Checklist Earthing Lightning

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Project Logo

Project Name :
Project No. :

BURJ AL FARDAN OFFICE TOWER- LUSAIL COM 13


967-12( P-377)

Client

Form Ref. No. : IDC-EL-ICL-23.0

Proj. Manager/Consultants

Contractor

MEP Contractor

gr

INSTALLATION CHECKLIST - EARTHING & LIGHTNING PROTECTION SYSTEM (LPS)


Checklist Ref. No.:

IR Ref. No.:

Level/Area/Location :

Drawing Ref. No.:

Date of Inspection :

Specs. Ref. No. :

S/N

YES

Checklist Items

Materials used are as per the approved delivery inspection (MIR)

Check installation of air temination network which composed of but not


limited to the following: Air Terminal, Copper Tape, Down Conductor, etc.
is carried-out as per the approved shop drawing and methodology

Check air terminals and copper tapes are securely anchored and
clamped at proper intervals

Check tightness of bonding between the roof & down conductors and test
link

Check all exposed equipments and metal /steel works in the roof are
securely bonded to the air termination network

Check installation of earth temination network which composed of but not


limited to the following: Test Link, Earth Rod, Earth Pit, Main Earth Loop,
etc. is carried-out as per the approved shop drawing and methodology

Check test link location is in accessible position for isolation/


disconnection of the air termination network and enable testing of the
earth termination network

Check arth rods are driven in the approved location and are provided
with earth pit to allow access for bonding of main earth loop and LPS
earth lead to the earth rod

Check tightness of bonding between the earth rod, main earth loop, LPS
earth lead and test link

10

Check earth pit is provided with appropriate label, engraved "LPS Earth
Below"

11

Lightning Protection System installation is complete as per project


requirements and is ready for testing and commissioning

NO

Remarks / Comments

N/A

The above activities are found to be as per contract requirements and are ready for
release.

The above activities are correct and released for the next activity.

Checked by:
a. Site Electrical Engineer

Verified by (AEB Electrical Engineer):


b. Site QA/QC Engineer

Name/Signature

Name/Signature

Date

Date

Name / Signature
Date

Note: Checking and approval by AEB shall not relieve the Contractor from his obligation to perform the work in accordance with other contract documents and HSE requirements. This
inspection Checklist is a guide and shall be considered in the routine inspections BUT not limited to it.

Checklist for Installation of GI Conduit AccessoriesAEB - CSD Quality Forms

Form No.: CSD-CL-E-1.2

You might also like