of quantities and give
their own cost. The execution of each work in the bill of quantities . It is sometimes called
Abstract Form
The following table shows a typical abstract form.
Item
Description of work(2)
No.(1)
Unit(3) Quantity(4)
Rate(5)
Amount(6)
1. Item No. In this column, the item number of the work is written, and this number may
be obtained from the take-off sheet.
2. Description: In this column, the description of the work is written as per their
specification.
HARAMAYA UNIVERSIY
65
1.2
Description of work
A. SUBSTRUCTURE
1. Earth work
Clear the to an average depth of 25cm
from NGL
Pit excavation for footing to a depth n/e
2.00 on ordinary soil.
1.3
1.4
1.5
Unit
Quantity
Rate
Amo
unt
122.51
66.60
18.30
3.31
1.6
53.46
2.1
2.2.
55.26
11.34
66
CIVIL
HARAMAYA
2.3.
2.4.
3.1
3.2
1.1
UNIVERSITY
4.9
3.31
17.34
33.05
1.08
1.08
1.2
2.1
2.1
1.3
4.43
1.4
137.53
2.1
2.2
2.3
88.16
7.92
67
4.1
5.1
5.2
56.02
m
m
43.22
50.80
134.11
167.33
50.67
Bid document
Bid document is a package containing the bill of quantities of a building project along with
the necessary architectural, structural, sanitary, and electrical drawings. The main objective
of bid document is:
-
68
CIVIL
HARAMAYA
UNIVERSITY
2. Conditions of contract
This is the governing part of the document that mainly states how the whole contractual
agreement is enforced, workers are administered, payment is made, disputed are settled,
failures are treated and so on. Almost all conditions of contract are more or less the same in
interpreting Ethiopian Building and Civil Codes. Important changes may arise on facts of:
b) Payment system
-payment is usually made every month based on measured amount of work. But
sometimes it is possible to settle payment at the end of some phase of construction.
d) Penalties
-For late submission of work behind schedule, the contractor may be penalized
depending on the agreement.
These and other agreements may be made between the contractors and client. The
agreement should be written in the condition of contract.
3. Past performance
In the bid document sold to prospective bidders, a table requesting information on the
past performance of bidders can be included to allow the contractors to specify some
project they were recently engaged in, and how they dealt with. This will help to
differentiate among competent bidders based on the performance the showed on the
projects of similar magnitude to ours. The performance is measured by the completion
time and the project cost (variation)
69
6. Drawings:
Drawings are key instrument to understand the scope of the project, and the
construction method. Contractors badly need them, to estimate actual quantities for
themselves. Therefore, floor plan, site plans, foundation plans, roof plans, elevations,
sections, details, structural drawings sanitary drawings, and electrical drawings are
enclosed.
7. Bill of quantities
The specifications of all the works in the project are written in the abstract form. The
contractors will fill in unit prices against each item of work in the bill of quantities.
The total construction cost is calculated by summing up the prices in the total price
column.
70
CIVIL
HARAMAYA
Water=12
110 kg/
UNIVERSITY
=1320kg
Example:
Calculate the amount of material for 50cm undressed foundation wall bedded in cement
mortar of 1:2 ratios, if the volume of the foundation is 4 .
From the attached table you can see that for the foundation wall the following materials are
required.
Stone=1
Cement=150kg
Sand=0.42
Stone=4
Cement=4
Sand=4
150
0.42
=4
=60kg
=1.68
Example: calculate the amount of materials required for 25mm thick cement mortar
plastering in 1:3 mix ratios in three coats, if the area of plastering is 100 .
From table, the amount of materials required 10 area of wall plastering is:
Cement=114.84kg
Sand=0.25
plastering will be
Bidding
Bidders are invited to offer their price for all works in the bill of quantities, and compactions
are made among them based on their offer. It is not only the price but their past performance
equipment, professional person. But price plays the greatest role in selecting the winner.
According to the new rule, for governmental projects, contractors eligible party in the process
of bidding are those who are registered by the revenue office regarding live.
A contractor is supposed to submit his offer in two copies, one originals and one copies
before the expiry of the submission date.
HARAMAYA UNIVERSIY
71
72
CIVIL
HARAMAYA
UNIVERSITY
Materials List
Break Down
Prepared by: Nasir
Siraj &
Tura Maskala
Haramaya University
Civil Engineering
5th year
HARAMAYA UNIVERSIY
73
concrete
Class one concreteC-20 and above
Class two concrete.C-15 and below
Never include lean concrete in any one of above classes as it is
assumed to take no load at all
The following table for breakdown of concrete is given on the following
assumptions.
Assuming 30% shrinkage and 5% wastage
For mechanical mix..w/c=0.4-0.5
For hand mix w/c=0.4-0.65
HARAMAYA UNIVERSITY CIVIL ENGINEERING DEPARTMENT
74
CIVIL
no
1.
HARAMAYA
UNIVERSITY
Note :- hand mix shall only be allowed for class concrete and shall not
be allowed for concrete of class C-20 and above.
Type of work
Materials required to procedure 1 of concrete
Concrete grade C -7
Mixing method mechanical
Mix ratio 1:4:8
Specified use beam conc.
Concrete grade C-15
Mixing mechanical
Mix ratio 1:2:4
Specific use stru. Conc.
Concrete grade C-20
Mixing method mechanical
Mix ratio 1:2:3
Specific use struc.conc.
Cement=150 kgs
Sand=773 kgs
Gravel=1890kgs
Water=60 litter
Cement=200 kgs
Sand=754 kgs
Gravel=1843 kgs
Water=80 litters
Cement=275kgs
Sand=754 kgs
Gravel =843 kgs
Water=10 litter
Cement=300 kgs
Sand=777.5 kgs
Gravel=1645.5 kgs
Water=120litter
75
Materials required
1. 10cm-12cm upper and lower eucalyptus wood truss member with
50% wastage =1.5ml/ml
2. Halls = 0.04kgs/ml
3. Band iron=0.12kgs/ml
4. 8cm -10 cm vertical and diagonal truss member with 60%
wastage=1.6ml/ml
5. Halls =0.06kgs/ml
6. Band iron =0.17kgs/ml
76
CIVIL
HARAMAYA
UNIVERSITY
Materials required
1. 5 x10 cm zigba wood upper member in the truss with
15%wastage=1.15kgs/ml
2. Halls =0.03kgs/ml
3. Brand iron=0.12kgs/ml
4. 5 x10 cm zigba wood lower member with 15% wastage=1.2kgs/ml
5. 2(2.5 x 15 cm) zigba wood lower member with 15% wastage=2.30
mts/ml
6. Noll=0.04kgs/ml
7. Band iron=0.20kgs/m
c. Truss out of 2.5x15cm zigba wood
Material required
1. 2(2.5 x15cm) zigba wood upper and lower materials with 15%
wastage =2.30mts/ml
2. Nails=0.03kgs/ml
3. Band iron=0.10kgs/ml
4. 2(2.5 x15cm) diagonal and vertical member with 29%
wastage=2.4mts/ml
The general formula for quantizing concrete making materials is given below. You can use
this formula for more calculation over any concrete of your need.
Assume the following:
Concrete mix ratio is= a:b:c
Total volume of concrete=z
Total sum of part=r
Density of cement=u
Density of fine aggregate=v
Density of coarse aggregate=w
Amount of cement=(a/r) z x u x 1.30 x1.05
Amount of sand=(b/r) z x v x1.30 x 1.05
Amount of gravel=(c/r) z x w x 1.30 x 1.05
Note: 1.30 is given for the shrinkage property of the concrete and 1.05 is given for the
probability of wastage at site.
77
Proportion
of cement
mortar
Cement:san
d
1:3
1:4
1:5
1:6
B.
AREA
12mm thick with
20% wastage
Volume of mortar
is 0.144
Cement
( kgs )
sand
( )
Cement
(kgs)
sand
( )
Cement
(kgs)
Sand
( )
Cement
(kgs)
Sand
( )
66.15
53.00
44.1
37.80
0.14
0.15
0.16
0.16
79.10
63.80
52.68
45.15
0.17
0.16
0.19
0.19
102.90
82.43
68.60
58.80
0.22
0.24
0.25
0.25
114.84
92.00
76.56
65.62
0.25
0.25
0.27
0.28
Area
Proportion of
lime mortar
Lime :
cement
5mm with 5%
wastage
Volume of mortar
is 0.0575
1:2
Lime
(kgs)
45.08
Sand
( )
0.048
Lime
(kgs)
91.77
Sand
( )
0.097
Lime
(kgs)
110.12
Sand
( )
0.116
1:3
25.36
0.054
50.20
0.109
60.86
0.130
1:4
27.54
0.058
55.09
0.116
666.10
0.139
78
CIVIL
HARAMAYA
2.1.
2.2.
UNIVERSITY
Cement=150kgs/
Sand=0.42 /
Brick masonry
1. Half brick wall bedded in compo mortar of mix ratio 1:2:9 both sides left for
plastering.
Materials required :
1. Brick =58 pcs/ ( 5% wastage is assumed)
2. Compo mortar= 0.0353 ( 10 mm joints and 15% wastage are
assumed)
2.1.Cement=5 kgs/
2.2.Lime =14 kgs/
2.3.Sand =0.8 /
2. One brick wall bedded in compo mortar of ratio 1:2:9 mix ratio both side left for
plastering.
Material required
1. Brick =115pcs/
(5% wastage is assumed)
2. Compo mortar=0.085 / ( 10mm joints & 15% wastage are
assumed).
2.1 Cement =12.5 kgs/
2.2 Lime=34 kgs/
2.3 Sand=0.8 /
3. One and half brick will bedded in compo mortar of ratio 1:2:9 both
sides left for plastering.
Material required
1. Brick =173pcs/ (5% wastage is assumed)
2. Compo mortar=0.113 / (10mm joints & 15%wastage are assumed)
2.1. Cement=17kgs/
2.2. Lime=45kgs/
2.3. Sand=0.27 /
HARAMAYA UNIVERSIY
79
II.
III.
10cm thick hollow concrete block wall bedded in cement mortar 1:4
Materials required
1. H.C.B with 5% wastage=13pcs/
2. Mortar with 20% wastage=0.0153 /
2.1.Cement=5 kgs/
2.2.Sand=0.014 /
15cm thick hollow concrete block wall bedded in cement mortar 1:3
Material required
1. H.C.B with 5% wastage =13 pcs/
2. Mortar with 20% wastage=0.0203 /
2.1.Cement=6kgs/
2.2.Sand=0.028 /
20cm thick hollow concrete block wall bedded in cement mortar 1:3
Material required
1. H.C.B. with 5% wastage =13pcs/
2. Mortar with 20% wastage=0.027 /
2.1.Cement=10kgs/
2.2.Sand=0.028 /
Type of work
368
1.05
306
1.10
80
CIVIL
HARAMAYA
B. COMPO MORTAR
No.
Type of work
1
2
3
UNIVERSITY
1
2
Type Of work
HARAMAYA UNIVERSIY
81
Pointing
Brick wall pointed with cement mortar 1:3 with 15% wastage per 10 square
meters of area of wall.
Material required
1. Mortar =0.03 /10
1.1.Cement=13.78kgs/10
1.2.Sand=0.03
Stone wall pointed with cement 1:3 with 12% wastage per 10 square meters of
area of wall.
Materials required
1. Mortar=0.06 /
1.1.Cement=27.56kgs/
1.2.Sand=0.06
Bricks wall pointed with cement mortar1:3 with 10% wastage per 10 square
meters of area of wall.
Materials required
1. Mortar=0.02 /
1.1.Cement=9.19kgs/10
1.2.
Sand=0.02
Brick wall pointed with cement mortar 1:4 with 15% wastage per 10 square
meters of wall
Materials required
1. Mortar=0.03 /
1.1.
Cement=11.04kgs/10
1.2.
Sand=0.03
Stone wall pointed with cement mortar 1:4 with 12% wastage per 10 square
meters of area of wall
Material require
1. Mortar=0.06 /10
1.1.Cement=22.08kgs/10
1.2.Sand=0.06
Hollow block wall pointed with cement mortar 1:4 with 10% wastage per 10
square meter of wall
Material required
1. Mortar=0.02 /10
1.1.Cement=7.36kgs/10
HARAMAYA UNIVERSITY CIVIL ENGINEERING DEPARTMENT
82
CIVIL
HARAMAYA
UNIVERSITY
1.2.Sand=0.02
MATERIAL LIST CALCULATION FOR FLOORING
flooring
Flooring includes all these material used for covering the surface wall and floor.
A. FLOORING
i.
20 x20 x2 Terrazzo tile with 20%wastage bedded in cement
mortar of mix ratio 1:4
Material required:
1. Terrazzo tile=26pcs/
2. 2.5cm thick mortar with10% wastage
2.1.Cement=10.12kgs/
2.2.Sand=0.0275 /
ii. Cement screed flooring with an average thickness of 2.5cm
Material required
1. Mortar of 1:3 ratio with 15% wastage =0.03
2. 2.1 cement=13.78kgs/
3. 2.2 sand=0.024 /
iii. 2cm thick marble slate flooring bedded with cement mortar 1:4
Material required:
1. Marble slate with 20%wastage =1.20 /
1.1.Cement=10.12kgs/
1.2.Sand=0.29 /
iv.
Materials required
1. Marble chip with 20% wastage=1.20 /
2.1. Cement=10.12 kgs/
2.2. Sand=0.29 /
v.
1.5mm, 2mm or 2.5mm thick plastic flooring
Materials required
1. Plastic tile with 5% wastage(size 25 x 25)=17pcs/
2. Plastic tile with 5% wastage (30 x30 )=12pcs/m2
3. Adhesive including wastage =0.3kgs/m2
vi.
Wooden flooring
Materials required
1. Boarding with 2% wastage=0.02m2/m2
2. Nails (4-6 cm length) = 0.06kgs/m2
vii.
Carpet flooring
HARAMAYA UNIVERSIY
83
Materials required
1. Carpet with 5% wastage =0.05m2/m2
B. WALLING
i.
Materials required
1. Ceramic tiles( size 15 x15 ) =47pcs/ m2
2. Mortar with 10% wastage =0.001 m2/m2
2.1 cement =0.37kg/ m2
2.2 sand =0.001m3/ m2
2.3 Cement for grouting the joint = 0.01kgs/ m2
ii.
Mosaic wall tiles with 20% wastage bedded in cement mortar 1:4
Materials required
1. Mosaic tiles =1.02 m2/ m2
2. Mortar with 10% wastage = 0.01 m2/ m2
2.1 cement=0.37 kg/ m2
2.2 sand =0.001 m3/ m2
2.3 cement for grouting the joints =0.02 kgs/ m2
C. SKIRTING
i.
Materials required
1. Tile with 10% wastage ( 10 x10 ) 17pcs/1m3/ m2
2. Mortar with 10% wastage 0.04 1m2/ m2
2.1 cement=0.22 kgs/ml
2.2 sand=0.006 m3/ pcs
ii.
iii.
/ml
84
CIVIL
HARAMAYA
iv.
UNIVERSITY
D. WINDOW SILL
i.
Materials required
1. Marble slate 2 or 3 cm thick=1m/m2
2. Mortar with 10% wastage =0.007
/ml
/ml
2.1.cement= 2.6kg/ml
2.2.sand=0.007
/ml
Materials required
1. Priming coat to fill the pores of the surface to prepare smooth base
for the first paint coat =62.5 gm/m2
1.1 stucco =50gm/m2
1.2 animal or vinavil glue=12.5gm/m2
first coat =0.07 lit/ m2
second coat=0.06 li/ m2
brush for plastic paint 40 x 140 mm=1pcs/500 m2
sand paper=0.01 m2/ m2
HARAMAYA UNIVERSIY
85
Materials required
1. Priming coat to fill the pores of the surface to prepare smooth base
for the first paint coat =62.5 gm/m2
1.1.Stucco =50gm/ m2
1.2.Animal or vinavil glue=12.5gm/ m2
2. First coat=0.07 lit/ m2
3. second coat=0.06 li/ m2
4. third coat=0.05 lit/ m2
5. brush for plastic paint 40 x 140 mm=1pcs/500 m2
6. sand paper=0.01 m2/ m2
7. gypsum=0.03 kg/ m2
Materials required
1. Priming coat = 62.5 gm/ m2
1.1. Stucco =50 gm/ m2
1.2.Animal or vinavil glue=12.5gm/ m2
2. First coat=0.08 lit/ m2
3. second coat=0.07 li/ m2
4. third coat=0.05 lit/ m2
5. brush for plastic paint 40 x 140 mm=1pcs/500 m2
6. sand paper=0.01 m2/ m2
7. cement mortar = 0.02 kg/ m2
Materials required
1. Priming coat = 62.5 gm/ m2
1.1 Stucco =50 gm/ m2
1.2.Animal or vinavil glue=12.5gm/ m2
2. First coat=0.08 lit/ m2
3. second coat=0.07 li/ m2
4. third coat=0.04 lit/ m2
86
CIVIL
HARAMAYA
UNIVERSITY
Materials required
1. First coat=0.13 lit/ m2
2. second coat=0.11 li/ m2
3. brush for plastic paint 40 x 140 mm=1pcs/500 m2
Materials required
1
material required
1
material required
1. First coat=0.6 lit/ m2
2. second coat=0.05 li/ m2
3. third coat = 0.04 lit/ m2
4. solvent or thinner for 1st and 2nd coat = 0.51 lit/gal
5. brush 4" or 5" =1pcs/200 m2
6. stucco = 0.05 kgs/m2
7. sand paper 0.007 m2/ m2
material required
HARAMAYA UNIVERSIY
87
materials required
1. cement paint = 0.51 lit/m2
2. brush 4" or 5" =1pcs/200 m2
materials required
3. cement paint = 1.25 lit/m2
4. brush 4" or 5" =1pcs/200 m2
Materials required
1. Priming coat = 62.5 gm/ m2
1.1 Stucco =50 gm/ m2
1.2.Animal or vinavil glue=12.5gm/ m2
2. First coat=0.09 lit/ m2
3. Knitting
3.1. Stucco = 0.05 lit/m2
3.2. Gypsum = 0.04 lit/ m2
4. Second coat = 0.08 lit/ m2
5. third coat=0.07 lit/ m2
6. brush for plastic paint 40 x 140 mm=1pcs/400 m2
7. sand paper=0.07 m2/ m2
materials required:
1. anti-rust = 0.04 lit/ m2
2. solvent (thinner) for 1st or 2nd coat = 0.5 lit/ m2
3. first coat = 0.04 lit/ m2
88
CIVIL
HARAMAYA
UNIVERSITY
Materials required:
1. Bitumen emulsion for primer coat with 5% wastage = 0.42 kgs/ m2
2. One coat of bitumen emulsion with 5% wastage = 0.79 kgs/ m2
Materials required:
Materials required:
1. Bitumen emulsion for primer coat with 5% wastage = 0.42 kgs/ m2
2. One coat of bitumen emulsion with 5% wastage = 0.79 kgs/ m2
HARAMAYA UNIVERSIY
89
1.
2.
Materials required
1.
2.
One ply of glass fibres with 10% wastage & lap = 1.2 m2/ m2
Materials required
1.
2.
Two plies of glass fibres with 10% wastage & lap = 2.4 m2/ m2
3.
4.
90