Potash Environmental Review Document Revised Final
Potash Environmental Review Document Revised Final
Potash Environmental Review Document Revised Final
Prepared for:
Port Metro Vancouver
100 The Pointe
999 Canada Place
Vancouver, British Columbia
V6C 3T4
Submitted by:
Andre Olivier, P.Eng.
Manager, Engineering and Environment
Pacic Coast Terminals Co. Ltd.
2300 Columbia
Port Moody, British Columbia
V3H 5J9
Prepared by:
Andrew MacKay, M.E.S., EP
Envirochem Services Inc.
#206 - 267 West Esplanade
North Vancouver, British Columbia
V7M 1A5
April 30 , 2014
i
PCT Potash Handling System Project Environmental Review Document
EXECUTIVE SUMMARY
This document was prepared as a requirement of the Port Metro Vancouver project permitting
process. It includes project rationale, an overview of existing conditions, proposed installation
details, environmental controls during construction and operations, communications and steps
taken to protect First Nations cultural heritage. The document was prepared through a
collaborative effort among the following organizations:
PCT has been in operation at the Port Moody site since the early 1960s. To date, a wide variety
of commodities have been safely transferred from land to vessels bound for international
markets. However, since the 2004-2007 period, tonnage handled of key commodities,
Monoethylene Glycol (MEG) and Sulphur, have declined 40% and 64% respectively. To ensure
future viability of the terminal, PCT decided to expand operations including the proposed
Potash handling system.
The PCT/KSPC Potash handling system will be a vital link in the potash supply chain that begins
with the $4.1 Billion mine in Saskatchewan, ending in export markets world-wide. Three grades
of Potash will be introduced to the stable, low risk operating environment at PCT.
The proposed project will be preceded by several separately permitted site improvements
including water management system upgrades (e.g., clarifier installation) and decommissioning
of the secondary settling pond. After backfilling, the former pond area will be the location of
the Potash storage building. In summary, the proposed Potash handling system project will
involve installing and operating the following key assets:
New railcar bottom dumper building including below ground dumper vault, indexer and
two dedicated high efficiency baghouses for dust control;
A new conveyor network beginning at the railcar bottom dumper tunnels to the
proposed Potash storage building. Dust will be controlled by new conveyor transfer
point baghouses. Additionally, conveyors will either be covered or fully enclosed (e.g.,
within a tube). The existing Shiploading conveyor from the proposed building to Berth II
will also be covered;
ii
PCT Potash Handling System Project Environmental Review Document
A new fully enclosed 160,000 MT Potash storage steel/wood building, with two new
automated stacker/reclaimers and a two way belt system for optimal commodity
handling efficiency. Rip rap will be installed in the foreshore to provide lateral support
for the Potash building while also preventing shoreline erosion.
Water treatment system upgrades including isolated drainage systems separating
potash from sulphur and installation of a new settling and aeration basin and a water
storage tank system. Rail track re-alignment in the main yard extending west to Reed
Point Marina. Careful designs were prepared to minimize disturbance to existing utilities
and foreshore habitat.
Modification to the existing Berth II quadrant shiploader with three new chutes and
chute support towers. Two new baghouses will be installed for dust control on the
shiploader, one each for the transfer conveyor and the spout.
Installation of two new substations that provide additional electrical power drawn from
BC Hydro grid for the Potash handling system.
PCT enjoys a positive relationship with the local community which continues to built-up
operational excellence, innovative design and honest two-way communication. That approach
has been carried forward to the proposed Potash handling system where project planning has
strived to achieve a balance between economic, operational efficiencies and facilitating
highest and best land use while preventing or minimizing environmental, social or cultural
impacts. From creating jobs, boosting local commerce to dust control, protecting foreshore
habitat and First Nations heritage preservation, PCTs proposed $170 million Potash handling
system clearly supports the PMV Vision for an efficient and sustainable Gateway.
Page iii
TABLE OF CONTENTS
1.0
INTRODUCTION .................................................................................................................... 1
2.0
3.0
3.1
3.2
3.3
3.4
3.5
3.6
4.0
PROPOSED PROJECT........................................................................................................... 11
4.1
4.1.1
4.1.2
4.1.3
4.1.4
4.1.5
4.1.6
4.1.7
Substations.............................................................................................................. 30
4.1.8
4.2
Project Schedule............................................................................................................. 31
4.3
4.4
5.0
5.1
5.1.1
5.1.2
5.1.3
5.1.4
5.1.5
5.1.6
Page iv
5.1.7
5.1.8
5.1.9
Traffic ...................................................................................................................... 51
5.2.1
5.2.2
Water Management................................................................................................ 59
5.2.3
5.2.4
Noise ....................................................................................................................... 60
5.2.5
5.2.6
6.0
7.0
COMMUNICATIONS OVERVIEW......................................................................................... 68
8.0
CONCLUSION ...................................................................................................................... 69
Page v
LIST OF FIGURES
Figure 1. Pacific Coast Terminals Location, Port Moody Arm, Port Moody, BC ............................ 1
Figure 2. Potash Supply Chain Summary ....................................................................................... 4
Figure 3. City of Port Moody Land Use Map .................................................................................. 6
Figure 4. Typical Section of Decommissioned Secondary Settling Pond ....................................... 9
Figure 5. Potash Handling System, Railcar Unloading, Potash Storage and Transfer to Ship ..... 11
Figure 6. Potash Handling System-Ship Loading .......................................................................... 12
Figure 7. Site Plan - Main Facilities .............................................................................................. 12
Figure 8. Site Plan, Extension of Y-Track to Accommodate Empty Rail Cars ............................... 13
Figure 9. Potash Unloading Area, Plan View ................................................................................ 14
Figure 10. Potash Unloading Area, Sectional View ...................................................................... 15
Figure 11. Unloading Area Underground conveyor tunnels ........................................................ 16
Figure 12. Conveyors Feeding the Potash Building, Plan View .................................................... 17
Figure 13. Above Ground Conveyors, Model View ...................................................................... 17
Figure 14. Potash Storage Building, Plan View ............................................................................ 18
Figure 15. Potash Storage Building, Section ................................................................................ 19
Figure 16. Potash Storage Building, Model View from North ..................................................... 19
Figure 17. Potash Storage Building, Model View from West....................................................... 20
Figure 18. Typical Staker/ Reclaimer Cross Section ..................................................................... 21
Figure 19. Ship Loader and Spout Storage Rack .......................................................................... 22
Figure 20. Track Y Extension from PCT to Reed Point Marina ..................................................... 23
Figure 21. Section at Retaining Wall ............................................................................................ 23
Figure 22. Section at Rip Rap Slope ............................................................................................. 24
Figure 23. Preliminary Layout (Plan) of Barge Landing Area ....................................................... 25
Figure 24. Preliminary Layout (Sections) of Barge Landing Area ................................................. 25
Figure 25. Modified Drainage for the Proposed Potash Handling System .................................. 28
Figure 26. Water Treatment System Process Flow Diagram ....................................................... 29
Figure 27. Design Footprint of Proposed Storage Building on Existing Habitat Types ................ 38
Figure 28. Rail Extension - Design Footprint of Proposed Works on Existing Habitat Types ...... 39
Figure 29. Preliminary Layout of Kyle Creek Spit ......................................................................... 40
Page vi
LIST OF TABLES
Table 1:
Table 2:
Table 3:
Table 4:
Table 5:
Table 6:
Table 7:
Table 8:
Table 9:
Table 10:
Table 11:
Table 12:
Projected Site Wide PCT Air Emissions in 2015 and 2020 ......................................... 56
Table 13:
Table 14:
Table 15:
LIST OF APPENDICIES
(see under separate copy)
Appendix 1.1:
Appendix 1.2:
Appendix 1.3:
Appendix 1.4:
Appendix 1.5:
Appendix 1.6:
Appendix 1.7:
Appendix 1.8:
Appendix 1.9:
Electrical Substations
Appendix 3.0:
Appendix 4.0:
Appendix 5.0:
Appendix 6.0:
Appendix 7.0:
Page vii
1.0
Page 1
INTRODUCTION
Pacific Coast Terminals Co. Ltd. (PCT) is a bulk commodity marine shipping terminal located at
the east end of Burrard Inlet, an area also known as Port Moody Arm (see Figure 1). PCT also
recognizes that it is operating within the traditional territories, including the Salish Sea, of
several First Nations such as the Musqueam, Squamish, Tsleil-Waututh and St:l. The terminal
has been operational in its current location, Port Metro Vancouver (PMV) leased land, since the
early 1960s and has long since established itself as a positive part of the unique Port Moody
community.
Figure 1. Pacific Coast Terminals Location, Port Moody Arm, Port Moody, BC
Currently PCT primarily handles sulphur and monoethylene glycol (MEG) and temporarily
handles steel making coal. However, recent declines in sulphur and MEG tonnage through PCT
have prompted operational changes to handle other commodities to improve the financial
viability of the terminal. In order to achieve this goal, PCT has committed to the following
sequence of five (5) carefully planned and vital projects:
1. Navigation Channel dredging in Port Moody Arm, to enable greater scheduling flexibility
and safety for vessels transiting to and from PCT subsequent to the planned operational
modifications. This project is currently under review by Environment Canada (EC) and
the Department of Fisheries and Oceans (DFO).
2. Installation of a Canola Handling System that will involve handling, temporary storage
and marine loading of food grade cooking oil bound for export markets. This project was
permitted by PMV in March 2014 and commissioning is expected in early 2015.
3. Waste water systems upgrade including clarifier installation.
Potash Project Environmental Review Document Final April 30.docx
Page 2
Introduction of three grades of potash that will be unloaded, stored and shipped. There
will be one industrial (white) and two fertilizer grades (standard and granular (pink).
Potash, a non-reactive, non-toxic naturally occurring mineral to the stable operating
environment at PCT.
New railcar bottom dumper building including below ground dumper vault, indexer and
two dedicated high efficiency baghouses for dust control;
A new conveyor network beginning at the railcar bottom dumper tunnels to the
proposed Potash storage building. Dust will be controlled by new conveyor transfer
point baghouses. Additionally, conveyors will either be covered or fully enclosed (e.g.,
within a tube). The existing Shiploading conveyor from the proposed building to Berth II
will also be covered;
Page 3
A new fully enclosed 160,000 MT Potash storage steel/wood building, with two new
automated stacker/reclaimers and a two way belt system for optimal commodity
handling efficiency. Rip rap will be installed in the foreshore to provide lateral support
for the Potash building while also preventing shoreline erosion.
Water treatment system upgrades including isolated drainage systems separating
potash from sulphur and installation of a new settling and aeration basin and a water
storage tank system. Rail track re-alignment in the main yard extending west to Reed
Point Marina. Careful designs were generated to minimize disturbance to existing
utilities and foreshore habitat.
Modification to the existing Berth II quadrant shiploader with three new chutes and
chute support towers. Two new baghouses will be installed for dust control on the
shiploader, one each for the transfer conveyor and the spout.
Installation of two new substations that provide additional electrical power drawn from
BC Hydro grid for the Potash handling system.
PCT has submitted this document as required by the PMV Project Review Process. It provides
an overview of existing operations and site conditions, engineering details on the proposed
Potash handling system, environmental mitigation for both construction and operations,
cultural preservation and an overview of public and First Nations communications to date.
Accordingly PCT is confident that the proposed Potash handling system supports the PMV
commitment for efficient and reliable movement of goods through the port while
integrating environmental, social and economic sustainability initiatives into all areas of port
operations.
Page 4
2.0
Page 5
PROJECT RATIONALE
PCT has been in operation at the Port Moody site since the early 1960s. To date, a wide variety
of commodities have been safely transferred from land to ocean going vessels bound for
international markets. However, since the 2004-2007 period, tonnage handled of key
commodities, Monoethylene Glycol (MEG) and Sulphur, have declined 40% and 64%
respectively. To ensure future viability of the terminal, PCT decided to expand operations to
include Canola Oil (under construction at this time) and more recently, Potash.
Adding Potash to the PCT site makes good sense as it will provide numerous socio-economic
benefits while minimizing environmental impact. The project and subsequent operations will
play an important role in the local economy given some recent trends:
PCT is currently the third largest taxpayer in the City of Port Moody and after the full
expansion will be the largest single taxpayer.
Major industry in Port Moody currently contributes 14% of all tax revenue (equal to $6.6
million). As a result of the downsizing of industry (two oil refineries and the sawmill have
significantly reduced operations and Andres Wines closed down) in the community, this has
fallen from a high of almost 50% contribution back in the 1980s.
The City has publicly raised concern about the diminishing major industrial tax base in the
community. Members of the City of Port Moody council all expressed support and
enthusiasm for PCTs planned expansion projects and the benefits it will provide to the City
in terms of jobs and increased tax revenue.
For over 50 years, PCT has provided economic stability in Port Moody. This currently involves
generating several million dollars a year in taxes, salaries and purchasing in the local (and
regional) community. The planned $170,000,000 Potash handling system project alone is
expected to generate numerous economic benefits including the creation of over 500 man
(person) years of work, local and regional materials purchasing (estimated value of $3million)
and an additional long-term tax revenue stream. At the same time the company has been
mindful to minimize potential nuisance associated with industrial sites. Steps taken range
include noise barrier installations, community notification in advance of planned maintenance
activities that may generate non-continuous noises, working within Port Moody noise by-law
limits and contractor workforce staging to minimize local traffic.
It is important to note that the proposed Potash project is also highly compatible with the latest
version of the City of Port Moody Official Community Plan (February 2014). PCT is located on
land designated as general industrial (see Figure 3Error! Reference source not found.). The
OCP, which defines the general industrial designation as development of heavy industrial uses
such as manufacturing and port related uses, remains compatible with the PCT operation.
Furthermore, the OCP industrial policy states that, the future employment needs of Port
Moody will be met by a number of strategies such as supporting existing industrial
Potash Project Environmental Review Document Final April 30.docx
Page 6
businesses. Furthermore, the overall project planning approach also supports other
community goals including sustainability by considering multiple decision-making values (e.g.,
economic, environmental, social and cultural) and implementing energy efficiency options
during design and construction.
Page 7
Since handling a peak sulphur throughput of 4.4 million MT in 2004, sulphur handling volumes
have gradually declined by over 64% to 1.6 million MT in 2013.
Page 8
Variable speed pumps and a surge tank located at Berth 1 to protect system overpressurizing;
Recovery of residual glycol from the marine loading arm into a dedicated vessel at Berth
1 using a Nitrogen purge;
Storage tanks with automated valves on inlets and outlets that close on power failures
and emergency shutdown;
Overfilling protection including interlocks between rail car unloading pump and high
tank levels;
Emergency shutdown stations at all operator stations: railcar unloading, marine loading
and at the control building;
Portable and mobile control system tablet interfaces allowing supervisors to
continuously monitor systems while roaming the site; and
A portable emergency shutdown given to vessels to stop shore-side pumps and close
valves during an emergency.
Page 9
Many system fail-safe features similar to the MEG system including pressure controls,
tank level alarms and emergency shut-down.
Page 10
4.0
Page 11
PROPOSED PROJECT
This section describes the proposed facilities that will be used to handle potash at (PCT). In
general, potash will arrive on site in covered bottom unloading railcars and will be brought into
the new railcar unloading building one car at a time. Within this enclosed environment, potash
will be released from the bottom of each railcar onto an underground conveyor located in a
tunnel beneath the train tracks. Dust collection systems will capture dust originating from this
process. The conveyor will daylight above ground near the existing maintenance building and
the potash will continue through a series of new transfer towers before entering the new
Potash Storage Building.
Within the storage building, three grades of potash will be handled by two automated stacker /
reclaimers and reversible conveyor systems. Potash will be transferred and loaded into ships
using PCTs existing sulphur ship loading equipment, modified to accommodate potash. Dust
will be minimized by covering or completely enclosing all conveyors and by installing dust
collection systems on all transfer points.
Upgrades to the electrical power supply and distribution system, water treatment system and
rail yard at PCT will be required to support the project. A general overview of the potash
system is illustrated in Figure and Error! Reference source not found.further below.
Figure 5. Potash Handling System, Railcar Unloading, Potash Storage and Transfer to Ship
Page 12
More information on the components of the potash handling system is provided below.
Construction, operations and environmental information is presented in Section 5.0.
Page 13
Area
Unit
Value
Railcar unloading
cars/hr.
40
Receiving capacity
tonnes/hr.
4,000
(nominal capacity)
Stacking rate
tonnes/hr.
3,000
(nominal
capacity/Per
machine)
Reclaiming rate
tonnes/hr.
3,500
tonnes
tonnes
tonnes
40,000
60,000
60,000
Shiploading capacity:
tonnes/hr.
5,000
Overall capacity
2016:
2020:
tonnes/yr.
36,000
startup Q4 2016
tonnes/yr. 2,200,000
Storage capacity
Industrial:
Standard:
Granular:
Notes
maximum design
capacity
The main equipment that will be used to transfer the potash throughout the new facilities is
shown in the Process Flow Diagrams (PFDs) provided in Appendix 1.2.
Page 14
Page 15
The unloading pit will be constructed using secant piles to provide the structural and water
retaining structure. Once the secant piles are installed, the pit will be excavated using
excavators and/or hydro vac trucks. The excavated materials will be reused onsite as fill or
removed from site depending on the environmental and geotechnical properties. The
excavation may require minor dewatering during the excavation process.
4.1.2 Conveyors, Conveyor Tunnels and Transfer Towers
Potash is unloaded onto underground conveyor C-41 and is conveyed north to an underground
transfer point, where it is placed onto conveyor C-42. The underground transfer point includes
ladder access and a dust control system.
A plan view of the potash unloading area underground conveyor tunnels is shown in Figure 11
below.
Page 16
Maintenance
Bldg.
Sulphur
Stockpile
Conveyor C-42
Emerging Point
Railcar Unloading
Area
Underground
Transfer
Conveyor C-41
After the emerging point, conveyor C-42 becomes a fully enclosed conveyor and gallery. No
material from the conveyor system will be able to fall to the ground. This provides safety to a
fairly busy maintenance area and ensures no potash gets into the sulphur area surface water
collection system.
Potash travels on conveyor C-42 to transfer tower T-42, and then to transfer tower T-43 and
into the storage building via transfer towers T-44 and T-45. All transfer towers are fully
enclosed and equipped with dust control systems. Conveyors after T-42 are covered.
Plan and model views of the above-ground conveyors between transfer tower T-42 and the
Potash Storage Building are shown in Figure 12 and Figure 13 below. Additional drawings are
included in Appendix 1.4.
Page 17
Transfer
Tower T-45
Transfer
Tower T-43
Transfer
Tower T-42
Conveyor C-43
Transfer
Tower T-44
Conveyor C-42
The underground conveyor tunnels will be constructed in a similar method using a combination
of secant piles and open cut excavation. The excavated materials will be reused onsite as fill or
removed from site depending on the environmental and geotechnical properties. The tunnels
will be cast in place concrete which will then be backfilled using recycled or import material.
Potash Project Environmental Review Document Final April 30.docx
Page 18
The above ground conveyors will be erected on the ground and lifted into place and attached to
the transfer towers using cranes. The foundations of the transfer towers will be cast in place
concrete footings.
4.1.3 Potash Storage Building and Staker/Reclaimers
The proposed potash storage building is approximately 264m long, 83m wide and 34m high at
the peak. It is designed to store up to 160,000 tonnes of potash in three different grades;
standard, granular and industrial. A concrete separation wall will be installed between the
fertilizer (standard/granular) and industrial grades to maintain product quality. The storage
building will be constructed using steel frames to support a wooden roof and will sit on driven
pile supported concrete foundations. Long and narrow wooden building extensions will be
added to the north end of the storage building to house the tripper portion of the
stacker/reclaimer equipment when it is at the north end of the building.
The storage building will be located adjacent to the water and will be designed to current
seismic codes. Soil densification by means of stone columns will be implemented between the
storage building foundation and the shoreline. The stone columns will be installed along the
foreshore to improve the ground response to a seismic event. Shoreline improvements using
rip rap embankments are also planned. Fire truck access is provided by road access all around
the building.
Plan and section views of the Potash Storage Building are shown on Figure 14 and Figure 15
below. Model views of the Potash Storage Building are shown on Figure 16 and Figure 17
immediately following. Additional drawings are included in Appendix 1.5.
Page 19
Page 20
The storage building is a purely industrial structure that does not normally support a substantial
human occupancy and is therefore considered a special structure under the National Building
Code of Canada. As such, it is intended to comply with the general definition of a building per
the NBCC for the purpose of good design only. Alternative measures/solutions for life safety
that are considered appropriate for special purpose industrial structures will be proposed. This
is discussed in more detail in the Code Concepts Report by Gage Babcock & Associates included
in Appendix 1.6.
Page 21
The storage building is required to keep the potash dry and maintain product quality. The
potash stockpiles within the building are managed by two automated stacker/reclaimer
machines. The two machines are located on either side of the building and travel the length of
the building on rails to create the stockpiles (stacking) or transfer potash from the stockpiles to
the ship loading system (reclaiming). A row of concrete columns run the length of the building
are used to support an elevated central rail system to support the stacker/reclaimer booms.
Reversible conveyors C-51 and C-52 run along each long wall and work with the
stacker/reclaimers to achieve this function.
A typical stacker/reclaimer is shown on Figure 18 below. Additional drawings are included in
Appendix 1.5.
The sub grade preparation for the Potash Storage Building will include both stone columns and
piles. The stone columns will be installed along the foreshore to improve the ground response
to a seismic event. The piles will be installed to provide a foundation for the Stacker/Reclaimer
and the building itself. The storage building will be erected from sections of building or
equipment (trucked or barged to site) and assembled onsite and erected in place using cranes.
4.1.4 Ship Loader Modifications
PCTs existing ship loader will be modified so that it can be used for both sulphur and potash.
These modifications will include:
Two additional potash loading spouts and a new structure that will be used to store the
loading spouts when not in use.
One potash sampling system.
Two dust control systems; one of the transfer point between conveyor C-89 and the ship
loader and one for the loading point.
Structural modifications to accommodate the new product.
Page 22
The modifications to the ship loader will include new equipment delivered to site via trucks or
barge and assembled and installed in place using cranes.
4.1.5 Rail Track Modifications
Some modifications and additions need to be made to the existing rail infrastructure at PCT in
order to accommodate both the full and empty potash railcars.
The modifications include several new crossovers between existing tracks in PCTs rail yard.
Some existing track needs to be modified (straightened or re-routed) to allow for the new
crossovers to be installed.
The new track includes Track P (approximately 200m) that will run through the new Unloading
Building and an extension of Track Y (approximately 500m) from the northern end of PCT
towards Reed Point Marina.
The new Track Y extension will be used for storage of empty potash railcars and will be located
adjacent to Track X, currently used for storage of empty sulphur railcars. The existing bank will
generally be moved seaward a few metres to accommodate the new track. The land
reclamation will be backfilled with hydraulic fill materials and contained by a lock block wall
along the northern end and rip rap along the southern end. Several drainage culverts will
require extension or modification and two of Imperial Oils pipelines (located in a single right of
way) will be crossed and protected.
Page 23
A plan view, wall section and a rip rap section for the Track Y extension shoreline protection
area shown on Figure 20, Figure 21, and Figure 22Error! Reference source not found. below.
Drawings of all rail track modifications are included in Appendix 1.7.
Page 24
This construction will involve land based construction activities using excavators and tracked
machinery with materials being delivered by barge. The plan for staff and equipment staging is
temporary access from Reed Point Marina. A temporary road will be constructed from Reed
Point Marina to the construction area for the new Track Y extension. The access road will be
removed once construction is complete. The plan for material delivery is to develop a barge
landing between Reed Point and the PCT Terminal to act as a delivery point for fill materials.
During construction, this will be the staging point for both the structural fill and lock block wall
as well as the new rip rap for the shore.
The barge landing area will be built with recovered rip rap (that is being replaced for new
construction), aggregate fill and larger rip rap. The barge landing will then be converted into an
islet that will include fish and wildlife habitat offsets for the project (see section 5.1.4.3 for
more details). A preliminary layout for the barge landing area is depicted by Figure 23 and
Figure 24.
The preliminary layout presents all of the salient features of the barge loading facility.
Advanced design will define details and specifications for construction. The advanced design
process will investigate prospective means to decrease the footprint on the nearshore subtidal
environment; this process will maintain the delivery of intertidal habitat offsets to the project.
Page 25
Page 26
Fire water lines will be upgraded and extended to provide fire water to the potash
dumper building and the potash storage warehouse.
Storm runoff from the potash warehouse roof will be directed to the ocean. Runoff
from the north side of the warehouse will drain directly to the ocean. Runoff from the
south side will enter a storm drain and will normally flow to the ocean. Water quality of
the runoff will be monitored, and if it is found that the runoff is impacted, the roof
runoff will be directed to the sites sulphur wastewater treatment system.
Storm runoff from areas potentially impacted with potash fines (such as under the
conveyors and near the west end of the potash storage warehouse) will be directed to a
new potash wastewater treatment system (see Figure 25Error! Reference source
not found. which shows modified drainage).
Page 27
(KCl) would cause corrosion problems to PCTs steel infrastructure if the treated
wastewater was recycled.
In order to segregate the two water systems, certain pump stations will be dedicated for
the potash wastewater systems, and others will be dedicated for the sulphur-only (or
non-potash) wastewater systems.
The potash wastewater treatment system will be similar to the existing PCT wastewater
treatment system, and will include two parallel primary settling basins for grit removal
and oil skimmers to remove residual oils. The primary settling basins have been sized to
treat the 10 year, 24 hour storm event, which equates to 42 L/s, given the catchment
area of potash impacted surfaces. The primary settling basins will be followed by an
aeration chamber, where mixing and pH adjustment will occur. The treated wastewater
will then be pumped into a storage tank prior to discharge to the municipal sanitary
sewer. The storage tank will be sized to accommodate a 1-in-5 year storm event when
discharging at a flow rate of 15 L/s to the sanitary sewer. During extreme storm events,
PCT will implement operational management tools such as limiting upstream flows,
turning off pump stations to allow local pooling of water on site, increasing the flow rate
from the Potash Wastewater treatment system to the sanitary sewer in order to limit
the risk of overflow events. See Figure 26Error! Reference source not found. which
shows a summary of the upgraded water treatment process.
Other site service upgrades that will be involved include re-grading certain areas and paving.
Figure 25. Modified Drainage for the Proposed Potash Handling System
Page 28
Page 29
Page 30
4.1.7 Substations
There will be four important installations to power the Potash handling system. These are
described below (and see drawings in Appendix 1.9).
Substation A
A new 25 kV substation will provide the increased power requirements to the entire site. This
replaces the existing 12.5 kV service at the northwest side of the property.
A new power distribution center and transformers will distribute the power to the existing site
and the new Substation D.
Substation D
Substation D is a new electrical building which will supply power to most of the potash project
electrical loads, including the conveyors, stacker/reclaimers and dust collection systems.
MCC 5/7 Electrical Building
The power for the potash unloading building and associated equipment will be supplied from
the existing MCC 5/7 electrical building.
Substation C
The new water treatment electrical loads will be supplied out of the existing Substation C
electrical building.
In general, the wiring for the potash project will utilize teck 90 cables on cable tray.
4.1.8 Control Systems
New infrastructure, including the automated Potash storage staker / reclaimers will be
integrated into the existing distributed control system (DCS) infrastructure at PCT.
Please see Appendix 1.11 for 3D model views of the proposed installations.
Page 31
Milestones
Date
April 2014
April 2014
January 2015
Mechanical Completion
August 2016
Complete commissioning
November 1, 2016
Regulator / Infrastructure
Owner
Status
Metro Vancouver
Scheduled May
29, 2014
submission
Scheduled May 2,
2014 submission
Metro Vancouver
Process underway
Process underway
Process underway
Detailed design
development
Page 32
Potash
Products
Product Characteristics
Chemical
Name
Appearance
Potassium
Chloride
99% KCl
Compacted
Potassium
Chloride (KCl),
99%
White,
pellets
Very
faint
60er Kali
dustfree
Potassium
Chloride (KCl),
>94%
Pink,
crystalline
Very
faint
60er Kali
gran.B
Potassium
Chloride (KCl),
>94%
Pink,
granular
Very
faint
Water
Soluble
5.0
Page 33
ENVIRONMENTAL MANAGEMENT
Potential
Environmental Issues
Activities / Sources
Groundwater Control
Excavation dewatering
Foreshore Habitat
Alteration
Air Emissions
Key Controls
Contaminated Soil
Potential
Environmental Issues
Page 34
Activities / Sources
Key Controls
Traffic
Heritage Preservation
Unless vehicles or equipment are in active use, idling will be prohibited to prevent
unwarranted emissions.
All on-site equipment and applicable transient vehicles coming to and from the construction
site are anticipated to have US EPA Tier II engine emission ratings (or better) for better air
emissions quality on and off-site. See Appendix 2 for equipment and vehicle types and
ratings.
Page 35
Location
Secant piles will be the primary method of groundwater control, essentially diverting the water
table away from the excavated worksite. Continuous pile walls will be established to an
approximate depth of 12m by sequential drilling and concrete filling. The secant walls will serve
two purposes: groundwater deflection and they will also remain in
place as structural foundations for the railcar dumper pit and
connecting conveyor tunnels.
Dewatering pumps, with diversion to the PCT water treatment
system, have successfully been used for the Canola handling system
construction project. Final dewatering and treatment options will
be made at a more detailed stage of construction execution
planning.
Page 36
2.76
2.10
1.40
0.03
- 1.98
- 3.15
- 3.35
PCT (m)
33.19
32.58
31.88
30.51
28.50
27.33
27.13
The alignment and character of the existing shoreline is the product of terminal operations.
Characteristic habitat types that occur at and about the project location include:
Backshore (land above HHWL large tide)
at the potash warehouse location, a row of planted coniferous trees along the top of
bank that provide landscaping and screening of industrial operations;
at the rail extension location, a row of planted deciduous shrubs and naturally
occurring trees along the top of the stresswall, and naturally occurring deciduous
and coniferous trees and associated understorey vegetation west to the terminal
rock rip rap installed to provide shoreline armouring, which is partly shaded by the
trees and is unvegetated.
Page 37
rock rip rap installed to provide bank armouring, which consists of mid-tide
elevation rocks vegetated by macroalgae (i.e. rockweed, Fucus gardneri) and
colonized by attaching invertebrates (i.e. barnacles and mussels); generally,
rockweed occurs on the rock rip rap up to approximately 0.8 m geodetic; barnacles
occur on the rip rap up to approximately 1.2 m geodetic;
at the potash warehouse location, mudflat extends from the toe of rip rap (ranging
from 0.05 to -0.8 m geodetic) seaward; mudflat is largely unvegetated, except for
rockweed that has attached to scattered gravel and cobble once associated with
shoreline armouring; mudflat is comprised fine sands, silts and clays that are
predominantly of fluvial origin;
at the rail extension location, beach extending from the toe of rip rap (from
approximately -1.0 m geodetic) seaward; the beach consists of sand and gravel with
shell hash, particularly seaward of the rock scour protection at the base of the stress
wall, and becomes coarser with a cobble, gravel veneer at about Reed Point and to
the terminal; the coarser cobble and large gravel typically supports a dense covering
of rockweed; east of Reed Point, rock armour of the upper slope has fallen to the
lower beach; a discontinuous boulder veneer covers much of the gentle sloping
beach; this veneer supports a dense cover of rockweed.
Page 38
Figure 27. Design Footprint of Proposed Storage Building on Existing Habitat Types
The rail extension from the terminal westward to approximately the eastern limit of Reed Point
Marina engages approximately 600 m of shoreline. The design, from approximately Reed Point
Marina to Reed Point, encapsulates shoreline features constructed for the West Coast Express
project. These include a concrete stresswall, rip rap scour protection at the base of the wall,
and the narrow strip of shrub plantings immediately landward of the top of the wall.
The design of the rail extension impacts backshore vegetation, rip rap and beach. Backshore
vegetation retained occurs entirely at Reed Point. Backshore vegetation associated with the
top of the stresswall, west of Reed Point, and associated with the top of bank armour, east of
Reed Point, is lost. Existing rip rap and other bank armour is largely covered by the design rip
rap. Beach is impacted east of Reed Point by design rip rap.
Design impacts are considered permanent impacts to habitats. Habitat types impacted by the
project are depicted by Figure 28. Permanent impacts attributable to the current design of
proposed works include 2040 m2 of backshore trees/shrubs, 3300 m2 of rip rap, and 820 m2 of
beach.
Page 39
Figure 28. Rail Extension - Design Footprint of Proposed Works on Existing Habitat Types
Page 40
The preliminary layout of of Kyle Creek Spit is presented by Figure 29. The design spit creates
riparian woodland (670 m2), intertidal marsh (190 m2), and cobble beach (575 m2). The design
footprint occurs upon intertidal mudflat. The design does not markedly encumber fluvial
drainage of Kyle Creek or dendritic drainage of intertidal flats.
The design results in the loss of 935 m2 of intertidal mudflat. Intertidal mudflat of the
Schoolhouse and Kyle creeks estuary encompasses 17.7 ha. The relative impact to intertidal
mudflat is small. The capacity of estuary mudflat to sustain fishery species is not unduly
affected. Any negative effects are substantially exceeded by the positive effects of design
habitats upon the capacity of the estuary, in particular at and about Kyle Creek, to sustain life
history functions for salmon. It is this net benefit to juvenile salmon that is foundation of the
offset the spit provides to permanent impacts associated with both the potash building and the
rail extension.
Page 41
Reed Island
The eastern half of Port Moody Arm (east and south of Reed Point Marina) is a shallow marine
feature. It is largely characterized by peripheral intertidal flats. The shallow subtidal
environment is largely characterized by fine sands, silts and clays. Abrupt vertical features,
such as bedrock bluffs, typically do not transcend the bottom of the arm to the high water
mark.
Hard substrates that occur within the photic zone of Port Moody Arm provide ideal attachment
for macroalgae, such as rockweed within the intertidal zone, and sugarkelp (Laminaria
saccharina) within the subtidal zone. Macroalgae provide habitat for a myriad of invertebrates
that are prey for fishery species. Macroalgae within the shallow subtidal are particularly
important in providing cover and refuge for the juvenile life history stages of fishery species.
These species, such as Dungeness crab (Metacarcinus magister), often shift back and forth
between habitat types, such as shallow subtidal flats and kelp stands.
Hard substrates, dependent upon configuration within the water column, and independent of
macroalgae, can function as a reef and provide important habitat for species that exploit reef
environments. Reefs provide structural complexity important to the life history stages of
fishery species. This complexity is particularly important within a homogenous waterscape that
is the bottom of Port Moody Arm.
The preliminary layout for Reed Island is presented by Figure 30 Reed Island is created from
the temporary barge landing area. Aggregates above the intertidal zone are removed utilized
for construction of the rail extension. Aggregates comprising the temporary fill road are also
removed and utilized for rail construction. The integration of the barge landing area and the
island designs substantively reduces temporary impacts of fish and fish habitats within Port
Moody Arm.
The island incorporates intertidal marsh (520 m2), beach (350 m2), intertidal reef (1035 m2) and
subtidal reef (2125 m2). The design footprint occurs predominantly on subtidal mudflat.
Substrates along the shoreward subtidal margin of the design footprint consist of a mix of
cobble, gravel, sand, mud and shells.
The loss of subtidal mudflat attributable to the preliminary layout is 3955 m 2. Subtidal mudflat
within the eastern end of Port Moody Arm (east of western pipeline of IOCO refinery)
encompasses 147.2 ha. The relative impact to subtidal mudflat is small. The capacity of
subtidal mudflat of Port Moody Arm to sustain fishery species is not unduly affected. Any
negative effects are substantially exceeded by the positive effects of design habitats upon the
capacity of Port Moody Arm to sustain life history functions for fishery species. It is this
exceedance that substantively offsets permanent impacts to habitats associated with both the
potash building and the rail extension.
Page 42
Page 43
Figure 31. Location of Beach Created Through Removal of Existing Rip Rap
Habitat Account
The habitat budget (Table 7) accounts for permanent impacts to fish habitats and habitat
offsets attributable to the current design of proposed works and the preliminary layout of
offset habitats. Temporary impacts attributable to temporary construction features, such as
temporary construction roads, are not included in the budget. Habitats affected by temporary
features, such as the salt marsh at Reed Point, will be restored.
The budget presents habitat types that are specific in character (e.g. substrate, vegetation,
location according tidal water level). The rip rap habitat type, however, is relatively general in
character. Existing rip rap varying dramatically in rock size, slope and elevation; a typical crosssection does not exist for the entire project shoreline. It does, however, traverse only
backshore and intertidal environments. Existing rip rap does not engage the subtidal
environment within the design footprint of the project.
A large component of existing rip rap occurs within the intertidal zone. This is important in that
this element of the shoreline environment, that has its origins with development, does sustain
habitat for fish. At high tide, it provides refuge and prey for fish. The encrusting invertebrate
and algal communities founded on rip rap sustain habitat for numerous invertebrates that are
important prey for fish.
Page 44
It is logistically and cost prohibitive to survey existing rip rap to define whether it is backshore
or intertidal. In lieu of such information it is worthy to note that design rip rap largely offsets
impacts to rip rap that occurs within the intertidal zone. This rip rap that is associated with the
design of proposed works, and the functions it provides as fish habitat, is substantively
augmented by intertidal rip rap and boulders that will define part of Reed Island constructed as
part of the overall project.
The context of rip rap as a habitat feature, for the purposes of a habitat budget for this project,
is adequately expressed as two categories: backshore/intertidal rip rap; and, subtidal rip rap.
Subtidal rip rap is a reef feature associated with the slopes of Reed Island. The backshore and
intertidal portions of the vertical wall associated with the rail extension are not included in the
habitat budget.
The backshore vegetation impacted by proposed works has little value as fish habitat. The
vegetation occurs well above the higher high water elevation (large tide). As such, there is little
overhang above the surface of the water during any tide; the prospect of insect drop to the
surface where it is available as prey for fish is poor. The contribution of particulate organics
(i.e. leaf and needle drop) to the aquatic environment is inconsequential in sustaining
invertebrate herbivores and detrivores that are prey for fishery species. The production of such
herbivores and detrivores is largely dependent upon intertidal and subtidal alga.
Shading of backshore vegetation typically occurs upon rip rap and the nearshore intertidal
beach and mudflat. Where shading is relatively intense, it limits the cover of alga, an important
element of the nearshore ecology of the arm.
Shading does not benefit shore spawners (i.e. surf smelt (Hypomesus preticosus) and sand lance
(Ammodytes hexapterus)). Substrates are too fine along the potash warehouse shoreline to
sustain successful spawning. Substrates are too coarse along the rail extension shoreline, east
of Reed Point, for spawning. At Reed Point, where substrates could prospectively sustain
successful spawning, backshore vegetation is retained relatively intact. Backshore vegetation
west of Reed Point is comprised predominantly of shrubs; the vegetation rarely shades beach
substrates. In any regard, shore spawning has not been documented within the shoreline
environments of proposed works.
Page 45
Habitat Type
Backshore Woodland
3260
Riparian Woodland
670
Intertidal Marsh
710
Intertidal Beach
820
1115
Intertidal Mudflat
1220
5630
5680
2125
Subtidal Flat
3955
Page 46
Consideration will also be given to identify the most efficient transportation with the lowest
environmental footprint possible. Options will include but not be limited to:
hot loading soil from excavations directly to truck transport to end-user(s) or landfill;
hot loading soil from excavations directly to truck, transfer to a nearby barge (e.g., from
the adjacent sawmill site and subsequently delivered to a site via tug and barge; or
combined with temporary on-site storage (stockpiles) before truck / barge delivery to
final destinations.
Figure 32. Historical Soil Quality near Railcar Dumper Pit and Tunnel Excavation Areas
Page 47
Figure 33. PCT Site Historical Soil Quality near Planned Installations
Page 48
Page 49
Solid Waste
Handling Options
Re-Use On-Site
Recycle
Asphalt
Excavation Soil
(fill)*
Trees**
Dimensional
Wood
Wood Pallets
Paper and
Cardboard
Scrap Metal
Paint***
Organics
(Lunchroom)
Plastic Wrap
*approximately 3500m3 from dumper and tunnel excavations
**compost
***partly finished cans to Transfer Station, dry cans to municipal waste
Disposal
Page 50
Hazardous waste generation is expected to be minimal and may include small volumes of:
Unless the materials such as sealants and solvents can be re-used by contractors for
subsequent job sites, they will be submitted to licensed transfer stations. Used sorbents will be
disposed as hazardous waste with licensed operators with applicable manifests for waste
tracking.
5.1.7 Hazardous Materials Management
The volume of hazardous materials used for construction purposes,
including equipment fuels, is planned to be kept to a minimum. All
products will be approved by a safety coordinator prior to use on site.
Small volume hazardous materials such as spray paints, solvents and
sealants will be stored in designated prefabricated fireproof sheds. Small
volume fuels (gasoline and diesel) will be stored in 20L jerry cans and
placed in containment when not in active use. Note that mobile refuelling services will be contracted to provide diesel to equipment on-site - bulk fuel storage
will therefore not be required. Propane cylinders will stored at required distances from other
combustible and flammable products. All products will be used and stored in compliance with
the National Fire Code.
5.1.8 Noise and Vibration
Noise and vibration will result from primarily piling and site preparation activities. Sources and
planned durations are summarized in Table 9 below.
Table 9: Potential Construction Noise Sources and Duration
Source
60
Stone columns
55
30
20
Vibration is expected to be limited to the PCT site and not be a nuisance off-site at nearby
properties that are predominantly zoned industrial and commercial, including the adjacent rail
yard.
Potash Project Environmental Review Document Final April 30.docx
Page 51
Every attempt will be made during construction planning to limit noise duration including the
possibility of overlapping activities. Other initiatives to minimize noise will include complying
with the Port Moody Sound Level Bylaw requirement to limit construction activities between
7:00 am -8:00 pm.
As a courtesy to the community, notices will be placed in local newspapers and possibly other
media to alert them of planned construction activities. PCT management will also record and
respond to attributable complaints on a timely basis.
5.1.9 Traffic
The use of local roadways will increase during the construction phase as a result of equipment
and material deliveries, site services and contract labour transits. This will involve an estimate
of approximately 7,500 trips over the construction period (see Appendix 2 for an estimate of
transient vehicle trips and a list of on-site equipment).
To minimize potential traffic delays in Port Moody, particularly on approach to PCT, several
steps will be taken, such as (but not limited to):
Using designated truck routes which will be a condition for contractors (e.g., haulers,
deliveries);
Coordination with City of Port Moody planners;
Where possible, deliveries by barge to completely avoid road use;
Avoidance of typical local morning and afternoon rush hours; and
Courtesy project notifications (reminders) in local media sources (e.g., newspapers,
websites) and on the PCT website.
Page 52
Potential
Environmental Issue
Activities / Sources
Key Controls
Air Emissions
Water Management
Waste Management
Noise
Recycled; landfilled
Licensed landfill
Visual Impact
Vessel Traffic
Page 53
sulphur, coal, glycol and canola handling for the year 2015;
sulphur, glycol, canola and potash handling for the year 2020; and
air emissions associated with the construction of infrastructure required to handle
potash.
The difference between the 2015 and 2020 emission inventories considers the incorporation of
Potash handling to overall site wide air emissions. Note that PCT plans to discontinue handling
coal after the Potash handling system is commissioned.
Air emissions from proposed potash handling activities will be controlled with dust collectors at
all transfer points, while commodity transportation by rail (CP Rail) and marine vessels will
otherwise generate the vast majority of emissions to air. PCT (and /or its partner K&S Canada)
has no direct control of vessels or rail operations other than the scheduling frequency for
commodity transportation. However, rail and marine vessel scheduling efficiency is a vital
component in terminal planning logistics, including effectively managing costs. Furthermore,
the marine and rail transportation industries are separately governed to manage air emissions
(including the PMV Air / Eco-Action programmes which involve using low sulphur fuels while in
port).
The air contaminants considered for this emission inventory include carbon monoxide (CO),
sulphur dioxide (SO2), nitrogen oxides (NOX), inhalable particulate matter (PM10), respirable
particulate matter (PM2.5), total volatile organic compounds (VOC), ammonia (NH3), diesel
particulate matter (DPM), black carbon, and greenhouse gases (GHG) such as carbon dioxide
(CO2), methane (CH4) and nitrous oxide (N2O).
Page 54
PCT itself is directly responsible for few of the significant air emission sources at the facility,
which is based on the reliance on other companies to supply the necessary shipping, rail and
trucking transport. As such, a large part of the effort to compile the emission inventory
involved determining the engine characteristics of transportation sources managed elsewhere.
It is anticipated that PCT will handle up to 2,200,000 tonnes of potash annually, on its way to
markets in Asia and other parts of the world. Table 11 outlines recent historical and projected
future commodity handling at PCT.
Table 11: Historical and Projected Future Commodity Handling at PCT
Year
Coal
Potash
Glycol
Canola
2010
2,289,040
625,958
2011
2,025,274
168,229
615,797
2012
1,735,229
287,696
613,264
2013
1,580,000
430,000
650,000
2014
1,500,000
300,000
675,000
175,000
2015
1,500,000
300,000
700,000
425,000
2016
1,380,000
300,000
36,000
725,000
475,000
2017
1,300,000
1,000,000
750,000
540,000
2018
1,220,000
1,250,000
775,000
575,000
2019
1,140,000
1,500,000
800,000
575,000
2020
1,060,000
2,200,000
825,000
575,000
Changes in site wide air emissions from the baseline year 2015 to the future year 2020 are
shown in Table 12 and total emissions associated with the construction of potash infrastructure
at PCT (Table 13). The results indicate that:
Page 55
A previous emission inventory completed for PCT operations from 2001 to 2005 is also
presented for comparison purposes. It is noted that emission estimation methodologies have
changed since this previous inventory was completed; however, there have been significant
reductions in site-wide emissions based on improvements in marine and locomotive engine
technologies, which results in lower predicted site-wide emissions in 2015 and 2020 in
comparison to historic emission rates. Overall, the estimated emissions of CO, NOx, VOC, SO 2,
combustion-related PM10 and PM2.5, and fugitive dust are lower for 2015 and 2020 than the
estimates provided for the 2001-2005 period.
Please see Appendix 5 for the complete air emissions inventory report for more details.
Page 56
Table 12: Projected Site Wide PCT Air Emissions in 2015 and 2020
Year
2015
2020
Emission
Source
Ships
Rail
Trucking
Light Duty
Vehicle
Off-Road
Fugitive Dust
Total
Ships
Rail
Trucking
Light Duty
Vehicle
Off-Road
Fugitive Dust
Total
CO
4.1943
2.4923
0.0006
NOx
33.001
3.8290
0.0021
VOC
0.9843
0.6485
0.0001
SO2
1.7034
0.0029
neg.
PM10
0.7990
0.0861
0.0002
N2O
0.0690
0.1299
neg.
CO2e20
3374
576
0.7
CO2e100
1959
418
0.7
NH3
0.0046
0.0190
neg.
0.4342
0.0368
0.0114
0.0012
0.0069
0.0027
0.0013
0.0002
62.4
0.0008
0.0009
63
63
0.0079
0.0399
7.16
5.4681
1.0955
0.0003
0.0964
36.97
39.744
4.6522
0.0010
0.0098
1.65
1.3171
0.4798
0.0001
0.0005
1.71
2.2143
0.0027
neg.
0.0029
38.363
39.26
1.0596
0.1107
0.0001
0.0013
19.181
20.00
0.9749
0.1074
0.0001
0.0005
0.82
0.9749
0.1074
neg.
0.0004
0.68
0.8091
0.0896
neg.
81.2
1,842
1877
291
0.68
0.0024
0.27
0.3186
0.0164
neg.
0.0032
0.20
0.0897
0.1202
neg.
84
4097
4515
614
0.7
83
2523
2640
409
0.7
0.0001
0.03
0.0059
0.0274
neg.
0.3358
0.0212
0.0060
0.0011
0.0067
0.0025
0.0011
0.0002
56.3
0.0006
0.0006
57
57
0.0064
0.0868
6.99
0.2096
44.63
0.0214
1.82
0.0010
2.22
0.0067
23.518
24.70
0.0031
11.567
12.66
0.0013
1.08
0.0011
0.90
176.5
2,402
0.0053
0.34
0.0068
0.22
182
5369
180
3286
0.0001
0.04
N2O
0.2614
CO2e20
5787
CO2e100
4252
Table 13: Expected Air Emissions from Potash Handling System Construction
CO
8.3515
NOx
23.720
VOC
1.2354
SO2
0.0235
PM10
0.8725
NH3
0.0065
Page 57
Fully enclosed or covered conveyors and fully enclosed transfer towers (previously
mentioned in Section 4.2);
Conveyor transfer points will each have attendant fabric filter dust collection systems
(baghouses), with typical 99.9% dust removal efficiency. See Table 14 which provides
a summary of fabric filter locations. Note that final design and supplier selection are to
be finalized.
Operation / Location
Emission
Point #
31, 32
33
34
35
Dust Control
Units
2
1
1
1
36
37
38
39
Please see Appendix 6 for dust collection drawings (and related system specifications for
Shiploader units).
Page 58
Page 59
Page 60
5.2.4 Noise
With similar design and operating activities, excluding the fully enclosed storage building, the
proposed Potash system is expected to have the same low noise profile as the existing Sulphur
handling system. Potash operations including railcar unloading, conveyors, dust collectors with
silencers (e.g. see Sandvik specifications in Appendix 6) and ship loading are not expected to
generate noise levels above existing sound levels. The system will be designed to operate with
the limits indicated in the City of Port Moody Sound Level Bylaw.
Railcar delivery and marine vessel transiting can create noises (continuous and non-continuous)
above background that may be noticed by local citizens.
Although these sounds are part of PCTs history and present day operations, the company takes
reasonable steps to attenuate noise, including:
Page 61
Several renderings of the proposed Potash storage building were superimposed into
photographs taken from various vantage points in Port Moody. The renderings were prepared
and studied to maintain view corridors to the North Shore for the homes to the south of the
site as much as possible. This included lowering the storage building height to allow a view to
the opposing shoreline (e.g., Pleasantside) for most of the overlooking homes located on the
south slope. While best practical efforts were made to minimize visual impacts, some homes
on the south of the terminal will have partially obstructed views (see Figure 35).
After the building size and shape had been optimized to minimize its overall impact on the
community, the colour was then explored. The Architectural team reviewed many options for
providing a cost effective and durable solution. It was determined that a Forest Green colour
was best suited for the building as it blends in with the adjacent backgrounds better than
anything else explored (see Figures 36 and 37) and considering previous community feedback
on other projects.
Page 62
Page 63
Year
Drybulk Tankers
Liquid Tankers
Total Tankers
2000
97
61
158
2001
84
64
148
2002
91
64
155
2003
93
69
162
2004
104
78
182
2005
97
82
179
2006
91
69
160
2007
84
72
156
2008
77
73
150
2009
57
68
125
2010
58
53
111
2011
53
51
104
2012
54
43
97
2013
50
43
93
2014E
47
53
100
2015E
53
60
113
2016E
50
61
111
2017E
61
63
124
2018E
64
63
127
2019E
67
63
130
2020E
78
63
141
Page 64
6.0
Page 65
As previously stated, PCT recognizes that it is operating within traditional territories of multiple
First Nations, including but not limited to the Musqueam, Squamish, Tsleil-Waututh and St:l
Nations. Given the project areas location within First Nations territories and proximity to
known archaeological sites (Figure 38), as well as the projects scope including multiple
excavations that penetrate through native soil depths, PCT is voluntarily undertaking a
comprehensive Archaeological Impact Assessment (AIA) to preserve subsurface cultural
artifacts that may be present within the project area.
The objectives of an AIA are to:
identify, record, and assess archaeological sites within the PCT project sites;
identify and evaluate possible impacts to these (potential) archaeological sites that may be
caused by any future development of the property (namely the Potash handling project);
and,
recommend appropriate impact mitigation management actions (if required).
In March 2014, archaeologists were contracted from Kleanza Consulting Ltd. to conduct the
AIA. In summary, the AIA will involve three sequential phases of field planning, field work and
reporting as follows:
Phase I:
Field Planning
A desktop review including basic archaeological, historical and ethnographic background
research involving review of readily available articles, reports, records and maps. The
Remote Access to Archaeological Data (RAAD) database administered by the provincial
Archaeological Branch will be consulted to determine if any previously recorded
archaeological sites are located within or nearby the project area. This stage may include a
visit to provincial and local archives as well as examination of archival and air photos of the
project area(s).
Liaison with First Nations to review available traditional use information and sharing draft
reports and maps. Inlailawatash Forestry Limited Partnership (owned by Tsleil-Waututh) has
agreed to provide mapping and background research services.
Assembling and submitting archaeological permit applications.
Inviting First Nations representatives to participate in a site visit.
Phase II:
Page 66
Field Visit
Field investigations will be conducted to locate, record and evaluate archaeological sites
(potentially) present in the project area. The field crew will be comprised of two archaeologists
and up to three First Nations Field Technicians. Field investigations will include any of foot
traverses to observe the project area for possible archaeological evidence; subsurface testing
using relevant tools and equipment ranging from shovels and possibly excavators near surface
and augers to investigate more deeply buried sediments; and recording and marking of
archaeological site(s) if discovered.
Phase III:
Reporting
Key tasks will include data analysis, reporting writing, mapping and development of any
required mitigation recommendations. The report will be submitted to participating First
Nations and the Archaeology Branch. The Branch will also be notified of any archaeological
site(s) are discovered. A Chance Find procedure will also be generated and provided to
construction excavation operations to further improve the detection of artifacts potentially not
identified during field investigations.
At the time of submitting this document, several elements of the AIA were underway or near
completion, including:
Page 67
Page 68
The Growing Our Business section of the PCT website provides an ongoing reference for the
proposed potash expansion project. Information includes an overview of potash, a summary of
terminal improvements and a short video illustrating the site expansion (see bottom of
presentation and rendering page: http://www.pct.ca/code/navigate.asp?Id=63).
Many of these activities will continue during the PMV project review period, including voluntary
information sharing with local First Nations (i.e., Squamish, TWN, Musqueam and St:l). First
Nations representatives will be informed that these information sharing sessions will in no way
substitute PMVs legal duty to consult and are being undertaken voluntarily by the PCT project
team to develop long-term relationships well beyond the project timeline.
Please see Appendix 7 for details on PCT communications and examples of community
engagement to date (April 30, 2014).
8.0
Page 69
CONCLUSION