Protection of Pipelines Affected by Surface Subsidence: JANUARY 1998
Protection of Pipelines Affected by Surface Subsidence: JANUARY 1998
CITATION
READS
78
3 AUTHORS, INCLUDING:
Yi Luo
West Virginia University
69 PUBLICATIONS 91 CITATIONS
SEE PROFILE
joints. The joints are often the weakest links in the pipeline
system under subsidence influence. The assessment of the
damage potential of subsidence on this type of pipeline is
mainly focused on whether the subsidence-induced bending
and pushing actions are capable of causing damages to the
joints and whether the pulling action is capable of causing
leakage at the joints.
For pipelines constructed with welded, heat-fusion or
rigidly bolted joints, the joints are at least as strong and rigid
as the pipeline itself. This type of pipeline can be treated as
acontinuous beam. A method for assessing the stress level on
a pipeline with rigid joints under the influence of longwall
subsidence was developed using beam theory (Peng and Luo,
1988) and has been successfully applied in recent years. Due
to the complexity of the problem, it was realized that development of a universally applicable method for assessing the
stress on a buried pipeline is a very complicated task. Therefore, the proposed method is limited to pipelines that can be
considered as buried "thin" pipelines with rigid joints.
Wi TRANSACTIONS
VOL. 302
where
W = wall thickness of the pipeline;
R =radius of major subsidence influence, which increases
with overburden depth;
E = Young's modulus of the pipeline material; and
S,,, = maximum possible subsidence
SOCIETY FOR MINING. METALLURGY, AND EXPLORATION.
INC.
Original Surface
m
-
\
b
a
r
Buried Pipeline
0.1
50
1W
1x1
MO
250
XX)
2%
Ovehurden Depth, m
Fig.
where
p is Poisson's ratio of the pipeline material and
Pf is the internal pressure.
Stress due to thermal expansionlcontraction (a,). The
temperature difference between the time when the pipeline is
SOCIETY FOR MINING. METALLURGY, AND EXPLORATION. INC
0.1
4
50
1w
1%
m
Overburden Depth, m
where
his the coefficient of thermal expansion/contraction of the
pipeline material,
T is the temperature during subsidence and
To is the temperature when the pipeline was installed.
Residual stress due to pipeline installation (ai).
Stress due to vertical curvature (ak).Because the pipeline
is thin and weak, it will bend the same amount as the
surrounding soil; thus, it will have the same amount of
curvature as the ground. Therefore, the maximum stress
caused by the surface curvature, located on top and bottom of
the pipeline, will be
EDk
2
ol(
=where
k is the subsidence-induced surface curvature along the
pipeline's axial direction.
Stress due to horizontal strain (a,). During the ground
subsidence process, the ground surface is either stretched or
compressed. The ground tensile or compressive strains will
be transmitted through friction force to the buried pipeline.
To estimate the stress caused by the horizontal strain, the
following two extreme conditions should be considered first:
TRANSACTIONS VOL. 302 99
$1
where
(I is the friction angle between the surrounding soil and the
pipeline outer surface.
An angle of 30" could be used for the friction angle when the
surrounding soil is tightly compacted and fairly dry. The
strain due to the coverage of a longer subsided surface can be
determined by the following equation
+ + Oi k Ok + OE
O,,?
= Ofa Ot
(7)
Main contributors to stresses on pipeline. The maximum stress on a 760-mm (30-in.) steel pipeline is estimated
using Eqs. (2) through (7) and plotted in Fig. 3. In preparing
this figure, the parameters shown in Table 1 were used.
Figure 3(a) clearly shows that the maximum stress on a
buried pipeline is larger in thinner overburden. This is because larger movements and deformations are expected under such conditions. The maximum stress on this pipeline
ranges from 563 to 4,505 MPa (81,700 to 653,400 psi) for
overburden depths of 305 and 61 m (1,000 and 200 ft),
respectively. Compared to the ultimate strength of pipeline
steel, which is in the range of 314 to 373 MPa (45,500 to
54,000 psi), and the commonly used permissible stress of 248
MPa (36,000 psi), the estimated maximum stress is very high
SOCIETY FOR MINING, METALLURGY, AND EXPLORATION. INC
100
1W
2W
260
SW
Parameters
US Units
SI Units
Mining height
Panel width
Pipe wall thickness
Steel, Poisson's ratio
Young's modulus
Thermal coefficient
Internal pressure
Friction angle
6.5 ft
850 ft
0.75 in.
0.3
3 x l o 7 psi
6.7 x 10" I/Fo
200 psi
30"
1.98 m
259 m
19 m m
0.3
2.07 x 10QPa
1.2 x 1 0.5 I/Co
1379 kPa
30"
Overburden Depth, m
\I
'0.W .......................................
1W
160
'
..
In.Rn.
.........................
2W
250
Overburden Depth, m
Mitigation techniques
If the estimated stress level on a buried pipeline is higher
than the permissible stress of'a
material, appropriate
mitigation measures should be employed during the ground
subsidence process to prevent it from being damaged by the
subsidence process.
In the design of the mitigation measures, emphasis should
be placed on the effective reduction of the horizontal strain
and vertical curvature that the pipeline is subjected to, because they are always the No. 1 andNo. 2 sources of stress on
a buried pipeline, respectively.
SOCIETY FOR MINING, METALLURGY, AND EXPLORATION, INC.
?I
I--
4 Uncovering in T e ~ l o nZone
<
.A
--
..
I
.#
Fig. 4 - Uncovering methods in convex (left) and concave (right)
bending zones.
-.
..
Tallentry
'
MLnlng Direction
Case studies
In the past few years, the proposed stress-assessment
methods for buried pipelines were successfully applied in the
assessment of subsidence influences on and design of mitigation measures for various pipelines affected by the subsidence process associated with longwall mining. As an example, the protection of a section of water-supply pipeline,
about 2,367 m (7,765 ft), was recently carried out by the
authors. The protected pipeline was a 305-mm (12-in.) steel
pipeline that was constructed with welded joints. The wall
thickness was 19 mm (314 in.). It was buried between0.61 and
1.22 m (2 and 4 ft) below the ground surface along a stream
in the flat area of a gentle valley. The pipeline was laid over
four successively mined longwall panels. The widths of the
longwall panels ranged from 256 to 283 m (840 to 930 ft), and
each of the chain pillar systems between the panels was 56 m
(185 ft) wide. The average mining height was 1.98 m (6.5 ft),
while the overburden depth m the area was about 195m (640 ft).
Based on Fig. 2, the critical diameter of a buried "thin"
pipeline under this condition is at least 1,270 mm (50 in.),
considerably larger than the 305-mm (12-in.) diameter of the
pipeline. Therefore, this pipeline can be considered as a
buried "thin" pipeline, and the proposed stress-assessment
method can be applied.
Figure 5 shows the layout of the water pipeline over
longwall panel No. 4. The angle between the pipeline and the
mining direction was about 62". The predicted final subsidence and horizontal displacement along the pipeline are
shown m Fig. 6.
The predicted maximum subsidence and horizontal displacement were about 1,234 and 396 mm (4.05 and 1.3 ft),
respectively. It should be noted that panel No. 3 had been
mined previously, and an additional amount of subsidence,
about 244 mm (0.8 ft), was expected over the chain pillars
between the two panels.
The predicted stresses on the top and bottom of the
pipeline without uncovering are shown in Fig. 7. The permissible tensile and compressive stresses of the pipeline steel,
248 MPa (6,000 psi), are also plotted in this figure. The stress
profiles on the top and bottom points of the pipeline nearly
overlapped each other along the full length, mainly due to the
fact that the stresses caused by vertical curvature in this case
was much smaller them that by the horizontal strain. The
Panel
no.
-50
100
50
I50
2W
250
YYI
Length
affected,
m
Uncovered Uncovered
Total
in Tension in Comp. uncovered
zone,
length,
zone,
m
m
m
1,177
285
277
562
41 8
120
70
190
383
122
122
244
390
108
131
239
350
..
-5QO
...
Rnd n4
,
-tom&::,
-50
50
?M
150
2W
150
WJ
350
Kiusalaas, J., and Albert, E.K.. 1983. "SPASID: A Computer Program for Predicting
Ground Movement Due to Underground Mining," The Pennsylvania State University.
Report to USBM under contract No. J0295031,201 pp.
Luo. Y., and Peng, S.S., 1989, "CISPM - A subsidence prediction model,' Proceedings
of the Rock Mechanics as a Guide lor Efficient Ufilization of Natural Resources - 30th US
Symposium, A.W. Khair, ed.. West Virginia University. Morgantown, WV, pp. 853-860.
sible one, which is still more than 30% lower than the ultimate
strength, implied the necessity for employment of such
mitigation measures for this pipeline.
Luo, Y., and Peng, S.S.. 1990a, "A malhematical model for predicting final subsidence
basin in hllly regions," Proceedings 01 the AEG National Syrnposium on Mine Subsidence
- Prediction and control, C.D. Elifrits, ed., Association of Engineering Geologists, pp.
223-231 (Republished in AEG Bulletins).
Conclusions
Luo, Y.. and Peng. S.S., 1990b, "A mathematical model for predicting subsidence over
chain pillars between mined-out longwall panels," Proceedings of the AEG National
Symposium on Mine Subsidence - Prediction and Control, C.D. Elifrits, ed., Association
of Engineering Geologists, pp. 247-257 (Republished in AEG Bulletins).
Luo, Y.. and Peng, S.S., 1991, "Some new findings from surface subsidence monitoring
over longwall panels," Mining Engineering, SME. Littleton CO, October, pp. 1261-1264.
Luo, Y.. and Peng, S.S., 1992, "A comprehensive dynamic subsidence prediction model
for longwall operations", Proceedings of the 1l t h International Conference on Ground
Controlin Mining. N.I. Aziz and S.S. Peng, eds.. University of Woolongong. Woolongong,
Australia, pp. 51 1-516.
Luo, Y., and Peng. S.S., 1993, "Using influence function method to predlct surface
subsidence caused by high extraction room and pillar mining", Proceedings of the 7th
International FM Symposium on Deformation Measurement, W.F. Teskey, ed., University
of Calgary, Calgary, Alberta, Canada, pp. 342-353.
Peng, S.S., and Luo. Y., 1988a, "Determination of stress field in buried thin pipelines
resulting from ground subsidence due to longwall mining," Mining Science and Technology, Vol. 6, pp. 205-216.
Peng. S.S., and Luo. Y., 1988b, "Monitoring and prediction of surface dynamicsubsidence
due to longwall coal mining," Proceedingsofthe 5th InternationalSymposium on Deformation Measurement, C. Chrzanowski and W. Wells, eds., University of New Brunswick,
Fredericton. New Brunswick, Canada, pp. 320-429.
Peng, S.S.. and Luo, Y., 1992, "Comprehensive and integrated subsidence prediction
model - CISPM (V2.0),' Proceedings of the 3rd Workshop on Surface Subsidence Due
to Underground Mining. S.S. Peng, ed., West Virginia University, Morgantown, WV, pp.
22-31.
References
Peng. S.S., Luo, Y.. and Zhang. Z.M., 1995, "Subsidence parameters - Their definitions
and determination." Transactions, SME, Vol. 300, pp. 60-65.
Adamek, V., and Jeran. P.W.. 1985, "Precalculat~onof subsidence over longwall panels in
the northern Appalachian coal region," Proceedings of the USBM Technology Transfer
Seminar, P~ttsburgh,PA. USBM. IC 9042, pp. 34-56.