Basilan Lumber Co
Basilan Lumber Co
Basilan Lumber Co
FACTS:
1.
2.
3.
4.
The plaintiff Basilan Lumber Company entered into a contract with the defendant Cagayan Timber Export
Company, whereby the latter agreed to deliver to the former 1,200,000 board feet of exportable logs not
later than May 31, 1951. This contract is dated April 25, 1951. Subsequently, in an agreement dated July 3,
1951, the logs to be delivered were reduced to 500,000 board feet and the delivery thereof was to be made
not later than July 15, 1951. But in another agreement of August 22, 1951, the contract was again amended,
increasing the amount to be delivered to 740,000 board feet of logs to be delivered on or about September
1,1951. In this contract, it was further agreed that a minimum of 50,000 board feet per gang per hatch per
weather working day would be loaded.
The plaintiff sold the logs to a Japanese buyer, who had entered into a contract with the plaintiff through the
East Asiatic Company, which acted as intermediary. The logs were to be loaded on the "Kanatsu Maru"
which was chartered by the Japanese buyer and which arrived in the Philippines on September 9, 1951, at
the place agreed upon for loading. It stayed in port for a total of 8 days, but was able to load only 483,672
board feet supplied by defendant.
There were four hatches in the vessel, hence the loading was to have lasted two and a half days, more or
less. However, it actually took 7 days to load because no sufficient logs were available at the place where
the loading was to take place and because of the poor stevedoring service. Hence the demurrage amounted,
as per decision of the Court of First Instance, to $4,141.16. As to dead freight, which corresponds to the
freight of the logs which were not delivered shipside, the same amounted to $5,673.43. So, the total amount
of demurrage and dead freight is $9,814.59, or P19,629.18. This is the amount awarded in the Court of First
Instance. Legal interest on the said amount and attorney's fees amounting to P2,000 were also granted.
CA: reversed CFI decision. Because the damages in question are yet to be suffered and are not actual, they
may fall under the general category of prospective damages.
PETITIONERS CONTENTIONS: the demurrage and dead freight due the buyer in Japan had already been paid by the
East Asiatic Company, Ltd., through which the Basilan Lumber Company sold the logs. The receipts evidencing
such payment had been submitted as Exhibits "I-1", "J" and "K", in accordance with debit notes (Exhs. "G" and "H"
Deposition); in accordance with the decisions of United States courts, it is enough that there is proof or reasonable
certainty that substantial future damages will result in order that a recovery for damages can be had; that the
majority of the provisions of the Uniform Sales Law had been adopted in the Civil Code, so that the decisions of
American courts in the matter of damages should be applied; also invoked provisions in their contract In case of
non-compliance by the SELLER with the amended contract conditions, the SELLER hereby agrees to indemnify the
BUYER for whatever damages the BUYER would be held liable to their buyers in Japan as a Consequence thereof
SUPREME COURT:
1. NCC 2199 denies the grant of speculative damages, damages not actually proved to have existed and to have
been caused to the party claiming the same
2. In the case at bar the evidence shows that actual damage was caused to the agent through which petitioner
sold the logs to a Japanese buyer, as said agent had already paid the same to the latter. However, there is no
proof that respondent had already paid the agent said damages, or that it had already been required to pay
the same, and while these have not happened the damage to the petitioner may not, under the above-cited
article of the Civil Code, be deemed to have actually been caused to him.
3. As regards the express terms of the agreement holding the seller liable for the damages it may cause the
buyer, the same are merely declaratory of the obligation assumed, not an obligation which the obligee may
demand in compliance with upon breach of the terms of the contract and even before actual payment of
damages by the one who breached the agreement, because the obligee has not yet actually suffered the
damage or paid the same to the person to whom damage was caused. It is only when the obligee actually
suffers the damage, that compliance, with the obligation may be demanded.