Validation Report 7.5 MW Lubuk Gadang Small Hydropower Plant at West Sumatera, Indonesia in Indonesia
Validation Report 7.5 MW Lubuk Gadang Small Hydropower Plant at West Sumatera, Indonesia in Indonesia
Validation Report
01 997 9105065323
I. Project description:
Project title:
Host Country:
Indonesia
AMS-I.D. version 17
Methodology:
Large Scale
Small Scale
Party
Project Participants
Indonesia (Host)
Switzerland
No
Contract party
II. Validation:
Validation Team
India
India
Indonesia
----
Indonesia
----
Mr. Kanal M. P
India
X
X
X
X
Validation Phases:
Desk Review
Follow up interviews
Resolution of outstanding issues
Validation Status:
Corrective Actions / Clarifications Requested
Full Approval and Submission for Registration
Rejected
Version No.:01
Page 2
Trainee TR
India
Expert to TR
Technical Reviewer
Trainee Auditor
India
Team Member
(Auditor)
Technical Expert
Appointed for
Sectoral Scopes
Full name
Local Expert
Affiliation
TV Rheinland
Team leader
Role
Validation Report
01 997 9105065323
Released
Version No.:01
Distribution
No distribution without permission from the
Client or responsible organizational unit
Unrestricted distribution
Page 3
Validation Report
01 997 9105065323
Validation criteria
The following CDM requirements have been considered:
- Article 12 of the Kyoto Protocol,
- Modalities and procedures for CDM (Marrakech Accords)
- Subsequent decisions by the COP/MOP and CDM Executive Board
- Host country criteria
- Criteria given to provide for consistent project operations, monitoring and reporting.
The host part is Indonesia and the Annex I country is Switzerland. Both parties fulfill the participation
criteria and have approved and authorized the project and the project participants. The DNA from
country name confirms that the project assists in achieving sustainable development.
The project correctly applies the baseline and monitoring methodology AMS-I.D., version 17, Grid
connected renewable electricity generation.
The project results in reductions of CO2 emissions that are real, measurable and give long-term benefits
to the mitigation of climate change. It is demonstrated that the project is not a likely baseline scenario.
Emission reductions attributable to the project are hence additional to any that would occur in the
absence of the project activity.
This validation did not reveal any information that indicates that the project can be seen as a diversion
of ODA funding towards Indonesia.
Version No.:01
Page 4
Validation Report
01 997 9105065323
The monitoring plan provides for the monitoring of the projects emission reductions. The monitoring
arrangements described in the monitoring plan are feasible within the project design and it is TRCs
opinion that the project participants are able to implement the monitoring plan.
By generating renewable electricity which will displace fossil fuel based grid electricity, the project
results in the reductions of CO2 emissions that are real, measurable and give long term benefits to the
mitigation of climate change.
The total emission reductions from the project are estimated to be 229,642 t of CO2e over a 7 year
crediting period, averaging 32,806 t of CO2e annually. The emission reduction forecast has been
checked and it is deemed likely that the stated amount is achieved given the underlying assumptions
do not alter.
The validation protocol describes total of (17) findings which include:
Nine (9) Corrective Action Requests (CARs);
Eight (8) Clarification Requests (CLs);
No Forward Action Requests (FAR) was raised during this validation; and all findings have been closed
satisfactorily.
TRC concludes that the CDM Project Activity 7.5 MW Lubuk Gadang Small Hydropower Plant at West
Sumatera, Indonesia, as described in the PDD version 05 dated 27/12/2012 meets all the relevant
UNFCCC for CDM project activities including article 12 of the Kyoto Protocol, the modalities and
procedures for CDM (Marrakesh Accords) and the subsequent decisions by the COP/MOP and CDM
Executive Board.
The selected baseline and monitoring methodologies (AMS-I.D., Version 17) are applicable to the
project and correctly applied. The TRC therefore requests the registration of the project as a CDM
project activity with UNFCCC.
Mr. Raj Kumar Deka (Team Leader)
Version No.:01
Page 5
Validation Report
01 997 9105065323
Abbreviation:
BE
Baseline Emissions
BM
Build Margin
CA
CAR
CDM
CERs
CL
Clarification Request
CM
Combined Margin
CO2
Carbon dioxide
CO2e
DNA
DOE
EB
EIA
ER
Emission Reductions
FAR
FSR
GHG
Greenhouse gas(es)
GSC
IDR
Indonesian Rupiah
IPCC
kWh
Kilowatt hour
Leakage
LoA
Letter of Approval
MHPP
MoV
Means of Verification
MP
Monitoring Plan
MWe
Megawatt electrical
MWh
Megawatt hour
N/A
Not Applicable
O&M
Version No.:01
Page 6
Validation Report
01 997 9105065323
ODA
OM
Operating Margin
PDD
PLF
PP
Project Participant
PPA
QC/QA
SCAL
SD
Sustainable Development
SSC PA
UKL
UNEP
UNFCCC
UPL
VVM
WACC
Version No.:01
Page 7
Validation Report
01 997 9105065323
TABLE OF CONTENTS
1
1.1
1.2
INTRODUCTION .........................................................................................................................9
Objective
9
Scope
9
2
2.1
2.2
2.3
2.4
2.5
METHODOLOGY ..................................................................................................................... 10
Desk Review of the Project Design Documentation
10
Follow-up Interviews with Project Stakeholders
12
Resolution of Outstanding Issues
14
Internal Quality Control
16
Validation Team
16
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
VALIDATION FINDINGS........................................................................................................... 16
Approval and Participation
16
Project Design Document
18
Project Description
18
Baseline and Monitoring Methodology
20
Additionality
36
Monitoring
47
Sustainable Development
50
Environmental Impacts
50
Local Stakeholder Consultation
51
Comments by Parties, Stakeholders and NGOs
51
Version No.:01
Page 8
Validation Report
01 997 9105065323
1 INTRODUCTION
The organization Swiss Carbon Assets Ltd has commissioned the DOE
TV Rheinland (China) Ltd. to perform a validation of the CDM Project Activity 7.5 MW Lubuk
Gadang Small Hydropower Plant at West Sumatera, Indonesia in Indonesia (hereafter called
the project). This report summarizes the findings of the validation of the project, performed
on the basis of UNFCCC criteria for the CDM, as well as criteria given to provide for consistent
project operations, monitoring and reporting. The term UNFCCC criteria refers to Article 12
of the Kyoto Protocol, the CDM modalities and procedures or the simplified modalities and
procedures for small-scale CDM project activities (as applicable) and the subsequent decisions
by the CDM Executive Board.
1.1 Objective
The purpose of a validation is to have an independent third party assess the project design. In
particular, the project's baseline, monitoring plan, and the projects compliance with relevant
UNFCCC and host Party criteria are validated in order to confirm that the project design, as
documented, is sound and reasonable and meets the identified criteria. Validation is a
requirement for all CDM projects and is seen as necessary to provide assurance to
stakeholders of the quality of the project and its intended generation of certified emission
reductions (CERs).
1.2 Scope
The validation scope is defined as an independent and objective review of the project design
document (PDD). The PDD is reviewed against the relevant criteria (see above) and decisions
by the CDM Executive Board, including the approved baseline and monitoring methodology.
The validation team has, based on the recommendations in the Validation and Verification
Manual employed a rule-based approach, focusing on the identification of significant risks for
project implementation and the generation of CERs.
The validation is not meant to provide any consulting towards the project participants.
However, stated requests for clarifications and/or corrective actions may have provided input
for improvement of the project design.
Version No.:01
Page 9
Validation Report
01 997 9105065323
2 METHODOLOGY
The validation consists of the following three phases:
I. A desk review of the project design documents
II.
On-site visit and follow-up interviews with project stakeholders
III.
The resolution of outstanding issues and the issuance of the final validation report and
opinion.
The following sections outline each step in more detail.
Reference
Reference Document
/P01/
/P02/
/P03/
/P04/
/P05/
Validation contract in between TUV Rheinland (China) Ltd. and Swiss Carbon
Assets Ltd. dated 11/07/2011.
/P06/
Spread sheets for emission reduction calculations and Grid Emission Factor.
/P07/
/P08/
/P09/
/P10/
/P11/
/P12/
Version No.:01
Page 10
Validation Report
01 997 9105065323
2.
3.
4.
5.
6.
Power Purchase Agreement in between PT. SKE (seller) and PT. PLN
(Persero) Wilayah Sumatera Utara.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
Data which forms the basis for debt equity ratio for benchmark
calculation- Value taken from Feasibility Study
17.
The duration, return interval used and the period to which the beta given
in the worksheet 529-Raw data Bloomberg pertains to
18.
/P13/
/P14/
/P15/
Training Plan.
/P16/
/P17/
Version No.:01
Page 11
Validation Report
/P18/
01 997 9105065323
/P19/
/P20/
Single line diagram for electricity generation, auxiliary consumption and export
/import to/from the grid drawing
/P21/
/P22/
/P23/
/P24/
/P25/
/P26/
Letters from DNA of Indonesia regarding the published value of grid emission
factor:
1) B-277/Dep.III/LH/01/2009, dated 19/01/2009
2) 494/21/650.1/2009, dated 13/02/2009
Document
/B01/
/B02/
/B03/
Version No.:01
Page 12
Validation Report
01 997 9105065323
/B04/
/B05/
Date
Organization
Topic
Mr. Enda M.
Rangkuti
General
Manager, PT
Selo Kencana
Energi
Swiss Carbon
16/08/2011
/I-01/
Name
/I-02/
Version No.:01
Page 13
Validation Report
Ms. Ratna
Nawang Sari
01 997 9105065323
Assets Ltd.
data
archiving
and
reduction calculations
emission
Head of
Secretariat DNA,
Republic of
Indonesia
The objective of this phase of the validation is to resolve any outstanding issues which need be
clarified prior to TV Rheinlands positive conclusion on the project design. In order to ensure
transparency a validation protocol is customised for the project. The protocol shows in
transparent manner criteria (requirements), means of verification and the results from
validating the identified criteria. The validation protocol serves the following purposes:
It organises, details and clarifies the requirements a CDM project is expected to meet;
It ensures a transparent validation process where the validator will document how a
particular requirement has been validated and the result of the validation.
The validation protocol consists of three tables. The different columns in these tables are
described in the figure below. The completed validation protocol for this project is enclosed in
Appendix A to this report.
Findings established during the validation can either be seen as a non-fulfilment of CDM
criteria or where a risk to the fulfilment of project objectives is identified. Corrective action
requests (CAR) are issued, where:
i)
ii)
iii)
there is a risk that the project would not be accepted as a CDM project or that emission
reductions will not be certified.
A request for clarification (CL) may be used where additional information is needed to fully
clarify an issue.
Validation Protocol Table 1: Validation requirements
Checklist Question
Version No.:01
Reference
Means of
verification (MoV)
Comment
Page 14
Validation Report
01 997 9105065323
Gives
reference to
documents
where the
answer
to
the checklist
question or
item
is
found.
Explains
how
conformance with
the
checklist
question
is
investigated.
Examples of means
of verification are
document review
(DR) or interview
(I). N/A means not
applicable.
The section is
used to elaborate
and discuss the
checklist question
and/or
the
conformance to
the question. It is
further used to
explain
the
conclusions
reached.
Validation Protocol Table 2: List of Requests for Corrective Action (CAR) and Clarification (CL)
Draft report clarifications
and corrective action
requests
Ref. to checklist
question in table 2
Summary of project
owner response
Validation conclusion
Reference
to
the
checklist
question
number in Table 2
where the CAR or CL is
explained.
This
section
should
summarise the validation
teams responses and final
conclusions. The conclusions
should also be included in
Table
2,
under
Final
Conclusion.
Summary of project
owner response
This
section
should
summarise the validation
teams responses and final
conclusions. The conclusions
should also be included in
Table
2,
under
Final
Conclusion.
Reference
Reference
to
the
checklist
question
number in Table 2
where the CAR or CL is
explained.
Version No.:01
Page 15
Validation Report
01 997 9105065323
Type of Involvement
India
India
India
India
Mr. Ramaiyer
Ramachandran
Indonesia
----
Mr. Rahmawati
Noor
Indonesia
----
Mr. Kanal M. P.
India
X
X
Technical
Reviewer
Reporting
Support
Technical
Expert Input
Report and
protocol
Writing
Site Visit +
Interview
TV
Rheinland
Appointed for
Sectoral Scopes
Desk review
Full Name
Supervising
the work
Affiliation
X
X
3 VALIDATION FINDINGS
The findings of the validation are stated in the following sections. The validation criteria
(requirements), the means of verification and the results from validating the identified criteria
are documented in more detail in the validation protocol in Appendix A.
The final validation findings relate to the project design as documented and described in the
revised and resubmitted project design documentation.
Version No.:01
Page 16
Validation Report
01 997 9105065323
The below table summarizes the project participants and parties involved. The letters of
approval /P03/ were found to be unconditional with respect to 45 (a) to (d) VVM, ver. 01.2
/B01/. The copy of the LoAs /P03/ were verified against the original LoA issued by the host
country DNA. The contents of the LoA and the signature of the authorized issuer were also
compared with those of other approval cases issued by the host country DNA. Also from the
interview with representative of DNA of Indonesia /I03/ confirm the authenticity of DNA
letter. Thus, validation team considers that the given one is authentic and thus confirms to the
requirement of 47 VVM, ver 01.2 /B01/. In line with the requirements of 49 and 50 of
VVM, ver 01.2 /B01/.
The below table summarizes the project participants and parties involved. The authenticity of
the letters of approval has been validated by TV Rheinland validation team. These LoA(s) are
therefore regarded as valid and meeting the requirements.
Project participants
Parties involved
Indonesia (host)
Switzerland
LoA received
Yes
Yes
Date of LoA
19/12/2011
24/10/2011
B053/KNMPB/12/201
1
G514-3487
PP
PP
Validation
of
authenticity of the
LoA has been done
against the original
LoA issued by the host
country DNA /P03/.
Validation
of
authenticity of the LoA
has been done against
the original LoA issued
by the Annex-I country
DNA /P03/.
Valid
Valid
Yes
Yes
Voluntary participation
Yes
Yes
Diversion
of
official
development aid towards
host country
No
No
Project contribution to SD
Yes
Yes
APPROVAL
Reference to document
LoA received from
Validation of authenticity
Validity of LoA
PARTICIPATION
Version No.:01
Page 17
Validation Report
01 997 9105065323
Validation of ODA
The validation team did not reveal any evidence that this project activity can be seen as a
diversion of ODA. It is also confirmed by the interview with representative of PP during site
visit interview and declaration submitted by PP /P10/ dated 29/07/2011.
Confirmation of MoC
The Modalities of Communication (MoC) /P04/, signed on 12/09/2011, was received from the
PP. As required in Procedures for Modalities of Communication between Project Participants
and the Executive Board, the validation team has verified that the name of the authorized
signatories for future communication related to the corresponding scope of authority with
UNFCCC has been clearly mentioned in the MoC. The MoC has been checked as per the latest
MoC form as per VVM, version 01.2 and found correct. The validation team confirms that the
signatory and contact details on the MoC /P04/ are authorized and credible.
Version No.:01
Page 18
Validation Report
01 997 9105065323
/P12-4/ is considered for the estimation of gross generation by the project activity which is in
compliance with para 3(a) of EB 48, Annex 11. The total emission reductions due to the project
activity works out to be 32,806 tCO2e per year based on the net annual exportable power
generation. This net annual exportable power generation is ex-ante estimated by deducting
1.73% auxiliary consumption and transmission losses from the gross electricity generation
figures.
PT. Selo Kencana Energi and Swiss Carbon Assets Ltd. are the host and Annex 1 PPs
respectively for the given project activity and the same confirmed by letter of approvals /P03/
from DNAs of Indonesia and Switzerland respectively.
The technology used in the project is indigenously available in Indonesia and no transfer of
technology is envisaged. The technology applied is deemed current good practice and is not
expected to be replaced within the crediting period. The project activity contributes to the
sustainable development criteria of the host country in terms of social, economical,
technological and environmental benefits achieved due to the project activity.
The operational lifetime of the project has been determined as 20 years which is the
manufacturer specification /P12-3/. The operation and maintenance will be carried out by the
PP. The project participant has opted for a renewable crediting period of 21 years and the first
crediting period is for 7 years. The start date of the crediting period is mentioned as
01/01/2013 or the project registration date, whichever is later. The start date of operation
of the project activity is not yet fixed. This is a Greenfield project and also the energy
generating equipment is not being transferred from another activity, which is complying 50
of EB 44 along with the methodology compliance, hence no leakage have to be considered.
Based on the information furnished by the project participants, no diversion of ODA
contributes to the financing of the project /P10/. Geographical and temporal boundaries of the
project are clearly defined.
The starting date of project activity, project duration and crediting time are presented in the
table below.
Starting date of project
Crediting period
7 years (renewable)
Herewith, the Validation Team summarizes major changes between webhosted PDD and final
version of PDD for submission as follows:
Version No.:01
Page 19
Validation Report
01 997 9105065323
Topic
Webhosted PDD
Project title
Parties
Project
participants
Scope
Methodology and
activity scale
Amount of
emission
reductions (tCO2)
Additionality
Project starting
date
IRR
01/08/2011
N/A
32,806 tCO2e
No change
The start date of the project
activity is 01/12/2011 /P11-1/
Version No.:01
Page 20
Validation Report
01 997 9105065323
Applicability criteria for the baseline methodology /B02/ are assessed by the validation team
by means of document review and interview. It is agreed in the validation teams opinion that
the project activity fully met the criteria as described below:
Applicability
Criteria fulfilled
criteria as per
methodology
AMS-I.D. ver.17
/B02/
1
of
methodology.
2
of
methodology.
3
of
methodology.
4
of
methodology.
Version No.:01
Yes
No
Yes
No
Yes
No
Yes
No
Means of Validation
Page 21
Validation Report
5
of
methodology.
6
of
methodology.
7
of
methodology.
01 997 9105065323
Yes
No
Yes
No
Yes
No
8
of
methodology.
Yes
No
The assessment of the projects compliance with the applicability criteria of the methodology
AMS-I.D. (version 17) as documented in the PDD part B and annex 3, which are evaluated in
detail under the validation protocol in Appendix A to this report based from the webhosted
PDD.
There is no registered small-scale project activity under the CDM or an application to register
another small-scale CDM project activity by the project participant within the previous two
years with the same project category and technology within 1 km of the project boundary of
the proposed project. This is confirmed by the validation team during the on-site interview
with the representative of PP /I-01/. In addition, the validation team has checked up with the
UNFCCC website/CDM Pipeline published by UNEP RISO Centre1 /B04/ and not identified other
small-scale project being developed by the project participant. Therefore, the proposed
project is not deemed to be a de-bundled component of a large project activity. In accordance
http://cdmpipeline.org/
Version No.:01
Page 22
Validation Report
01 997 9105065323
Version No.:01
Page 23
Validation Report
01 997 9105065323
NA
No
NA
NA
NA
Are the registered SSC PA and
the proposed SSC PA in
transport
sector
involving
boundaries /sources that are
mobile? (as per EB 35,
paragraph 58 & 59 )
NA
NA
NA
NA
NA
NA
Do SSC PAs comprise of independent
subsystems / measures =<1% of
applicable SSC threshold implemented in
multiple locations (see para 7)?
NA
NA
NA
Version No.:01
Page 24
Validation Report
01 997 9105065323
Thus the validation team considers that the project participant has correctly applied the
approved methodology for the project activity.
Version No.:01
Page 25
Validation Report
01 997 9105065323
Emission
GHGs
involved
Baseline emissions
CO2
Project emissions
Leakage
CO2
Description
Major emission source, which is emitted from the
electricity generation by fossil fuel-fired power
plants connected to the Sumatera grid.
Only during the emergencies and for start-ups
fossil fuel may be consumed which will be
accounted as project emissions.
N/A
In summary, the project boundary was correctly identified in accordance with the
methodology AMS-I.D. (version 17). All greenhouse gas emissions occurring within the
proposed project activity boundary as a result of the implementation of the proposed CDM
project activity have been appropriately addressed in the PDD.
The identified project boundary and selected sources of emissions are justified for the project
activity. The validation of the project activity did not reveal other greenhouse gas emissions
occurring within the proposed CDM project activity boundary as a result of the
implementation of the proposed project activity which are expected to contribute more than
1% of the overall expected average annual emission reduction, with respect to the
methodology applied.
Version No.:01
Page 26
Validation Report
01 997 9105065323
The identified baseline scenario is in line with the methodology AMS-I.D version 17 /B02/, is
the equivalent electricity that would in absence of the project activity, have been generated by
the operation of the grid-connected power plants connected to the Sumatera.
As per the applied methodology AMS-I.D. (version 17), The baseline scenario is that the
electricity delivered to the grid by the project activity would have otherwise been generated
by the operation of grid connected power plants and by the addition of new generation
sources into the grid.
The validation team confirms that the proposed project activity meets the above requirement.
Therefore, the baseline scenario as prescribed in the AMS-I.D. (version 17) is applicable to the
proposed project activity. The validation took cognizance of 105 of VVM (version 01.2).
The approved baseline
applicable to the project
methodology
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
explicit criteria
implicit
criteria
(e.g.
available
scenarios, applicability of formulas for
BE/PE/LE calculations)
Version No.:01
Page 27
Validation Report
01 997 9105065323
project activity
Yes
No
Yes
No
The approved baseline methodology has been correctly applied to identify realistic and
credible baseline scenarios, and the identified baseline scenario most reasonably represents
what would occur in the absence of the proposed CDM project activity.
All the assumption and data used by the project participants are listed in the PDD and
supporting documents. All documentation relevant for establishing the baseline scenario are
correctly quoted and interpreted in the PDD. Assumptions and data used in the identification
of the baseline scenario are justified appropriately, supported by evidence and can be deemed
reasonable. Relevant national and/or Sectoral policies and circumstances are considered and
listed in the PDD.
Version No.:01
Page 28
Validation Report
EGBL, y
01 997 9105065323
EFCO2, grid, y
Version No.:01
Page 29
Validation Report
01 997 9105065323
Yes
Same as above
No
Yes
Same as above
No
Yes
Same as above
No
If
applicable:
the
fuel
consumption of each fuel type
in the relevant year(s);
Yes 2006
IPCC Guidelines
No
Greenhouse Gas Inventories
Version No.:01
for
National
Page 30
Validation Report
01 997 9105065323
Yes
Not Applicable.
No
Yes
Not Applicable.
No
The project/grid electricity system is rightly considered as Sumatera grid (Cp Step 1 of the
tool).
Step 2 of the tool provides an option to include off-grid power plants in the project electricity
system. Only grid connected power plants for the EF calculation as per the option I under the
step 2.
For the calculation of OM emissions factor, the simple OM emission factor calculation method
is rightly chosen because the low cost must run power plants (only hydroelectric power plants)
constitute less than 50% of the total grid generation during 2005 -2007. As power plants
registered as CDM project activities in Indonesia are only hydro power projects (which are
LCMR power plants), these are excluded in calculating simple OM.
Simple OM is rightly calculated by preferred option B {=equation (6) of tool} as plant specific
fuel consumption data; plant specific net electricity delivered to grid, NCV of the fossil fuel
types, fossil fuel emission factors are made available through data provided and approved by
the Directorate General of Electricity and Energy Utilization (DJLPE). Furthermore generation
weighted average for three years (2005, 2006, 2007) has been considered and stated in the
Annex3 of the PDD /P02/ for the computation of Simple OM, which is reproduced as below:
EFgridOM= (10,640,244+10,580,383+11,536,438)/ (11,514,809+11,751,548+12,911,406) = 0.906
tCO2/MWh
Where,
Simple OM EF of Sumatera Grid for year 2005 = 10,640,244 tCO2
Simple OM EF of Sumatera Grid for year 2006 = 10,580,383 tCO2
Simple OM EF of Sumatera Grid for year 2007 = 11,536,438 tCO2
Net Electricity Generated for year 2005 = 11,514,899 MWh
Net Electricity Generated for year 2006 = 11,751,548 MWh
Net Electricity Generated for year 2007 = 12,911,406 MWh
The identification of BM plants follows option (b) of Step 5 of the tool. BM is rightly computed
using equation number (12) and adopted equation number (2) of the tool. Power plant
registered as project activities are excluded in the sample group that is used to calculate the
BM. The data source and process of calculation OM and BM are based on the data that is
available at the time of submission of the CDM-PDD to the DOE for validation.
Version No.:01
Page 31
Validation Report
01 997 9105065323
The simple OM emissions factor was calculated as 0.906 tCO2e/MWh and the BM emissions
factor as 0.581 tCO2e/MWh.
EFgrid,OM,y and EFgrid,BM,y are calculated as 0.906tCO2e/MWh and 0.581tCO2e/MWh
respectively. In accordance with ACM0002 that weight factors of wOM = wBM = 0.5 have been
used to calculate the combined grid emission factor as follows (Equation 13 of the tool):
EFgrid,CM,y = ( EFgrid,OM,y x wOM ) + ( EFgrid,BM, y x wBM )
= (0.906 X 0.5) + (0.581 X 0.5)
EFgrid,CM,y = 0.743 tCO2e/MWh
As it can be verified, the emission factor (EFgrid,CM,y) is calculated by using the latest version of
the "Tool to calculate the emission factor for an electricity system". It is determined ex-ante
and consists of the weighted average factors of operating margin (EFgrid,OM,y ) and build margin
(EFgrid,BM,y).
The grid emission factor calculation used in the PDD is the calculation issued by DJLPE, the unit
within the Ministry of Energy and Mineral Resources /P26-1/ which is responsible in electricity
and energy utilization policies, regulations and programs. The net calorific value (NCV),
electricity generation (EG) and fuel consumption (FC) information are all based on the data
provided by IPCC 2006 Guidelines for GHG Inventories /B04/ which are representable and
appropriate to use.
The data sources were considered official and validation team confirmed that those data were
appropriately applied to the calculation. The final value of CM been cross checked with
published value on IGES web site (http://www.iges.or.jp/en/cdm/report_grid.html).
The GHG emissions reduction calculations are transparently documented and appropriate
assumptions regarding the expected amount of electricity generated have been used to
forecast emission reductions. All the assumptions made for the estimation of annual emission
reduction are verified by the validation team from the approved FSR /P12-1/, operating life of
the project activity /P12-3/, plant load factor estimation as per the re-feasibility study report
/P12-1/.
According to the applied formulae in the PDD /P02/, the emission reductions (ERy) by the
project activity during the crediting period is the difference between the baseline emissions
(BEy) and sum of emissions arising from leakage (LEy) and project (PE y), which is expressed as
follows:
ERy = BEy - PEy - LEy
The leakage (refer section 3.4.2 of this report) and ex-ante calculation of project emission are
zero. Leakage is not applicable as the transfer of equipment does not apply to this green-field
Version No.:01
Page 32
Validation Report
01 997 9105065323
project activity utilizing new purchased equipment (Cp 22 of AMS I.D, version 17/B02/ and
50 of EB 44).
According to the applied methodology the baseline emissions are demonstrated in section
B.6.3 of PDD and are calculated as follows:
BEy = EGBL,y * EFCO2,grid,y
Where:
BEy
EGBL,y
EFCO2,grid,y
PEFC,y
For the calculation purpose in the validation the import of electricity has been considered zero.
Version No.:01
Page 33
Validation Report
01 997 9105065323
The Project activity is run-off river therefore, the project emissions from reservoir and project
emissions from operation of geothermal power plants are zero.
PEGP,y = PEHP,y = 0 tCO2e
Hence , PEy = PEFC,y
The project emission from fossil fuel combustion will be determined as per Tool to calculate
the project or leakage CO2 emission from fossil fuel combustion version 02:
Where:
PEFC,j,y
the CO2 emission from fossil fuel combustion in process j during the year y
(tCO2e/yr)
FCi,j,y
the quantity of fuel type i combusted in process j during the year y (mass or
volume unit/yr)
COEFi,y
COEFi,y
NCVi,y
the weighted average net calorific value of the fuel type i in year y (GJ/mass
or volume unit)
EFCO2,i,y
the weighted average CO2 emission factor of fuel type i in year y (tCO2/GJ)
Where:
The emissions reductions due to the project activity were estimated ex-ante to be 32,806
tCO2e per year in the PDD /P02/ /P06/ and calculated as follows:
ERy
Version No.:01
Page 34
Validation Report
01 997 9105065323
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Based on the calculations and results presented in the sections above the implementation of
the project activity will result in an average ex-ante estimation of emission reduction
conservatively calculated to be 32,806 tCO2e per year for the selected crediting period.
All assumptions and data used by the project participants are listed in the PDD and/or
supporting documents, including their references and sources. All documentation used by the
project participants as the basis for assumptions and source of data is correctly quoted and
interpreted in the PDD. All values used in the PDD are considered reasonable and conservative
in the context of the proposed CDM project activity. The baseline methodology has been
applied correctly to calculate project emissions, baseline emissions, leakage and emission
reductions. All estimates of the baseline, project and leakage emissions can be replicated using
the data and parameter values provided in the PDD.
Version No.:01
Page 35
Validation Report
01 997 9105065323
3.5 Additionality
The project is a small scale project activity. Therefore, in accordance with 28 of the simplified
modalities and procedures for small-scale CDM project activities, Project Participant (PP) has
demonstrated the additionality of the project activity using Guidelines on the demonstration
of additionality of small-scale project activities (Version 09.0) and Guidance given vide Annex
5 of EB 62. The project developer has chosen investment analysis (Benchmark analysis) to
demonstrate the additionality of the project using post tax project IRR as financial indicator
and weighted average costs of capital (WACC) as benchmark. All the input parameters
supporting financial indicator have been sourced from the re-Feasibility Study Report (FSR),
which has been prepared by the project participant which was submitted to the bank. The
benchmark selected is in conformity with guidance 12 of Annex 5, EB 62 read with 112 of
VVM (ver.1.2); input parameters used are appropriate, based on credible sources and
conservative; the assumptions used are in conformity with various guidance issued by EB; the
input parameters have been cross checked for their correctness and appropriateness by the
validation team based on its sectoral and local expertise and information; and in the above
background, validation team concludes that the project is additional.
Version No.:01
Page 36
Validation Report
01 997 9105065323
In the above background, the project fulfills the condition stipulated vide paragraphs (2) of
Annex 13 of EB 62 read with 100 and 101 of VVM (01.2). Therefore, Validation Team
concludes that there was a prior consideration of CDM and CDM was seriously considered in
the decision to implement the project activity.
3.5.2 Alternatives
This is a hydro power project and is based on the Methodology AMS-I.D., Ver. 17. The
methodology states, If the project activity is the installation of a new grid-connected
renewable power plant/unit, the baseline scenario is the electricity delivered to the grid by the
project activity that otherwise would have been generated by the operation of grid-connected
power plants and by the addition of new generation sources.
Paragraph 105 of VVM, (ver. 01.2) states that PDD is required to identify credible alternatives
to the project activity in order to determine the most realistic baseline scenario, unless the
approved methodology that is selected by the proposed CDM project activity prescribes the
baseline scenario and no further analysis is required. Since the approved methodology AMSI.D., (ver. 17) on which the project activity is based on, prescribes the baseline scenario, no
further analysis of alternatives is required for the project activity.
Validation Team, therefore, concludes that the PDD and the validation report conforms to the
guidance given by EB vide paragraph 105 of VVM (Ver.01.2).
Version No.:01
Page 37
Validation Report
01 997 9105065323
In the above background, as subsequent paragraphs would reveal, Validation Team concludes
that the additionality justification given by the project developer is in accordance with the
requirements derived from the approved CDM methodology and the methodological tools
referred therein as well as the guidance given by EB vide paragraphs 108-110 of VVM (01.2).
The project developer has chosen post tax project IRR as financial indicator. Having regard to
the fact that the project is funded by debt and equity and that it is in private sector, post tax
project IRR is considered as an appropriate financial indicator to demonstrate the additionality
as it takes into account the return on both debt and equity. Additionality Tool and Guidance
on Investment Analysis permit the use of project IRR as one of the financial indicators for
additionality demonstration. Moreover, project IRR is invariably used by the banks and
investors alike to gauge the investment-worthiness of the project. The financial indicator
chosen is, therefore, appropriate for the project type and decision making context (conformity
to paragraph 3 of Step 2 (b) of Additionality Tool).
Therefore, the validation team concludes that the investment analysis and the financial
indicator selected are appropriate for the project activity. Since the financial indicator of
project activity breaches the benchmark only with CDM benefits, it is reasonable to assume
that the investment would not have taken place without CDM benefits (conformity to
paragraph 112 (c) of VVM - 01.2) and therefore, Validation Team concludes that CDM benefits
were decisive factor in the investment decision.
Appropriateness of benchmark:
The project developer has chosen project IRR to demonstrate the additionality of the project.
Guidance on the Assessment of Investment Analysis (Ver. 05) states, Local commercial
lending rates or weighted average costs of capital (WACC) are appropriate benchmarks for a
project IRR3.
The WACC has been chosen as benchmark for the project activity by the PP. It is based on
average debt and equity from project planned financial structure at 80% of capital cost by loan
and 20% of equity. The applied beta for this project is adjusted based on the unlevered total
beta values for power industry, published data. The Indonesian long-term government bond
rate is considered as risk free rate. Thus, the applicable benchmark conforms to guidance 12
and 13 of Annex 5, EB 62. The PP has assumed WACC rate at 16.01% which is calculated using
the commercial lending rate published by Bank Indonesia for investment purpose by private
national banks in Republic of Indonesia (http://www.bi.go.id/NR/rdonlyres/365FA82B-A53E40C6-A609-436E8D5BB2AF/22921/Appendices1.zip) and the beta calculation.
WACC and Beta calculation for the benchmark: The equation by which the WACC calculation is
done is mentioned below:
3
Version No.:01
Page 38
Validation Report
01 997 9105065323
Re = Rf + a * Rm Where,
WACC
E/V
D/V
Re
Rd
Tc
Rf
: Beta of industry
Rm
Rate
D
Rb
Value
80%
12.18%
Tc
E
Rf
25%
20%
9.50%
Rm
5.00%
1.70%
WACC
16.01%
Source /P12/
Debt proportion based on re-FSR financial modeling
http://www.bi.go.id/web/en/Statistik/Statistik+Ekonomi+dan+Keuang
an+Indonesia/Versi+HTML/Sektor+Moneter/#
Government regulation No.36 year 2008
Equity proportion based on re-FSR financial modeling
Based on Indonesian government bonds rate. Bond rate is taken from
the Central bank of Indonesia previous to investment decision and for
a duration equal to the technical lifetime of the project activity
Market risk premium4 from Damodaran.
http://www.stern.nyu.edu/~adamodar/pc/archives/ctryprem10.xls
Total beta (unlevered) from Damodaran.
http://www.stern.nyu.edu/~adamodar/pc/archives/totalbeta10.xls
Calculation
In the webhosted PDD, project developer had considered 20.27 % as the benchmark based on
weighted average costs of capital (WACC). However, during the discussions, validation team
pointed out that the interest rate prevailing at the time of decision making as evidenced by an
international publication are all lower. Project developer therefore, selected the lowest of the
interest rates 16.01% - as the benchmark. Please refer Table 2 of validation protocol for
closure of all CAR/CL. Since it is conservative and conforms to guidance 12 and 13 of Annex 05,
EB 62, Validation team accepted the benchmark.
The validation therefore concludes that the benchmark applied is suitable for the financial
indicator selected and it is reasonable to assume that the investment would not have taken
place at a return lower than the benchmark (in as much as the financial indicator breaches the
4
The Market Risk Premium equals Total Risk Premium subtracted by Country Risk Premium
Version No.:01
Page 39
Validation Report
01 997 9105065323
benchmark only with CDM benefits). Thus, the selected benchmark conforms to guidance 12
and 13 of Annex 58, EB 51 as well as Annex 5, EB 62 and paragraph 112 of VVM (01.25). In the
above background, validation team concludes that the selected benchmark is appropriate,
conservative and conforms to various EB guidelines.
Parameters and assumptions used:
The project involves installation of 7.5 (=2 X 3.75) MW turbines at Lubuk Gadang generating
44,150 MWh of power and selling to PT. PLN (Persero) (state utility body) at an estimated tariff
of IDR 787.00/kWh for (y1-y20). The three important parameters, which determine the project
IRR of the project, are project cost, financing pattern and profitability estimates.
The project cost includes civil cost, equipment cost, electro mechanical work cost, engineering
cost and contingencies. All these costs are based on Notes on Review of Hydrology (re-FSR)
/P12-1/, which is the basis for investment analysis.
The project is envisaged to be financed 80% through debt and 20% by equity. The debt equity
ratio is essentially dependent on the banks assessment of risk profile of the project and is
generally a negotiating factor. Therefore, the leverage adopted is in conformity with the
normal financing structure of infrastructure projects in Indonesia.
The profitability estimates of the project, which forms the basis for IRR calculation is based on
installed capacity, PLF, power tariff, O&M cost, interest, depreciation, taxation. Major input
parameters used in the additionality demonstration, basis thereof and the appropriateness of
the value used are given in the following table:
Parameter
Installed Capacity
(MW)
Lubuk Gadang
Value
applied
20
2X3.75
=7.5
2010 Economic Report on Indonesia, Appendices, table 22. Interest Rate on Rupiah Credits by Group of Banks
(http://www.bi.go.id/web/en/Publikasi/Laporan+Tahunan/Laporan+Perekonomian+Indonesia/lpi_2010.htm)
Version No.:01
Page 40
Validation Report
01 997 9105065323
Domestic Currency
Loan from SMI (IDR
in million)
Interest rate on
Loan Issued by
Central Bank of
Indonesia
115,767
12.18%
The loan amount is based on Loan Sanction Letter /P122/. Project developer has submitted a copy of the loan
sanction letter and validation team observed that the
amount was considered in the financial indicator
calculation is in conformity with loan sanction letter.
Guidance 11 of Annex 5, EB 62 states, In cases where a
post-tax benchmark is applied the DOE shall ensure that
actual interest payable is taken into account in the
calculation of income tax. Therefore, consideration of
loan amount is in conformity with guidance 11 of Annex
5, EB 62. Validation team checked the sanction letter
/P12-2/ and found the value to be correct and
appropriate.
The interest rate is based on the loan sanction letter
issued by the Central Bank of Indonesia /P12-2/. Since
Guidance 11 of Annex 5, EB 62 requires that actual
interest payable should be taken into account in the
calculation of income tax where a post-tax benchmark is
applied, consideration of interest rate based on the loan
sanction letter /P12-2/ conforms to Annex 5, EB 62.
Validation team checked the sanction letter /P12-2/ and
found the value to be correct and appropriate.
http://www.bi.go.id/web/en/Statistik/Statistik+Ekonomi+
dan+Keuangan+Indonesia/Versi+HTML/Sektor+Moneter/
#
Repayment
(quarters)
24
Moratorium
(quarters)
Version No.:01
Page 41
Validation Report
01 997 9105065323
Generation (MWh)
O&M cost in
(2.5% of capital cost)
IDR million per year
Power tariff
(IDR/kWh)
44,150
787
Water retribution
Depreciation (years)
Version No.:01
25
Page 42
Validation Report
01 997 9105065323
Salvage Value
(10 % of Project
Cost)
(IDR Million)
As could be observed all the input values are based on Notes on Review of Hydrology (re-FSR)
/P12-1/, PPA /P12-6/, Loan sanction letter /P12-2/. Re-FSR was prepared in 01/03/2011/12-1/
and the investment decision was made in 05/04/2011/P08/ based on the re-FSR. Paragraph
113 of VVM (01.2) states, where the re-FSR has been the basis of the decision to proceed with
the investment in the project, the period of time between the finalization of the re-FSR and
the investment decision should be sufficiently short to confirm that it is unlikely in the context
of the underlying project activity that the input values would have materially changed. Since
the time elapsed between the re-FSR preparation date and the Board Meeting date (In which
serious consideration of CDM benefits was made), is less than six months, the validation team
concludes that the input parameters used in the re-FSR were valid and applicable at the time
of investment decision. The source for input parameters, the method adopted to cross check
the information/data and the appropriateness of the same are given along with the input
parameters.
Version No.:01
Page 43
Validation Report
01 997 9105065323
As evident from the details given above, the validation team had evaluated the parameters
used in the financial calculations and confirms that the underlying assumptions are
appropriate and the financial calculations are correct.
Since the input parameters have been sourced from the re-FSR, the gap between the re-FSR
finalization date and the decision making date being less than 6 months, validation team
concludes that the input parameters are reliable, credible and appropriate for the project
activity and conforms to Annex 13, EB 61. Thus, the Validation also conforms to the guidance
given vide 111,112 and 114 of VVM (Ver. 1.2) /B01/.
In this context one issue that assumes importance is the power tariff considered in
additionality demonstration. Electricity tariff has been assumed at IDR 787.00/kWh for (y1y20), which was signed prior to the board consideration when the PPA was signed. Please refer
to the Table 2 of the validation protocol for closure of CAR/CL. Therefore, validation team
concludes that the tariff assumed for the project activity is appropriate and correct.
In the light of the above, validation team is convinced that the concern expressed by EB vide
48 of the minutes of the 49th Meeting and 69 of the 51st Meeting has been duly addressed
by the PP and the tariff considered in additionality determination is appropriate to the project
activity.
Cross checking parameters: Investment cost, financing pattern, terms of loan, O&M cost,
interest, depreciation and tax rate have been cross checked with loan application letter /P1202/, Income Tax Act /P12-7/ and various decrees along with decisions governing depreciation
and taxes. The documents supporting the financial calculations, in the opinion of validation
team, are therefore authentic and appropriate. The input parameters were found to be
appropriate.
Thus, the guidance given by the EB vide 87, 95 and 111 of VVM (Ver. 01.2) /B01/ have been
taken care of in validation of the project.
Assessment of correctness of computation: The assessment involved checking the data input
extracted from re-FSR and other published documents (mainly Government), adoption of
correct accounting principle and arithmetical accuracy. Validation team checked the re-FSR,
published government documents and ensured that right input has been taken in the project
cost and projections. The accounting principles adopted with respect to computation of
interest, block of assets and tax computation were found to be in order. The arithmetical
accuracy was also found to be correct. Thus, the validation has taken into consideration the
guidance given by EB vide 109 and 110 of the VVM (01.2).
The project IRR has been computed for a period of 20 years of operation /P12-3/, which is the
life time of the project and is in conformity with the Annex 5 of EB 62 and Annex 15 of EB 50.
As required by Annex 5 of EB 62, the expected realisation on the sale of assets at the end of
the operating life has been taken as salvage value in the terminal year. Since the assets have
Version No.:01
Page 44
Validation Report
01 997 9105065323
been fully depreciated, the salvage value represents only the profit expected to be realised by
disposal of assets at the end of the operating life of the project (guidance 4 of Annex 5, EB 62).
In computing the IRR, the project developer has taken into account, profit after tax,
depreciation and interest on term loan and salvage value (in the terminal year). The principle
adopted conforms to the accepted accounting and taxation principles.
The financial analysis is in accordance with the Tool for demonstration and assessment of
additionality version 06 and the Guidelines on the assessment of investment analysis
version 04. All input parameters used in the IRR calculation were valid at the time of
investment decision making. The validation team confirms that the project IRR post tax
without any CDM revenue works out to be 13.89% which is below benchmark of 16.01%. It is
clearly demonstrated that the proposed project activity without CER revenues is financially
unattractive. The validation took cognizance of 97, 112 and 113 of VVM (version 01.2).
3.5.3.1. Sensitivity analysis
The guidance on assessment of investment analysis /B03-h/ requires the robustness of the
conclusion arrived at to be proved through a sensitivity analysis. Guidance 20 of Annex 5, EB
62 states, only variables, including the initial investment cost, that constitute more than 20%
of either total project costs or total project revenues should be subjected to reasonable
variation. Guidance 21 states, as a general point of departure variations in the sensitivity
analysis should at least cover a range of +10% and -10%. The project developer has identified
investment cost, O&M cost, electricity generation and tariff as the most critical assumptions.
There are no other expenses or costs which could be subjected to variation as all of them have
been considered either directly or indirectly in the sensitivity analysis. Though O&M cost does
not constitute more than 20% of project revenue, validation team considered appropriate to
subject it to sensitivity analysis, which is in conformity with Guidance 20 of Annex 5, EB 62. All
the four variables have been subjected to 10% variation. The sensitivity analysis reveals that
even under more favourable conditions, the IRR would not cross the benchmark return as
given in the following table:
Input Values
Total investment
Power Generation
O&M Cost
Benchmark
-10%
15.59%
12.28%
14.05%
Baseline
13.89%
13.89%
13.89%
16.01%
+10%
12.43%
15.42%
13.72%
Variation by 10% was considered appropriate for the project because, the inflation rate in
Indonesia is 6.59%. As evident, the project remains additional even under such conditions. A
further analysis of the projections reveals that the projects would become non- additional only
in the following cases:
Version No.:01
Page 45
Validation Report
Parameters
01 997 9105065323
Variation
Power
generation goes
up by
13.90%
Tariff goes up by
13.75%
O&M cost
comes down by
-131.50%
Investment cost
comes down by
-12.20%
In the above background, the most plausible scenario is only an increase in the project cost
and not the other way round. Such an occurrence will undoubtedly worsen the projects IRR
Version No.:01
Page 46
Validation Report
01 997 9105065323
further rendering the CDM benefits imperative for survival. Moreover, the PP has also pointed
out that the project cost does not include interest during construction, which also forms the
cost of the project. If this were to be included, the project IRR would go down further.
Validation team is in agreement with PPs submission. Having regard to the assessment of
conformity of additionality demonstration and benchmark selection to the latest version of the
Guidance issued by EB on the assessment of investment analysis, plausibility and
appropriateness of parameters used and correctness of financial calculations, validation team
concludes that the project scenario is not economically feasible without benefits from CER
sales in as much as the project IRR reaches 13.89 % without CDM benefits.
3.5.4. Barrier analysis
PP has not used barrier analysis to demonstrate additionality. Since the additionality of the
project has been demonstrated using investment analysis, barrier analysis is not mandatory
and this is in conformity with the Additionality Tool.
3.5.5. Common Practice Analysis
Since it is a small scale project activity, PP is not required to demonstrate common practice
analysis.
3.6 Monitoring
The monitoring plan is included in Section B.7 of the PDD /P02/ based on the approved
monitoring methodology AMS-I.D. Version 17 /B02/ titled Grid connected renewable
electricity generation and is correctly applied to the CDM project activity. This methodology
/B02/ stipulates that monitoring shall consist of monitoring of Quantity of net electricity
supplied to the grid in year y. This confirms the requirement of 122 of VVM ver. 01.2 /B01/.
The validation team also confirms with representative of PP during onsite visit /I-01/, whether
the monitoring plan can be implemented in the context of the project activity and was
satisfied with the implementation plan of the monitoring plan.
Version No.:01
Page 47
Validation Report
01 997 9105065323
Parameters
Description
1.
EGBL,y
2.
FCi,j,y
3.
NCVdiesel,y
4.
diesel,y
5.
EFCO2,diesel,y
Version No.:01
Page 48
Validation Report
01 997 9105065323
Technical Specification of Energy Metering as per the Metering Code stipulated by Minister of
Energy and Mineral Resources, Republic of Indonesia. Please ref Annex: Validation Protocol Table 2 for details on closure of CAR/CL.
The validation team considers that the monitoring plan has complied with the requirements in
the approved methodology hence confirms compliance of 123(b) of VVM ver. 01.2 /B01/.
Monitoring parameters: the monitoring parameters of the project include quantity of net
electricity supplied to the grid including amount of diesel fuel used in the project activity,
weighted average of NCV for the diesel, weighted average density of diesel used in the
project activity and weighted average CO2 emission factor for diesel.
Operational and management structure: management structure is illustrated for the CDM
project monitoring;
Monitoring Equipment and Relative Location: metering equipment to monitor electricity
export and import electricity (located at commercial metering point);
Quality Control and Data Archive: arrangement of meter calibration; procedures for
corrective actions agreed upon by both parties when meter malfunctions; safekeeping of
the data collected during monitoring; and collection of monitored data and report
preparation.
Quantity of net electricity supplied to the grid in year y is monitored as per the requirement of
24 bullet (5) of the monitoring methodology /B02/ applied for the project activity hence
confirms compliance of 123(a) of VVM ver. 01.2 /B01/. Net electricity supplied to the grid is
calculated as the difference of electricity exported and electricity imported by the project
activity and the same is used for the calculation of emission reduction. For ex-ante calculation
of emission reduction, the import electricity has been considered as zero.
Implementation of the plan
According to document review and on-site interviews with the representatives of the PP /I01/, detailed monitoring procedures, monitoring structure, monitoring items and functions are
clearly demonstrated in the PDD /P02/ which will enable subsequent verification of the
projects emission reductions in line with the applied methodology. The validation team
confirms that as per 24 of EB 23, the specific uncertainty levels, methods and associated
Version No.:01
Page 49
Validation Report
01 997 9105065323
accuracy level of measurement instruments and calibration procedures used for various
parameters and variables are identified in the PDD /P02/ along with detailed quality assurance
and quality control procedures. The accuracy class and the method and frequency of
calibration of the electricity meters confirm to the national standards /B06/. This also complies
with 17of the general guidelines of the small scale project activities EB 61, annex 21. All the
monitored data will be archived until 2 years after the crediting period or the last issuance of
CERs whichever occurs later to facilitate cross-checking during the crediting period. Please ref
Annex: Validation Protocol - Table 2 for details on closure of CAR/CL.
Hence the validation team considers that the PP is capable to implement the monitoring plan
and satisfies the requirement of 123(a) of VVM, Ver. 01.2 /B01/.
Version No.:01
Page 50
Validation Report
01 997 9105065323
validation team noted that the EIA report /P24/ had been approved by the ministry, which
further confirms that the EIA report meets the requirement of the national law of Indonesia.
Version No.:01
Page 51
Validation Report
01 997 9105065323
Appendix A
CDM VALIDATION PROTOCOL
7.5 MW Lubuk Gadang Small Hydropower Plant at West Sumatera, Indonesia
in
Indonesia
Report No. 01 997 9105065323
Version No.:01
Page 52
Validation Report
01 997 9105065323
UNFCCC CDM
rules
/I-01/
/P01/
/P03/
1.2
UNFCCC CDM
rules
/I-01/
/P03/
DR, I
DR, I
Draft
conclusion
Final
conclusion
CAR 01
OK
CAR 01
OK
Version No.:01
Page 53
Validation Report
1.3
1.4
1.5
1.6
1.7
01 997 9105065323
UNFCCC CDM
rules
/I-01/
/P03/
DR, I
UNFCCC CDM
rules
/I-01/
/P03/
DR, I
UNFCCC CDM
rules
/I-01/
/P03/
DR, I
UNFCCC CDM
rules
/I-01/
/P01/
/P03/
/P04/
DR, I
UNFCCC CDM
rules
/I-01/
/P03/
DR, I
Version No.:01
OK
CAR 01
OK
CAR 01
OK
CAR 01
OK
CAR 01
OK
Page 54
Validation Report
1.8
01 997 9105065323
UNFCCC CDM
rules
/I-01/
/P01/
DR, I
DR
2.
2.1
PDD
(A.3, Annex 1)
/P01/,/P03/
/P01/
/P03/
/I-01/
DR, I
/P01/
/B05/
/B06/
DR
2.2
3.
3.1
3.2
Version No.:01
/P01/,/B05-a/
DR
OK
OK
CAR 01
OK
CAR 01
OK
OK
OK
CAR 02
OK
Page 55
Validation Report
4.
01 997 9105065323
/P01/
/P11/
/P16/
/P17/
/P21/
/P25/
/I-01/
DR, I
4.2
/P01/
/P11/
/P16/
/P17/
/P18/
/I-01/
DR, I
4.3
Version No.:01
PDD (A.4.2)
/P01/
/P11/
/P16/
/I-01/
DR, I
CL 02
CL 03
CL 04
CL 09
OK
CL 05
OK
OK
OK
Page 56
Validation Report
4.4
5.
5.1
General requirements
01 997 9105065323
/P01/
/P11/
/I-01/
DR, I
UNFCCC website,
PDD
/B02/
DR
UNFCCC website,
PDD (B.2)
/P01/,/B05/,/I-01/
DR, I
PDD(A.4.5)
/P01/
/B06/
/I-01/
DR, I
OK
OK
OK
OK
OK
OK
CL 06
OK
Version No.:01
Page 57
Validation Report
01 997 9105065323
UNFCCC website,
/P01/
/B02/
/I-01/
UNFCCC website,
/P01/
/B02/
DR
UNFCCC website,
/P01/
DR
PDD(B.3)/P01/,
Meth(/B02/)
/I-01/
DR,I
5.3
DR, I
Same as above.
Subject to closure CL 07.
Yes, the selected methodology has been
correctly quoted in all related
documents.
OK
OK
CL 07
OK
OK
OK
OK
OK
Project boundary
Version No.:01
Page 58
Validation Report
01 997 9105065323
/P01/
/B.3/
/B02/
DR
CL 01
OK
This section is not applicable for smallscale project as per PDD filling guidelines
and the applied methodology.
This section is not applicable for smallscale project as per PDD filling guidelines
and the applied methodology.
OK
OK
OK
OK
OK
OK
PDD (B.4)
/P01//B02/
DR
PDD
(B.4, B.5)
/P01/ /B02/
DR
/P01/
/B02/
DR
Version No.:01
Same as above.
Page 59
Validation Report
01 997 9105065323
DR
OK
OK
DR
OK
OK
UNFCCC website,
/P01//B02/
DR
PDD (B.4)
/P01//B02/
DR
Same as above
PDD (B.4)
/P01/ /B02/
DR
PDD (B.5)
/P01/ /B05/
DR
OK
OK
PDD (B.4)
/P01/ /B02/
DR
OK
OK
5.5
UNFCCC website,
/P01//B02/
UNFCCC website,
/P01/
CL-07
OK
Version No.:01
Page 60
Validation Report
01 997 9105065323
PDD
(B.6.1,B.6.3)
/P01/
/B02/
PDD
(B.6.1, B.6.3)
/P01/
/B02/
PDD
(B.6.2,Annex 3)
/P01/
5.6
PDD
(B.6.3,B.7.1)
/P01/
PDD
(B.6.3,B.7.1)
/P01/
/B03/
DR
CAR06
OK
CAR05
DR
CAR04
OK
DR
OK
OK
DR
OK
OK
DR
OK
OK
Leakage
Version No.:01
Page 61
Validation Report
01 997 9105065323
/P01/
/B02/
DR
OK
OK
/P01/
/B02/
DR
Same as above
OK
OK
/P01/
/B02/
DR
Same as above
OK
OK
O.K.
O.K.
OK
OK
6.
7.
Additionality
7.1
/P01/
/P07/
/I-01/
/P01/
/P06/
/B05/
/I-01/
DR, I
Same as above.
OK
OK
/P01/
/P06/
/B05/
/I-01/
DR, I
Same as above.
OK
OK
Version No.:01
DR, I
Page 62
Validation Report
01 997 9105065323
/P01/
/P06/
/P07/
/P11/
/B05/
DR
/I-01/
Version No.:01
/P01/
/I-02/
OK
OK
DR, I
OK
OK
DR, I
OK
OK
OK
OK
DR, I
Page 63
Validation Report
01 997 9105065323
7.2
DR, I
OK
OK
DR, I
OK
OK
Identification of alternatives
This section is not applicable for smallscale project as per PDD filling guidelines
and the applied methodology.
OK
OK
This section is not applicable for smallscale project as per PDD filling guidelines
and the applied methodology.
OK
OK
Version No.:01
Page 64
Validation Report
01 997 9105065323
This section is not applicable for smallscale project as per PDD filling guidelines
and the applied methodology.
OK
OK
This section is not applicable for smallscale project as per PDD filling guidelines
and the applied methodology.
OK
OK
CL 08a)
CL 08c)
CL 08d)
CL 08g)
CAR 03(a,o)
OK
7.3
Investment Analysis
Version No.:01
PDD(B.5)/P01/
/P09/
/P11/
PDD(B.5)/P01/
/P09/
/P11/
PDD(B.5)/P01/
/P09/
/P11/
DR
DR
DR
CAR 03c)
CL 08h)
OK
OK
Page 65
Validation Report
01 997 9105065323
PDD(B.5)/P01/
/P09/
/P11/
PDD(B.5)/P01/,
/P09/,
/P11/
PDD(B.5)/P01/,
/P09/,
/P11/
PDD(B.5)/P01/,
/P09/,
/P11/
Version No.:01
PDD(B.5)/P01/,
/P09/,
/P11/
PDD(B.5)
/P01/,
/P09/,
/P11/
DR
DR
DR
DR
DR
CAR03(j,k)
CL 08e)
CAR 03i)
OK
OK
CL 08f)
CAR 03h)
OK
CL08b)
OK
CL 08i)
CAR 03(b,d
e,g,p)
OK
CAR 03(f,I,m,n)
OK
DR
Refer to section 7.1.1.
Page 66
Validation Report
7.4
01 997 9105065323
Barrier analysis
Same as above
7.5
Version No.:01
Page 67
Validation Report
01 997 9105065323
8.
Monitoring plan
8.1
/P01/
/B02/
/P01/
/B02/
8.2
Version No.:01
CAR08
OK
OK
OK
DR
DR
Page 68
Validation Report
8.3
8.4
01 997 9105065323
/P01/
/B02/
8.6
8.7
8.8
8.9
CAR07
OK
DR
OK
OK
DR
Yes
the
measurement
accuracy
addressed and deemed appropriate as it
complies the requirement of national
law.
OK
OK
DR
OK
OK
DR
OK
OK
8.5
DR
/P01/
/B02/
/P01/
/B02/
/P01/
/B02/
PDD(B.7.1)/P01/,
/B02/
/B05/
DR
OK
OK
/P01/
DR
OK
OK
Version No.:01
Page 69
Validation Report
01 997 9105065323
/P01/
PDD (B.7.1)/P01/
/P01/
/I-01/
/P01/
PDD(B.7.2)/P01/,
/P19/
/P01/
/B05/
DR
OK
OK
DR
OK
OK
DR, I
OK
OK
DR
OK
OK
DR
Same as above
OK
OK
DR
OK
OK
DR
OK
OK
DR
OK
OK
/I-01/
8.17 Are procedures identified for emergency
preparedness for cases where emergencies
can cause unintended emissions?
Version No.:01
/P01/
Page 70
Validation Report
01 997 9105065323
/P01/,
/B02/,
DR
OK
OK
DR
OK
OK
DR
OK
OK
DR
OK
OK
DR
OK
OK
DR
OK
OK
8.2
/B05/
9.
Sustainable development
9.1
Version No.:01
/P01/,
/B02/
/B05/
/P01/,
/B02/
/B05/
/P03/
Page 71
Validation Report
9.2
01 997 9105065323
PDD(A.2)/P01/
DR
OK
OK
/P01/
/P12/
/I-01/
DR I
OK
OK
/P01/
/P12/
/I-01/
DR, I
OK
OK
OK
OK
10.
/P01/
/P12/
/I-01/
DR, I
/P01/
/P12/
/I-01/
DR, I
OK
OK
/P01/
/P12/
/I-01/
DR, I
OK
OK
Version No.:01
Page 72
Validation Report
01 997 9105065323
11.
/P01/
/P12/
/I-01/
PDD (E.2)
/P01/
PDD(E.3)/P01/
DR
DR
DR
OK
OK
OK
OK
OK
OK
OK
OK
OK
OK
Environmental impacts
/P01/
/P01/
Version No.:01
DR
/P14/
DR
/P14/
Page 73
Validation Report
01 997 9105065323
/P01/
/P01/
DR
/P14/
DR
/P14/
/P01/
/P01/
DR
OK
OK
OK
OK
OK
OK
OK
OK
/P14/
/P14/
DR
12.
Specific validation requirements for SSC-CDM project activities (VVM F.2 of Validation)
12.1.
Version No.:01
/P01/
/B02/
/B05/
DR
OK
OK
/P01/
/B02/
/B05/
DR
OK
OK
Page 74
Validation Report
01 997 9105065323
/P01/
/B02/
/B05/
DR
OK
OK
/P01/
/B02/
/B05/
DR
OK
OK
/P01/
/P14/
/B06/
DR
OK
OK
DR
Version No.:01
PDD (B.5)/P01/
/B02/
/B05/
OK
Page 75
Validation Report
01 997 9105065323
DR
DR
I
OK
OK
OK
/P01/
DR
NA
/P01/
/B02/
DR
NA
Version No.:01
Page 76
Validation Report
12.6.5
01 997 9105065323
/P01/
/B02/
DR
NA
Version No.:01
Page 77
Validation Report
01 997 9105065323
Table 2:
List of Requests for Corrective Action (CAR) and Clarification (CL)
Validation / Verification Manual
(35) The DOE shall raise a corrective action request (CAR) if one of the following occurs:
(a) The project participants have made mistakes that will influence the ability of the project activity to achieve real, measurable additional
emission reductions;
(b) The CDM requirements have not been met;
(c) There is a risk that emission reductions cannot be monitored or calculated.
(36) The DOE shall raise a clarification request (CL) if information is insufficient or not clear enough to determine whether the applicable CDM
requirements have been met.
The wording of CAR/CL shall clearly address nonconformity or seek clarification, and avoid instructive / consultative language in order to prevent actual or perceived
consultancy.
No.
1.
CAR/CL
Observation (CAR/CL)
CL-01
Version No.:01
Reference
(Table1)
5.3.1
Revised
section(s
)/
Summary of project owner response
Annex(s)
of the
PDD
The value of 42,705 MWh/year is the A.4.1.4
electricity generated per year before
the deduction of transmission loss.
The value of 41,965 MWh/year is the
net electricity supplied to the Grid
after deduction of transmission loss.
In the PDD Ver.2 the net electricity
generation and supplied is revised as
per the data from third party (PT SMI
as the loan debtor). The revised net
electricity supply to grid is 39,420
MWh. The difference is occurred
because PT SMI is using Capacity
Factor of 60% on their calculation.
Validation Report
2.
CL 02
01 997 9105065323
Editorial mistakes:
1) First sentence in section A.2.
2) On p 5 of the PDD, title of
the Type of the project
activity is incorrect.
3) All figures / values/ units
need to be as per the
UNFCCC requirements.
4) The statement The project
will ..... line respectively. on
p 3.
5) Footnotes of the meth are
repeated and also numbers
are not in line with the
meth. in section B.2
6) Full form of AMDAL on p 30
of the PDD.
7) Symbols
of
all
the
parameters should be in line
with the applied meth, tool
(like LEy, etc.).
4.1
Version No.:01
4) OK
5) It seems the CL has not been
understood by the PP. The
footnotes are to be kept in the
applicability criteria table but
Page 79
Validation Report
01 997 9105065323
3.
CL 03
4.
CL 04
5.
CL 05
6.
CL-06a
Version No.:01
A.4.2
A.4.5
The
complete
de-bundling
guideline reference is added in
the revised PDD. This CL is closed.
B.4
B.5
4.1
Page 80
Validation Report
01 997 9105065323
CL-06b
CL-06c
7.
8.
Version No.:01
Page 81
Validation Report
CL-06d
Version No.:01
01 997 9105065323
Page 82
Validation Report
01 997 9105065323
10.
CL-06e
Version No.:01
Page 83
Validation Report
11.
CL-06f
Version No.:01
01 997 9105065323
Page 84
Validation Report
Explanation is accepted. CL is
closed
CL-06h
CL-06i
12.
CL-06g
13.
14.
01 997 9105065323
Version No.:01
Page 85
Validation Report
Response is accepted. CL is
closed
The
explanation
is
not
convincing. The response is
qualitative and not quantitative.
CL seeks the conformity of the
project to paragraph 112 (c) of
VVM and not Annex 13, EB62 or
Attachment A to appendix B or
Annex 34, EB 35. CL is open
15.
CL-06j
16.
CL-06k
Version No.:01
01 997 9105065323
3rd Assessment:
Inclusion of the CDM revenue in
the IRR calculation is appropriate
hence CL-06k is closed.
Page 86
Validation Report
01 997 9105065323
18.
CL 07
For the statement on p 17 of the
PDD The project ......covered in
Sumatera Power Grid, according
to the PT PLN (Persero). PP
needs to provide objective
evidence and also mention the
same in the PDD.
Version No.:01
Response is accepted. CL is
closed
B.6.1
Page 87
Validation Report
01 997 9105065323
CL 08
20.
CAR01
Version No.:01
D.1
PDD
Validation Report
01 997 9105065323
CAR 02
22.
CAR 03a)
Version No.:01
PDD
B.5
2nd response:
1) The statement of Since this
technology is quite common, the
technology transfer is not difficult to
implement at the project activity.
Was mentioned to explain about the
technology transfer process would not
have difficulty due to the run-of-river
project is a well-known technology in
Indonesia. However to have a better
understanding from public reader the
sentence is revised. The revised is
available at PDD Ver 3 section A.4.2
para 2 page 6.
On section B.5 of PDD clarification was
provided (under heading Investment
Analysis) : Among of above options in
the Attachment A to the Appendix B
Page 89
Validation Report
23.
CAR 03b)
Investment analysis section
should
explain
how
the
investment analysis selected,
(benchmark analysis in this case)
conforms to guidance 19 of
Annex 5, EB 62.
24.
CAR 03c)
Version No.:01
01 997 9105065323
of
simplified
modalities
and
procedures from small scale CDM,
Investment analysis is selected for the
assessment of additionality. Since the
approved
methodology
AMS-I.D
version 17 prescribes the baseline,
further discussion on the alternatives
is not required for the project activity.
The investment analysis section has
been revised to confirm the guidance
19 of Annex 5, EB 62, please refer to
P02_PDD Lubuk_Version 2_111129
section B.5 the supply of electricity
from a grid this is not to be considered
an investment and a benchmark
approach is considered appropriate.
2nd response:
Refer to the guidance of EB 52 annex
5:
Para 19: if the alternative to the
project activity is the supply of
electricity from a grid this is not to be
considered an investment and a
Page 90
Validation Report
01 997 9105065323
Version No.:01
Page 91
Validation Report
01 997 9105065323
CAR-03d
2nd response:
Revision is made that the clarification
of interest rate and taxation is moved
under heading investment analysis.
Resultant
benchmark
and
its
parameter to calculate the benchmark
has been included in Table 6 of PDD
section B.5.
Page 92
Validation Report
01 997 9105065323
26.
CAR-03e
27.
CAR-03f
Version No.:01
Page 93
Validation Report
28.
CAR-03g
29.
CAR-03h
Version No.:01
01 997 9105065323
Page 94
Validation Report
01 997 9105065323
30.
CAR-03i
Operating life of the project has
been considered at 20 years and
Annex 15, EB 50 has been cited
as the basis. As per Annex 15, EB
50, the life is 150,000 hours or
17.1 years and not 20 years.
Further, since overhaul charges
are provided once in 5 years,
restricting the operating life of
the project to 20 years is neither
appropriate nor acceptable.
Version No.:01
Explanation
is
accepted.
However, when the overhaul
charges have been accounted
once in 5 years, restricting the
life of the project to 20 years is
neither
appropriate
nor
acceptable. Guidance 3 also
states, Both project IRR and
equity IRR calculations shall as a
preference reflect the period of
expected operation of the
underlying
project
activity
(technical lifetime). Moreover,
such overhaul charges do not
seem to have been assumed by
other projects. CAR is open
Page 95
Validation Report
31.
CAR-03j
Version No.:01
01 997 9105065323
2nd response:
The selection of the technical lifetime
of 20 years has been in conformity
with Annex 15 EB 50 and Investment
Analysis Guidelines para 3.
Overhaul considered on the FSR
document in 2010 (see FSR document
page 143).
To be conservative, overhaul cost has
been removed from the calculation.
Please refer to worksheet P07_Lubuk
Gadang_IRR_Version 3_120830.xls.
3rd Assessment:
As per the Annex 15 EB 50 and
Investment Analysis Guidelines
para 3, 20 years of operational
life time has been accepted
hence this CAR is closed.
2nd response:
For conservative reason as explained
in the CAR-03i, overhaul costs has
been removed from our project IRR
calculation
(see
P07_Lubuk
Gadang_IRR _Version 3_120827.xls.)
3rd Assessment:
The overhaul costs has been
removed in the revised IRR
calculation sheet hence this CAR
is closed.
Page 96
Validation Report
01 997 9105065323
CAR-03k
Version No.:01
3rd Assessment:
The explanation for contingency
Page 97
Validation Report
01 997 9105065323
2nd response:
a. Contingency
The explanation regarding the 2011
re-FSR and 2010 FSR is available on 2nd
response for CAR-03h.
Regarding the loan application letter
send to bank, it should not be the
financiers responsibility to cover
contingency, therefore it was not
mentioned. Later on this statement is
informed to PP by email from PT. SMI
(Mr. Novi Arriyadi).
The percentage of contingency and
the total project cost with contingency
is available on the re-FSR financial
analysis sheet. Moreover, contingency
has been considered in the FSR in
2010 (Lubuk Gadang Feasibility Study
in 2010.doc page 159, Table
Alternative III (7.5 MW) Recapitulation
of Estimate Cost Lubuk Gadang
MHPP).
Contingency must be considered due
to the uncertainty risk for renewable
energy power plant at such early stage
of development. Moreover, registered
CDM hydro projects in Indonesia
Version No.:01
Page 98
Validation Report
01 997 9105065323
considered
the
inclusion
of
contingency on their project cost. The
project which considered contingency
is listed below:
- Parluasan Hydro Electric Power
Plant
- 10 MW Tangka/Manipi Hydro
Electric Power Plant
There are some studies regarding
contingency as below:
- World
bank
study
Version No.:01
Page 99
Validation Report
01 997 9105065323
CAR-03l
Version No.:01
Page 100
Validation Report
34.
CAR-03m
35.
CAR-03n
Version No.:01
01 997 9105065323
P07_Lubuk
Gadang_IRR_Version
3_120830.xls)
The re-FSR document / Investment
Project Budget Planning document
showed the revised project schedule,
which indicated that the project
would be commission in December
2012. Therefore, we assumed full
electricity revenue of 12 months on
2013.
2nd response:
The interest calculation has been
revised into quarterly repayment with
interest rate of 16.01%. (see
P07_Lubuk
Gadang_IRR_Version
3_120830.xls).
The complete FSR is attached. There
was a problem to convert the word
document into pdf version. We
attached the word version of the
Feasibility
Report
full
English
Page 101
Validation Report
01 997 9105065323
36.
CAR-03o
Version No.:01
Page 102
Validation Report
37.
CAR-03p
38.
CAR-03q
39.
CAR-03r
Version No.:01
01 997 9105065323
Page 103
Validation Report
01 997 9105065323
Version No.:01
Page 104
Validation Report
Version No.:01
01 997 9105065323
Page 105
Validation Report
f)
Version No.:01
01 997 9105065323
e) This
statement
is
unacceptable as the politicoeconomic systems in the four
countries chosen are totally
different and hence the risk
varies. Moreover, some of
the companies are not solely
engaged
in
power
generation. Therefore, to
consider the average beta
value of select companies as
proxy for risk of power
generating
company
in
Indonesia does not conform
to paragraph 112 (b) of VVM
and therefore not acceptable
f)
Explanation is accepted.
However, clarify the reasons
Page 106
Validation Report
01 997 9105065323
Version No.:01
Page 107
Validation Report
i)
j)
considering
commercial
lending rate at 16.01% when
as per the document
furnished the rate is 13.11%
considering
2007
commercial lending rate
when
the
investment
decision is reported to have
been taken much later
Version No.:01
01 997 9105065323
activity.
h) This correction using the DE
ratio and tax rate of each
company - has been made
after the CAR was raised.
Based on the sectoral and
local expertise DOE can state
that the DE ratio and Tax rate
given in the case of Indian
companies does not appear
to be correct. Moreover,
after unlevering the beta, for
reasons not clear it has been
divided by correlation (not
known of what) to arrive at
the total beta and then from
that average beta is arrived
at. This average beta is again
relevered using the average
market debt equity ratio and
presumable Indonesian tax
rate. It is not clear whether
any standard text book
recommends this approach at
all] Hence, the resultant asset
beta is not reliable.
i)
Page 108
Validation Report
01 997 9105065323
j)
2nd response:
3rd Assessment:
a. Issue closed
b. in the project activity, the risk
free rate is determined from
the coupon rate of the
government
bond.
This
approach is similar to other
registered CDM projects in
Indonesia, using Government
bond coupon rate from the
Version No.:01
Page 109
Validation Report
01 997 9105065323
Indonesian
Central
Bank
statistics (www.bi.go.id).
c. Data for risk premium value is
revised,
taken
from
Damodaran database.
Based on the Investment
valuation, A. Damodaran,
second Edition, page 224,
the basic proportion that
the risk premium in any equity
market can be written as:
Equity risk premium = Base
premium for Mature Equity
Market + Country Premium
Version No.:01
Page 110
Validation Report
01 997 9105065323
Version No.:01
Page 111
Validation Report
01 997 9105065323
Version No.:01
Page 112
Validation Report
01 997 9105065323
Therefore,
it
is
most
appropriate to use unlevered
total beta in the project
benchmark
calculation
compared to unlevered beta
value.
The unlevered total beta is
being levered by applying the
tax rate and Debt:Equity ratio
of the project (the financing
structure for this project
consists of the 80% of loan
and 20% equity. This amount
of debt used to finance the
project). The formulae to
calculate the levered beta is as
follow (soft copy of the
reference is furnish in the
excel sheet):
BL = Bu {1+(1-Tc)x(D/E)}
Where :
BL is levered beta for equity
Bu is the unlevered beta (beta
without any debt)
Tc is the corporate tax rate
D/E is the debt/equity ratio
(above
formulae
from
Damodarans
Investment
Valuation page 265, also
mentioned an increase in
financial leverage will increase
Version No.:01
Page 113
Validation Report
01 997 9105065323
Version No.:01
Page 114
Validation Report
01 997 9105065323
Version No.:01
Page 115
Validation Report
01 997 9105065323
Clarification
discussed in
above.
g. Clarification
discussed in
above
h. Clarification
discussed in
above
i.
is given as
the point (e)
is given as
the point (e)
is given as
the point (e)
Issue closed
CAR 04
Version No.:01
B.6.1
B.6.1
Validation Report
CAR 05
Version No.:01
01 997 9105065323
2nd Assessment:
Steps of tool to calculate
emission factor have been
provided in section B. 6.1 of the
revised
PDD
along
with
justification of GEF has been
revised in section B.4 hence CAR04 is closed.
B.6.1
B.6.3 B.7
Page 117
Validation Report
01 997 9105065323
CAR 06
Version No.:01
B.6.2
Page 118
Validation Report
44.
CAR 07
01 997 9105065323
B.6.3
B.7
CAR is open.
PP needs to address the points
like:
2nd response:
The fossil fuel consumption of 1 ton
for operational of Emergency DG set is
an assumption number only (it is
conservative, for such minihydro plant
scale). By having this assumed fuel
consumption number, PP could
configure the Emission Reduction
value after deduction of Project
Emission.
The fossil fuel consumption will be
monitored in litre and converted into
ton.
45.
CAR 08
Version No.:01
Validation Report
b)
c)
d)
e)
Version No.:01
17.
The data units should be in
line with the applied meth.
PP needs to clarify whether
the Electricity exported to
grid is same Gross electricity
generation.
PP needs to clarify the
compliance of the statement
The
net
electricity
export/supplied to a grid is
the difference between the
measured quantities of the
grid electricity and the import.
If applicable, cross check net
electricity supplied to a grid as
gross energy generation in the
project activity power plant
minus the auxiliary/station
electricity
consumption,
technical losses and electricity
import from the grid to the
project power plant measured
at
the
grid
interface/connection used for
billing purposes on p 12 of
the applied meth.
Referring to the statement
The PPA with the ........ the
main meter. on p 27 of the
PDD, PP needs to clarify
whether there is any check
meter installed.
01 997 9105065323
B.7
thoroughly
resubmission.
before
2nd Response:
1) With
this
declaration
where there would no
possibility of 2nd export
meter this point is closed.
2) Section B.7.1 has been
revised in the submitted
PDD which is as per the
PDD filling guideline hence
CAR-08 is closed.
Page 120
Validation Report
01 997 9105065323
2nd response:
1). As stated in the Lubuk Gadang PPA,
article 4 (2.1), the project
proponent will build JTM 20 kV
from powerhouse to Lubuk
Gadang Interconnected Point.
Hence, no possibilities of two
export grid substation for Lubuk
Gadang project specifics.
2). The net electricity generation for
baseline emission calculation is
revised (see PDD Version 3 section
B.7.1) page 30
46.
CAR-09
Version No.:01
B.8
Page 121
Validation Report
01 997 9105065323
Version No.:01
FAR number
Reference
Nil
----
----
----
Page 122
Appendix B
CERTIFICATES OF COMPETENCE
Version No.: 01
Page 123
Version No.: 01
Page 124
Version No.: 01
Page 125
Version No.: 01
Page 126
Version No.: 01
Page 127
Version No.: 01
Page 128
Version No.: 01
Page 129
Version No.: 01
Page 130
Version No.: 01
Page 131
Version No.: 01
Page 132
Version No.: 01
Page 133