Step 1: Collect List of Loads
Step 1: Collect List of Loads
generally accepted industry practice. The following methodology assumes that the load schedule
is being created for the first time and is also biased towards industrial plants. The basic steps for
creating a load schedule are:
Step 2: For each load, collect the electrical parameters, e.g. nominal / absorbed
ratings, power factor, efficiency, etc
Step 3: Classify each of the loads in terms of switchboard location, load duty and load
criticality
Step 5: For each switchboard and the overall system, calculate operating, peak and
design load
Process loads - are the loads that are directly relevant to the facility. In factories and
industrial plants, process loads are the motors, heaters, compressors, conveyors, etc
that form the main business of the plant. Process loads can normally be found on
either Mechanical Equipment Lists or Process and Instrumentation Diagrams (P&ID's).
Non-process loads - are the auxiliary loads that are necessary to run the facility, e.g.
lighting, HVAC, utility systems (power and water), DCS/PLC control systems, fire
safety systems, etc. These loads are usually taken from a number of sources, for
example HVAC engineers, instruments, telecoms and control systems engineers,
safety engineers, etc. Some loads such as lighting, UPS, power generation auxiliaries,
etc need to be estimated by the electrical engineer.
Rated power is the full load or nameplate rating of the load and represents the
maximum continuous power output of the load. For motor loads, the rated power
corresponds to the standard motor size (e.g. 11kW, 37kW, 75kW, etc). For load items
that contain sub-loads (e.g. distribution boards, package equipment, etc), the rated
power is typically the maximum power output of the item (i.e. with all its sub-loads in
service).
Absorbed power is the expected power that will be drawn by the load. Most loads
will not operate at its rated capacity, but at a lower point. For example, absorbed
motor loads are based on the mechanical power input to the shaft of the driven
equipment at its duty point. The motor is typically sized so that the rated capacity of
the motor exceeds the expected absorbed load by some conservative design margin.
Where information regarding the absorbed loads is not available, then a load factor of
between 0.8 and 0.9 is normally applied.
Power factor of the load is necessary to determine the reactive components of the
load schedule. Normally the load power factor at full load is used, but the power
factor at the duty point can also be used for increased accuracy. Where power factors
are not readily available, then estimates can be used (typically 0.85 for motor loads
>7.5kW, 1.0 for heater loads and 0.8 for all other loads).
Efficiency accounts for the losses incurred when converting electrical energy to
mechanical energy (or whatever type of energy the load outputs). Some of the
electrical power drawn by the load is lost, usually in the form of heat to the ambient
environment. Where information regarding efficiencies is not available, then estimates
of between 0.8 and 1 can be used (typically 0.85 or 0.9 is used when efficiencies are
unknown).
Voltage Level
What voltage level and which switchboard should the load be located? Large loads may need to
be on MV or HV switchboards depending on the size of the load and how many voltage levels are
available. Typically, loads <150kW tend to be on the LV system (400V - 690V), loads between
150kW and 10MW tend to be on an intermediate MV system (3.3kV - 6.6kV) where available and
loads >10MW are usually on the HV distribution system (11kV - 33kV). Some consideration
should also be made for grouping the loads on a switchboard in terms of sub-facilities, areas or
sub-systems (e.g. a switchboard for the compression train sub-system or the drying area).
Load duty
Loads are classified according to their duty as either continuous, intermittent and standby loads:
1) Continuous loads are those that normally operate continuously over a 24 hour period,
e.g. process loads, control systems, lighting and small power distribution boards, UPS
systems, etc
2) Intermittent loads that only operate a fraction of a 24 hour period, e.g. intermittent
pumps and process loads, automatic doors and gates, etc
3) Standby loads are those that are on standby or rarely operate under normal
conditions, e.g. standby loads, emergency systems, etc
Note that for redundant loads (e.g. 2 x 100% duty / standby motors), one is
usually classified as continuous and the other classified as standby. This if purely
for the purposes of the load schedule and does not reflect the actual operating
conditions of the loads, i.e. both redundant loads will be equally used even though
one is classified as a standby load.
Load criticality
Loads are typically classified as either normal, essential and critical:
1) Normal loads are those that run under normal operating conditions, e.g. main process
loads, normal lighting and small power, ordinary office and workshop loads, etc
2) Essential loads are those necessary under emergency conditions, when the main
power supply is disconnected and the system is being supported by an emergency
generator, e.g. emergency lighting, key process loads that operate during emergency
conditions, fire and safety systems, etc
3) Critical are those critical for the operation of safety systems and for facilitating or
assisting evacuation from the plant, and would normally be supplied from a UPS or
battery system, e.g. safety-critical shutdown systems, escape lighting, etc
Where
Operating load
The operating load is the expected load during normal operation. The operating
load is calculated as follows:
Where
Peak load
The peak load is the expected maximum load during normal operation.
Peak loading is typically infrequent and of short duration, occurring
when standby loads are operated (e.g. for changeover of redundant
machines, testing of safety equipment, etc). The peak load is calculated
as the larger of either:
or
Where
Design load
The design load is the load to be used for the design for equipment sizing, electrical studies, etc.
The design load is generically calculated as the larger of either:
or
Where
The following electrical load parameters were collected for the loads identified in Step 1:
Load Description
Abs. Load
Rated Load
PF
Eff.
750kW
800kW
0.87
0.95
750kW
800kW
0.87
0.95
Recirculation pump A
31kW
37kW
0.83
0.86
Recirculation pump B
31kW
37kW
0.83
0.86
Sump pump
9kW
11kW
0.81
0.83
Firewater pump A
65kW
75kW
0.88
0.88
Firewater pump B
65kW
75kW
0.88
0.88
HVAC unit
80kW
90kW
0.85
0.9
AC UPS System
9kW
12kW
0.85
0.9
7kW
10kW
0.8
0.9
4kW
5kW
0.8
0.9
Suppose we have two voltage levels, 6.6kV and 415V. The loads can be classified as
follows:
Load Description
Rated Load
Voltage
Duty
Criticality
800kW
6.6kV
Continuous
Normal
800kW
6.6kV
Standby
Normal
Recirculation pump A
37kW
415V
Continuous
Normal
Recirculation pump B
37kW
415V
Standby
Normal
Sump pump
11kW
415V
Intermittent
Normal
Firewater pump A
75kW
415V
Standby
Essential
Firewater pump B
75kW
415V
Standby
Essential
HVAC unit
90kW
415V
Continuous
Normal
AC UPS System
12kW
415V
Continuous
Critical
10kW
415V
Continuous
Normal
5kW
415V
Continuous
Essential
Load Description
Abs
Load
PF
Eff.
Vapour recovery
compressor A
750kW
0.8
7
Vapour recovery
750kW
0.8
Intermittent
Standby
P
(kW)
Q
(kVAr)
P
(kW)
Q
(kVAr)
P
(kW)
Q
(kVAr)
0.9
5
789.5
447.4
0.9
789.5
447.4
compressor B
Recirculation
pump A
31kW
0.8
3
0.8
6
36.0
24.2
Recirculation
pump B
31kW
0.8
3
0.8
6
36.0
24.2
Sump pump
9kW
0.8
1
0.8
3
10.8
7.9
Firewater pump A
65kW
0.8
8
0.8
8
73.9
39.9
Firewater pump B
65kW
0.8
8
0.8
8
73.9
39.9
HVAC unit
80kW
0.8
5
0.9
88.9
55.1
AC UPS System
9kW
0.8
5
0.9
10.0
6.2
Normal lighting
distribution board
7kW
0.8
0.9
7.8
5.8
Essential lighting
distribution board
4kW
0.8
0.9
4.4
3.3
936.6
542.0
10.8
7.9
973.3
551.4
SUM TOTAL
Q (kW)
936.6
542.0
5.4
4.0
97.3
55.1
789.5
447.4
Operating load
942
546.0
Peak load
1,731.5
993.4
Design load
1,825.7
1,047.9