Oracle EAM Guide
Oracle EAM Guide
Login to oracle
Select SAGT_EAM_SUPER_USER
Select Asset Groups
If the name is not already exists, enter a description and set template to @Asset
Group and set serial generation to At receipt or you can use Predefined instead of
at receipt, and fill starting prefix and starting number.
Once you save an asset group, you can`t undo it, so double check when entering the data.
Save
Special Case
When adding a Virtual Asset number, fill the asset number and asset group with the
same name (Group has to be created prior to this operation) and leave the parent asset
number field Empty.
Adding an Activity
Apply Done.
Save
Select Organization Assignment tab and put a tick assigned field.
Save
Activity Association
Find the same activity as you entered before in the master activities and select it.
Select the corresponding asset group and asset number to the particular maintenance
plan.
Save
Now you can put work orders under the newly added maintenance plan.
Asset Hierarchy
Login to Oracle
Select Maintenance Super User
Go to Home Assets Simple Search
Enter the asset number, (Ex: Prime Movers) and Select it.
Change View mode to Hierarchy and click on GO.
Now you can view the asset hierarchy of the particular asset you, selected.
Routing
Login to Oracle.
Select SAGT_EAM_SUPER_USER
Go to Setup Routing Standard Operations
Click on NEW
Fill code, description, department, shutdown type
Do until all the maintenance steps are added.
Save and Close the form.
Go to Activities Maintenance Routing
Select the maintenance plan (plan had to be added prior to this operation, follow
Adding an activity + Activity Association).
Select the correct code numbers, as you entered before.
Save
Click on Routing Network
Click on the PLUG button, and make connections as necessary.
o i.e. draw arrows as the process happens
Now you can create work orders