0% found this document useful (0 votes)
151 views1 page

Procedure Checklist ASTM C 31 Making and Curing Concrete Test Specimens in The Field

This procedure checklist outlines the steps to make and cure concrete test specimens according to ASTM C 31 standards. It involves filling molds in layers, rodding each layer to consolidate the concrete, tapping the molds to release air, and striking off excess concrete. The specimens are then marked for identification and moved to initial curing storage to prevent moisture loss.

Uploaded by

mike murdoc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
151 views1 page

Procedure Checklist ASTM C 31 Making and Curing Concrete Test Specimens in The Field

This procedure checklist outlines the steps to make and cure concrete test specimens according to ASTM C 31 standards. It involves filling molds in layers, rodding each layer to consolidate the concrete, tapping the molds to release air, and striking off excess concrete. The specimens are then marked for identification and moved to initial curing storage to prevent moisture loss.

Uploaded by

mike murdoc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Revised: September 29, 2015

C. Roberts

Procedure Checklist
ASTM C 31 Making and Curing Concrete Test Specimens in the Field
Test procedures for 4 x 8 inch or 6 x12 inch cylinders using concrete with a slump 1 inch
P

N/A

Item
1.

Use a scoop to place concrete in the mold. Use care to distribute the material evenly around
the perimeter of the mold.

2.

For the first layer:

3.

Fill the mold with the appropriate quantity of concrete: approximately the volume for a 4 x
8 inch mold or the volume for a 6 x 12 inch mold.

4.

Rod the layer 25 times throughout its depth, using care not to damage the bottom of the
mold. Distribute the roddings uniformly over the cross section of the mold.

5.

Tap the outsides of the mold lightly 10 to 15 times with the mallet (or open hand if susceptible to
denting or other permanent distortion if tapped with a mallet) to close any holes left by rodding and
to release any large air bubbles that may have been trapped.

6.

For the second layer:

7.

Fill the mold with the appropriate quantity of concrete to fill a 4 x 8 inch mold or to
approximately the volume for a 6 x 12 inch mold.

8.

Rod the layer 25 times, penetrating into the layer below approximately 1 inch. Distribute the
roddings uniformly over the cross section of the mold.

9.

Tap the outsides of the mold lightly 10 to 15 times with the mallet (or open hand if susceptible to
denting or other permanent distortion if tapped with a mallet) to close any holes left by rodding and
to release any large air bubbles that may have been trapped.

When 4 x 8 inch cylinders are used, skip Step 10 and proceed with Step 14. When 6 x 12 inch cylinders are used,
proceed with Step 10.
10.

For the third layer:

11.

Add an amount of concrete that will fill the mold after consolidation.

12.

Rod the layer 25 times, penetrating the layer below approximately 1 inch. Distribute the
roddings uniformly over the cross section of the mold.

13.

Tap the outsides of the mold lightly 10 to 15 times with the mallet (or open hand if susceptible to
denting or other permanent distortion if tapped with a mallet) to close any holes left by rodding and
to release any large air bubbles that may have been trapped.

14.

Adjust the concrete level of under-filled and overfilled molds if necessary.

15. .

Strike off any excess concrete with the tamping rod, or with a handheld float or trowel if
appropriate, to produce a flat even surface.

16.

Verify that the specimen mold has been marked to identify the concrete it represents.

17.

Immediately after finishing, provide protection to prevent sample moisture loss and move
the specimens to an initial curing place for storage.

Remarks:

Comparison Criteria: N/A

Date: _______________ Technician: ____________________________ IA Observer: _____________________________


Technicians E-mail Address: ___________________________________________________________________________
Employers/ Supervisors E-mail Address: _________________________________________________________________