Schedule For Primavera

This document provides a breakdown of tasks, quantities, productivity rates, durations, manpower, and equipment required for the construction of a TNB substation. Key elements include: - Site clearance, piling works, substructure works including ground beams and slabs, superstructure works including columns and roof, architectural works such as brick walls and plastering, and infrastructure works including drainage, roads, and signage. - Quantities of materials needed for each task along with expected productivity rates and duration to complete tasks based on available manpower and equipment. - Tasks will require workers from various specializations like barbenders, carpenters, masons, painters, and drainage layers supported by equipment like
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
570 views4 pages

Schedule For Primavera

This document provides a breakdown of tasks, quantities, productivity rates, durations, manpower, and equipment required for the construction of a TNB substation. Key elements include: - Site clearance, piling works, substructure works including ground beams and slabs, superstructure works including columns and roof, architectural works such as brick walls and plastering, and infrastructure works including drainage, roads, and signage. - Quantities of materials needed for each task along with expected productivity rates and duration to complete tasks based on available manpower and equipment. - Tasks will require workers from various specializations like barbenders, carpenters, masons, painters, and drainage layers supported by equipment like
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

TNB SUBSTATION (PRIMAVERA)

ITEM

DESCRIPTION

PRELIMINARIES

1
2
3

Site clearance
Hoarding and signage
Temporary work

EARTH WORK

Cut to formation level (26 x 18 x 0.3)

PILING WORKS

1
2

Test pile (Dinamic test, PDA)


Piling (spun piles/ driven piles- 12m)

SUB- STRUCTURE

QUANTITY

PRODUCTIVITY RATES

DURATION (DAYS)

MANPOWER

MACHINES

600 m2
100 m
-

1200 m2/ day


80 m/ day
-

1 day
2 days
6 days

1 general worker
2 semi- skilled, 1GW
-

1 Backhoe, 1 bulldozer, 2@3 dumb truck


1 backhoe, 1 concrete mixer
-

140.4 m3

7 m3/ trip/ truck x 6 trip x 2 truck


=84 m3/ day

2 days + 1 day down time = 3 days

1 GW (flagman)

1 excavator, 2 dumb truck ( x boleh


backhoe sbb takut jumpa batu), 1
bulldozer.

1 nos
21 nos

6 nos/ day/ machine

6 days
4 days

1 piler, welder (untuk sambung), 1


GW

Lean concrete (26 x 18)

468 m2

26 x 18 x 0.05 = 23.4 m3
6m3/ trip/ truck x 2 truck x 2 trip = 24 m3/ day

1 day

1 gang = 4 men (1 poker vibrator, 2


levelling, 1 bucket) + 1 GW

Ground beam
a) Rebar

8200 kg

120-250 kg
180 kg/ man day/ 4 men
=720 kg/ day

12 days

b) Formwork

360 m2

6- 12 m2
8 m2/ man day x 4 men
=32 m2/ day

12 days

c) Concrete

42 m3

9 m3/ trip/ truck x 1 nos


6 m3/ trip/ truck x 1 nos
= 15 m3

3 days

1 piling rig, 1 welding set, & oxy cutter

1 mobile crane, 1 pocker vibrator

4 barbender, 1 GW
1 bar bending cutting machine

4 carpenter, 1 GW
1 cutting table

1 gang concretor = 4 men + 1 GW


1 mobile crane, 1 poker vibrator

Con 1
(1)

(4)

Con 2

Con 3

(8)

(12)

F/work
1

TNB SUBSTATION (PRIMAVERA)


3

Ground slab
BRC & concrete

SUPER STRUCTURE

Column @ 4.5 m (height)

Roof beam + slab

468 m2 x 0.250
=11.7 m3

8 nos

9 m3/ trip/ truck x 3 truck x 3 trip


=81 m3

2 days

*BRC
= 250 m2/ day x 2BRC layer

250 m2/ day x 2 BRC layer

1 gang BRC = 2 men

1 set f/ work @ 1.5 m


4 set f/ work @ 6 m

6 days + 2 extra days prep work


= 6 days

4 barbender, 2 skilled (f/work), 1


gang concretor, 2 GW

3 days concrete for every 4 work days


(hari ke- 4 baru concrete)
= 12 days

4 barbender, 6 carpenter, 1 gang


concretor + 3 GW (+ 1 GW for
carpenter)

60- 90 m2
= 8- m2/ gang/ day

6 days

1 gang = 3 @ 4 roofer (2 installer,


welder (if steel)/ carpenter (if
timber), leveler, 1 GW

1 mobile crane, 1 welding set (if steel)

80- 120 m2
= 100 m2/ gang/ day

5 days

1 gang = 3@ 4 roofer

1 mobile crane

468 m2 x 0.15
= 70.2 m3

1 gang concrete + 1 GW
1 poker, 1 mobile crane, 1 backhoe

1 poker, 1 mobile crane, 1


barbending cutting machine, 1
cutting table

L 26 ; W 18
- construction joint ( tak boleh
tempat yg ada loading)
- Kena lebihkan 1/3 @ kurangkan
1/3 utk concrete for roof

ROOFING WORK

Roof structure

Roof covering

468 m2

TNB SUBSTATION (PRIMAVERA)


G

ARCHIRECTURAL WORKS

Brickwall/ brick work

26 x 4.5 x 2(t&b)
18 x 4.5 x 2(l&r)
= 396 m2

6- 12 m2
8 m2/ man day x 6 men
=48 m2/ day

Door & window

1 door & 4
windows

2 doors & 4 windows/ 2 men/ day

Plastering

396 x 2
= 792 m2

8- 12 m2
12 m2/ man/ day x 6 men
= 72

Floor finishes

468 m2

8- 12 m2
12m2/ man/ day x 4 men
=48m2

10 days

Painting
a) Skim coat

1260 m2
40- 80 m2
40 m2/ man/ day x 4 men
= 160 m2

8 days

60- 120m2
80 m2/ man/ day x 4 men
= 320 m2

4 days

b) Finish coat

6)

Door & window

MECHANICAL & ELECTRICAL

Fire protection *

Air conditioning (ACMV) *

Cold water system

Electrical works *

Telecommunication works *

Alarm & CCTV *

Sanitary & plumbing + pipeline water


reticulation

LPG piping

BMS

1 door & 4
window

4 painters
1 sky lift
4 painters

2 doors & 4 windows/ 2 men/ day

TNB SUBSTATION (PRIMAVERA)


10

Rain water system


*yang diguna pakai for this project

INFRA / EXTERNAL WORKS

M & E external work

9 days

3 M & E workers

1 backhoe

Drainage works

12 m3/ 4 trip x 3 lorry

6 days

2 drain layer, 1 GW

1 backhoe

Road works
a) sub- base (aggregate + sand)

300 m3

140 m3/ team/ day

3 days

3 skilled, 2 unskilled

1 backhoe, 1 roller- compactor, 1 back


pusher, 1 vibro compactor

b) road base (crusher run)

700 m3

140 m3/ team/ day

7 days

3 skilled, 2 unskilled

1 backhoe, 1 roller- compactor, 1 back


pusher, 1 vibro compactor

c) binder coarse (ACBC)

120 m3

120 m3/ team/ day

1 day

3 skilled, 2 unskilled

1 paver machine, 1tandem- roller (sekali


dgn steam roller)

d) wearing coarse (ACWC)

120 m3

120 m3/ team/ day

1 day

3 skilled, 2 unskilled

1 paver machine, 1tandem- roller (sekali


dgn steam roller)

e) road kerb

100 m

80 m/ team/ day

2 days

2 skilled, 1 unskilled

1 kerb machine

f) road marking

400 m

300m/ team/ day

2 days

2 skilled, 1 unskilled

1 thermoplastic machine

g) road signage

4 nos

12 nos/ team/ day

1 day

2 semi- skilled

1 backhoe

1
2
3