NCR Template

This document summarizes a nonconformance report (NCR) issued by Petroliam Nasional Berhad (Petronas) for their Refinery and Petrochemical Integrated Development Project (RAPID). The NCR was issued for two nonconformances related to electrical cable installation. Specifically, [1] cable trays and ladders were not properly secured to supports as required by project standards and [2] on-site fabricated fittings were used instead of manufacturer-approved fittings. An investigation determined the root causes were failures to follow procedures and improper work practices. The proposed disposition was to rework the nonconforming installations to meet project requirements.

Uploaded by

chikannos
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
716 views2 pages

NCR Template

This document summarizes a nonconformance report (NCR) issued by Petroliam Nasional Berhad (Petronas) for their Refinery and Petrochemical Integrated Development Project (RAPID). The NCR was issued for two nonconformances related to electrical cable installation. Specifically, [1] cable trays and ladders were not properly secured to supports as required by project standards and [2] on-site fabricated fittings were used instead of manufacturer-approved fittings. An investigation determined the root causes were failures to follow procedures and improper work practices. The proposed disposition was to rework the nonconforming installations to meet project requirements.

Uploaded by

chikannos
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

Petroliam Nasional Berhad (Petronas)

Refinery and Petrochemical Integrated Development Project


(RAPID)

Form 01301
Revision 0
Oct 2014
Page 1 of 1

INTEGRATED PROJECT MANAGEMENT TEAM (IPMT)

NCR No.:

RAPID-0001-PMC-ELENCR-1000-0005

(Number by Area Site


QA/QC NCR Controller)

Date issued:

Contract No.:

Contractor:

TAG / ITEM / LINE No.:

DISCIPLINE:

10/10/2016
CCSM

P. O. No.:

WBS (Work Breakdown Structure) No.:

MANUFACTURER NAME: U-LI

TURNOVER SYSTEM No.:

ELECTRICAL
AREA / LOCATION OR UNIT
NAME: COMMON AREA
/RFCC1/ RFCC2

Attachment: Attachment A,B,C,D &


Drawing

Initiated by:
HAMIDI BIN ROZEMIN

Date:
10/10/2016

Hold Tag:
Yes
No

DWG. No. / Rev.:


RAPID-P0001-CCSM-ELE-STD1300-1220 (Power Installation
Typical Details )

Spec. Std. No. / Rev.:


Vendor Typical Layout (U-LI Steel Cable
Ladder Typical Layout & U-LI Steel Cable
Tray Layout)

.
Audit No. (If Applicable):

DESCRIPTION OF NONCONFORMANCE (by Initiator)


A. Power Installation Typical Details (RAPID-P0001-CCSM-ELE-STD-1300-1220)
Cable tray shall be secured to cable tray support with hold down clamp. Refer to page 10/25 and page 20/25
Cable ladder shall be secured to cable ladder support with hold down clamp. Refer to page 20/25
Connector plat shall be install in between two cable ladder or cable tray for connection purpose.
Non Conformance:
1. Cable tray secured to cable tray support with bolt & nuts. Please refer to attachment A
2. Connection in between cable tray using Spot-welded techniques. Please refer to attachment A.

B. Vendor Typical Layout (U-LI Steel Cable Ladder Typical Layout & U-LI Steel Cable Tray Layout)

All fitting , i.e. bends, tees, risers, elbows, etc. shall be supplied by ladder rack or tray manufacturer. Please
refer to attachment D

Non Conformance:
1. Site fabricated fitting used at site. Please refer to attachment C

ROOT CAUSE (Analyze by IPMT QA Manager)

CAUSE CODE(S): C08,C09

NCR Cause Code Index: C01=Client Driven, C02=Communication, C03=Equipment/Material, C04=External Phenomenon, C05=Location Driven, C06=Management
Driven, C07=No Procedure, C08=Not Following Procedure, C09=People Driven, C10=Systems Driven, C11=Work Environment

DISPOSITION:

Use as is

Rework

Repair

Other

Petroliam Nasional Berhad (Petronas)


Refinery and Petrochemical Integrated Development Project
(RAPID)

Form 01301
Revision 0
Oct 2014
Page 1 of 1

INTEGRATED PROJECT MANAGEMENT TEAM (IPMT)

Attachment A2:
DISPOSITION
PROPOSED

AGREED THE
PROPOSED
DISPOSITION

Sheet(s), if needed
By Contractor Construction Engineer:
Print Name/Sign
____________________________________
By IPMT Construction Engineer:
Print Name/Sign
____________________________________
By IPMT Site QA: Print Name/Sign
By IPMT EPCC Discipline Engineer:
Print Name/Sign
____________________________________
By IPMT QA Manager:
Print Name/Sign

Date:
_______

Design Engineer Approval Required the Disposition


(Definition by IPMT QA Manager):
Yes

No

_______

Note(s) and Approval by Design Engineer if required.

Date:
_______

DISPOSITION
COMPLETED BY

Attachment A3:

Note(s):

Approved by:
Contractor: QA/QC Manager,
Print Name/Sign
Sheet(s), if needed

Date
Design Engineer
Print Name/Sign

ACTION VERIFIED AND NON-CONFORMANCE CLOSED


VERIFICATION METHOD
DOCUMENT REVIEW

INSPECTION

OTHER

IPMT QA/QC INSPECTOR: Print Name/Sign

Attachment A4: Sheet(s), if needed


DATE (dd/mm/yy) :

VERIFIED DISPOSITION AND RECOMMENDED CLOSURE OF NCR


IPMT QA Manager or IPMT EPCC/Package QA/QC Manager:

Print Name/Sign

DATE (dd/mm/yy) :

Date