Al Ain Stadium & Mixed Use Development Phase 1.1: Inspection & Test Plan For Installation of Telephone & Data System

This document outlines an inspection and test plan for the installation of telephone and data systems at Al Ain Stadium & Mixed Use Development Phase 1.1. It details 5 items to be inspected, including document approvals, material verification, installation, cleaning/protection, and document review. For each item, it specifies the acceptance criteria and roles of the main contractor (BAM International), subcontractor (ETA), and consultant in verifying and approving the inspections. Upon completion and sign-off of all inspections and non-conformance reports, the system will be handed over for use.

Uploaded by

midhun murali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
477 views7 pages

Al Ain Stadium & Mixed Use Development Phase 1.1: Inspection & Test Plan For Installation of Telephone & Data System

This document outlines an inspection and test plan for the installation of telephone and data systems at Al Ain Stadium & Mixed Use Development Phase 1.1. It details 5 items to be inspected, including document approvals, material verification, installation, cleaning/protection, and document review. For each item, it specifies the acceptance criteria and roles of the main contractor (BAM International), subcontractor (ETA), and consultant in verifying and approving the inspections. Upon completion and sign-off of all inspections and non-conformance reports, the system will be handed over for use.

Uploaded by

midhun murali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 7

ALAINSTADIUM&MIXEDUSEDEVELOPMENTPHASE1.

1of7+2
.

TITLE

INSPECTION&TESTPLANFOR

Ref.No.

: ITPMEP08

Rev.No.

: 0

INSTALLATIONOFTELEPHONE&DATASYSTEM Date

: 12.08.2012

ALAINSTADIUM&MIXEDUSEDEVELOPMENTPHASE1.1

INSPECTION&TESTPLANFOR
INSTALLATIONOFTELEPHONE&DATASYSTEM

ITPMEP08

ALAINSTADIUM&MIXEDUSEDEVELOPMENTPHASE1.1

2of7+2
.

TITLE

INSPECTION&TESTPLANFOR

Ref.No.

: ITPMEP08

Rev.No.

: 0

INSTALLATIONOFTELEPHONE&DATASYSTEM Date
MAINCONTRACTOR:
BAMINTERNATIONAL

SUBCONTRACTOR:
ETA

: 12.08.2012

ALAINSTADIUM&MIXEDUSEDEVELOPMENTPHASE1.1

3of7+2
.

TITLE

INSPECTION&TESTPLANFOR

Ref.No.

: ITPMEP08

Rev.No.

: 0

INSTALLATIONOFTELEPHONE&DATASYSTEM Date

: 12.08.2012

REVISIONRECORD

Thiscoverpageisarecordofallrevisionsofthedocumentidentifiedabovebynumberandtitle.Allpreviouscover
pagesareherebysupersededandaretobedestroyed.

Thecontractorhasthefullrighttomodify,amendorchangeMethodStatementandsupportingdocumentsasrequired
orasdeemednecessary.Allsuchdocumentswillbesubmittedtothe"Consultant's"forapproval.

Rev.
No.

Date

Prepd'By

00

12.08.12

AJEES

Chkd'By
BAMApproval DescriptionandPageNumbersofRevisions

ANA

MAINCONTRACTOR:

SUBCONTRACTOR:

ALAINSTADIUM&MIXEDUSEDEVELOPMENTPHASE1.1

4of7+2
.

TITLE

INSPECTION&TESTPLANFOR

Ref.No.

: ITPMEP08

Rev.No.

: 0

INSTALLATIONOFTELEPHONE&DATASYSTEM Date
BAMINTERNATIONAL

ETA

: 12.08.2012

INSPECTION TEST PLAN


AL AIN STADIUM & MIXED USE DEVELOPMENT PHASE 1.1

REF. No. : ITP-MEP-08


REV. No.: 0
DATE
: 12.08.12

INSPECTION & TEST PLAN FOR


INSTALLATION OF TELEPHONE & DATA SYSTEM
AREA

LEVEL

ITEM NO.
1

DESCRIPTION

SPECIFICATION / CRITERIA

Document Approvals
Material Approvals

Material submittals

Quality Documents

Method Statement ref. MS-MEP-08


Quality Control Procedure ref. QCP-MEP-08

INSPECTION & ACCEPTANCE


ETA
BAM
CON

Materials Verification

Approved material submittals

Inspection of Materials Received at site

Project Specification

Storage

Manufacturer's Recommendations &


Method Statement no.MS-MEP-08

Installation
Safety Clearance

Project Safety Plan

Installation

Project Specification
Method Statement ref. MS-MEP-08
Approved shop drawings

VERIFYING
DOCUMENT

Project Specification
Inspection for Installation of Telephone &
Data System

of the area
MEP-08

Approved shop drawings


Mehtod statement MS-

FM-MEP-08A

INSPECTION TEST PLAN


AL AIN STADIUM & MIXED USE DEVELOPMENT PHASE 1.1

REF. No. : ITP-MEP-08


REV. No.: 0
DATE
: 12.08.12

INSPECTION & TEST PLAN FOR


INSTALLATION OF TELEPHONE & DATA SYSTEM
AREA

LEVEL

ITEM NO.
4

DESCRIPTION

INSPECTION & ACCEPTANCE


ETA
BAM
CON

SPECIFICATION / CRITERIA

Cleaning Protection
Cleaning on completion of the activity

Method statement No. MS-MEP-08

Protection (if required) against possible

Method statement No. MS-MEP-08

damages till Commissioning/Handing-over


5

VERIFYING
DOCUMENT

Document Review
Site Inspection Reports

Signed & Approved

Test Certificates (if applicable)


Pressure Test Report (if applicable)
NCRs (if any)

Handed-over
Signed & Approved
All NCRs Closed & Signed off

H
H
H

R
R
R

R
R
R

LEGEND :

H - HOLD FOR INSPECTION

W - WITNESS INSPECTION

SUBCONTRACTOR :

ETA APPROVAL

BAM APPROVAL

CONSULTANT APPROVAL

NAME :

NAME

NAME :

SIGN

SIGN

SIGN

DATE

DATE

DATE