FIDIC Suite of Contracts PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

The FIDIC Suite of Contracts

Less well know FIDIC contracts are also


available such as the Turquoise Book for
Dredging and Reclamation Works published in
January 2006 and the White Book model
services agreement published in October 2006

Introduction

The FIDIC suite of contracts now covers a


wide range of projects and methods of
procurement. It is therefore likely that any
international contractor or consultant working
outside of the UK will frequently encounter
FIDIC conditions of contract.

The FIDIC suite of contracts


The FIDIC suite of construction contracts is
written and published by the International
Federation of Consulting Engineers. The FIDIC
acronym stands for the French version of the
Federations name (Federation Internationale
des Ingenieurs-Conseil).
The best known of the FIDIC contracts are the
Red Book (building and engineering works
designed by the Employer) and the Yellow
Book (M&E, building and engineering works
designed by the Contractor). The original
edition of the Red Book dates back to 1957.
In recent years FIDIC has published many
new contracts to complement the suite. The
first of the new contracts was the Orange
Book for design, build and turnkey works
published in 1995.
In 1999 FIDIC published a revised suite of
contracts with updated versions of the Red
and Yellow books together with a Green Book
as the short form of contract and a Silver
Book for turnkey contracts.
More recently in 2005 FIDIC published an
amended version of the Red Book for use by
Multilateral Development Banks and in 2007
published a seminar edition of the Gold Book
for Design, Build and Operate contracts.

Sub-contractors will similarly encounter FIDIC


derived conditions of contract where they are
operating internationally. Even subcontractors
that only operate within a particular country
will from time to time encounter FIDIC
derived conditions where they are operating
within a supply chain governed by a FIDIC
main contract.
Employers may also use FIDIC conditions
where the local standard conditions of
contract are not suited to the procurement
route and there is a need to avoid the risks
and expense of preparing a bespoke contract.
The different forms of contract within the
FIDIC suite are organised around the extent
of design and other responsibilities assumed
by the Employer and the Contractor. The suite
is therefore now aligned with common
procurement strategies rather than the nature
of the construction works.
Where works are predominantly designed by
the Employer, then the Red Book is the
appropriate form of contract. Where works
are predominantly designed by the Contractor
the Yellow Book is appropriate regardless of
whether the works were heavy civils or M&E.
The Silver Book is clearly intended for use on
Turnkey projects and the Gold Book where

m ak ing the d if f eren ce

The FIDIC Suite of Contracts


the contractor operates the asset in addition
to designing and building.
Employers may benefit from utilising FIDIC
conditions where potential bidders are from
different countries. In such cases the bidders
may perceive the use of the familiar FIDIC
conditions as increasing the attractiveness of
enquiry. This could translate into lower
tenders as the contract risks should be better
understood by the bidders.
The FIDIC forms can therefore be applied to a
wide range of differing engineering and
construction projects; from traditional civil
engineering to hi-tech windmills and heavy
duty oil and gas process plants.
FIDIC has reduced the number of clauses in
all of the recent contracts. The Orange Book
contained 20 clauses, as now do the Red,
Yellow and Silver Books. Previously, the Red
Book had 72 clauses.

taken to ensure that no ambiguity is created,


either with the General Conditions or between
the clauses in the Particular Conditions. It is
essential that all these drafting tasks, and the
entire preparation of the contract documents,
are entrusted to personnel with the relevant
experience of the contractual, technical and
procurement aspects of the project.
The suite does not currently include a
standard form of subcontract although in
2004 FIDIC stated that a Subcontract form
would be a desirable addition to suite. It is
expected that if a subcontract form is
published that a version for use with the Red
Book main contract will be first.
The main forms of contract are described
further in some detail below

FIDIC has also standardised the terms across


the full suite so that wherever possible the
same words and definitions have the same
meanings and the clauses are now grouped in
a logical manner across all the contracts.
Knowledge of one form of FIDIC conditions is
therefore of immediate benefit in respect of
other forms.
Each of the main conditions of contract in the
suite now contains a core of common
conditions with little significant difference
between them.
Amendments to the standard published FIDIC
contracts are incorporated by the inclusion of
Particular Conditions and guidance on how to
prepare the Particular Conditions is published
by FIDIC. Where Particular Conditions are
incorporated into the contract care must be

m ak ing the d if f eren ce

The FIDIC Suite of Contracts


Under the usual arrangements for this type of
contract, the Contractor constructs the Works
in accordance with design provided by the
Employer. However it may also be suitable for
contracts which include, or wholly comprise,
the contractors design.
An area of potential concern for Contractors is
that there is no reference to an impartial
Engineer in the contract. The contract
nominates a member of the Employers
personnel as the authorised person to fulfil
the traditional duties of the Engineer.

Green Book
Short Form of Contract
First Edition 1999
Contents of Contract Book






Agreement
General Conditions
Rules for Adjudication
Notes for Guidance

The Short Form of Contract is recommended


for engineering and building work of relatively
small capital value. The Guidance Notes for
the Green Book recommended that generally
it should not be used on projects with a
contact value greater than US$500,000.
However, depending on the type of work and
the circumstances, the Green Book may be
suitable for contracts of considerably greater
value.

The intention is that all contract documents


will be incorporated in the Appendices to the
Agreement. The Appendices will therefore
include such documents as the Contractors
offer and the Employers acceptance together
with all the correspondence in between.
The standard General Conditions are intended
to be applicable to the majority of projects
although it is possible to introduce Particular
Conditions if these are required to amend the
Green
Book
and
provide
for
special
circumstances of the project.
To assist in the preparation of tender and
contract documents Notes for Guidance are
included within the Green Book. However
these notes do not form part of the Contract.
It is interesting to note that the Green Book
includes Rules for Adjudication which is an
innovation for a suite of contracts that is
traditionally thought of as being relevant to
the international market and not domestic to
the UK.

It is a flexible document containing all the


essential administrative and commercial
arrangements. It is possible to easily amend
and supplement the provisions of the Green
Book with differing options incorporated via
the Appendix.
The Green Book is likely to be most suited
fairly simple or repetitive work or work of
short duration without the need for specialist
sub-contracts.

m ak ing the d if f eren ce

The FIDIC Suite of Contracts


such projects it would be more appropriate to
use the Yellow Book or Silver Book.
As with earlier versions of the Red Book
administration of the project and supervision
of the works is carried out by an Engineer
who is employed by the Employer. The
engineer is responsible, amongst other things,
for issuing instructions, certifying payments
and determining completion.

Red Book

Payments are normally determined by


measurement and applying the rates and
prices from the bill of quantities. There is an
option for payment to be on the basis of a
lump sum.

Conditions of Contract for Construction


For Building and Engineering works
designed by the Employer
First Edition 1999
Contents of Contract Book
 General Conditions
 Guidance for the Preparation of the
Particular Conditions
 Forms of Tender and Contract Agreement
 Dispute Adjudication Agreement
The Red Book provides conditions of contract
for construction works where the design is
carried out by the Employer. The current Red
Book bears little resemblance to
its
predecessors. Earlier versions of the Red Book
were drafted for use on civil engineering
projects. The current edition drops the words
civil engineering from the title and this
signifies a move away from the Red Book only
being applicable to civil engineering works.

Where the engineer is required to determine a


matter or settle a claim he is required to
consult with each of the parties to try and
reach an agreement. If agreement cannot be
reached the engineer must make a fair
determination taking due regard of all
relevant circumstances.
If an engineers determination is not agreed
by either of the parties then the dispute will
be referred to a Dispute Adjudication Board
for a decision. The DAB is formed of one or
three people who are jointly appointed by the
parties. If the decision of the DAB is not
accepted by any of the parties then the final
step will be resolution via an international
arbitration.

In line with the rest of the FIDIC suite the


focus is now more on type of procurement
rather than the nature of the works. The Red
Book
is
therefore
applicable
to
any
construction works were the Employer carries
out the design.

The General Conditions and the Particular


Conditions together comprise the Conditions
of Contract. Guidance is provided in the Red
Book for the preparation of Particular
Conditions should it be necessary to modify
the General Conditions. The Guidance also
contains various forms of security such as
parent company guarantee, advance payment
bond and a retention guarantee which can be
selected as applicable to the contract via the
Particular Conditions.

The Red Book is intended for use on projects


where the employer carries out the design but
it also allows for some elements of the project
to be Contractor designed. The Red Book is
not suitable for use where most of the works
are to be designed by the Contractor and for

This Red Book concludes with example forms


for the Letter of Tender, the Appendix to
Tender (providing a check-list of the subclauses which refer to it), the Contract
Agreement, and a Dispute Adjudication
Agreement.

m ak ing the d if f eren ce

The FIDIC Suite of Contracts






International Bank for Reconstruction and


Development (The World Bank)
Islamic Bank for Development Bank
Nordic Development Fund

It is expected that all of the participating


MDBs will adopt this edition of the FIDIC
document
in
their
standard
bidding
documents in the future.
Use of these MDB conditions should
significantly reduce the number of additions
and amendments to be included in the
Particular Conditions.

Red Book (MDB edition)


Conditions of Contract for Construction
For Building and Engineering works
designed by the Employer
MDB Edition 2005
Contents of Contract Book






General Conditions
Guidance for the Preparation of the
Particular Conditions
Forms of Tender and Contract Agreement
Dispute Adjudication Agreement

As part of their standard bidding documents


the Multilateral Development Banks (MDBs)
have for a number of years required their
borrowers or aid recipients to adopt the FIDIC
Conditions of Contract.
The FIDIC MDB edition of the Red Book
simplifies the use of the FIDIC contract for the
MDBs, their borrowers and others involved
with project procurement, such as consulting
engineers, contractors and contract lawyers.

Nevertheless, most projects will have special


requirements which will necessitate some
specific changes. The contract therefore
retains provision for Particular Conditions as is
common with other FIDIC contracts.
As with the main Red Book this MDB edition
also includes sample forms for Contract Data,
Securities, Bonds, Guarantees and Dispute
Board agreements.
In most cases, the amendments which have
been made to produce the MDB edition are
those arising from the requirements of the
MDBs, except for some minor changes of an
editorial nature.
However, in the case of the dispute provisions
contained in Clauses 20.2 to 20.8 and in the
associated Appendix, the opportunity has
been taken to make other amendments which
FIDIC considered an improvement on the
earlier wording as contained in the Red Book
1999 edition.

The following MDBs that have all participated


in the preparation of this edition of the Red
Book:








African Development Bank


Asian Development Bank
Black Sea Trade and Development Bank
Caribbean Development Bank
European Bank for Reconstruction and
Development
Inter-American Development Bank

m ak ing the d if f eren ce

The FIDIC Suite of Contracts


Administration of the project and supervision
of the works is carried out by an Engineer
who is employed by the Employer. The
Engineer is responsible, amongst other
things, for issuing instructions, certifying
payments
and
determining
completion.
Interim payments of the lump sum Contract
Price are made as work proceeds, and are
typically based on instalments specified in a
schedule

Yellow Book
Conditions of Contract for
Plant and Design-Build
For electrical and mechanical plant, and for
building works, designed by the Contractor
First Edition 1999
Contents of Contract Book
 General Conditions
 Guidance for the Preparation of the
Particular Conditions
 Forms of Tender and Contract Agreement
 Dispute Adjudication Agreement
The Yellow Book provides conditions of
contract for construction works where the
design is carried out by the Contractor. The
current Yellow Book bears little resemblance
to its predecessors. The current edition drops
the words electrical and mechanical works
from the title and in line with the rest of the
FIDIC suite the focus is now more on type of
procurement rather than the nature of the
works.
The Yellow Book is therefore applicable to the
provision of electrical and/or mechanical
plant, and for the design and execution of
building or engineering works. Under the
usual arrangements for this type of contract,
the Contractor designs and provides the
works in accordance with the Employers
requirements
which
may
include
any
combination of civil, mechanical, electrical
and/or construction works.

Where the engineer is required to determine a


matter or settle a claim he is required to
consult with each of the parties to try and
reach an agreement. If agreement cannot be
reached the engineer must make a fair
determination taking due regard of all
relevant circumstances. If an engineers
determination is not agreed by either of the
parties then the dispute will be referred to a
Dispute Adjudication Board for a decision. The
DAB is formed of one or three people who are
jointly appointed by the parties. If the
decision of the DAB is not accepted by any of
the parties then the final step will be
resolution via an international arbitration.
The General Conditions and the Particular
Conditions together comprise the Conditions.
Guidance is provided for the preparation of
Particular Conditions should it be necessary to
modify the General Conditions. The Guidance
also contains various forms of security such
as parent company guarantee, advance
payment bond and a retention guarantee
which can be selected as applicable.
The General Conditions as drafted may not
suit the Employers particular needs (for
example the standard inclusion of advance
payments). Care must be taken in the
preparation of the Particular Conditions and
completion of the Appendix to avoid creating
ambiguities around such conditions. A major
area for consideration when preparing
Particular Conditions is the risk allocation for
ground conditions which is an Employer risk in
the standard draft.
The Yellow Book concludes with example
forms for the Letter of Tender, the Contract
Agreement, and a Dispute Adjudication
Agreement.

m ak ing the d if f eren ce

The FIDIC Suite of Contracts


The Orange Book is drafted for use where the
Contractor carries total liability for design. For
the Employer, such single-point responsibility
may be advantageous, but the benefits may
be offset by having less control over the
design process and more difficulty in imposing
varied requirements.
Under the usual arrangements for a designbuild contract, the Contractor is responsible
for the design and provision of works. The
works may include any combination of
engineering (including civil, mechanical,
electrical, etc) and building works.

Orange Book
Conditions of Contract for
Design-Build and Turnkey
First Edition 1995
Contents of Contract Book
 General Conditions
 Guidance for the Preparation of the
Particular Conditions
 Forms of Tender and Agreement
The Orange book was published in 1995 to
provide a design and build option to the then
current FIDIC suite. The Orange Book was the
first FIDIC contract to adopt the now current
FIDIC style of drafting and was a template for
the drafting teams when preparing the 1999
suite of contracts.
When the Orange book was published the Red
and Yellow Books were still aimed at
procurement of civil engineering and plant
installation respectively. At the time it added
a clear design and build and turnkey option
into the available suite of contracts.
Since the publication in 1999 of the latest Red
and Yellow Books there is now less focus on
the type of project and more focus on the
implementation of different procurement
strategies. It is now likely that an Employer
requiring a design and build or turnkey
project under a FIDIC contract would use a
1999 edition of the Yellow Book for design
and build or a Silver Book for Turnkey.

The Orange Book is intended for use on


turnkey
contracts,
under
which
the
Employer's requirements usually include
provision of a fully-equipped facility, ready for
operation at the turn of a key. The exact
Employer requirements will need to be fully
detailed to describe the design, construction,
fixtures, fittings and equipment required to be
provided by the Contractors design.
When used for turnkey projects it may be
necessary to impose a requirement for the
Contractor to operate the Works, either for a
few months' commissioning period, or for
some years' operation on a build-operatetransfer basis. If this is the case then the
FIDIC Gold Book may now be more
appropriate.
There are many sub-clauses within the
Orange Book which FIDIC decided were
generally applicable and these are included in
Part I - General Conditions. The Orange Book
is arranged to accommodate modification and
supplementing of the General Conditions by
the inclusion of Part II - Conditions of
Particular Application. The Orange Book
contains a section of guidance on preparing
the Part II conditions. The Part I and Part II
conditions together govern the rights and
obligations of the parties.

m ak ing the d if f eren ce

The FIDIC Suite of Contracts


assumes responsibility, subject to some
exceptions, for the accuracy of the Employers
Requirements which is a major difference to
usual design and build contracts.
Given the high level of risk transfer the
Employer must allow time sufficient time in its
procurement programme for the Contractor to
obtain and consider all relevant information
before signing the contract.

Silver Book
Conditions of Contract for
EPC/Turnkey Projects
First Edition 1999
Contents of Contract Book
 General Conditions
 Guidance for the Preparation of the
Particular Conditions
 Forms of Tender and Contract Agreement
 Dispute Adjudication Agreement
The Silver Book is suitable for use on process,
power and private-infrastructure projects
where a Contractor is to take on full
responsibility for the design and execution of
a project. Risks for completion to time, cost
and quality are transferred to the Contractor
and so the Silver Book is only suitable for use
with experienced Contractors familiar with
sophisticated risk management techniques.
For many large projects construction is only
one part of a wider complicated commercial
venture and financial or other failure of the
construction project will jeopardize the whole
venture. The Silver Book approach may suit
such projects as it will provide a greater level
of cost certainty than can be achieved under
the more traditional forms of the FIDIC suite.
To obtain this increased cost certainty the
Silver Book requires the Contractor to accept
a higher level of risk than is typical under
most other forms of contract. The Silver Book
transfers the risk of ground conditions to the
Contractor. Similarly the Contractor also

Not all risk is passed to the Contractor under


the Silver Book and the Employer still retains
risks for war, terrorism and Force Majeure.
Through the use of Particular Conditions it is
possible for the Employer and Contract to
agree alternative risk sharing arrangements
before entering into the Contract.
Following award of a project under the Silver
Book the Contractor will be given freedom to
carry out the work in his chosen manner,
provided
the
end
result
meets
the
performance
criteria
specified
by
the
Employer. Consequently, the Employer should
only exercise limited control over the
Contractors work.
There is no reference to an Engineer in the
Silver Book. This is because the Employers
reduced
influence
on
the
engineering
generally. Checking of engineering is more
concentrated
on
validating
the
endperformance and validating the potential ease
of operation, maintenance and spares.
The Silver Book provides conditions relating to
Tests on Completion and Taking Over only
takes place after successful completion of the
tests. Such provisions are important for
EPC/Turnkey projects where the purpose of
the contract is to provide the Employer with a
working facility.
Guidance is provided for the preparation of
Particular Conditions should it be necessary to
modify the General Conditions.
As with the other FIDIC contracts the Silver
Book contains various forms of security and
concludes with example forms for the Letter
of Tender, the Contract Agreement, and a
Dispute Adjudication Agreement.

m ak ing the d if f eren ce

The FIDIC Suite of Contracts


Operation Period differs significantly from the
20 years adopted.
The document is recommended for general
use where tenders are invited on an
international basis.
The contract attempts to include all conditions
of a general nature, which are likely to apply
to the majority of DBO contracts, as General
Conditions.

DBO Contract
Conditions of Contract for
Design, Build and Operate Projects
First Edition 2008
Contents of Contract Book
 General Conditions
 Particular Conditions
 Sample Forms
Following publication of the Orange Book in
1995 and the Red, Yellow and Green Books in
1999 it became clear that there was a
growing need for a contract combining a
design-build obligation with a long-term
operation commitment.
The approach and layout of the DBO contract
is more similar to the FIDIC Silver book than
any other contract within the FIDIC suite.
The DBO contract adopts a green-field DBO
scenario with a 20 year operation period and
a single contract awarded to a single
contracting entity (which will almost certainly
be a consortium or joint venture) to optimise
the coordination of innovation, quality and
performance, rather than award separate
contracts for design-build and for operation.
Under the DBO contract the Contractor has no
responsibility for either financing the project
or for its ultimate commercial success.

However it is recognised that many employers


or
governments,
or
even
different
jurisdictions, particularly if the conditions
were to be used on domestic contracts, may
require special conditions of contract, or
indeed particular procedures, which differed
from those included in the General Conditions.
For this reason, the DBO document Particular
Conditions Part B Special Provisions includes
advice to drafters of contract documents who
wish to add Special Provisions to replace or
supplement the clauses to be found in the
General Conditions.
Users who wish to adopt the conditions for
use with a different scenario (such as a brown
field operate, design, build) or with an
operation period significantly different to the
20-year period assumed, are referred to the
DBO Contract Guide which identifies the
clauses which will require amending by
including Special Provisions, and gives
comprehensive guidelines and suggestions on
how the various issues should be addressed.
Successful performance of a long-term DBO
contract requires that the parties fully
understand the overall time framework and
the need for a long-term commitment by both
the employer and the contractor. It has
therefore been necessary to introduce new
procedures and new terminology which are
not to be found in the other FIDIC forms of
contract.

The DBO contract, as written, is not suitable


for contracts which are not based on the
traditional DBO sequence, or where the

m ak ing the d if f eren ce

You might also like