0% found this document useful (0 votes)
74 views8 pages

Terminal Inst & Commissioning Forms

The document provides forms for capturing installation and configuration data for new Eclipse terminal installations, including: 1) An Eclipse Terminal Installation and Configuration Form to record terminal details, networking configuration, link/radio parameters, tributary configuration, auxiliary port configuration, grounding checks, and sign-offs. 2) An Eclipse Terminal Installation Inspection Report checklist to document the inspection of antenna, ODU, IDU, cabling, grounding, and site cleanliness. 3) An Eclipse Terminal Customer Acceptance Form to document customer receipt of installation documents. The forms provide fields for planning data to prepare for installation, as-built data recorded at the site, and comments. Instructions are included to

Uploaded by

Gossan Anicet
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
74 views8 pages

Terminal Inst & Commissioning Forms

The document provides forms for capturing installation and configuration data for new Eclipse terminal installations, including: 1) An Eclipse Terminal Installation and Configuration Form to record terminal details, networking configuration, link/radio parameters, tributary configuration, auxiliary port configuration, grounding checks, and sign-offs. 2) An Eclipse Terminal Installation Inspection Report checklist to document the inspection of antenna, ODU, IDU, cabling, grounding, and site cleanliness. 3) An Eclipse Terminal Customer Acceptance Form to document customer receipt of installation documents. The forms provide fields for planning data to prepare for installation, as-built data recorded at the site, and comments. Instructions are included to

Uploaded by

Gossan Anicet
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 8

Aviat Networks

Eclipse Terminal Installation and Commissioning Forms


Ver 1.3 June 2010

Introduction
Purpose is to provide:

A prompt for preparing data for new installations.

A datapack for installers.

A data entry form to capture additional as-built data.

An as-built record with sign- off.


Associated forms included in this file are:

Installation Inspection Form

Customer Acceptance Form

Remedial Action Form


Navigation:

The Master Site Data column lists entries required. Click on a


+ tab at the far left of the screen to open up required data
entry rows. Click tab to close.

The Build / As-Built Data column is for data entry. Build data
is data to be entered at the planning (datapack prep) stage. Asbuilt data is data to be entered at site, mostly from Portal.

The Portal column highlights the data to be entered


and data to be entered from Portal.

The Comments column is to capture any additional data.


See the Example Form for additional guidance.
Forms can be printed.
Forms can be user-customized to support more, or less data.
Important! Please provide feedback on the use of these forms.
Feedback is needed to provide guidance on what improvements should
be made to assist the application and usability of these forms. Please

Eclipse Terminal Forms: V1.3 June 2010

Commercial-In-Confidence

Aviat Networks

Eclipse Terminal Installation and Configuration Form


Installer:
Installer Contact Details:
Scheduled Start Date:
Scheduled Completion Date:
New or Existing Site:
Electrical Supply OK yes/no:
Site Grounding OK yes/no:
Antenna Mounts OK yes/no:
Site Security OK yes/no:
Site Plans Included yes/no:
Master Site Data
Terminal
IDU type
ODU type
Terminal name
Site name
Site grid reference
Tech services contact details
NOC contact details
Site location
Site access
Rack number/name
IDU location in rack
Chassis serial number
-48Vdc power supply connection

For Site:
General Instructions:

Build / As-Built Data

Portal
Entry
/
To To
= Enter into Portal
Record
From = Enter from Portal
From
To

Comments

To
To
To
To

See attached map

(All serial numbers begin with three letters)

Networking
Terminal IP address
Subnet mask
Static or dynamic routing
Static routing data
DHCP yes/no; address range
Trap destinations

To
To
To
To
To

Link/Radio
Link name/number
Remote end site name
Remote end terminal/node name
Local antenna type
Local antenna diameter
Antenna serial number
Height on tower / pole mount ID
Initial pointing (compass/map ref)
Polarization
ODU direct mounting, yes/no
ODU serial number
ODU cable length required
Protected yes/no
Link protection type
Trib protection type (TT or TA)
Tx frequency
Rx frequency
T/R spacing
Tx power
Detected forward power
Capacity
Modulation
ATPC yes/no
ATPC data
Expected RSL
Indicated RSL
Expected RSSI
Indicated RSSI
Expected fade margin
Measured fade margin
G.826 link check
Alarms check
Performance check

To
To
To

To
To
To
To
To
To
To
From
To
To

From
From
From
From
From
From

E1 Tributaries
DS1 Tributaries
STM1/OC3 Tributary
Ethernet Ports
Mode of operation
Channel 1 capacity
Channel 2 capacity
Terminal I+C Form: V1.3 June10

To
To
To
Commercial-In-Confidence

Aviat Networks
Duplex & speed
MdiX
Priority mapping
Flow control yes/no
Disable address learning y/n
Max frame size
Enable link status propagation y/n
VLAN tagging
Link aggregation
RWPR settings
Port names
Ethernet Ports

To
To
To
To
To
To
To
To
To
To
To

AUX
Auxiliary port
Type, port settings, name
Circuit name
Alarm I/O
Alarm actions

To
To

Date/Time
(Specify Date/Time setting)

To

BER Circuit Checks


Trib-trib BER check
(Specify the trib[s] and period)

From

Ethernet Link Checks


Summarize the tests applied and the
results
Alarms exit check
Active alarms yes/no

From

Ground checks
Single point bldg ground y/n
Master Ground Bar resistance
Rack to MGB resistance
-48V PSU to MGB resistance
Tower ground resistance(s)
Other resistance readings
Meter used
Site Inspection Report completed
yes/no
Hardware Installation completed
Name:
Signature:
Date:

Node Installation & Tests completed


Name:
Signature:
Date:
Completion Comments

Terminal I+C Form: V1.3 June10

Commercial-In-Confidence

Aviat Networks

Eclipse Terminal Installation and Configuration Form


Installer:
Installer Contact Details:
Scheduled Start Date:
Scheduled Completion Date:
New or Existing Site:
Electrical Supply OK yes/no:
Site Grounding OK yes/no:
Antenna Mounts OK yes/no:
Site Security OK yes/no:
Site Plans Included yes/no:
Master Site Data
Terminal
IDU type
ODU type
Terminal name
Site name
Site grid reference
Tech services contact details
NOC contact details
Site location
Site access
Rack number/name
IDU location in rack
Chassis serial number
-48Vdc power supply connection

Networking
Terminal IP address
Subnet mask
Static or dynamic routing
Static routing data
DHCP yes/no; address range
Trap destinations
Link/Radio
Link name/number
Remote end site name
Remote end terminal/node name
Local antenna type
Local antenna diameter
Antenna serial number
Height on tower / pole mount ID
Initial pointing (compass/map ref)
Polarization
ODU direct mounting, yes/no
ODU serial number
ODU cable length required
Protected yes/no
Link protection type
Trib protection type (TT or TA)
Tx frequency
Rx frequency
T/R spacing
Tx power
Detected forward power
Capacity
Modulation
ATPC yes/no
ATPC data
Expected RSL
Indicated RSL
Expected RSSI
Indicated RSSI
Expected fade margin
Measured fade margin
G.826 link check
Alarms check
Performance check
E1 Tributaries
Bal or Unbal
No. tribs req.
Trib names
Circuit names
Connect to
E1 Tributaries

Terminal I+C Form V1.3 June10

For Site: Plaza

Joeseph Brown
021 362 700
15-Sep-05
18-Sep-05
Existing
Yes
Yes
Yes
Intruder alarm has been disabled
Yes
Build / As-Built Data

IDU 20x
ODU 300hp
E116
Plaza
Eastxxx Southxxx
021 362 701
021 362 702
10km East of Masterton
Off Murrays Road
1A
Directly under terminal E10
LES00934567
Provide and install 5A Cct Breaker on supply
panel at top of rack

General Instructions: 4-wheel drive access only. This time of the


year the track will be wet and slippery. Please do a battery check
and run the back-up diesel generator for about 30 mins and check
associated panel lights. Should all be green.

Portal
Entry
/
To To
= Enter into Portal
Record
From = Enter from Portal
From

Comments

To
To
To
To
To
See attached map

(All serial numbers begin with three letters)

192.168.11.1
225.225.255.0.
RIP 2
N/A
Yes, 192.168.11.2 to 192.168.11.10
N/A

To
To
To

Plaza-Weston
Weston
E109
VHLP2-180-EX
0.6M
AN35239
28M
183 degrees
Vertical
Yes
SNA7687988
40m
No
N/A
N/A
17.85 GHz
18.25 GHz
400 MHz
17 dBm
17.1 dBm
20xE1
16 QAM
No

To
To
To

To
To

To
To
To
To
To
To
To
From
To
To
To

-51 dBm
-50 dBm
1.25
1.27
35 dB
37 dB
Zero errors over 14 hours
No active alarms
All indications normal

From
From
From
From
From
From

Unbal
18
Pla/Wes 1 - 18
Pla/Wes 1 - 18
Rack BNC panel: ports 1 to 18

Commercial-In-Confidence

To
To
To

Aviat Networks

Master Site Data

Build / As-Built Data

DS1 Tributaries
STM1/OC3 Tributary

Portal
Entry To /
Record
From

Comments

Ethernet Ports
AUX
Auxiliary port
Type, port settings, name
Circuit name
Alarm I/O
Input 1, active condition

Sync, default, Aux Plaza/Weston


Bel/Lak

To
To

Digital input, active high

To

Input 2, active condition


Output 1, active condition
Output 2, active condition
Output 3, active condition
Output 4, active condition
Alarm I/O
Alarm actions
Destination IP address, slot, and output. 192.168.2.1, slot 4, output 2.
Trigger(s).
AUX alarm input 1.

To
To
To
To
To

Destination IP address, slot, and output.


Trigger(s).
Destination IP address, slot, and output.
Trigger(s).
Destination IP address, slot, and output.
Trigger(s).
Destination IP address, slot, and output.
Trigger(s).
Alarm actions

To

To

To
To

Sync to Portal PC Date/Time

BER Circuit Checks


Trib-trib BER check
(Specify the trib[s] and period)

BER check completed on trib 2 to Weston. No


errors over 12 hours.

From

Alarms exit check


Active alarms yes/no

No active alarms

From

Other resistance readings


Meter used
Hardware Installation completed
Name:
Signature:
Date:

At commissioning check that the destination


output (bell) at Belmont activates when the
intruder alarm is activated. Also check that the
alarm event is raised at the NOC.

To

Date/Time
(Specify Date/Time setting)

Ground checks
Single point bldg ground y/n
Master Ground Bar resistance
Rack to MGB resistance
-48V PSU to MGB resistance
Tower ground resistance(s)

Wire to intruder alarm: alarm is active when circuit


is broken.

To

Yes
0.62 ohms
0.15 ohms
0.27 ohms
Not possible to measure. Cannot get meter jaws
around the ground straps.
Prova clamp-on, model DX

Serial number 00458

Joe Brown
18 September 2005

Node Installation & Tests completed


Name:
Signature:
Date:

Joesphine Brown

Completion Comments

Road access is OK.


Shelter door hinges very corroded.
Checked diesel generator & all OK

Terminal I+C Form V1.3 June10

18 September 2005

Commercial-In-Confidence

Aviat Networks

Eclipse Terminal Installation Inspection Report

For Site:

Check for correct and complete installation of:


Item

Pass

Fail

Comments

Antenna Mounting
Antenna side support (if used)
ODU fastening
ODU grounding
ODU connector weatherproofing
ODU cable fastening
ODU cable grounding
Lightning surge suppressor(s)
IDU location in rack
IDU is labelled (if required)
IDU grounding
IDU power supply wiring
Trib cables are correctly and neatly installed
Trib cables are numbered (if required)
Alarms all-clear
Site left clean and tidy
Site photos taken (if required)
Site ground measurements (if required)
Checked by:
Name:
Signature:

Date:
Additional Comments:

Terminal Inst. Insp. Report: V1.3 June10

Commercial-In-Confidence

Harris Stratex Networks

Eclipse Terminal Customer Acceptance Form


Site Name:
Eclipse Terminal Name:
Related documents

Received Yes/No

Eclipse Installation and Commissioning Form:


Eclipse Installation Inspection Report:
Acceptance Category*

Category

Accepted / Conditionally Accepted / Not Accepted:


*If conditionally accepted or not accepted, the action required to
achieve acceptance must be detailed in a Remedial Action Form

Signed By:
Customer
Name:
Signature:
Title:
Date:
Stratex Networks
Name:
Signature:
Title:
Date:

Terminal Acceptance Form V.1.3 June10

Commercial-In-Confidence

Aviat Networks

Eclipse Terminal Remedial Action Form


Site Name:
Eclipse Terminal Name:
Item No.

Description of Remedial Action Required

Responsibility

Signed As Completed
Customer
Name:
Signature:
Title:
Date:
Stratex Networks
Name:
Signature:
Title:
Date:

Terminal Remedial Action Form V1.3 June10