Unit2 Multi
Unit2 Multi
2.
8.
(B)
(C)
(D)
6.
$207 000
3 764 units
$253 000
2 070 units
7.
12 500
18 750
20 000
25 000
4.
5.
3.
(A)
(B)
(C)
(D)
period cost
manufacturing overhead
product cost
administrative cost
realized cost
opportunity cost
conversion cost
accrued cost
Meave Company used a predetermined overhead rate last year of $2 per direct labour hour, based on an estimate
of 37 500 direct labour hours to be worked during the year. Actual costs and activity during the year were:
Actual manufacturing overhead cost incurred
Actual direct labour hours worked
$70 500
36 000
10.
$1 500 under-applied
$1 500 over-applied
$3 000 under-applied
$4 500 over-applied
$110 000
$111 000
$113 400
$115 500
$12 000
$15 000
$16 875
$18 750
Product Period
$ 792
$198
$2 376
$594
$1 584
$396
$2 970
$0
11.
13.
The Malda Company requires 60 000 units of Product Q for the year. The units will be used evenly throughout
the year. It costs $90 to place an order. It costs $10 to carry a unit in inventory for the year. What is the
economic order quantity (EOQ) rounded to the nearest whole unit?
(A) 600
(B)
735
(C)
900
(D) 1 040
14.
Pinder Company uses FIFO method in its process costing system. Department A is the first stage of the
companys production process. The following pertains to conversion costs for May for Department A:
Units
Work in process, beginning (40% complete)
44 000
Started in April
Completed in April and transferred to Department B
Work in process, ending (60% complete)
352 000
374 000
22 000
352 000
369 600
387 200
396 000
15.
16.
17.
A cost that would be included in product costs under BOTH absorption costing and
variable costing would be
(A)
(B)
(C)
(D)
18.
The following diagrams represent cost behaviour patterns that might be found in a company's
cost structure. The vertical axis represents the total costs and the horizontal axis represents
levels of activity (volume). Which graph illustrates the cost pattern for an electricity bill made
up of flat charge plus a variable cost after a certain number of kilowatt hours are used?
(A)
19.
Output
(B)
Output
20.
supervisor's salary
machinery depreciation
variable manufacturing costs
variable selling expenses
(A)
(B)
(C)
(D)
50
Output
(C)
21.
Output
22.
(D)
normal standards
practical standards
ideal standards
budgeted standards
23.
The Caswell Company uses a job-order cost system. The following information was recorded for
September:
Added during September
Job Number
September 1
Inventory
Direct
Materials
Direct Labour
$1 500
$ 450
$300
2
3
4
2 100
750
375
2 250
6 000
450
225
600
1 125
The direct labour wage rate is $15 per hour. Overhead is applied at the rate of $7.50 per
direct labour hour. Jobs 1, 2, and 3 have been completed and transferred to finished goods.
Job 2 has been delivered to the customer.
The ending Work in Process inventory is
(A)
(B)
(C)
(D)
$ 6488
$ 7 725
$ 8025
$11363
26.
24.
The Penny Corporation's direct labour cost is 25% of its conversion cost. If the
manufacturing overhead cost for the last period was $45 000 and the direct materials
cost was $25 000, what was the direct labour cost?
(A) $15 000 (B) $20 000 (C) $33 333 (D)
25.
$60 000
Joan Giles is paid 10 % of the gross sales of her department as salary per month. Joan
27.
received $15 000 each month for the last three months. Which of the following
methods BEST describes how Joan is paid?
$320,
$550,
$600,
$640,
Indirect
Cost
Job
Cost
$600,
$450,
$320,
$600,
$ 920
$1 300
$ 920
$1 240
A machine was purchased at a cost of $20000. The machine will provide cost savings of $3
500 EACH year for TEN years, after which time it will have a salvage value of $2 500. If the
company's discount rate is 12 %, what is the net present value of the machine? (See
Appendix on page 13 for tables)
(A)
(B)
(C)
(D)
($ 225)
$ 580
$ 2 275
$17 500
2004
28.
Cost
and
Management
Accounting is different from
Financial Accounting in ALL of
the following ways EXCEPT that
31.
30.
$56
$63
$70
$94.50
A standard cost is
(A)
maxi
ahead
cost
(B)
mum profit
a target cost for the period
(C)
the average cost of
production in
the cost period
(D)
always greater than active
32.
(B)
(C)
(D)
34.
33.
other conventional
methods.
Controllable costs can BEST be
defined as
(A)
(B)
of
plant expansion
costs which are the
responsibility of a
manager
costs which are the
responsibility of employees
(C)
35.
December 2001
January 2002
February 2002
36.
Purchases
$
16 000
14 000
20 000
37.
Sales
$
30 000
25 000
18 000
$ 1 800
$ 2 500
$ 25 000
$ 29 500
38.
$14 000
$16 000
$20 000
$25 000
How much cash was collected from credit sales in the month of February 2002?
(A)
(B)
(C)
(D)
$16 200
$22 500
$24 000
$27 000
53
39.
What is the BEST method of payment to employees that could be used by a firm when
output is difficult to measure and where wages are not affected by the level of output?
(A)
(B)
(C)
(D)
40.
Bonus
Piece-rate
Fixed salary
Commission
Which of the following BEST describes the type of costing often called 'full costing'?
(A)
(B)
(C)
(D)
Standard costing
Variable costing
Activity-based costing
Absorption costing
allocation in its cost centre No. 10. Cost data for a production period are as follows:
Estimated
Overheads
Machine hours
Prime cost
41.
$
82 605
7 210
126 000
42.
$
85 000
7 500
125 000
Actual
$ 619 under-absorption
$ 916 over-absorption
$ 916 under-absorption
$9 116 over-absorption
54
43.
44.
Managerial accounting
(A)
(B)
(C)
1 year
2 years
3 years
4 years
(D)
45.
What is the value assigned to the ending inventory if Worme uses the last in first out method
LIFO)?
(A)
(B)
(C)
(D)
46.
$4 480
$5 040
$5 360
$5 432
What is the value assigned to the ending inventory if Worme uses the first in first out method
(FIFO)?
(A)
(B)
(C)
(D)
$4 480
$5 040
$5 360
$5 432
55
49.
(B)
(C)
(D)
50.
$1000 adverse
$7 100 adverse
$8 100 adverse
$9 000 adverse
The net present value of a project is positive. However, the company did not accept
this project. One can assume that for this
project
(A)
48.
600
690
800
864
51
(A)
(B)
(C)
(D)
$93000
000 $163 000
000
52.
$158
$218
.
Berbice Co. applies overheads to jobs at the
rate of 40 per cent of direct labour cost. Direct
materials of $1 250 and direct labour of
$ 1 400 were expended on Job AB - 424 during
June. At May 31, the balance of Job AB
-424 was $2 800. What was the June 30
balance ?
(A)
(B)
(C)
(D)
56
$7 100 adverse
$7 200 favourable
$8 100 adverse
$8 100 favourable
$3210
$4760
$5450
$6010
53.
54.
machine hours
standard material cost
direct labour
number of complaints
(A)
(B)
(C)
(D)
$ 677
$1 391
$2 142
$4658
57
2005
55.
28.
58.
$2500
15
56.
18
(B)
(C)
(D)
1 125 (A)
Ibs 1 (B)
732 Ibs (C)
4 082 (D)
Ibs
1 125 lbs
1 732 lbs
4 082 lbs
5 774 lbs
57.
requires a group of
accounts that is entirely
different from the group
of accounts used in
financial accounting
focuses solely on
determining how much it
costs to manufacture a
product or provide a
service
provides
product/service cost
information as well as
information for internal
decision making
is required for business
record-keeping as are
financial accounting and
tax accounting
59.
(A) $2 713
(B) $2 770
(C) $2 812
(D) $3 025
Tony Persad applies overheads to
jobs at the rate of 40 per cent of
direct labour cost. Direct material of
$1 250 and direct labour of $1 400
were expended on Job No. 44
during June. At May 31, the balance
of Job No. 44 was $2 800. What was
the June 30 balance of job No. 44?
(A) $3 210
(B) $4 760
(C) $5 450
(D) $6 010
A firm estimates that its annual carrying cost for material ABC is $.30 per lb, demand is 50 000 lbs, and ordering costs are $100 per order. The EOQ (rounded to the
nearest pound) is
60.
61.
$2 700 U
$2 700 F
$2 610 F
$2 610 U
$1 050 F
$1 890 F
$3 105 F
$3 105 U
63.
Activity
Cost Pool
Estimated
Cost
Expected Activity
Product A
Product B Total
Moulding
Waxing
Finishing
$17 600
$12 000
$26 000
800
500
800
300
200
400
1 100
700
1 200
(A) $18.53
(B) $21.67
(C) $46.33
(D) $65.00
What cost is to be allocated to
Product A for moulding?
(A)
(B)
$12 800
$17 336
(C)
(D)
$17 600
$38 700
65.
11500
12000
12500
14000
(C)
(D)
67.
68.
66.
realized cost
opportunity cost
conversion cost
accrued cost
(A)
(B)
(C)
(D)
69.
Prime Cost
no
yes
yes
yes
Product Cost
yes
no
yes
yes
Direct Cost
yes
yes
no
yes
yes
no
yes
no
Eversley Inc. manufactures products on a job order basis. The job cost sheet for Rose Hill job shows the
following for March:
Direct materials
Direct labour (100 hours at $7.25)
Machine hours incurred
Predetermined overhead rate per machine hour
$5 000
$ 725
40 hours
$ 26
At the end of March, the total cost appearing on the Rose Hill job cost sheet will be
(A)
(B)
(C)
(D)
$5725
$5765
$6765
$8325
60
70.
(A)
(B)
(C)
(D)
37 800
40 200
40 800
42 000
73.
74.
71.
Alex Co. makes small metal containers. In
December the company began with 250
containers in its work-in-process inventory
that were 30 per cent completed as to
material and 40 per cent completed as to
conversion costs. During the month, 5 000
containers were started. At month end, 1
700 containers were still in its work-inprocess inventory (45 per cent completed
as to material and 80 per cent completed
as to conversion costs). The company uses
the weighted average method. The
equivalent units for conversion costs for the
month of December are
(A)
(B)
(C)
(D)
(C)
(D)
75.
3450
4560
4610
4910
(A)
72.
(B)
(C)
(D)
Direct
Job Cost
Indirect
Cost
Cost
The Net Present Value method of evaluating proposed investments
measures a project's internal rate of
ignores cash flows beyond the
return
payback period
(A)
(B)
(C)
(D)
$ 640
$1 100
$1200
$1240
$1200
$ 900
$ 640
$1200
$1 840
$2000
$1 840
$2480
61
78.
76..
77.
RoseHall Inc. is considering the purchase
of a $100 000 machine that is expected to
result in a decrease of $15 000 per year in
cash expenses. This machine, which has
no residual value, has an estimated useful
life of 10 years and will be depreciated on
the straight-line basis. What would be the
accounting rate of return for this machine?
(A)
(B)
(C)
(D)
(A)
(B)
(C)
(D)
250
750
1 000
1250
79. .
15 per cent
20 per cent
25 per cent
35 per cent
80
81.
step-down method
reciprocal allocation method
direct allocation method
sequential allocation method
The Indian Grill Corporation had the following balances in its records:
50 000
48 000
180 000
195 000
1 220 000
62
2007
82.
83.
Beginning inventory
Purchases August 5
Purchases August 15
Ending inventory
(C)
85.
(A)
(B)
(C)
(D)
(D)
84.
(D)
emphasizes a current
perspective
allows the use of a budget
$ 8 960
$10 080
$10 720
$10 864
87.
88.
$56.00
$63.00
$70.00
$94.50
63
89.
(B)
(C)
(D)
90.
(C)
(D)
(B)
(C)
(D)
(C)
(D)
supervisor's salaries
machinery depreciation
variable manufacturing costs
variable selling expenses
94.
95.
92.
91.
93.
96.
64
97.
101.
An investment project with an initial
investment of $ 10 000 will produce cash flows as
follows: $5 100 in Year 1, $3 600 in Year 2, $1
300 in Year 3, and $2 800 in Year 4. What is
the payback period for this project?
(A)
(B)
(C)
(D)
(B)
(C)
(D)
99.
The net present value and the internal rate of
return are MORE effective methods of capital
budgeting than the payback method because
they
(A)
(B)
(C)
(D)
100.
Which of the following are NOT period
costs?
(A)
(B)
(C)
(D)
(B)
(C)
1 year
2 years
3 years
4 years
98.
The net present value of a project is positive.
However, the company did not accept this
project. One can assume that, for this project,
(A)
(A)
Marketing costs
General and administrative costs
Research and development costs
Manufacturing costs
(D)
102.
(A)
fixed
(B)
variable
(C)
avoidable
(D)
sunk
In March 2007, the beginning balance of the
raw materials inventory account for Kyla Inc
was $46 000. The ending inventory balance for
103.
July was $47 000. Raw materials used during
the month totalled $127 120. The cost of raw
materials purchased during the month was
(A)
(B)
(C)
(D)
$125320
$126120
$128120
$174120
65
105.
(A)
(B)
(C)
(D)
$15 000
$25000
$37500
$75 000
Items 106- 107 refer to the f o llo w in g
108.
information.
The Claudia Corporation used a weightedaverage process costing system. The firm
started production of 75 000 units. It
completed and transferred out 85 000 units.
The ending work-in-process comprised 10 000
(A)
(B)
(C)
(D)
$ 180.00
$ 1 000.00
$ 1 180.00
$ 2 450.00
What is the conversion cost per equivalent
unit in April?
109.
units that were 40 per cent complete. All
direct material costs were added at the
beginning of the process.
106.
(A)
(B)
(Q
(D)
The equivalent units for direct materials are
(A)
(B)
(C)
(D)
75000
85000
89000
9500
107.
$ 300.00
$1 111.11
$1 411.11
$2 722.22
66
110.
GuyCo Disk Company has beginning work-inprocess of 100 000 units that is 90 per cent
complete as to conversion costs. The
company started production of 300 000 units
during the current period and completed and
transferred out 350 000 units. The ending
work-in-process inventory consisted of 50 000
units which were 65 per cent complete as to
conversion costs. The equivalent units of
production for conversion cost using the
F.I.F.O. method are
113.
112.
James purchases tyres at $300 each and sells
them for $400 each. His fixed costs are $8
000. How many tyres will James need to sell in
order to break even?
(A)
(B)
(C)
(D)
111.
40
60
80
100
(D)
$ 7.30
$11.30
$11.55
$13.05
67
117.
2.50
$ 1.75
$21 875
(A)
(B)
(C)
(D)
10 000
$26 250
118.
(A) $4 375.00 U
(B) $4 375.00 F
(C) $6 562.50 U
(D) $8 750.00 U
(B)
(C)
(D)
119.
115.
What is the variable overhead efficiency
variance?
(A)
(B)
(C)
(D)
$2187.50
U
$2187.50 F $2
937.50 F $9
937.50 F
116.
120.
period costs
prime costs
overhead costs
conversion costs
121.
Ending
$ 6 000
$ 7 500
$17 300
$11 700
122.
Direct labour is $9.60 per hour and overhead
for the month is $9 600. The company uses 1
500 direct labour hours and purchases $21
000 of raw material.
The total manufacturing costs for June are
123.
The prime costs for June are
A.
B.
C.
D.
$14 400
$33 900
$
$
Allocation
measure
Total Cost
$150 000
Reviewing
Number of
$175 000
receiving reports receiving reports
Making phone
calls
Number of
phone calls
$225 000
$ 26 250
$ 61 250
$ 70 000
$175 000
A.
$ 40 250
B.
$ 95 750
C.
$136 000
D.
$225 000
Items 127 129
refer to the following information.
Panday Inc uses a job order costing system
and the following information is available
from its records. The company has the
following jobs in process: Numbers 5, 8, and
12. The raw materials used cost $120 000,
direct labour costs $8.50 per hour; and factory
overhead is applied at a rate of $10.20 per
direct labour hour. Direct labour hours per
job are 2 500, 3 100, and 4 200, respectively.
127.
130.
What is the total amount of overhead applied
to Job Number 8?
(A)
(B)
(C)
(D)
$18 250 $26 350
$30 000 $31 620
.128
(A)
(B)
(C)
(D)
129.
The direct material was requisitioned for each
job (Numbers 5, 8 and 12) at 30 per cent, 25
per cent, and 25 per cent, respectively. The
$2 700 F
$2 700 U
$2610F
$2610U
(A)
(B)
(C)
(D)
$6 960 under-applied
$6 960 over-applied
$63 960 over-applied
$63 960 under-applied
132.
$1 050 F
$1 890 U
$3 105 F
$3 105 U
133.
134.
ideal standards
practical standards
normal standards
budgeted standards
(B)
(C)
(D)
$ 141 550
$30 000
8 years
12 per cent
10.0
5.335
12.0
4.968
12.5
4.882
13.0
4.799
13.5
4.718
14.0
4.639
14.4
4.562
71
APPENDIX
Present Value of $1
1%
1
2
3
4
5
6
7
8
9
10
0.9901
0.9803
0.9706
0.9610
0.9515
0.9420
0.9327
0.9235
0.9143
0.9053
2%
0.9804
0.9612
0.9423
0.9238
0.9057
0.8880
0.8706
0.8535
0.8368
0.8203
4%
0.9615
0.9246
0.8890
0.8548
0.8219
0.7903
0.7599
0.7307
0.7026
0.6756
6%
0.9434
0.8900
0.8396
0.7921
0.7473
0.7050
0.6651
0.6274
0.5919
0.5584
8%
0.9259
0.8573
0.1400
0.0840
0.5194
0.6162
0.0535
0.0215
0.6256
0.8086
10%
0.9091
0.8264
0.7513
0.6830
0.6209
0.5645
0.5132
0.4665
0.4241
0.3855
12%
14%
16%
0.8929
0.7972
0.7118
0.6355
0.5674
0.5066
0.4523
0.4039
0.3606
0.3220
0.8772
0.7695
0.6750
0.5921
0.5194
0.4556
0.3996
0.3506
0.3075
0.2697
0.8621
0.7432
0.1549
0.1083
0.4867
0.5396
0.0623
0.0317
0.5806
0.7321
12%
14%
16%
2%
4%
6%
8%
10%
0.9901
0.9804
0.9615
0.9434
0.9259 0.9091
0.8929
0.8772
0.8621
2
3
4
5
6
7
8
9
10
1.9704
2.9410
3.9020
4.8534
5.7955
6.7282
7.6517
8.5660
9.4713
1.9416
2.8839
3.8077
4.7135
5.6014
6.4720
7.3255
8.1622
8.9826
1.8861
2.7751
3.6299
4.4518
5.2421
6.0021
6.7327
7.4353
8.1109
1.8334
2.6730
3.4651
4.2124
4.9173
5.5824
6.2098
6.8017
7.3601
1.7833
1.9232
2.0073
2.5267
3.1429
3.1964
3.2179
3.8435
4.6521
1.6901
2.4018
3.0373
3.6048
4.1114
4.5638
4.9676
5.3282
5.6502
1.6467
2.3216
2.9137
3.4331
3.8887
4.2883
4.6389
4.9464
5.2161
1.6052
1.7601
1.8684
2.3552
2.8947
2.9570
2.9887
3.5693
4.3013
1.7355
2.4869
3.1699
3.7908
4.3553
4.8684
5.3349
5.7590
6.1446
72