Inspection & Test Plan For Cold-Hot Water (PPR) Pipe Work: 1 Material

This document outlines the inspection and test plan for cold-hot water pipe work. It details 5 activities: 1) ensuring approved materials are used, 2) using approved drawings, 3) proper installation according to drawings, 4) hydrostatic testing of water supply pipes, and 5) final inspection. Each activity lists specific tasks, responsible parties, verification documents, control procedures, and inspection frequency and acceptance criteria.

Uploaded by

rkss
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views1 page

Inspection & Test Plan For Cold-Hot Water (PPR) Pipe Work: 1 Material

This document outlines the inspection and test plan for cold-hot water pipe work. It details 5 activities: 1) ensuring approved materials are used, 2) using approved drawings, 3) proper installation according to drawings, 4) hydrostatic testing of water supply pipes, and 5) final inspection. Each activity lists specific tasks, responsible parties, verification documents, control procedures, and inspection frequency and acceptance criteria.

Uploaded by

rkss
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

INSPECTION & TEST PLAN FOR COLD-HOT WATER (PPR) PIPE WORK

PROJECT
CONSULTANT
MAIN CONTRACTOR
MEP CONTRACTOR
Document No.
ACTIVITY
ACTIVITY
DESCRIPTION
NO.
Material:
1
Pipes and accessories as per
1.1
approved material submittals
Drawings:
2
Approved drawings to be used.
2.1
3
3.1
3.2

Installation:
Ensure pipe routing are done
as per the drawing.
Ensure the pipe joints are properly
made and tight and secured.

3.3

Ensure that space between supports


are as per app. drawing.

4
4.1

Testing:
Hydrostatic Testing of water supply

CONTROL PROCEDURE/
SPECIFCATION

RESPONSIBLE
PARTY

Inspection:
Final Inspection of installation

VERIFYING
DOCUMENT

INSPECTION & ACCEPTANCE


IDC MEP

QA/QC

AEB

Approved Material
Submittal

QA Inspector

After Receiving

Material Inspection
Request

As per the Location

QA Inspector

During
Installation

Not Applicable

Approved Shop Drawing

QA Inspector

During Installation

Inspection
Request

As per approved
Method Statement
Approved Shop Drawing

QA Inspector

During
Installation
During
Installation

Inspection
Request

Inspection
Request

As per specification

QA Inspector

After

Inspection
Request

Inspection
Request

QA Inspector

pipe to ensure joint tightness


5
5.1

FREQUENCY

Installation
As per the drawing

of drainage pipes.
LEGEND: H- Hold Point (Notification Required, Presence Mandatory)
S - Survelliance
R - Review of Document

QA Inspector

After
Installation

W - Witness Point (Notification Required, Presence Not Required)


I - Inspection/Test