Dev-Aad-mp-sp-jpk-1058 Rev b2 Welding and NDT of Cs Linepipe To Bs 4515-1 (2004)
Dev-Aad-mp-sp-jpk-1058 Rev b2 Welding and NDT of Cs Linepipe To Bs 4515-1 (2004)
Dev-Aad-mp-sp-jpk-1058 Rev b2 Welding and NDT of Cs Linepipe To Bs 4515-1 (2004)
PROJECT
SPECIFICATION
TITLE
PROJECT NO.
06-3022.01 / 06-2999.01
REF.
ANDREW: 06-3022-01-K-1-013
DEVENICK: 06-2999-01-K-1-015
NO. OF SHEETS
77
ANDREW
DOCUMENT NO.
DEV-AAD-MP-SP-JPK-1058
DEVENICK
DOCUMENT NO.
DEV-DEV-MP-SP-JPK-1072
STAMP
B2
09/09/2009
DC
SE
ACH
CBN
B1
28/08/2009
DC
CF
ACH
RR
A2
28/07/2009
DC
AL
AH
CBN
A1
30/03/2009
SE
GAS
AWL
CBN
REV
DATE
REVISION
BY
CHK
LE
QA
PM
COMMENTS SHEET
REVISION
A1
DATE
30/03/2009
COMMENTS
A2
28/07/2009
B1
28/08/2009
B2
09/09/2009
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
1.0
INTRODUCTION ........................................................................................................4
1.1
1.2
Safety..............................................................................................................................4
1.3
Definitions .......................................................................................................................4
1.4
Abbreviations ..................................................................................................................5
1.5
1.6
Pre-Production Consultation...........................................................................................8
1.7
1.8
1.9
Records...........................................................................................................................9
1.10
2.0
NORMATIVE REFERENCES...................................................................................12
2.1
2.2
Conflict of Information...................................................................................................12
2.3
Revisions ......................................................................................................................13
2.4
Referenced Documents................................................................................................13
2.5
3.0
3.1
General .........................................................................................................................16
4.0
4.1
4.2
5.0
EQUIPMENT ............................................................................................................26
6.0
Page 1 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
6.1
General .........................................................................................................................27
6.2
7.0
WELDING CONSUMABLES....................................................................................29
7.1
General .........................................................................................................................29
7.2
8.0
8.1
General .........................................................................................................................31
8.2
Changes Affecting Qualification and Approval (Essential Variables) of butt welds .....35
8.3
9.0
9.1
9.2
10.0
10.1
General .........................................................................................................................47
10.2
10.4
Fillet Welds for Sleeves, Sockets, Slip-on Flanges or Other Attachments ..................48
10.5
10.6
10.7
11.0
11.1
11.2
11.3
11.4
Alignment ......................................................................................................................51
11.5
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
11.6
11.8
11.9
12.1
General .........................................................................................................................59
12.2
Personnel Qualification.................................................................................................61
12.4
Radiographic Testing....................................................................................................61
12.5
12.6
12.7
13.0
13.1
13.2
Introduction ...................................................................................................................73
H.2
General .........................................................................................................................73
H.3
H.4
Production Welding.......................................................................................................75
Page 3 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
INTRODUCTION
0B
1.1
Purpose of Document
14B
This specification when read in conjunction with the referenced standards, specifications,
other listed documents and relevant data sheets, defines the minimum technical
requirements for the field welding and NDT of carbon steel linepipe in accordance with BS
4515-1: 2004 for sour-service conditions (applicable to steel grades up to X65).
Paragraph numbers in this specification correspond to BS 4515-1: 2004.
Modifications to BS4515-1: 2004 are identified as Add or Modified to Read in this
U
specification.
1.2
Safety
15B
All risks to personnel and the environment resulting from the Andrew and Devenick
Projects should be As Low As Reasonably Practicable (ALARP). Safety is the primary
consideration during design and all risks associated with the design shall be minimized by
adhering to the relevant governing design codes, and COMPANY International procedural
requirements.
1.3
Definitions
16B
Approval
CONTRACTOR
Linepipe
Shall
Should
Page 4 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
1.4
Abbreviations
17B
AC
Alternating Current
ACCP
ALARP
Ar
Argon
ANSI
ASNT
ASTM
AWS
BAM
BGAS-CSWIP -
BGAS Transco-
BINDT
BS
British Standard
C Eng
Chartered Engineer
CEIIW
CO2
Carbon Dioxide
CSWIP
CVN
Charpy V Notch
DC
Direct Current
Dipl Ing
DWDI
DWSI
Page 5 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
EN
European Norm
EWE
FDIS
FL
Fusion Line
GMAW
GSFCAW
GTAW
HAZ
HSE
HSEQ
HV
Vickers Hardness
ID
Inside Diameter
IIW
IQI
ISO
IWE
MDT
mm
Millimetres
MPE
MUT
NDT
Non-Destructive Testing
NIST
O2
Oxygen
OD
Outside Diameter
Pb
Lead
Pcm
Page 6 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
PE
Professional Engineer
PGMAW
PQR
pWPS
RE
Radiographic Examination
RMS
SAW
SI
1.5
Statutory Instrument
SMAW
SMYS
SWE
SWV
SWSI
TWI
UT
Ultrasonic Testing
VE
Visual Examination
WPS
WPQ
WPQR
WPQT
Welding, cutting, NDT, and associated operations shall be undertaken in a safe manner
and with due regard to individual health and safety, and the minimisation of environmental
impact consistent with COMPANY requirements. Welding, cutting, NDT activities, and
associated operations shall feature in CONTRACTORS operational safety planning and in
the safety audit schedule. ANSI Z49.1 or similar codes should be followed.
Page 7 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Pre-Production Consultation
19B
Pre-production meetings shall be held with the COMPANY and any appropriate third-party
inspection personnel in order to ensure that all parties fully understand the requirements.
These meetings shall be held before welding procedure qualification testing and before
commencement of fabrication.
The COMPANY Welding Engineer shall be consulted at the following stages:
1. During bid evaluation to agree the basic welding and NDT methods proposed and to
advise on acceptability.
2. Before weld procedure qualification for approval of the proposed welding procedures
(pWPS).
3. Before production welding for approval of the final WPS.
Duties of the Contractor
1.7
20B
Construction, welding and pipe-lay shall be carried out by a well trained and qualified
workforce employing reliable, modern, and well maintained equipment and shall also be fully
compliant with safe and environmentally sound working practices at all times.
Unless advised otherwise by COMPANY welding and associated equipment including, but
not limited to: heating equipment, fluxes, gases, filler metals, welding units, mechanical
handling, testing equipment, and NDT equipment shall be supplied and appropriately
calibrated.
Be responsible for the compliance of sub-contractors with this specification.
1.8
Quality Conformance
21B
The CONTRACTOR shall demonstrate to the satisfaction of the COMPANY that his activities
within the scope of this document comply with ISO 3834 Parts 1 & 2 and the relevant
sections of BS EN ISO 9001.
Page 8 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
1.9
2B
Documents required by this specification shall be gathered, collated, indexed, stored, and
finally presented to COMPANY for secure long term storage.
A log identifying, by number, each pipe or fitting and identifying the weld numbers joining
them to other items shall be compiled.
Each circumferential weld (whether a field joint or shop-made weld) shall be allocated a
unique number, which shall be used for reference to the weld in reports and test documents.
All documentation shall be available in an agreed, good quality, electronic format.
Contractors Personnel
1.10
23B
1.10.1 General
73B
A competent and suitably qualified Welding Engineer shall be employed. The Welding
Engineer shall be responsible for the technical aspects of all welding operations including
the following:
Qualification of welders;
Page 9 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Welding Inspectors shall, as a minimum, hold current certification to any of the following
standards:
Page 10 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
AWS QC1 (1996 or later edition) Senior Certified Welding Inspector (SCWI).
Page 11 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
NORMATIVE REFERENCES
1B
2.1
Specification Compliance
24B
This specification has been written to be in full compliance with BP GIS 43-333 Guidance on
Industry Standard BS 4515-1 2004 for Pipeline Welding. Non-applicable paragraphs and
clauses of this GIS to this specification are detailed within technical deviation (JPK-DR-002).
CONTRACTOR shall be in complete compliance with the requirements of the following GIS
documents unless instructed otherwise by this specification:
GIS 43-311
GIS 43-312
GIS 43-313
GIS 43-339
GIS 18-012
Note: Within the GIS documents CONTRACTOR shall replace the words must and
should with shall to read as mandatory requirements. Any shall or must in commentary
(text in blue italics) does not specify an ETP requirement.
The CONTRACTOR is responsible for the quality of materials and workmanship in
performance of the work.
2.2
Conflict of Information
25B
In the event of any conflict, inconsistency or ambiguity between the contract documents, this
Specification or any other specification and associated data sheets, or with any of the
applicable codes, standards and regulations the CONTRACTOR shall immediately inform the
COMPANY in writing and receive written clarification from the COMPANY before preceding
with the work.
Page 12 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Project Documents
76B
The following documents pertaining to the Andrew and Devenick Projects are related or
applicable to this Specification:
DEV-AAD-MP-DS-JPK-1055 /
DEV-DEV-MP-DS-JPK-1070
DEV-AAD-MP-SP-JPK-1056 /
DEV-DEV-MP-SP-JPK-1073
DEV-AAD-MP-DS-JPK-1075 /
DEV-DEV-MP-DS-JPK-1074
DEV-AAD-MP-DS-JPK-1095 /
DEV-DEV-MP-DS-JPK-1075
DEV-AAD-ME-SP-JPK-1096 /
DEV-DEV-MP-SP-JPK-1015
Revisions
2.3
26B
The latest issues for the relevant standards, codes, statutory regulations and specifications
referenced herein shall be applied to the work.
Referenced Documents
2.4
27B
It is the responsibility of the CONTRACTOR to ensure that he has received from the
COMPANY all specifications, etc which are referenced within applicable specifications to
enable him to understand and comply with all aspects of the work to be performed for the
COMPANY.
Codes and Standards
2.5
28B
The CONTRACTOR is responsible for the quality of the work and compliance with the
requirements
of
the
Specifications as listed.
applicable
International
Codes,
Statutory
Regulations
and
ANSI/AWS A4.3
ANSI/AWS A5.32
ANSI/AWS C5.3
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
ANSI/AWS Z49.1
2.5.2
ANSI/AWS QC1
BS 4515-1 (2004)
BS EN 288:9
BS EN 1043
BS EN 10045
BS EN 10204
BS EN 12074
BS EN 1435
Non-Destructive
Examination
of
Welds.
Radiographic
BS EN 14717
BS EN ISO 15609-1
2.5.3
BS EN ISO 9001
ISO 2504
ISO 3690
Page 14 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
ISO 5173
ISO 5580
ISO 6507-1
ISO 11699-1
Classification
of
Film
Systems
for
Industrial
Radiography
ISO 14731/FDIS
ISO 17636
ISO 17638
2.5.4
Others
80B
ASTM E1815-96
Page 15 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
3.1
General
29B
This document shall be read hereafter in conjunction with BS 4515-1; 2004 as clarified,
amended or supplemented below.
3.5 Contractor
See 1.3
3.6 Employer
For Employer read COMPANY
Add:
U
Page 16 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
BS 4515-1: 2004
Supplement
Page 17 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
BS 4515-1: 2004
Supplement
Whether
additional
NDT
methods for fillet welds apply.
All
changes
from
approved
weld
procedures/specifications shall be subject to
prior written COMPANY approval and, where
necessary and appropriate, to the successful requalification of WPS and/or welders.
Page 18 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
BS 4515-1: 2004
Supplement
Not applicable.
The
method
of
linepipe
manufacture, including seal
weld and longitudinal weld
details where these items are
present in CRA clad and lined
pipelines.
Not applicable.
Not applicable.
Whether
the
strength
contribution of the CRA layer
has been used in the design.
Not applicable.
aa
Not applicable.
ab
Not applicable
Page 19 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
BS 4515-1: 2004
Supplement
ac
Not applicable.
ad
Not applicable.
ae
Not applicable.
af
Not applicable.
ag
Not applicable.
ai
aj
Add:
ah
U
4.2
The items to be approved by the COMPANY are included in this Specification as additions or
clarifications or amendments to the appropriate Sections of BS 4515-1: 2004.
Clause
BS 4515-1: 2004
Supplement
Welding consumables to be
used.
Page 20 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
BS 4515-1: 2004
Supplement
Applicable.
Page 21 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
BS 4515-1: 2004
Supplement
Page 22 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
BS 4515-1: 2004
Supplement
Methods of attaching
removing thermocouples.
and
All
non-destructive
testing
procedures to be used.
aa
ab
ac
ad
ae
Page 23 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
BS 4515-1: 2004
Supplement
af
ag
ah
Joining
technique
and
equipment for brazing or
aluminothermic welding of
anode bonding leads.
ai
Refer to ah.
aj
As ah above.
ak
Not applicable.
al
Whether
grinding,
wire
brushing or filing of the internal
surface of CRA clad and lined
pipelines is permitted.
Not applicable.
am
Not applicable.
Not applicable.
an
ao
ap
Page 24 of 75
Not applicable.
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
BS 4515-1: 2004
Supplement
aq
Approval
of
welding
consumable
handling
and
storage procedure
ar
as
at
au
av
aw
ax
Method of
coatings
end
ay
az
ba
bb
Full scale
(H.3.1)
removing
bend
procedure
Page 25 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
EQUIPMENT
4B
Add
U
Page 26 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
WELDING PROCESSES
5B
Add:
U
General
6.1
32B
Mechanised and automatic welding processes are preferred and should be used whenever
possible for pipeline girth welding.
automatic gas metal arc welding (GMAW) which may include single, multi-torch, or tandemarc variants of the process and the use of cored wires.
If mechanised or automatic processes are proposed for main line welding, tie-in welding, or
multiple jointing of pipeline sub-assemblies, the bid shall include full details of the
processes to be used, the associated welding equipment, and the proposed area of
application.
For mainline welding applications, the proposal shall list the number of welding stations
(root pass to final capping pass) either on the firing line (offshore lay barge) or spool base
and detail the equipment and number of welders and other personnel required to operate
each station. Full details of the welding shelters shall also be provided.
Page 27 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Page 28 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
WELDING CONSUMABLES
7.1
6B
General
34B
Add:
U
The selection of electrodes, filler materials and wire/flux combinations shall be approved by
the COMPANY.
In principle, the yield strength of the weld metal should be selected to ensure that the yield
strength of the deposited pipeline girth welds overmatches the actual yield strength of the
parent pipe material. The deposited weld metal shall also meet the specified ductility,
toughness, and limiting hardness criteria in accordance with this specification.
The definition of a batch (lot) of consumables shall be that stated in 3.26.
7.1.1
A weld root chemical analysis shall be carried out on each welding procedure.
The
Add:
U
The storage and handling of welding consumables shall be in accordance with BP GIS 18012. A detailed consumable storage and handling plan shall be submitted for COMPANY
review and acceptance.
Shielding gases shall meet the requirements of BS EN ISO 14175 or AWS A5.32. Gases
shall be pre-mixed and bottled by the supplier and shall have certificates of compliance.
The certificates shall show the composition and dew point.
Subject to COMPANY approval, standard Ar/CO2 gases may be mixed at site.
7.2.1
Add:
U
Page 29 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
7.2.2
83B
Add:
U
Only the batches of consumables mechanically tested during qualification of the weld
procedure shall be used for production welding of the following pipeline types:
Add:
U
Each cast and batch of consumables for production welding shall be subjected to the
following tests during qualification of weld procedures:
1 set of weld metal CTOD (tests required only for pipelines with ECA based
acceptance criteria or if required by designer).
The testing shall be in accordance with Section 8.3. The results shall meet the levels
required for the relevant weld procedure(s) and if applicable the ECA.
Page 30 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
BUTT WELDS
8.1
General
36B
Welding procedure qualification test shall be carried out specifically for pipe, valve, flange
and fitting materials using contract materials or COMPANY approved equivalent materials.
The WPQT shall simulate the production welding and shall be undertaken as far as
practicable under site ambient conditions.
Add following third paragraph:
U
Repair weld procedure shall be required for each type of repair expected during production.
It is not necessary to make a full circumferential repair weld. It is only required to make
sufficient repair weld to provide material for mechanical testing.
Repairs shall comply with Figure 1 of BS 4515-1.
Single pass repairs are only permitted for cap defects.
Each repair type to be used in production shall be separately qualified e.g.
Cap repair.
Intermediate repairs (Repairs made with a different process during the course of
making the girth weld, e.g. SMAW repairs to an automatic root).
Individual repair weld procedure qualification excavations shall be limited to 300 mm.
Excavations shall be made to simulate those expected during production using the
appropriate profile and depth. Note: The excavation shall be mimicked and a drawing
included within the WPQT documentation package.
Add:
U
Repair welds and welding to forgings shall be made using low hydrogen welding
consumables/filler metals i.e. < 5ml/100g. Electrodes for SMAW shall be vacuum packed
and used in accordance with the manufacturers recommendations.
Page 31 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
8.1.1
The WPS shall incorporate the information required by BS EN ISO 15609-1, BS EN 288-9,
and the following:
Material manufacturer.
Arc energy.
Hot wire diameter, feed speed, current, and voltage (if applicable).
For multi-wire processes the following parameters shall also be specified on the WPS when
applicable:
Electrode spacing.
Page 32 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
For welding processes involving multiple heads, the COMPANY Welding Engineer may
require further parameters to be shown on the WPS.
8.1.3
Pipe, valves, flanges, and fittings from different manufacturers, or manufactured from
materials supplied from different sources or in different supply conditions, require separate
procedure qualification as detailed in 8.2.2 & 8.2.3, unless a material grouping is approved by
the COMPANY.
8.1.4
During weld procedure qualification, all relevant procedure data, irrespective of whether the
item is a listed essential variable, shall be captured and recorded. Sufficient information
shall be recorded to allow full replication of the procedure qualification welds. A record of
the data shall be kept for the purpose of aiding production and to assist with the diagnosis
of problems, but need not be formally entered on to the PQR, e.g. GMAW/PGMAW
machine slope-in settings.
The methods of measuring the welding parameters and the records to be kept shall be
agreed with the COMPANY Welding Engineer.
Following WPQT, the pWPS shall be revised to reflect the parameters recorded during
qualification. For each welding pass the values for current, voltage and travels speed shall
be recorded on the WPS by either:
Within the range recorded during WPQT, noting that transient and anomalous
values should not be used to establish the parameter range;
The final WPS shall state parameters for each pass. However, if fill passes (i.e. passes
other than root, hot pass and cap) have similar values, the parameters may be combined
on the WPS.
When a welding consumable or group of consumables is qualified to weld several different
components or pipe sizes, every effort should be made to ensure that the parameters
specified on the individual WPSs are common across the group of WPSs.
A WPS written with more than one supporting Procedure Qualification Record (PQR) shall
not permit optional processes, but shall specify the process for each pass.
Page 33 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Arc Energy
8B
The arc energy for each pass shall be calculated using the recorded values of current,
voltage and travels speed from the PQR without the addition of a percentage.
Arc energy shall be recorded for each pass on the PQR.
For multiple (electrically isolated) tandem electrode welding processes e.g. SAW or
PGMAW, the effective arc energy per pass shall be calculated as the sum of individual arc
energies for each electrode. For pulsed procedures, the effective arc energy shall be
calculated on the basis of RMS values.
Voltage and current shall be determined with calibrated meters and recorded for each pass
during WPQT welding using a suitable COMPANY approved monitoring equipment.
Note: Calculation of arc energy assumes each welding process has an efficiency of 1.
U
8.1.6
Records
89B
The details of each weld procedure shall be recorded. Forms used to record WPS and
WPQT details shall contain the relevant information. The format shall be subject to
approval by COMPANY.
The PQR documentation package for each WPS shall comprise:
As-run records.
NDT results.
Consumable certification.
The following data shall also be available if requested by the COMPANY Welding
Engineer:
Page 34 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
The approved WPSs and PQR packages shall also be available in a good quality electronic
format.
Period of Validity
8.1.7
90B
For new pipeline construction projects, new WPSs shall be prepared and qualified.
For the purposes of undertaking further work to an existing pipeline, a WPS may remain
valid indefinitely. The COMPANY Welding Engineer shall be consulted before re-using the
WPS.
Changes Affecting Qualification and Approval (Essential Variables) of butt welds
8.2
37B
Modified to Read:
U
The following restrictions apply to all welding procedure specifications in addition to those
given in BS EN 288-9 and BS 4515-1.
Page 35 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
ELECTRODE a
OR
FILLER
MATERIALS
Welding
b1
parameters
b2
b3i
b3ii
b4
b5
Preheat and p4
Interpass
Temperature
Add:
TRADE NAME
ANY CHANGE
Electrical stick-out
Any change exceeding 5mm
(SAW, GMAW/PGMAW,
GSFCAW)
Arc voltage
Any change outside the range
of the approved production
WPS
Wire feed speed
Any change outside the range
qualified
Welding current
Any change outside the range
of the approved
production
WPS
Travel speed
Any change outside the range
of the approved
production
WPS
Calculated value of arc Any change outside the range
energy
of the approved
production
WPS
Application of preheat
Any change.
8.2.1
Transfer of WPSs
91B
Welding procedures shall not be transferred from one CONTRACTOR or SUBCONTRACTOR to another without re-qualification.
Material Supply Condition
8.2.2
92B
Changes in the following material condition shall require re-qualification of the WPS:
8.2.3
Chemical Composition
93B
Page 36 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
CE IIW C
Pcm C
Mn Cr Mo V Ni Cu
6
5
15
Si Mn Cu Cr Ni Mo V
5B
30
20
60 15 10
Diameter
8.2.4
94B
The pipe diameter shall be within the limits shown in Table 8.1.
Table 8.1
U
<60.3
<60.3
60.3 to 323.9
323.9 to 610
D >610
>610
Weld Preparation
8.2.5
95B
For narrow gap welding, any change in bevel angle beyond 1, root face beyond 50%, or
root gap +0.5 mm, constitutes an essential variable. Any weld preparation with an included
angle of less than 20 shall be considered to be narrow gap welding.
For all other welding, any changes in bevel angle by more than 5, or variation in root
gap/root face by more than 50%, constitutes an essential variable.
8.2.6
Type of Joint
96B
Use or deletion of temporary, e.g. copper, backing rings or shoes shall be considered an
essential variable.
Change from a girth weld to a fillet weld shall constitute an essential variable. Fillet welds
shall be qualified separately.
The configuration, shape, and size of branch weld test pieces shall be the same as the
branch welds to be made in production.
The qualification of branch welds shall include an additional butt weld qualification to prove
the mechanical properties of the joint.
Page 37 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Filler Metal
97B
A change in batch number if consumable batch control has been specified (see
7.2.2).
Welding Machines
8.2.8
98B
The welding unit, power supply type, manufacturer, model number and software version
number shall constitute essential variables for semi-automatic, mechanised and automatic
welding.
8.2.9
Type of Current
9B
For pulsed welding, the type of current includes the pulse rate, pulse shape and maximum
and minimum current.
8.2.10 Preheat Temperature
10B
The use of rapid cooling of welds constitutes an essential variable unless simulated in
WPQT.
8.2.12 Time Interval
102B
For hydrogen controlled processes, an increase in the maximum time between completion
of the root pass and the start of the second pass shall not exceed the time lapse recorded
during the welding of the test piece.
8.2.13 Other Parameters
103B
Head angle, electrode spacing from top dead centre and direction of rotation for 1G
rotated welding.
Electrode spacing for welding procedures utilizing multiple electrodes e.g. tandem
wire SAW, or mechanized tandem wire or twin torch processes.
Page 38 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Destructive Testing
38B
Add:
U
The blanks from which the mechanical test pieces are machined may be cut from the
qualification weld using oxy-fuel gas cutting; but its dimensions shall be sufficient to allow
the material of the final machined test piece to remain unaffected by the heat from the
cutting operation.
Test specimens shall not be subjected to any elevated temperature degassing treatment.
The type and extent of mechanical testing shall be in accordance with Table 8.2. The test
piece locations shall be as shown in Figures 8.1 and 8.2.
Page 39 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
TYPE OF INSPECTION/TEST
Transverse Tensile Test
FULL PENETRATION
REPAIR
BUTT WELD
2 (diameters 323.9mm)
1h
Impact Test
4b,c,d
2b,c,d
Side Bends
2e
2e
Macro-examination and
hardness test
3f,g,h
1h
CTOD
3h,i
3h,i
NOTES:
a.
When an ECA is used to determine defect acceptance levels, a minimum of three all weld metal
specimens shall be taken.
b.
Additional sets of Charpy Impacts may be required by the COMPANY Welding Engineer. For example, if
very thick pipe is to be utilised or the combination of processes or consumables has not been adequately
sampled by the specified locations.
c.
For thicknesses greater than 20 mm, a total of 6 sets shall be required. The additional 2 sets shall be
taken from the outer surface (see Figure 3 BS 288-9).
d.
Impact testing is not required for pipe sizes below 60.3 mm diameter with thicknesses less than 12.7
mm.
e.
Side bends are only required for GMAW/PGMAW and GSFCAW (Vertically down) welding processes.
For Wt >25mm four side bends shall be conducted. For full and partial penetration repairs two side
bends are required.
f.
Additional macro-examinations and hardness tests are required for long seam T-intersections (see 8.3.3).
g.
For non-sour pipelines, the number of hardness surveys may be reduced (see 8.3.4).
h.
CTOD tests shall comprise a minimum of one set of weld metal and two sets of fusion line samples.
i.
Tests are only required for pipelines with ECA based acceptance criteria or if required by the pipeline
designer.
j.
Page 40 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
LOCATION OF TEST SPECIMENS FOR A FIXED POSITION GIRTH WELD PIPE FOR
U
UPWARDS WELDING
Key:
1 Area 1 for:
7
1
3
4
- 1 tensile specimen
2 Area 2 for:
- Impact test specimens (WCL, FL & FL+2mm)
- 1 macro test specimen
- Additional test specimens if required.
3 Area 3 for:
- 1 tensile specimen
4 Area 4 for:
- 1 macro test specimen
- 1 hardness test specimen
5 Area 5 for:
- AWT Specimens
6 Top for fixed pipe
7 Area 7 for:
- 1 macro test specimen
- 1 transverse tensile (>323.9mm)
- Impact test specimens (WCL, FL & FL +2mm)
8 Area 8 for:
- 1 transverse tensile (>323.9mm)
Figure 8.2
U
LOCATION OF TEST SPECIMENS FOR A FIXED POSITION GIRTH WELD PIPE FOR
U
DOWNWARDS WELDING
6
7
1
3
4
Page 41 of 75
Key:
1 Area 1 for:
- 1 tensile specimen
2 Area 2 for:
- 1 macro test specimen
- 1 hardness test specimen
- Side bends
3 Area 3 for:
- 1 tensile specimen
4 Area 4 for:
- Impact test specimens (WCL, FL & FL+2mm)
- 1 macro test specimen
- Additional test specimens if required.
5 Area 5 for:
- AWT Specimens
- 1 transverse tensile (>323.9mm)
6 Top for fixed pipe
7 Area 7 for:
- 1 macro test specimen
- 1 transverse tensile (>323.9mm)
- Impact test specimens (WCL, FL & FL+2mm)
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
8.3.1
104B
Add:
U
The results of all transverse weld tensile tests shall meet or exceed the specified
requirements for the pipe (base metal) with respect to specified tensile strength.
Transverse weld tensile specimens shall fail at a location within the HAZ or base metal.
Failure in the weld metal is unacceptable.
If base metals of different strength levels are used, then acceptance criteria shall be based
on the lower strength base metal.
8.3.2
Add:
U
The weld metal shall exceed the parent pipe SMYS by between 80 to 200MPa. Weld
metals exhibiting overmatching shall ensure this is not to the detriment of other mechanical
properties and shall be demonstrated through WPQT. Any large deterioration of properties
compared shall be cause for investigation by the CONTRACTOR and COMPANY Welding
Engineers. Weld metal overmatching shall be achieved at both room temperature and
maximum design temperature. The weld metal strength shall be considered in relation to
the actual pipe yield strengths when an ECA is used.
Macro-Examination
8.3.3
106B
Add:
U
Three macro-examination test pieces shall be taken from each WPQ. The locations shall
be at 12, 3 and 6 oclock (see Figures 8.1 and 8.2).
When girth welding SAW-welded linepipe, an additional macro-examination specimen shall
be extracted from the girth-weld at the T-intersection region between the girth weld and
seam weld.
All macro-examination specimens shall be polished to a metallographic (1m) finish and
etched in a 2-10% Nital solution, or other suitable COMPANY accepted etchant. The
etched specimens shall be thoroughly examined at 10 times magnification.
Page 42 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Hardness Testing
107B
Clarification:
U
All hardness testing shall meet the sour-service criteria as laid down in BS EN 288:9, Table
3. The parent material hardness shall not exceed the values permitted in the relevant
linepipe material specification.
Add:
U
1 - 2mm
t/2
1 - 2mm
NOTES:
1. Parent material indentations shall be at least 20 mm from the fusion line.
2. The first HAZ indentation shall be placed as close to the fusion line as possible. Further
indentations into the HAZ shall be separated by approximately 0.5 mm, however the minimum
Page 43 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
The macrophotographs shall show the position of each hardness indent and shall be
included in the PQR along with tabulation or diagram showing the result and location of
each indent. The maximum and minimum values shall be identified.
Impact Testing
8.3.5
108B
Clarification:
U
For gas pipelines the impact test temperature shall be no higher than minus 10C.
Clarification:
U
Impact tests shall be carried out in the fusion line + 2mm locations. The impact test
requirement for all pipe/bend/fitting/forging is 50J minimum average and 40J minimum
individual, for 3 specimens at the minimum design temperature.
Add:
U
8.3.6
Fracture toughness tests are only required for pipeline subject to an ECA, and shall be
conducted at minimum design temperature. The required minimum CTOD value shall be
0.15 mm unless otherwise justified through an ECA.
CTOD testing shall be undertaken in accordance with BS 7448 Parts 1 & 2 by a testing
laboratory specifically approved for CTOD testing by COMPANY.
Testing shall be based on the use of through thickness notched, single edge notched bend
(SENB) specimens (BS 7448 Part 1 paragraph 5.1) in the NP orientation, unless agreed
otherwise by COMPANY.
Test specimens shall be notched and fatigue cracked to sample the microstructures at the
weld centre line and in the coarse grained HAZ adjacent to the fusion line.
The number of valid test results employed to determine the characteristic CTOD of the
weld metal and HAZ microstructures shall comply with BS 7910 paragraphs K.2.3 and
7.1.5.5. This may require a greater number of CTOD specimens than listed in Table 8.2.
Page 44 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
The
The pre-crack tip is not more than 0.5mm from the fusion line.
8.3.7
Bend Testing
10B
Transverse root bend and side bend specimens shall be prepared and tested in
accordance with ISO 5173:
Specimens shall be of full material thickness and the root samples shall be nominally
25mm in width while the side bend specimens shall be nominally 10mm in thickness.
Testing shall not reveal any open weld defects greater than 3mm in length.
Tearing from the specimen edges up to a maximum length of 3mm shall be acceptable
provided that it is not associated with any weld defects.
Page 45 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
FILLET WELDING
9.1
Clarification: There are no additional NDT requirements to visual and MPE for fillet welds.
U
9.2
40B
Add:
U
Page 46 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
10.1
9B
General
41B
Add:
U
10.2
42B
Add:
U
Welder qualification tests shall be carried out on full diameter project pipe nipples. Test
welds shall be visually sealed at each end until at least the root bead and hot pass have
been completed around the full circumference.
All qualification welding shall be carried out in the presence of a COMPANY representative.
The COMPANYs decision on acceptance is final.
Welders shall weld at least 50% of the circumference of the test pipe.
Page 47 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Clarification:
U
The simulation of a fillet weld joint using flat plate welds shall not be permitted.
Add:
U
Procedures for welding and NDT of fillet welded attachments to pipelines shall be subject
to acceptance by the COMPANY.
The pipe area surrounding a fillet weld shall be tested for laminations using MUT up to a
distance of 100 mm surrounding the projected locations of the weld toes. Any laminations
found shall comply with the applicable project line pipe specification.
Where any fillet welds are to be made using multiple passes, the first pass shall be
deposited mainly on the pipe and the final weld pass shall not touch the pipe.
Completed fillet welds shall be examined by visual examination and MPE.
10.5
Modified to Read:
U
Non-Destructive Testing
45B
Add:
U
NDT of welder test-pieces for butt welds shall include visual examination, MPE. RE and
MUT/AUT if GMAW/PGMAW and GSFCAW (Vertical down) is used.
Where SMAW,
GTAW or SAW or GSFCAW (Vertical Up) is used visual examination, MPE, and RE shall
be used.
If the application of AUT for the inspection of pipeline girth welds has been agreed by
COMPANY, it may be used for the assessment of the welder qualification welds in place of
radiography. However, the acceptance criterion used shall be BS 4515-1 Table 6 and
section 13.1.2 of this specification, rather than an ECA based criterion.
Destructive Testing
10.7
46B
Add:
U
Page 48 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Page 49 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
PRODUCTION WELDING
10B
Add:
U
Any weld suspected of not having been produced in accordance with the accepted welding
procedure shall be cut out, and may be subject to investigation at the discretion of the
COMPANY.
11.1
Proximity of Welds
47B
Add:
U
The distance between pipeline girth welds shall not be less than twice the outside diameter
of the pipe.
The distance between pipeline girth and branch/attachment welds shall not be less than
one pipe diameter.
The distance between branch/attachment welds on the pipeline shall not be less than one
pipe diameter.
11.2
Add:
U
imperfections in the pipe ends to be repaired by grinding, prior to assembly for welding,
provided the remaining wall thickness is acceptable as confirmed by MUT.
If AUT is to be used, a reference line at a specified distance from the root face shall be
scribed onto the pipe surface to allow the exact location of the root bead to be identified.
Clarification:
U
On pipe which is to be cut back, a zone extending 100 mm from the proposed position of
the new field bevel shall be examined by VE, and MUT to check for laminations to the
requirements of the appropriate linepipe material specification.
Page 50 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Fusion Faces
49B
Add:
U
Surfaces contaminated with oil or grease shall be cleaned utilizing solvent. Degreasing of
base metal shall extend at least 50 mm from the edge of the fusion faces on both ID and
OD surfaces. All cleaning solvents shall be used from a suitable container, shall have all
necessary documentation available and be accepted by the COMPANY as HSE compliant.
Alignment
11.4
50B
Modified to Read:
U
Pipes shall be aligned with care. The alignment of abutting pipe ends shall minimize the
internal offset between surfaces. Any offset greater than 1.5 mm, provided it is caused by
dimensional variations within specified tolerances, shall be equally distributed around the
circumference of the pipe or fittings. Misalignment shall be reduced to a minimum by
rotation of the pipes to obtain the best fit.
Maximum misalignment shall be:
Add:
U
Modified to Read:
U
Powered internal alignment clamps shall be used for pipe-to-pipe butt welds. Where access
does not permit the use of an internal clamp for pipe-to-pipe welds, an external clamp shall
be used. For small diameters (<150 mm), the use of an external clamp may be proposed
for COMPANY acceptance. A welding sequence that distributes the stresses as evenly as
possible shall be used, e.g. two welders working diametrically opposite each other.
If an internal line-up clamp is used, the root run shall be 100% complete before the clamp
is removed. When an external line-up clamp is used, the root run shall be at least 50%
complete before the clamp is removed.
Page 51 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Internal line-up clamps shall not be removed until the completion of the root and hot pass.
Alternatively the CONTRACTOR shall present a case, supported by stress analysis, which
proves that a weld with only the root pass in place will not be adversely affected by
movement.
If an internal clamp incorporates a copper back-up bar, the backing bar shall be subject to
a full circumferential visual examination at least once every ten welds to ensure no fusion
of copper is taking place.
Add:
U
The COMPANY shall accept line-up methods for fittings and flanges.
Tack Welds
11.6
52B
Add:
U
All tack welds (if used) shall be deposited by qualified welders using low hydrogen welding
in accordance with an accepted welding specification. Where preheat is specified, it shall
be applied prior to tack welding and be effective over a distance equal to three times the
wall thickness or 75 mm whichever is the greatest and shall be maintained until the joint is
complete.
Alignment by tacking for fabrication welds, e.g. for pipe to flange joints, shall be subject to
the acceptance of the COMPANY. The following shall apply when tacking is used:
The preheat level required for the main WPS shall be applied for tacking and shall
be not less than 50C.
Page 52 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
The preferred method is bullet tacking. The bullets shall be made from compatible
linepipe material.
A minimum of four tacks shall be used for diameters >100mm. More tacks may be
required for diameters > 300mm.
All welding shall be confined to the weld preparation and not impinge on the root
area.
Tacks shall be removed by grinding as root welding progresses around the butt.
If tack welds are to be incorporated in to the final weld, they shall be at least 25mm
long and shall be thoroughly cleaned of slag and taper ground at each end to
ensure complete root continuity.
COMPANY may agree to waive MPE of the ground area following tack removal.
Stray Arcs
11.8
53B
Add:
U
The COMPANY shall have the option to require removal of weldments with more than one
arc burn from the pipeline.
Repair of parent material by welding is not permitted.
If blending to remove the effects of arc burns reduces the wall thickness below the
specified minimum, the defective pipe section shall be cut out and the pipe re-bevelled and
re-welded. Welding shall not be used to repair arc burns. For non-reeled applications, if a
nipple is used to replace the defective section, its length shall be at least two pipe
diameters.
Welding return cables shall be of sufficient cross-sectional area to prevent concentration of
current and shall be securely attached to prevent stray arcing. Attachment by welding shall
not be performed.
Clarification:
U
Areas showing stray arcs may only be repaired by mechanical removal of the defective
material and blending of the excavation. MPE together with confirmation that pipe or fitting
wall thickness is within specified tolerances shall be confirmed.
Page 53 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Weather Conditions
54B
Add:
U
When necessary, measures shall be taken, e.g. by covering the pipe ends, to prevent
water or other extraneous matter being channelled into the weld region.
The COMPANY shall decide if the protection given from the weather is adequate and that it
will not affect the quality of the completed weld.
11.10 Preheating and Post Weld Heat Treatment
5B
General
11.10.1
13B
Modified to Read:
U
Preheat and interpass temperatures shall be in accordance with the COMPANY approved
WPS.
As a minimum the preheat temperature shall be selected to ensure that:
The metal temperature is greater than 30C, or greater than 50C when moisture is
present on the pipe, or when the ambient temperature is below 5C.
The hardness requirement of Section 8.3.4 is met for the weld and HAZ.
If the weld is to be cooled rapidly to allow immediate AUT, this shall be simulated during
WPQT.
Assisted cooling shall not commence until the weld temperature has cooled
Preheating
14B
Add:
U
Page 54 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Add:
U
Thermocouples shall be attached to the pipe by the capacitance discharge method. After
use, the thermocouples junctions shall be removed by grinding and the area of attachment
shall be examined by MPE.
Page 55 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Add:
U
Procedures for cutting, joint preparation, setting-up, welding and NDT shall be subject to
COMPANY acceptance.
Forged fittings shall be used for branches and other pressure containing attachments
unless otherwise accepted by the COMPANY.
11.11.2
Spacing of Branches
16B
Add:
U
Refer to 11.1
11.11.4
Welding
17B
Add:
U
Where accessible and following completion of the full weld, the root bead shall be
ground flush on the inside of the pipe, its location clearly marked with indelible pen
and inspected by visual and MPE.
The full welds shall be examined with radiography using the SWE/SWV technique
with the film inside and radiation source outside, using a minimum source to film
distance of 600mm. A minimum of four equidistantly spaced separate exposures
shall be used for branches 150mm nominal bore. The DWE/SWV technique may
only be used if accepted by the COMPANY. In each event the centre radiation beam
shall pass through each weld region being tested at normal incidence to the weld
face.
The root bead and weld cap shall be examined by visual examination. Visual
examination of the root bore shall be undertaken through the bore of the fitting from
the outside of the pipe;
Weld caps shall be examined by MPE. Where access allows MUT shall be
undertaken from the inside surface of the fitting.
Page 56 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Add:
U
Contact tips shall not be fused into the weld metal. A visual inspection shall be undertaken
between weld passes to confirm no copper has been deposited.
11.13 Partially Completed Joints
58B
Add:
U
Offshore pipeline welds or welds on fittings, tie-in welds, or repairs shall not be allowed to
cool below the specified minimum preheat temperature before weld completion. No welds
shall be allowed to cool below preheat temperature before the completion four full
circumferential passes.
All welds shall be completed by continuous welding.
11.14 Fillet Weld Attachments
59B
Procedures for welding and NDT of fillet welded attachments to pipelines shall be subject to
approval by COMPANY.
The pipe area surrounding a fillet weld shall be tested for laminations using UT up to a
distance of 100 mm surrounding the projected locations of the weld toes. Any laminations
found (individual or cluster) shall not exceed a total area of 500 mm2. No lamination
regardless of size shall be permitted within 25 mm of the projected weld toes.
If any fillet welds are to be made using multiple passes, the first pass shall be deposited
mainly on the pipe and the final weld pass shall not touch the pipe.
Completed fillet welds shall be examined by VE and MPE.
11.15 Records
60B
Add:
U
All documentation required by this specification and BS 4515-1 shall be collated, indexed,
stored safely and presented to the COMPANY.
A log identifying, by number, each pipe or fitting and identifying the weld numbers joining
them to other items shall be compiled. Each circumferential weld (whether a field joint or
shop-made weld) shall be allocated a unique number, which shall be used for reference to
the weld in all reports, radiographs and test documents.
Quality records shall include the following:
Page 57 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Material certificates.
Consumable certificates.
WPSs.
Dimensional reports.
The above documentation shall be traceable back to individual weld numbers, where
applicable. The accepted WPS and PQR packages shall also be available in a good quality
electronic format.
Page 58 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
12.1
General
61B
Clarification:
U
Every pipeline weld shall be subject to individual examination and non-destructive test
using reliable, modern, and proven techniques, and shall be shown to meet the design
code acceptance criteria in all respects before the pipeline is put into service.
An ECA and CTOD tests are mandatory when pipeline installation is by reeling or S-Lay. For
the fabrication of spools CTODS and ECA is only required where the minimum design
temperature is lower than -46C and or thicknesses > 40mm. The use of an ECA shall not
be required on pipe diameters 6 and/or wt <10mm.
The use of narrow gap welding techniques (with an inclusive bevel angle 20) dictates
that AUT shall be required.
Each production butt weld shall be subjected to a visual (external), RT and supplementary
UT or AUT examination or a combination of both, unless otherwise agreed with the
COMPANY.
For wall thickness above 25 mm, AUT is the preferred NDT technique.
For manual or semi-automatic welding processes using a conventional bevel configuration,
one of the following NDT methodologies may be adopted subject to COMPANY review and
approval:
Where RT is the primary NDE method, MUT shall be used to supplement RT when
planar defects are detected during production welding. MUT shall be used to
establish defect size, height and position. An ECA (when required) shall be used to
develop the weld NDE acceptance standard taking cognizance of the NDE sizing
accuracy.
Page 59 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
accordance with GIS 43-339. The use of AUT is not permitted in place of radiography for
the following weld types:
MUT and MPE equipment and personnel shall be available at site for the full duration of
pipeline construction.
The COMPANY shall have the right to inspect or test any weld by non-destructive or
destructive means. This inspection may be made during the welding or after the weld has
been completed.
personnel in addition to any NDT undertaken by the CONTRACTOR. For example, the
COMPANY may choose to inspect welds by MUT.
On a pipe-laying barge, the weld shall not be moved past the weld repair station until the
interpretation of the radiograph and all other NDT is complete and the weld has been
judged satisfactory. Coating/ wrapping of a welded joint shall not begin until the weld has
been judged satisfactory, unless otherwise approved by COMPANY.
Clarification:
U
Completed welds may be ground when agreed with the COMPANY to facilitate NDT
provided the wall thickness complies with the minimum specified limit. Grinding shall
ensure no stress raisers and a smooth transition exists.
Page 60 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Personnel Qualification
62B
Modified to Read:
U
NDT personnel shall hold current Level 2 certification (or equivalent), specific to weld
testing, for the appropriate NDT methods to any of the following standards as a minimum:
ACCP (ASNT);
SNT-TC-1A (ASNT).
NDT personnel certificated to the requirements of a Written Practice under the rules of
SNT-TC-1A shall not be used, unless the Written Practice and the personnel certification
has been reviewed and accepted by COMPANY for the specific work.
Personnel engaged in AUT shall be qualified in accordance with GIS 43-339.
Radiographic Testing
12.4
63B
12.4.1 General
18B
Add:
U
Radiographic testing shall be conducted using X-ray equipment. Where the use of X-ray
equipment is impracticable, Iridium 192, Ytterbium 169 or Selenium 75 may be used
subject to acceptance by COMPANY. Other sources of gamma rays are not permitted.
Radiographic practice shall be in accordance with this specification and ISO 17636.
12.4.2 Approved Radiographic Procedures
19B
Add:
U
12.4.2.1 General
As part of the radiographic procedure qualification, test radiographs shall be produced
using each radiographic procedure planned for use; these shall be made on the welding
procedure qualification welds or welds made with the production WPS. The full
circumference of each test weld shall be radiographed.
Film type shall be ISO 11699-1 Class T2 or ASTM E1815-96 Class I, e.g., Agfa Structurix
D5 or Kodak Industrex T200, or finer grain (slower) film. Where it is shown that exposure
Page 61 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Exposure
conditions
(voltage,
current
and
duration,
Curie-minutes
and
Gigabecquerel-minutes);
IQI type and sensitivities, in percent of wall thickness, based on source-and film-side
indicators, respectively);
Film density;
Film overlap;
Archival life;
Page 62 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
SENSITIVITY REQUIREMENTS
U
THICKNESS
X RADIOGRAPHY
(1)
GAMMA RADIOGRAPHY
(mm)
SWSI
DWSI
DWDI
SWSI
DWSI
DWDI
4.5-6.0
2.0%
2.5%
3.2%
2.6%
2.7%
3.5%
>6.0-9.0
1.7%
2.0%
3.0%
2.4%
2.5%
3.2%
>9.0-14.0
1.5%
1.8%
Note 3
2.4%
2.5%
Note 3
>14.0-18.5
1.4%
1.7%
N/A
2.0%
2.2%
N/A
>18.5-26.0
1.3%
1.7%
N/A
1.7%
2.0%
N/A
>26.0-40.0
1.1%
1.7%
N/A
1.5%
1.8%
N/A
>40.0
Note 3
Note 3
Note 3
Note 3
Note 3
Note 3
Note 1 - Thickness for SWSI and DWSI is estimated for a single weld thickness
Note 2 - Sensitivity shall be no worse than the values given in this table. Sensitivity shall be
calculated using the formula:
Page 63 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Page 64 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Weld number.
Material grade.
Date.
WPS number.
Page 65 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Add:
U
For the main production pipeline and when agreed with the COMPANY, radiographic film
shall be digitized using methods that give adequate resolution and stored in electronic
media in an agreed manner with the COMPANY.
All radiographic film shall be dried thoroughly prior to viewing and shall be processed to
allow storage of the film without deterioration for a minimum period of 5 years
At the discretion of COMPANY, the radiographic CONTRACTOR shall satisfactorily
demonstrate that the film can be processed, using the site facilities, to have a fog level not
greater than 0.3.
One radiograph in every 100 shall be subjected to a residual thiosulphate test, to ensure
that the film has been suitably processed for 5 years storage.
shall form part of the radiographic procedure package for COMPANY approval.
Radiographs shall be stored in an environment that will not detrimentally affect the
radiographs. Boxes shall be used to store radiographs in multiples of 25, 50 or 100 welds.
The weld numbers that apply to the stored radiographs that each box contains shall be
clearly visible on each box.
12.5
12.5.1 General
12B
Add:
U
MUT shall comply with the requirements of ISO 17640. Specifications for MUT procedures
shall define the following:
Type of UT equipment;
Range of frequencies;
Method of calibration;
Surface requirements;
Coupling medium;
Examination techniques;
Page 66 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Reporting requirements;
Add:
U
Discontinuity indications having a amplitude above the reference level shall be assessed
against the requirements of Table 6 of BS 4515-1 and the following:
Linear indications (other than cracks) interpreted to be open to the surface are
unacceptable if they exceed a length equal to the wall thickness but not exceeding
25mm in total length in continuous 300mm length of weld or 8% of the weld length;
Linear indications interpreted to be buried within the weld are unacceptable if they
exceed a length equal to but not exceeding 50mm in total length in a continuous
300mm of weld or 15%of the weld;
Individual defects with a height greater than one pass height (determined after
reviewing a macro-section from the main line WPQT) but not greater than 4mm and
before interaction assessment shall not be permitted.
12.6
65B
Add:
U
The use of automatic ultrasonic testing shall be subject to COMPANY approval in each
instance. The qualification of the AUT procedures and production testing shall comply with
GIS 43-339.
12.7
Add:
U
Magnetic particle testing shall comply with the requirements of ISO 17638.
The non-fluorescent wet method of MPE using white contrast paint and an AC yoke (110V)
shall be used. Dry powder MPE may be used for repair groove inspection. The AC yoke
shall be capable of lifting 4.5 kg at 150 mm pole spacing. Poles shall make maximum
contact with the test surface during inspection. DC prods shall not be used.
Page 67 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Page 68 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
13.1
13.1.1 General
123B
Add:
U
The acceptance standards defined in Section 13.1.2 below shall be the minimum
requirement in which radiography is the primary NDT method. Where manual or semiautomatic welding processes are adopted with a conventional bevel configuration and RT is
the primary NDE method, MUT shall be used to supplement RT when cracks or planar
defects are detected during production welding. MUT shall be used to establish defect size,
height and position.
If the use of AUT has been approved by COMPANY, Section 13.1.2 below shall be
augmented by an ECA in accordance with BS 7910 (Level 3) to determine flaw dimensions
and acceptance levels which shall be subject to COMPANY approval (refer to Section
13.1.3 of this specification).
When unacceptable flaws occur in more than five consecutive welds or when, in the
opinion of the COMPANY, a particular flaw type becomes repetitive in terms of its size
and/or location, the cause of the flaws will be investigated by the Welding Engineers
working on behalf of the CONTRACTOR and the COMPANY. If necessary, welding will be
terminated until the cause of unacceptable flaws has been established and satisfactorily
resolved.
13.1.2 Acceptance Criteria Based on Quality Control
124B
Add:
U
In areas of weld preparation such as pipe ends, fusion faces and branches, planar defects
are not acceptable.
Add:
U
(BS 4515-1 Table 6f): The maximum length of incomplete penetration, lack of cross
penetration or lack of root fusion in any continuous 300mm weld length is limited to but not
exceeding 25mm.
Add:
U
(BS 4515-1 Table 6I) The maximum length of inter run fusion and lack of side fusion in any
continuous 300mm weld length is limited to but not exceeding 50mm.
Page 69 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
(BS 4515-1 Table 6g) Cracks or crack like defects are unacceptable. In the event that such
defects are detected the complete weld shall be cut from the pipeline and the cause of the
cracking shall be established to the satisfaction of the COMPANY.
Add:
U
(BS 4515-1 Table 6k) Tungsten inclusions Tungsten inclusions shall not exceed two per
weld and shall be separated by a minimum of 50 mm. The maximum dimension of a
tungsten inclusion not to exceed 3mm or 50% of the wall thickness, whichever is smaller.
(BS 4515-1 Table 6k) Copper inclusions are not permitted.
13.1.3 Acceptance Criteria Based on Engineering Critical Assessment (ECA)
125B
Add:
U
The use of alternative acceptance standards for girth welds shall be subject to COMPANY
approval before contract award. The ECA method and testing shall be proposed for
COMPANY approval before the commencement of WPQT.
The output of the ECA shall be used to develop the weld NDT acceptance standard. The
weld acceptance standard shall include an appropriate NDT sizing allowance (see GIS 43339) which shall be clearly documented. In addition to the limits derived from the ECA, the
following restrictions on defect size shall apply:
Irrespective of defect height, defects with a length greater than 7 times wall
thickness (after interaction assessment) shall not be permitted.
The COMPANY reserves the right to modify the ECA acceptance criteria.
Add:
U
Any weld suspected of not having been produced in accordance with the approved welding
procedure shall be cut out, and may be subject to investigation at the discretion of the
COMPANY.
Page 70 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Rectification of Welds
68B
Add:
U
A WPS for repair welding shall be in accordance with Section 8 of this specification.
Defects shall not be repaired in any part of the weld without prior acceptance by the
COMPANY. All repairs shall be witnessed by the COMPANY, and the relevant NDT
records shall be made available to COMPANY at that time.
Internal weld repairs shall not be permitted except for pipe-to-fitting welds where the repair
can be undertaken from the open end of the pipe or fitting, subject to successful welding
procedure qualification.
No more than two separate repairs are allowed in any single weld.
Welds with cracks (other than small crater cracks 4 mm in length) shall be removed from
the pipeline. The welding procedure shall be suspended until the cause is identified and
remedial measures implemented to prevent further occurrence. Production welding with the
suspended WPS shall only recommence following acceptance from COMPANY Welding
Engineer.
Small crater cracks shall be removed by local grinding and repaired.
For repair of arc burns, see 11.8.
13.2.2 Preparation for Re-Welding
128B
Add:
U
The minimum allowable repair length shall not to be less than 50 mm at the bottom of the
groove. Metal may be removed by thermal gouging followed by grinding. Grinding shall be
used for the last 3 mm through to the root. Air-arc gouging shall be controlled by a
procedure documenting the allowed variables as required by AWS C5.3.
If there are significant loads or deformation at the weld repair station, verified calculations
justifying the excavation size shall be submitted for COMPANY approval.
13.2.4 Re-Welding
129B
Add:
U
Internal weld repairs shall not be permitted except for pipe-to-fitting welds where the repair
can be undertaken from the open end of the pipe or fitting, subject to successful welding
procedure qualification.
Page 71 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
Mimic taken of repair profile and sketch included detailing (depth, position relative to
original weld, width and length of excavation);
Date of repair.
Page 72 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
H1
69B
Introduction
This section applies to pipelines subject to plastic deformation during installation, e.g.
installation by reeling.
When evaluating the amount of strain at the weld expected during installation, the effects of
misalignment, pipe strength variation, and coating stiffness shall be considered.
H.2
70B
General
H.2.1 Linepipe
130B
Pipelines welded in accordance with this appendix shall use linepipe that complies with the
additional high strain requirements of GIS 43-311, GIS 43-312, or GIS 43-313.
H.2.2 Welding Processes
13B
Welding processes not previously used by the CONTRACTOR with the proposed
installation method shall require full scale qualification trials. The extent of the trials shall be
determined by COMPANY.
Only low hydrogen processes shall be used.
H.2.3 Welding Consumables
132B
The consumable selection shall be approved by COMPANY and the consumable should
have a track record with the selected installation method.
The batch testing of weld consumables described in 7.2.2 shall be undertaken for each
batch of welding consumables not tested in the welding procedure qualification.
Additionally:
-
The minimum Charpy energy shall be 70J at the impact test temperature.
The yield and UTS of the test weld shall exceed the maximum exhibited yield and
tensile properties of the production pipe.
H.3
71B
H.3.1 Simulation
13B
The weld procedure qualification welds shall be subjected to full scale bending at the
maximum strain predicted during installation. The number of cycles shall be determined
from the number of cycles required for installation, plus any contingency operations and
Page 73 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
The type and number of welds. Each qualified WPS shall be included in the trial
test piece;
The length of the test string and the spacing of the welds;
The calculated maximum strain (based on the carousel & pipe diameters);
If a successful track record using the same vessel to install pipe of similar properties with
similar welding procedures can be demonstrated; then, at COMPANYs discretion, the full
scale trial may be omitted. The spool base, the time between cycles, and the temperature
shall be considered when evaluating existing data.
H.3.2 Non-Destructive Testing
134B
The weld procedure tests shall be subjected to the visual and non-destructive testing
specified in Section 8 of this specification before and after straining.
H.3.3 Mechanical Testing
135B
The strength of the welds shall be greater than the strength of the production pipes;
however, excessive overmatch should be avoided.
H.3.3.1 Evaluation of Weld Procedure Bending Trial Welds
136B
The welds shall undergo the mechanical testing specified in Section 8 of this specification.
However, the transverse tensile locations shall be rotated so that the test pieces are
removed from the cardinal points. It is anticipated that this will ensure that the areas
undergoing maximum straining will be tested.
H.3.3.2 Evaluation of Weld Procedures Waived Bend Trial
137B
When the full scale trial is waived, the weld procedures shall be subject to the full testing of
Section 8 of this specification plus the following strain aged testing. Weld coupons shall
Page 74 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2
1 macro-examination + hardness;
The testing shall be undertaken in accordance with Section 8 and the results shall meet the
requirements of Section 8 of this specification; however, any large deterioration of
properties compared with the unstrained specimens shall be cause for investigation.
H.4
72B
Production Welding
The maximum permitted pipe misalignment at the weld shall be 1.5 mm unless larger
misalignments are demonstrated to be tolerable and are agreed by COMPANY.
Page 75 of 75
DEV-AAD-MP-SP-JPK-1058 Rev B2
DEV-DEV-MP-SP-JPK-1072 Rev B2