SW Hydrostatic Pressure Testing Water Mains
SW Hydrostatic Pressure Testing Water Mains
GF
The length and diameter of main being tested and the number of joints and fittings.
The availability of a suitable potable water supply to fill and pressure test the main.
The location of a suitable discharge point for the water used after testing.
To prevent an Environmental Pollution Incident (EPI)
Any difference in elevation to meet the System Test Pressure (STP) and or the % of
trapped Air within the main.
Any temperature variations on site especially for PE pipelines and creep factors.
The size of pump and its capacity including its maximum pressure and flow.
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Anywhere a new main is being inserted into a host main as the new main can be damaged
by existing services or where the existing main has been cut out for new service to be
reinstalled or from shards from pipe bursting etc.
Larger diameters mains or longer section of mains shall be undertaken using the type 2
pressure test. Any new mains laid as part of mains rehabilitation program using the Open
Cut method shall be pressure tested using a type 2 pressure test.
Safety Note
This document sets out the requirements for undertaking, checking and validating
pressure tests in Scottish Water using industry best practice. It also provides the basic
guidelines for the safety and protection of personnel on site and the general public
during pressure the hydrostatic test. It is the responsibility of the individual hydrostatic
pressure testing company and its staff to further develop its own appropriate generic
and or site specific safety plans and control measures and with their implementation to
safely carry out hydrostatic pressure testing of Water Mains & Fittings in Scotland as
well as complying with any other appropriate legislation or documentation relating to
hydrostatic pressure testing in the UK.
I.e. The Health Safety Executive, Safety requirements for pressure testing Guidance
Note GS4
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Electronic copies of the hydrostatic pressure test submitted must include the pressure tests
Incremental readings (i.e. print outs 20sec), Pressure Decay Graphs, Flow meter readings
with the relevant supporting video or photographic evidence for validation.
SW also requires a site drawing with the highlighted section of main / mains being tested.
Geo tagged Photographic & or Video evidence Must now be provided with all hydrostatic
pressure test submission and include the following:
Hydrostatic Pressure test set up.
SW Licenced stand pipe and serial number.
Bored & Tapped Blank Plates used with additional valves to allow the safe removal of air.
Electronic Data Logger with serial number & the calibration date.
Flow Meter.
Dual Functional Logger if applicable with serial number & the calibration date.
GEO TAGGING Photos
Geo tagging is the process of adding a location, date and time to your photos and is now
required by SW as part of the validation process to confirm compliance with the various
elements of the hydrostatic pressure has been correctly undertaken on each site.
Here's how to do it: (Example for SW Samsung phones)
Open up the stock Samsung Camera app on the phone.
Look for the Settings 'Gear' icon and tap on it.
On the grid of settings that presents itself scroll down a little until you see "Location tags"
Tap to enable/disable as desired!
IPhones by default are already set to record the location information on photos and videos
taken using the camera app.
Photo editing apps and services, such as Lightroom, Aperture, iPhoto, Picasa, and Flickr,
also support geotagged images.
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
All pressure tests should have a minimum of 1 minute Ramp Up time & Maximum Ramp up
time of 30 minutes.
The minimum Pressure test duration for SW is 1 hour.
The maximum Test Pressure duration for SW is 10 hours. I.e. 30min Ramp up Time.
Any Pressure Test that requires being longer than 10 Hours in duration due to excessive
lengths of the main being tested or as a result of trapped air content etc should be notified to
SW and follow the SW waiver process in advance of the test.
Note: There is a higher likelihood of a pressure test failing when using incorrect pumps
(Undersized or Oversized) and ramp up times.
Short lengths of pipe work wherever possible should be undertaken using a hand
Pump.
The use of the hand pump will be based on the volume of water required to be added for
pipe pressurisation to STP and calculation of the Ramp Up / Load times effecting the
duration of the pressure test.
Litre / Minute (Pump out put) affect the Ramp Up time.
Note: There is No requirement to use a Flow meter if using a hand Pump. However the
volume of water used must still be physically recorded.
Any test that is not undertaken with a hand pump requires a Flow meter to be used.
A calibrated flow meter, with a resolution of 1 litre or better must be used to accurately
measure the volume of water added during the pressure rise phase to STP.
SW preference is for dual functional data loggers to be fitted to record Flow & Pressure.
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Swabs must only be inserted into the main on the actual day when physically carrying
out either swabbing or disinfecting the main using swabs with the correct amount of
chlorine tablets.
Swabs shall be used once only unless otherwise approved by SW & all swabs must be
accounted and recovered from the main.
Any work that does not follow this sequence of stages will be considered non-compliant with
respect to application of this Scottish Water DOMS procedures and Hygiene Code of
Practice.
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Starting Pressures
The starting pressure for any hydrostatic pressure test should preferably be zero to
accurately check and validate the ramp up time of the pressure test being undertaken.
The starting pressure within the main should not exceed 1 bar or the natural static head
within the main being tested whichever is the greater.
Any pre-pressurisation within the main must be recorded on the SW proforma to
accurately validate the pressure test.
Any attempt to shorten the pumping phase by increasing the initial pressure to local mains
pressure (pre-pressurisation) using an adjacent main is not allowed and will result in the test
being classed as invalid.
Only once the main has been slowly filled with potable water (prior to pressurisation), MUST
the data logger be connected and all information logged. (Unless using a dual functional
logger)
The pressure should then be raised to the correct level of System Test Pressure (STP) by
pumping in a controlled manner.
Any hydrostatic pressure test with the data logger fitted after ramping up the main
and reaching System Test Pressure (STP) will be an automatic fail.
DISTRIBUTION, OPERATION and MAINTENANCE STRATEGY
WORK PROCEDURE/INSTRUCTION
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Note: There is a Health & Safety risk to the person or persons undertaking the pressure
test especially with any air trapped within the main and the hydrostatic pressure test set
up detailed in the diagrams above and below.
SW Preference is to have Bored & Tapped blank plates fitted to the top flange of Duckfoot
bends at each end of the pressure test section to aid the removal of air and protect the main
from ground water entering the main.
This will facilitate and allow for the removal of as much air as possible from the test section.
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
All Pressure tests require either a Flow Meter & Pressure Gauge or Dual Functional Logger
to capture the volumes of water required and used for the ramp up to STP
(System Test pressure).
Note: Where short lengths of small bore main are being tested where a hand pump is being
used and volume of water added during ramp up can be measured in the pump reservoir, it
will not be required to use a flow meter.
SW preference is for data loggers to be fitted with GPS capabilities or requires Geo Tagged
Photographic evidence to be submitted with the test report for each hydrostatic test.
All Pressure test loggers must have UKAS Calibration Certifications & be traceable through
UKAS standards.
It is critical that the data logger is calibrated and set correctly to accurately record enough
readings at the correct intervals during both the ramp up time to check for the presence of
Air and to measure the rate of decay throughout the duration of the test.
SW now requires all pressure tests to be submitted in both PDF and in an electronic format
to check, interrogate and validate the test data.
When applying either the Water Loss or Water Added method to a hydrostatic
pressure test for pressure testing Ductile Iron and Steel Mains in Scottish Water
the pump being used must be adequate to raise the pressure in a controlled
manner and be able achieve the correct STP required.
Any hydrostatic pressure test that is using the Water Added method requires a
separate, specialised pump.
This pump must also be able to maintain and pump continuously in a controlled
manner at the required test pressure of the main / pipe being tested while
measuring the volume of water being pumped into the main to maintain the test
pressure.
This pump should also have data logging capabilities to accurately measure the
volumes of water being used.
This pump can if required also be used with the Water Loss method to accurately
measure the water required to bring the pipeline back to STP.
Alternatively, a hand pump could be used for the Water Loss method.
After preliminary condition of the main, the main must be raised to its
STP and measurement the amount of water required to maintain STP
using either of the methods must be accurately recorded.
The following is the basic principal and steps required to set up to
undertake either a Water Added or a Water Loss Test.
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Please Note
If the volume of water loss is calculated to be less than 0.025 Litres, then a
pressure loss test of 0.2 bar per hour should be used over the 1 hour test period.
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Note: SW Customer Connection staffs are required to send back confirmation and acceptance of
test results submitted for contractors to proceed to the next stage of commission mains
DISTRIBUTION, OPERATION and MAINTENANCE STRATEGY
WORK PROCEDURE/INSTRUCTION
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Ductile Iron
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
DISTRIBUTION,
OPERATION
andGraphs
MAINTENANCE
STRATEGY
Pressure
Test
& Test
Results
WORK PROCEDURE/INSTRUCTION
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
A secure pipeline that is free of leakage etc should have a graph that displays the
pressure decay with a constant logarithmic slope and graph.
If there is either a dramatic or a consistent increase in slope during the test this would
indicate leakage.
If n2/n1 values are 1.25, then the test is a pass.
Or alternatively if t4 calculation are used then,
If n3/n1 values are 1.25, then the test is a pass.
There are a number of factors that can affect a pressure test and the result which
include the following examples,
The type of pipe material being tested to its incorrect pressure rating.
Pressure testing different pipe materials at the same time.
Excessive lengths of mains being tested.
The number of sections of mains being tested at the one time.
The height difference in the pipeline elevation and or the location of the pressure test
set up.
Static Head or Pre pressurisation of mains.
The size of pump and the maximum test pressure of the pump used its flow rate for
pressurisation.
The presence and % of air in the system.
The accuracy of the testing equipment especially if not calibrated.
When the test starts and finishes and the correct t1, t2, t3 and t4 values are taken.
Any actual leakage.
The length of time the pressure test is required to be completed.
The number of joint and fittings including Air valve or service connections if bored &
tapped.
Flooding.
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Pressure testing should preferably be undertaken during dry weather as pressure testing in
wet weather or if the main is in water filled trenches it may mean that leaks are not identified
or detected.
Are all inline valves open to allow the passing and venting entrapped air?
Has the pump to pressurise the main to STP been correctly sized?
Too small of a pump will extend the test duration, and too large of a pump may prevent the
control of the test pressure.
Is all pressure test equipment calibrated and within date.
I.e. data logger, pressure gauges, Flow Meters, temperature recorders etc
Pipe material pressure test checked and confirmed i.e. SDR 17 tested to15 Bar test.
Document Control
This document is a CONTROLLED DOCUMENT when viewed on Wavelength.
The document becomes UNCONTROLLED if printed or downloaded from Wavelength or
any other source.
Refer to the Wavelength site for the latest version of this document.
Change Request
A change to this document can be requested by completing a Change Request Form - refer
to document DISTRIBUTION OPERATION and MAINTENANCE STRATEGY
GOVERNANCE (DOM-WN-GOV-00000001) for change request procedure.
Legal Notice
Copyright of this document is owned by Scottish Water. The document may not be copied or
reproduced in any way.
This document and the intellectual property rights in it belong to Scottish Water and except
where you are specifically licensed to use this document, you have no right to re-use
it. Disclosure of this document under freedom of information does not change the position on
(i) ownership and (ii) re-use.
Page 5 of 24
Aug 2016
DOM-WN-PRC-00000???
GF
Document
Section/
Reference
Number
Document /
Section Title
Version
Number
Date
Archived
Document /
Section
Page 5 of 24
Text Affected
Archived
Document / Section
Replaced By
Aug 2016