Inspection & Test Plan For Cold-Hot Water (PPR) Pipe Work: 1 Material
Inspection & Test Plan For Cold-Hot Water (PPR) Pipe Work: 1 Material
PROJECT
CONSULTANT
MAIN CONTRACTOR
MEP CONTRACTOR
Document No.
ACTIVITY
ACTIVITY
DESCRIPTION
NO.
Material:
1
Pipes and accessories as per
1.1
approved material submittals
Drawings:
2
Approved drawings to be used.
2.1
3
3.1
3.2
Installation:
Ensure pipe routing are done
as per the drawing.
Ensure the pipe joints are properly
made and tight and secured.
3.3
4
4.1
Testing:
Hydrostatic Testing of water supply
CONTROL PROCEDURE/
SPECIFCATION
RESPONSIBLE
PARTY
Inspection:
Final Inspection of installation
VERIFYING
DOCUMENT
QA/QC
AEB
Approved Material
Submittal
QA Inspector
After Receiving
Material Inspection
Request
QA Inspector
During
Installation
Not Applicable
QA Inspector
During Installation
Inspection
Request
As per approved
Method Statement
Approved Shop Drawing
QA Inspector
During
Installation
During
Installation
Inspection
Request
Inspection
Request
As per specification
QA Inspector
After
Inspection
Request
Inspection
Request
QA Inspector
FREQUENCY
Installation
As per the drawing
of drainage pipes.
LEGEND: H- Hold Point (Notification Required, Presence Mandatory)
S - Survelliance
R - Review of Document
QA Inspector
After
Installation