1.6 Project Control Plan
1.6 Project Control Plan
SERVICES PROJECT
No
0
X
X
X
X
X
X
X
X
X
1
2
3
4
5
6
7
8
9
10
11
12
Revised
2
3
4
Remarks
5
No
Revised
2
3
4
Remarks
5
19/11/10
20
ER
AW
PD
REV.
DATE
PAGE
S
DESCRIPTION
PREP
D
CHK
D
APP
D
OWNER
1. GENERAL
This document is a guidance to prepare a project control and reporting system
required by Energy Equity Epic (Sengkang) Pty,Ltd
1.1.Scope
PT BORNEO MITRA SINERGI PROJECT CONTROL PLAN
Control Forms
PT BORNEO MITRA SINERGI PROJECT CONTROL PLAN
Control Forms are tools to be used for the orderly execution of the
project control system, refer to Energy Equity Epic (Sengkang) Pty,Ltd
control forms. Such form is divided into: Authorization / Requisition
form, Planning Forms, Register form, etc.
3.2.Man-hours Control
3.2.1.
Man-hours Control Procedure
The Man-hours Control will depend on weekly time sheets process,
overtime authorization, and man-hours forecasting and trending. The
Man-hours Control process is summarized as follows:
3.2.1.1. BMS personnel will prepare their own weekly time sheet
and approved by their supervisor. The weekly time sheets and
corresponding overtime authorization, if any, will then be
submitted to BMS Project Control Team for recording.
3.2.1.2. Based on the recorded time utilization by each BMS
personnel ( if any), man-hours will be forecasted weekly and
trended. This shall be updated weekly. Such information shall
be used for man-hours cost forecast and trending and to
detect potential man-hours cost overrun ahead of time.
3.2.1.3. If potential over-run is detected, BMS shall analyze it to
determine the cause of the over-run. Upon finding of such
cause, corrective measure will be formulated and performed,
prior to include it in the weekly report.
3.2.2.
Man-hours Forecasting and Trending
BMS shall prepare forecast of man-hours required based on the project
requirements. The forecast is determined by considering the
remaining work.
The man-hours required for the remaining work will be trended by the
BMS Project Controller.
3.2.3.
Man-hours and Completion S-Curves
The Project Controllers prepares weekly the completion and manhours percentages S-Curves, showing plan/estimate vs. actual and
forecast man-hours, unless specified otherwise by Energy Equity Epic
(Sengkang) Pty,Ltd.
Since the original planned/estimated completion percentages are
measured based on the original estimated man-hours, the original
planned completion percentage S-Curve coincides with that of the
original estimated man-hours percentages.
The original estimate/plan will not be changed unless mutually agreed
by and between Energy Equity Epic (Sengkang) Pty,Ltd and BMS.
PT BORNEO MITRA SINERGI PROJECT CONTROL PLAN
3.3.Schedule Control
3.3.1.
Philosophy
Potential delays must be detected advance in time in order to have
sufficient time to formulate and perform corrective measures and thus
ensuring major activities completion in accordance to approved
Contract Master Schedule (CMS).
This philosophy can be successfully implemented by the following
procedures:
Weekly plan the activities and deliverables to be executed.
Control and Supervise the current project activities in
accordance the preceding week plan.
Identify the current plan changes/variance from the preceding
week plan.
3.3.2.
Schedule Control Procedure
The Schedule Control Procedures are as follows:
3.3.2.1. BMS to prepare look-ahead-schedule, by weekly, that plan
activities and deliverables to be executed in the form of bar
charts depicting weekly percent completion and the manhours required for each activity.
The preceding week time schedule will be adhered to as
closely as possible, while the unavoidable changes time
schedule will be implemented and noted.
3.3.2.2. Based on such plan, BMS will convert it to computerized
detailed activities schedule, the corresponding completion
man-hours and percent completion S-Curve.
3.3.2.3. If no potential delay is detected then the detailed activity
schedule shall be included in the weekly report and issued to
Energy Equity Epic (Sengkang) Pty,Ltd.
3.3.2.4. If potential delay is detected, BMS shall analyze it to
determine the cause of the delay. Upon finding of such cause,
corrective measure will be formulated and performed, prior to
include it in the weekly report.
3.3.2.5. BMS shall prepare Schedule Control as follow :
Engineering Schedule Control
Procurement Schedule Control incl. Purchasing,
Expediting and Inspection, Transportation.
Construction and Commissioning Schedule Control
3.4.Cost Control
The project cost will be monitored and controlled with the objective to detect
potential cost overrun sufficiently ahead of time to formulate and implement
corrective measures and thus ensures the approved budget is not exceeded.
If potential over-run is detected, BMS shall analyze it to determine the cause
of the over-run. Upon finding of such cause, corrective measure will be
formulated and performed, prior to include it in the weekly report.
The project cost is divided into direct and indirect cost. Direct cost are
included manhours, equipment, tools, consumables and material. Meanwhile
indirect cost are included project management team, computer utilization,
reproduction cost, etc.
BMS Cost Control is concerned with :
Influencing the factors which create changes to the cost baseline to
ensure that the changes are beneficial.
Determining that the cost baseline has changed.
Managing the actual changes when and as they occurs.
Preparing summary of payment by Energy Equity Epic (Sengkang)
Pty,Ltd to contract or as well as summary of approved change of
scope. This report shall be included in Weekly Status Report.
BMS Cost Control includes :
Monitoring cost performance to detect variances from plan.
Ensuring that all appropriate changes are recorded accurately in the
cost baseline.
Preventing incorrect, in appropriate and unauthorized changes from
being included in the cost baseline.
BMS will control the following costs during execution of PROJECT :
Man-hour
Labor
Equipment Usage
Material
Etc.
3.5.Change Order Control
3.5.1.
Philosophy
The proposed work change control is within the framework of Energy
Equity Epic (Sengkang) Pty,Ltd Request for Proposal Schedule, if any.
Any work change will be assessed, but only work changes defined in
Criteria of Change are included the change control procedure.
PT BORNEO MITRA SINERGI PROJECT CONTROL PLAN
3.5.2.
Criteria of Change
A work change is interpreted by BMS as any alternation to activities
which results in variation from any of the following documents:
Reference Documents Listed below :
Scope of Work
Design Basis
Contract Master Schedule
Contract Document
Engineering documents (such as drawings, specifications, etc.) that
have been approved by Energy Equity Epic (Sengkang) Pty,Ltd for
construction, procurement or control. Engineering changes will be
either mandatory or non-mandatory.
Work change control will be enacted after the reference and
engineering documents have been approved by Energy Equity Epic
(Sengkang) Pty,Ltd.
4. REPORTING
BMS will consult and coordinate with Energy Equity Epic (Sengkang) Pty,Ltd /
Project Task Force to meet the requirements in setting up an efficient and
effective Reporting. System frame work that will enable Energy Equity Epic
(Sengkang) Pty,Ltd and BMS to achieve the most effective communication both
internally and externally.
4.1.General
BMS shall provide Energy Equity Epic (Sengkang) Pty,Ltd with accurate and
complete information with respect to the WORK already performed, in
progress and planned; and the events affecting the performance of the
WORK and shall make available to Energy Equity Epic (Sengkang) Pty,Ltd all
relevant planning and reporting documents, including electronic access to
project data.
BMS may propose his standard forms for such reports, subject to approval by
Energy Equity Epic (Sengkang) Pty,Ltd. Consolidation of several reports on a
single form is permitted provided identification is not affected.
It is preferred for speed and accuracy that reports be set up for computer
printout. BMS however, may use other methods subject to approval by
Energy Equity Epic (Sengkang) Pty,Ltd provided reports are delivered Energy
Equity Epic (Sengkang) Pty,Ltd in a legible and timely manner.
Project reports are vehicles for project monitoring and consist of among
others the following periodic:
Weekly Status Reports
Monthly Reports The type and frequency of project periodic report
will be modified to suit particular need of individual project.
PT BORNEO MITRA SINERGI PROJECT CONTROL PLAN