Lesson 7 - CAPM - Prep - Cost Management - V2
Lesson 7 - CAPM - Prep - Cost Management - V2
CAPM & PMBOK are registered trademarks of the Project Management Institute, Inc.
Objectives
After completing this
lesson, you will be able
to:
Project cost management includes the processes involved in estimating, budgeting, and controlling costs so that
the project can be completed within the approved budget.
The project cost management plan is a subsidiary of the project management plan.
The techniques involved in estimating the cost of each project activity is similar to the ones used in estimating
project time.
Expert judgment, analogous estimating, bottom-up estimating, and reserve analysis are some of the techniques
used in cost management.
Control Account
In larger projects, costs are managed at a higher level rather than at an individual activity level. Under control account
technique, related activities are clubbed and their costs are managed as one unit.
Deliverable in WBS
The scope of a project is decomposed through a Work
Another
Deliverable in WBS
...
Control Account
Work
Package
Work
Package
Work
Package
Activity
Activity
Activity
Project charter
Enterprise environmental
factors
Organizational process
assets
Legend
Input
Output
Tools & Techniques
Planning Process
Expert judgment
Meetings
Analytical techniques
Estimate Costs
Estimate Costs is the process of developing an approximation of the monetary resources needed to complete project
activities.[2] It belongs to the Planning Process Group.
Project schedule
Human resource
management plan
Estimate Costs
Risk register
Enterprise environmental
factors
Project documents
updates
Basis of estimates
Organizational process
assets
Legend
Input
Output
Tools & Techniques
Planning Process
Expert judgment
Analogous estimating
Parametric estimating
Bottom-up estimating
Reserve analysis
Cost of quality
Project management
software
Three-point estimating
Determine Budget
Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to
establish an authorized cost baseline.[3] It is part of the Planning Process Group.
The cost baseline includes all authorized budgets, but excludes management reserves.
Control Costs
Control Costs is the process of monitoring the status of the project to update the project budget and manage changes
to the cost baseline.[4] It belongs to the Monitoring And Controlling Process Group.
Business scenario based questions on project cost control can be expected in the exam.
Exam Tips
11
Business scenario based questions on earned value management can be expected in the exam.
Exam Tips
12
Planned ValueExample
Q
A
13
If the planned value is $340, then the work planned is worth $340.
Earned value is the total of budget allocated to each of the activities that have been completed at that
point of time.
The resulting value is the earned value at that point of time.
Before the start of exam, please make a note of the formulas of earned value technique.
Exam Tips
14
15
Cynthia is a subject matter expert and Director of the Store Renovation Department. Because of her expertise and
experience in managing store remodels for the corporation, she and her team are the go to people for many
project managers. Donnell is the Project Manager for one of the stores in the southeast region. Because of the age
of the store, it has been classified as a Tier 1 Remodel, meaning it requires more work and a higher budget
allocation. Donnell has a budget of $850K to complete the entire schedule that has been defined for the project.
At the 30% mark of work completed on the project, Donnells team has spent $310K. What is a possible outcome
for Donnell?
Business ScenarioSolution
16
Donnell is concerned about the spending trend of his project being at .82, especially when they have not yet
made it to the halfway mark for the project. His previous Tier 1 remodels had a better CPI at this point in the
project. The project has faced some unexpected events, which the team had neither planed for nor
anticipated based on past performance. The Money allocated in the management reserve is able to cover
most of the expense, but not all. After evaluating the root cause of these risk factors, Donnell is able to link the
problems to the age of the store and the fact that none of the previous stores completed in the remodel
initiative are as old. The Project Sponsor is concerned about their ability to complete the project with the
remaining budget. Donnell is asked to re-assess the risk, collaborate with their structural engineer to
reevaluate the remaining activities so he can determine a revised budget and an estimate of what is needed to
complete remaining activities based on new information.
A software development project has four phases. Each phase takes a month to complete and is estimated
to cost $10,000 per phase. The phases are planned to be completed one after the other. Given the project
status at the end of three months, calculate the CV, SV, CPI, and SPI.
Project Phases
Month 1
Requirement Definition
S---------F
Month 2
Month 3
Month 4
S-------PF
---F
S----PF
Legend
S Start time
17
F Finish time
PF Partly finished
18
Term
Calculation
Value
$10,000+$10,000+$10,000
$30,000
$10,000+$10,000+$5,000
$25,000
$10,000+$12,000+$9,000
$31,000
$25,000-$31,000
-$6,000
$25,000-$30,000
-$5,000
$25,000/$31,000
0.80
Schedule Performance
Index (SPI)
$25,000/$30,000
0.83
19
Term
Formula
EV AC
EV PV
EV / AC
EV / PV
Key Terms
Given below are the key terms related to the cost concept:
Law of diminishing return
The more you put into something, the less you get out of it.
E.g., doubling the number of resources working on a project will not necessarily halve the time.
Working capital
The amount of money the company has to invest on the project and the day-to-day company operations.
Large assets purchased by the company lose value over time. The two forms of depreciation are straight line
depreciation and accelerated depreciation.
Straight line depreciation
The same amount of depreciation is provided for every year for the asset.
E.g., a car with a price tag of $10,000 and a useful life of 10 years, is depreciated by $1,000 every year.
Accelerated depreciation
Quiz
22
QUIZ
1
If earned value (EV) is $550, actual cost (AC) is $650, and planned value (PV) is $600, what is the cost
variance (CV)?
a.
-100
b. +50
23
c.
-50
d.
+100
QUIZ
1
If earned value (EV) is $550, actual cost (AC) is $650, and planned value (PV) is $600, what is the cost
variance (CV)?
a.
-100
b. +50
c.
-50
d.
+100
Answer: a.
Explanation: Apply the formula CV = EV AC to get the answer. Note that although PV is provided, it is not
used in solving this problem.
24
QUIZ
2
You, as a project manager, are in the process of midway review at the end of the first year of a $50K
project. The earned value analysis shows that the PV is $25K, the EV is $20K, and the AC is $15K. What
can be determined from these figures?
a.
25
c.
d.
QUIZ
2
You, as a project manager, are in the process of midway review at the end of the first year of a $50K
project. The earned value analysis shows that the PV is $25K, the EV is $20K, and the AC is $15K. What
can be determined from these figures?
a.
d.
Answer: d.
Explanation: SV = (EV-PV)=$20K-$25K= -$5K. CV = (EV-AC)=$20K-$15K = $5K. Looking at the data, it is
evident that the project is behind schedule and is also under budget.
26
QUIZ
3
a.
27
c.
d.
QUIZ
3
a.
d.
Answer: d.
Explanation: CPI = EV/AC, therefore if the CPI is 0.73, it means that the EV is less than the AC.
28
QUIZ
4
a.
29
c.
d.
QUIZ
4
a.
d.
Answer: c.
Explanation: Since the SPI (SPI = EV/PV) measures all project work, the critical path must also be analyzed
to determine whether the project will finish ahead or behind schedule.
30
QUIZ
5
As a project manager, when you present your initial cost estimate to the project sponsor for approval,
you are asked to cut the cost of the project by 10%. What would you do?
a.
Replace the originally planned resources with lesser skilled resources at lower rates.
31
c.
Strongly say no to the sponsor and walk away from the project.
d.
Ask all the team members to reduce the cost of their activities by 10%.
QUIZ
5
As a project manager, when you present your initial cost estimate to the project sponsor for approval,
you are asked to cut the cost of the project by 10%. What would you do?
a.
Replace the originally planned resources with lesser skilled resources at lower rates.
Strongly say no to the sponsor and walk away from the project.
d.
Ask all the team members to reduce the cost of their activities by 10%.
Answer: b.
Explanation: A project manager is responsible for managing cost overruns. If you have estimated it in a
certain way and its required to be reduced, you should determine the impact of any cost reduction actions.
Replacing the originally planned resources with lesser skilled resources is also an option, but the risks
associated with this action should be carefully investigated.
32
QUIZ
6
Which of the following is not a tool or technique used in the process of determine budget?
a.
Cost aggregation
b. Reserve analysis
33
c.
d.
Resource calendars
QUIZ
6
Which of the following is not a tool or technique used in the process of determine budget?
a.
Cost aggregation
b. Reserve analysis
c.
d.
Resource calendars
Answer: d.
Explanation: All the above tools and techniques are used for the determine budget process except resource
calendars, which is an input to this process.
34
Summary
Here is a quick recap of
what was covered in
this lesson:
Project cost management includes the processes involved in estimating, budgeting, and
controlling costs so that the project can be completed within the approved budget.
Cost management plan contains details on how to plan, manage and control the project
cost in relation to the cost baseline, and manage the cost variances.
Cost estimate is an educated guess of how much an activity or a project will cost.
Budget considers the cost estimate and accordingly sets aside funds for the completion
of the project.
Under control account technique, related activities are clubbed and their costs are
managed as one unit.
The four Project Cost Management processes are Plan Cost Management, Estimate
Earned Value Management technique indicates potential deviation of the project from
the cost and/or schedule baselines.
35
Thank You
CAPM & PMBOK are registered trademarks of the Project Management Institute, Inc.
36
References
[1] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) Fifth
Edition, Project Management Institute, Inc., 2013, Page 195.
[2] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) Fifth
Edition, Project Management Institute, Inc., 2013, Page 200.
[3] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) Fifth
Edition, Project Management Institute, Inc., 2013, Page 208.
[4] Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK Guide) Fifth
Edition, Project Management Institute, Inc., 2013, Page 215.
37