TIMELINE FOR REMAINING WORKS

Project Name: MHP____Golen Astore 136


kW_______________
Physical Progress:
Project
Component

Cumulative
Progress %
as of 10th
Nov, 2016

Time line for


Remaining works
Start Date
End Date

Intake Works
Excavation

Complete

Diversion

Complete

Reinforcement
Fabrication
RCC Pouring

Complete

Temporary
Cofferdams as
the water
level is rising
Stilling Basin
as per Engr.
Kashif design
on site
Small
Collection
Chamber
Intake
Protective
Work (GI Wire)
19m

Complete
Complete

Complete

Complete

Cutoff Wall

5th Apr,2017

20th
Apr,2017

1st Apr,2017

10th
May,2017

In Progress

30th

Approach
Canal
Excavation
Flood Wall

100%

Filling and

75%

Responsib
ility

Compaction
Pipe Canal

Nov,2017
Complete
20th
Nov,2016

10th
Dec,2016

15th
Apr,2017

30th
Apr,2016

10th
Apr,2017

25th
Apr,2017

Spill way

1st Apr,2017

10th
Apr,2017

Gate

1st Apr,2017

Sand Filling
RR Masonry
Canal
Slab Covering
PCC
Sedimentation
Tank
Excavation

100%

Reinforcement
Fabrication
RCC Pouring

100%

RR Masonry

100%

Plaster

100%

Spillway

0%

100%

100%

Gravel Trap
Excavation
RR Masonry

Complete

Grouting

Complete

PCC Bed

Complete

Baffle Wall

Complete

Headrace
Canal
Excavation

Complete

RR Masonry

Complete

Grouting

100%

PCC

70%

Plaster

Complete

Superpassage
( Masonry)
Slab Covering

Complete
25%

Fore bay
Excavation

Complete

1st Apr,2017

10th
Apr,2017

20thApr,201
7

15th
May,2017

Reinforcement
Fabrication
RCC Pouring

Complete

RR Masonry

Complete

Plaster

Complete

Spillway

Complete

Spillway
Plaster
PCC

20%

Complete

15th
Apr,2017

30th
Apr,2017

Anchor Blocks

1st Apr,2017

Penstock
Alignment
Power House

15th
Apr,2017

15th
Apr,2017
15th
May,2017

Complete

Excavation

Complete

Lean Concrete

Complete

Plum Concrete

Complete

Reinforcement
Fabrication
RCC Pouring

90%

RR Masonry

20%

Machine
Foundation

Depending on
availability of
foundation
Drawings by
manufacturer.
0%

Plaster
Tail Race
Canal
Protective
Work
Installation of
Electromecha
nical
Equipment
(E&M)
Procurement
Process
Delivery of
E&M

80%

10th
Apr,2017
10th
Apr,2017
1st Apr,2017

20th
Apr,2017
20th
Apr,2017
30th
Apr,2017

10th
april,2017

30th
April,2017

15th
May,2017
1st
May,2017
1st
May,2017

30th
May,2017
30th
May,2017
20th
May,2017

In progress

January
15,2017
May
15,2017

0%

January
15,2017

equipment
Installation of
E&M
equipment
Transmission
and
Distribution
(T&D)
Procurement
Process
Delivery of
T&D
equipment
Installation of
T&D
equipment
-----

Photo Gallery

May
20,2017

June
30,2017

September
10,2016
December
15,2016

18th
Nov,2016
April
1,2017

April
10,2016

June
15,2016

Fig 1

Fig 2

Stilling Basin Intake

Collection Chamber Reinforcement

Fig

Fig 4

3
Approach Canal Pipe
Fig 5

Collection Chamber
Fig 6

Filling Work for Approach Canal Pipe

Filling Work for Approach Canal