ISRO
ISRO
Department of Space
: 2 :
4. Time
Shri. Belgaonkar. P. V
Head, GIS-4/GID
System Integration Group
ISRO Satellite Centre,
HAL Airport Road,
Vimanapura Post,
Bengaluru 560 017.
Contact No. 23027159
E-mail: [email protected]
: 3 :
10. The Vendor[s] who do not participate in the Pre-EoI Meeting for Expression of
Interest will not be considered and shall be disqualified.
11. In the event if the Vendor[s] are unable to attend the Pre-EoI Meeting for
Expression of Interest physically, a Pre-EoI Meeting for Expression of Interest
through Video Conference / Skype / Conference Call shall be arranged by
ISRO Satellite Centre, Bengaluru upon the request from Vendor[s], if mutually
agreeable.
12. Data required for Security Clearance for Pre-EoI Conference on or
before July 11, 2016:
a.
b.
c.
d.
e.
f.
g.
Government of India
Department of Space
ISRO Satellite Centre [ISAC] of Indian Space Research Organization [ISRO] under
Department of Space, Government of India is the lead centre of ISRO for Design,
Development, Fabrication and Testing of all Indian made Satellites. As a sequel to its
mandate of spacecraft realisation, the Centre is engaged in the development of
cutting-edge technologies of relevance to its Satellite Building Activities and setting
up of infrastructure for Design, Development, Fabrication and Testing of Spacecraft.
The proposal is to invite Expression of Interest and to enter into Contract with
Industry for Systems Assembly, Integration and Testing [AIT] of Standard ISRO
Satellites at ISAC.
The Brief Description, Scope of Work, Tenure of Work, Manpower Estimation, Safety
Precautions, Non-Disclosure Agreements, etc., forming part of the AIT Activity is
available in the EoI Document which can be downloaded from our Websites
www.isac.gov.in and/or www.isro.gov.in under Tenders and submit along with the
Document fee Rs. 573/- in the form of Demand Draft drawn in favour of Accounts
Officer, ISAC, Bengaluru before the specified date and time.
2. Time
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
Table of Content
Sl No.
Chapter
Page No
1.
INTRODUCTION
2.
SCOPE OF WORK
15
3.
TENURE OF WORK
27
4.
MANPOWER ESTIMATION
33
5.
SAFETY PRECAUTIONS
37
6.
41
7.
45
8.
9.
RESPONSE FORMAT
Expression of Interest
51
57
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
Expression of Interest
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
1. INTRODUCTION
Expression of Interest
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
Expression of Interest
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
1. INTRODUCTION
1.1 ISRO Satellite Centre
ISRO Satellite Centre (ISAC) is one of the lead Centres of the Indian Space
Research Organisation
(ISRO)
development,
&
rescue
operations,
earth
observations,
natural
resource
Expression of Interest
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
such
as
electronic
and
mechanical
subsystem
parts
terms
Expression of Interest
of
volume
and
complexity.
Vendor
participation
on
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
a large scale is required not only to meet goals of ISAC but also for selfreliance resulting in higher throughput.
After successfully completing the vendors participation in subsystem level
fabrication and testing, ISAC is seeking to extend the scope of vendor
participation to spacecraft level assembly, integration and testing activities.
On successful completion of these tests, the spacecraft will be shipped to
the launch base for launch. The vendors which are interested in
collaborating with ISAC to assemble integrate and test satellites as per
ISACs procedures and guidelines shall express their interest for the same.
The details of ISACs requirements from vendors are provided in the
subsequent chapters.
Expression of Interest
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
SATELLITE SUBSYSTEM
MAINFRAME
SUBSYSTEM
STRUCTURE
THERMAL
MECHANISM
PROPULSION
POWER
PAYLOAD
SUBSYSTEM
COMMUNICATION
NAVIGATION
REMOTE SENSING
ACTIVITY
MISSION PLANNING &
ANALYSIS
RELIABILITY &
QUALITY ASSURANCE
ASSEMBLY
INTEGRATION &
TESTING
TTC-Baseband
AOCS
SENSORS,
ACTUATORS
INERTIAL SYSTEMS
COMMUNICATION
SYSTEM
Expression of Interest
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
PROPELLANT &
PRESSURANT
TANKS
NORTH SOLAR ARRAY
TTC ANTENNA
H
e
F
u
TTC HORN
EARTH SENSOR
O
x
WEST PANEL
Ku BAND
TWTA
KU
SHAPED
REFLECTOR
SOUTH PANEL
NORTH PANEL
EAST PANEL
KU
SHAPED
REFLECTOR
MOMENTUM
WHEELS
LAM
MAIN
STRUCTURE
SOUTH
SOLAR
ARRAY
BATTERY PANEL
Expression of Interest
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
(OSR),
insulation
(MLI)
sinks, surface
multi
blankets;
coatings,
layer
heat
paints,
release systems,
deployment
Expression of Interest
10
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
using
Expression of Interest
11
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
system
between the
provides
the
link
Expression of Interest
12
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
Payload subsystems
Communication
Satellite
Navigation Satellite
Navigation payload
Remote Sensing
Satellite
Space Science
Interplanetary Missions
IR
Expression of Interest
13
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
Expression of Interest
14
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSTRY
2. SCOPE OF WORK
Expression of Interest
15
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
16
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
2. SCOPE OF WORK
It is proposed to carry out the assembly, Integration and testing (AIT) activities of
two number of ISRO Standard bus satellites with the participation of the
prospective vendor. The entire activity is planned to be carried out in two phases
viz Phase-1 and Phase-2. During Phase-1, the AIT activities of the first satellite
will be done by ISAC while on-the-job training will be given to the vendor. The AIT
activities of the second satellite will be carried out by the selected vendor under
the supervision of ISRO/ISAC in phase-2.
After successful completion of Phase-2, potential vendors may be invited to take
up satellite fabrication activities on an end-to-end basis and/or carry out assembly,
integration and testing of spacecraft at ISAC/ISITE campus which is beyond the
scope of this EoI.
The Vendor shall take up the activity within ISAC premises at ISITE (ISRO
Satellite Integration and Test Establishment) campus, Marathalli, Bangalore. ISAC
will provide all necessary infrastructures & facilities to facilitate vendor to carry out
Assembly, Integration and Testing of ISRO Standard bus satellites.
The scope of work involved in each phase is discussed in brief below:
2.1 Phase 1: First ISRO Standard bus satellite realization (On-the-Job
Training):
A project team with
constituted after the selection of the qualified vendor. The required skilled
manpower from the vendor shall be inducted and provided an orientation training
programme on satellite systems and associated systems engineering concepts.
During the realization of first ISRO Standard bus satellite; the vendor will get onthe-job training on the assembly, integration and testing activities of the satellite.
The flight mainframe subsystems, payload, harness and all the other supporting
infrastructure/facilities, equipment, resources and accessories shall be provided
by ISAC. The vendor shall also be responsible in bringing out necessary
Expression of Interest
17
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
documentation for system assembly, integration and testing activities. All the
activities mentioned will be carried out using ISAC facilities/Infrastructure
2.1.2
2.1.3
2.1.4
2.1.5
Expression of Interest
18
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
2.
3.
4.
5.
6.
7.
Expression of Interest
on
Structure,
19
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
9.
10.
11.
Panel closure
12.
13.
14.
15.
16.
17.
EMI/EMC test
18.
19.
20.
21.
22.
23.
24.
25.
26.
Vibration Test
Expression of Interest
20
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
28.
Acoustic Test
29.
CATF test
30.
SP-1 IST
31.
one
roof.
Some
of
the
major
capital
intensive
equipment,
planning,
configuration
systems
management,
engineering,
procurement
contract
management,
management,
inventory
satellite project
21
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
22
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
vendor will be responsible for necessary documentation during all the stages
of system assembly, integration and test activities.
Sl.No
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
Expression of Interest
23
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
and in-house agencies during this phase. The vendor manpower shall
prepare a subsystem deliverable check-list and submit the report to
ISAC. Subsequent to the clearance of the checklist report by ISAC focal
point, the vendor shall initiate the spacecraft assembly and integration
activities.
2.2.2 Spacecraft Assembly And Integration Activities:
The vendor shall carry out the spacecraft assembly and integration
activities as per approved assembly sequence plan of ISAC as
summarized below. All the activities mentioned will be carried out using
ISAC facilities/Infrastructure.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
Panel closure
12.
13.
Expression of Interest
24
14.
15.
16.
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
CATF test
30.
SP-1 IST
31.
while ISAC QA/QC team will audit the activity at each stage. The vendor
shall report all anomalies/non-conformance related to AIT activities to
ISAC as and when observed. The vendor shall proceed to next stage
only after the clearance from the ISAC QA team. The vendor shall submit
Expression of Interest
25
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
26
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
3. TENURE OF WORK
Expression of Interest
27
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
28
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
3. TENURE OF WORK:
3.1 Phase -1 & Phase-2 Tenure of work
The first ISRO Standard bus satellite is required to be ready for shipment to
launch base by 8 months from the date of work order release. The second ISRO
Standard bus satellite shall be ready 10 months after the readiness of the first
satellite. The overall schedule is depicted below:
Expression of Interest
29
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
30
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
31
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
32
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
4. MANPOWER
ESTIMATION
Expression of Interest
33
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
34
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
4. MANPOWER ESTIMATION:
It is estimated that around 50 personnel are required from the vendor for a period of
about 18 months to realize the two ISRO Standard bus satellites. An approximate
manpower estimation with their qualifications required are as given below:
20 (8: mechanical, 12: electrical/electronic) engineers with a minimum
qualification of BE / BTech
15 technicians with a minimum qualification of Diploma
15 tradesmen with a minimum qualification of ITI
The man-power employed by the vendor shall have experience of working in
relevant / similar areas and must possess a minimum of first class pass marks /
percentage / grading with respect to their qualification. The vendor shall ensure that
the manpower provided by vendor shall be retained throughout the phase-1 and
phase-2 time period. The estimated manpower required to carry out the satellite AIT
activities depends upon the expertise and learning skill of the vendor manpower.
The above number may vary based on upon the spacecraft configuration and
complexity.
The vendor shall be provided with orientation and on-the-job training in order to get
acquainted with the satellite building activities during phase-1.
An orientation
training programme for the vendor manpower shall be provided wherein, they will be
introduced
to
satellite
subsystem,
system
engineering
aspects,
project
management, and subsystem fabrication and testing, spacecraft level AIT etc.
It will be followed by on-the-job training in the AIT activities of the first ISRO
Standard bus satellite such as thermal fabrication and implementation, propulsion
integration and test activities, subsystem assembly, integration and testing,
integrated spacecraft level testing, checkout operations, In other words, the vendor
man power shall participate in AIT activities with ISAC team to realize the first ISRO
Standard bus satellite. After the completion of the AIT activities of the first ISRO
Standard bus satellite, the manpower will be work on the second ISRO Standard
Expression of Interest
35
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
bus satellite. The on-the-job training will help vendor manpower to take up all
aspects of AIT activities of the second ISRO Standard bus satellite in phase-2.The
technical skill, competency and quality of the vendor manpower play a vital role in
the successful completion of the phase-1 and Phase-2.
Expression of Interest
36
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
5. SAFETY
PRECAUTIONS
Expression of Interest
37
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
38
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
5. SAFETY PRECAUTIONS
The vendor should strictly adhere to the general work rules, procedures and
office timings followed at ISAC.
The personnel of vendor must adhere to all the safety guidelines while handling
components, cards, and packages during testing and transporting, particularly the
ESD protection measures such as wearing ESD overcoats, footwear, wrist bands,
grounding and other measures as per ISAC ESD protection guidelines.
Vendor
is
responsible
to
ensure
the
safe
handling
of
the
sub-
assemblies/equipment being used during the AIT of the satellite. The vendor shall
strictly conform to the safety and security procedures laid by ISAC.
Expression of Interest
39
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
40
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
6. CONFIDENTIALITY
AND NONDISCLOSURE
Expression of Interest
41
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
42
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
43
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
44
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
7. GENERAL TERMS
AND CONDITIONS
Expression of Interest
45
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
46
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
This EoI is not an offer and is issued with no commitment. ISAC reserves
the right to withdraw the EoI and change or vary any part thereof at any
stage. ISAC also reserves the right to disqualify any vendor/proposal,
should it be so necessary at any stage.
7.2
Timing and sequence of events resulting from this EoI shall ultimately be
determined by ISAC
7.3
7.4
7.5
The vendor shall not subcontract the work related to satellite assembly,
integration & testing to any other third party without the permission of
ISAC.
7.6
7.7
7.8
The
cost
of
components/systems
damaged
due
to
Expression of Interest
47
7.9
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Minor rework and testing thereon required due to the above shall be
done by the vendor without any financial implications.
Expression of Interest
48
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
7.16 The Vendor shall provide the details of the ownership of the company
and details of owners / directors along with complete addresses of the
owners / directors and their other activities. If the company is owned by
another company similar details of the owner should be provided.
7.17 Not be insolvent, in receivership, or being wound up, not have its affairs
administered by a court or a judicial officer, not have its business
activities suspended, not have been blacklisted, defaulted and must not
be the subject of legal proceedings for any of the foregoing reasons;
7.18 Not have, and their directors and officers not have, been convicted of any
criminal offence related to their professional conduct or the making of
false statements or misrepresentations as to their qualifications to enter
into a procurement contract within a period of three years preceding the
commencement of the procurement process, or not have been otherwise
disqualified pursuant to debarment proceedings;
7.19 Not have a conflict of interest in the EoI in question as specified in the
EoI document
Expression of Interest
49
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
50
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
8. GENERAL
INSTRUCTION FOR
SUBMISSION OF EoI
PROPOSAL
Expression of Interest
51
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
52
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
8.1
A Pre-EoI
Expression of Interest
53
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
54
8.2
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
55
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
56
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
9. RESPONSE FORMATS
Expression of Interest
57
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Expression of Interest
58
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
9. RESPONSE FORMATS
9.1
Cover Letter
(Company letterhead)
[Date]
To,
HEAD, PURCHASE & STORES
ISRO Satellite Centre
HAL Airport Road, Vimanapura Post
Bangalore -560017
Karnataka
Dear Sir,
Ref: Expression of Interest for systems assembly, integration &
testing of standard ISRO satellites through Industry
Having examined the Expression of Interest (EoI), the receipt of which is hereby duly
acknowledge, we, the undersigned, intend to submit a proposal in response to the
Expression of Interest (EoI).
We attach hereto the response as required by the EoI, which constitutes our proposal
Primary and Secondary contacts for our company are:
Primary Contact
Secondary Contact
Name:
Title:
Company Name:
Address:
Phone :
Expression of Interest
59
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Primary Contact
Secondary Contact
Mobile:
Fax :
E mail :
We confirm that the information contained in this response or any part thereof,
including its exhibits, and other documents and instruments delivered or to be
delivered to ISAC is true, accurate, verifiable and complete. This response includes
all information necessary to ensure that the statements therein do not in whole or in
part mislead ISAC in its short-listing process.
We fully understand and agree to comply that on verification, if any of the information
provided here is found to be misleading the short listing process, we are liable to be
dismissed from the selection process or termination of the contract during the
realization of Phase-1 and Phase -2 , if selected to do so.
We agree for unconditional acceptance of all the terms and conditions set out in the
EoI document.
It is hereby confirmed that I / We are entitled to act on behalf of our company/
corporation/ firm / organization and empowered to sign this document as well as
such other documents, which may be required in this connection.
Dated this
(Signature)
(Name)
60
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Witness Signature :
Witness Name :
Witness Address:
.,
..,
the
Company
Secretary
certify
of
that
Date :
Signature :
(Company Seal)
Expression of Interest
61
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
9.2
Year of Establishment
9.2.2
Brief profile and core capabilities
9.2.3
of the vendor
Type
9.2.4
of
Vendor
Government/Public
sector
Undertaking/Private/Others
9.2.5
9.2.6
9.2.7
9.2.8
9.2.9
Expression of Interest
62
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
9.3
Sl
No.
Remark
Centre/Aerospac e
Purchase
of Work
Industry
order Status
/Contract
1.
2.
3.
4.
5.
6.
63
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
9.4
Stream
Mechanical
Electronics
Computer
Science
Others
Mechanical
Electronics
Computer Sci.
Others
Engg.
Engg.
Engg.
Engg.
Tech.
Tech.
Tech.
Tech.
0 to 2 years
>2
to
to
10
years
>5
years
>10 years
Expression of Interest
64
9.4.4
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
9.4.5 The vendor shall ensure that the manpower provided by vendor shall be
retained throughout the phase-1 and phase-2 time period. Yes/No
9.4.6 Is the vendor willing to work in regular shift (8 hrs shifts), two shift or three
shift mode operation if required depending upon the phase of the project.
Yes/No
9.4.7 The vendor shall provide all logistics support
Expression of Interest
65
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
9.5
Infrastructure Capabilities
9.5.1 List of major infrastructure presently available to build systems/subsystem
related to either satellite or launch vehicle or aerospace related systems
such as cleanroom, electronic fabrication facility, mechanical fabrication
facility, environment test chambers etc.(facilities used to execute orders
from ISRO Centres or aerospace vendors)
Name of
Year of
Brief
Infrastructure/Facility
commissioning
specifications
Sl.No
1.
2.
3.
4.
5.
9.5.2 Is
the
vendor
willing
to
invest
in
resources-
manpower/equipment/facilities/infrastructure? Yes/No
Expression of Interest
66
9.6
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Financial Details:
9.6.1 Financial Information
FY 2012-13
FY 2013-14
FY 2014-15
FY 2015-16
Revenue (in
INR Crores)
Profit before
Tax(in INR
Crores)
Revenue from
services(in
INR Crores)
9.6.1.1
9.6.1.1.1 Auditor certified statements for the last four years 201213,2013-14,2014-15 and 2015-16 (please includes only the
sections on profit and loss , revenue,and assets, not the entire
balance sheet)
9.6.1.1.2 Unaudited certified statements certified by the company
auditors for the latest year 2015-16(in case auditor certified
statement for 2015-16 is not available
9.6.1.1.3 Certification by the company auditors supporting the revenue
break up.
Expression of Interest
67
9.7
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Legal Aspects
9.7.1 The Vendor must be a registered company under the Companies Act, 1956
or a partnership firm registered under Partnership Act or a Proprietorship
firm. The vendor should be registered with the concerned departments
[Service Tax, Sales Tax, VAT etc] for legally carrying out its business
activities. The vendor should also have a valid PAN. The Vendor should
submit Self attested copy(ies) of the Certificates of Incorporation and other
certificates that are legally required for carrying out its business activities.
The certificates should be valid at the time of EoI submission and should be
certified by an authorized signatory. A copy of PAN Card should also be
submitted.
Expression of Interest
68
9.8
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Others
9.8.1 The Vendor shall provide the details of the ownership of the company and
details of owners / directors along with complete addresses of the owners /
directors and their other activities.
Expression of Interest
69
9.9
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Refer
Chapter
Description
No
2
8.
Compliance
(Yes/No)
Remark
Expression of Interest
70
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Description
er No
9.1.
9.2.
Compliance
(Yes/No)
Remark
Supporting
Document
Covering Letter
General Information
9.2.3.
9.3.
Aerospace/Space Related
Activities
Expression of Interest
71
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Chapt
Description
er No
9.3.1.
9.3.2.
Compliance
(Yes/No)
Remark
Supporting
Document
9.3.3.
9.4.
Acceptance to 9.3.3
9.4.3.
Expression of Interest
72
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Chapt
Description
er No
9.5.
9.5.1.
Compliance
(Yes/No)
Remark
Supporting
Document
Infrastructure Capabilities
List of major infrastructure as per
9.5.1 attached?
9.6.1.
Financial Details
All details & supporting documents
as per 9.6.1
9.7.
9.7.1.
Legal aspects
All details & supporting documents
as per 9.7.1
9.8.
9.8.1.
9.8.2.
9.8.3.
Others
All details & supporting documents
as per 9.8.1
All details & supporting documents
as per 9.8.2
All details & supporting documents
as per 9.8.3
Expression of Interest
73
SYSTEMS ASSEMBLY,
INTEGRATION & TESTING OF
STANDARD ISRO SATELLITES
THROUGH INDUSRTY
Chapt
Description
er No
9.8.4.
Compliance
(Yes/No)
Remark
Supporting
Document
The vendor has to provide the information as per the formats prescribed in
chapter 9 Response format 9.1 to 9.8. The overall compliance matrix as per
section 9.9 should also be submitted as per of the EoI proposal. All the above
inputs may be furnished in MS word document neatly typed in the above said
formats.
Expression of Interest
74