Final Module
Final Module
Module for
Department of Hydraulics
&
Water Resources Engineering
Faculty of Technology
Department of Hydraulics& Water Resources Engineering
COURSE OUTLINE
Course Name : Hydropower Engineering I
Course Code : HE 3161
Prerequisite : HENG 2133
1. Introduction
1.1. Sources of Energy
1.2. Merits and Demerits of Hydropower
2. Development of Hydropower
2.1. Hydropower Status in the World
2.2. Hydropower potential & Status in Ethiopia
3. Estimation of Water Power Potential
3.1. Water Power Potential
3.2. Firm and Secondary Power
3.3. Load Prediction and Demand Assessment
4. Classification and Types of Hydropower Development
4.1. Classification and Basis
4.2. Site selection ,Layouts and Capacity Computation
4.3. Storage and Pondage
5. Water Conveyance Structures
5.1. Intakes, Canals and Tunnels
5.2. Water Hammer Analysis
5.3. Surge Tanks
5.4. Forebays
5.5. Penstocks
5.6. Anchors
6. Hydropower Machines
6.1. Classification
6.2. Impulse, Momentum and Power of a Turbine
6.3. Design Consideration for Hydraulic Machines
6.4. Types of Turbines
6.5. Draft Tubes, draft Heads
6.6. Dimensioning of Turbines
6.7. Generator and Governors
REFERENCES:
1.
2.
3.
4.
5.
Following are some of the points and conversions which are useful:
1 m = 100 cm = 1000 mm
1 ft = 12 in = 0.3048 m = 30.48 cm
1 in = 2.54 cm
1 yd = 3 ft = 0.9144 m
1 ft2 = 0.0929 m2
1 sq metre (1 m2) = 10, 000 cm2
1 litre = 1000 cm3 = 1 m3
Mass density = mass / volume
Weight density = weight / volume
Electrical Energy:
In SI the units of electrical energy are J, kJ and kilowatt hours kWh. In Imperial, the unit of
electrical energy is the kWh and 1 kWh = 3600 kJ
Force:
Vector quantity, a push or pull which changes the shape and/or motion of an object
In SI the unit of force is the newton, N, defined as a kg-m / s2 .
Weight:
The gravitational force of attraction between a mass, m, and the mass of the Earth
In SI weight can be calculated from. Weight = F = mg , where g = 9.81 m/s2
Work
Scalar quantity, equal to the (vector) product of a force and the displacement of an object. In
simple systems, where W is work, F force and s distance. W = F X S
In SI the unit of work is the joule, J, or kilojoule, kJ and 1 J = 1 N-m.
Energy
Energy is the ability to do work, the units are the same as for work; J, kJ, and ft-lb
Power
A scalar quantity, equal to the rate of doing work. In SI the unit is the Watt W, kilo Watt or
Horse Power (h p)
1W=1J / s and 746 W = 1 h p
i
CHAPTER - I
INTRODUCTION
1.1 Sources of Energy:
The following two major sources of power generation may be identified on the basis of present
day importance. They are Conventional sources and Unconventional sources
a) Conventional sources
i) Thermal power
ii) Hydropower
iii) Thermo-nuclear power
b) Unconventional sources
i) Tidal power
ii) Solar power
iii) Geothermal power
iv) Wind power
v) Wave power
vi) Depression (solar) power
1.2 Energy Physical Bases and Measuring Units
Derivation:
Energy can be described as potential for work, which may be withdrawn if needed. The
source for any kind of energy on earth is the sun. This is also valid for nuclear and fossil fuel when
taking into account the genesis of the earth.
Table 1.1: Energy and Related Terms
Physical Term
Force = mass x acceleration
Unit
kg
s
Newton
N m J oule
J
s J W.s
s
Joule
work / time
Power
force x velocity
kg.m m Joule
.
Watt
s
s2 s
With the definition of power, one can state whether a defined energy reserve is transformed
slowly or fast: If the transformation is fast ( for instance burning with open flame), the power is high;
in case of slow transformation ( for instance burning in living organism), the power is low despite an
equal energy credit.
Units:
As the different energy forms are convertible into each other, the energy can be measured in
the units of physical work. The previous heat units (such as calorie, British Thermal Unit, etc. ) do
not, in their definition, refer to the mechanical heat equivalent (detected through experiments by J.P
Joule, 1818- 1889).
Table 1.2: Energy Units and Conversions
Energy
Unit
Application
Joule
Metric SI-unit
Kilowatt-hour
Obsolete
1 PS = 736 W
Calorie
Coal equivalent
British thermal unit
Watt
Power
Conversion
1 J = 1 watt-second
= 1Newton meter (NM)
Horse power
(metric)
Horse power
(English)
1 cal = 4.1868 J
1 kg SKE = 29.3 x 106 J
1 Btu = 1 055 J
= 2. 93x10-4 kWh
1W 1
J
m
1 N
s
s
1 HP = 746 W
Prefix
kilo
mega
giga
tera
peta
exa
Factor by which
the unit is
multiplied
103
106
109
1012
1015
1018
CHAPTER - II
HYDROPOWER AND ITS DEVELOPMENT
2.1 Advantages and Disadvantage of Hydropower
Hydropower has the following advantages over other sources:
i. Hydropower has a 'perpetual' source of energy, while thermal power has a depletable fossil fuel
source. Besides hydropower doesn't consume the water.
ii. Running cost of hydropower plant is very low compared to thermal and nuclear plant.
iii. Hydropower plants can be brought in to operation in few minutes while thermal & nuclear power
plants lack this capability. Thus hydropower plants are particularly useful in taking up short period
peak loads in a power grid system.
iv. Efficiency of hydropower system is very high (90-95%), while thermal power plants have low
efficiency, as low as 40%.
v. Hydropower development also provides secondary benefit such as recreation, fishing, flood control
etc, where storage is contemplated.
Some of the disadvantages of hydropower development are:
i. It is capital intensive & therefore rate of return is low.
ii. The gestation period is long. This period is low for thermal power plants.
iii. Hydropower is dependent on natural flow of streams. Since this is very variable the dependable or
firm power is considerably low compared to total capacity.
2.2 Worldwide development
The status of hydropower with respect to the total power generation varies considerably from country to
country. Developing countries need affordable energy to:
Increase agricultural productivity;
Deliver basic educational and medical services;
Establish adequate water supply and sanitation facilities, and
Build and power new job-creating industries
Worldwide, only 15.2% of the technically possible hydroelectric energy was developed by 1990.
The following table gives hydroelectric generation in 1990.
Table 2.1: Hydroelectric Generation in 1990 (in TWh/year).
Continent
Africa
Asia
Australia/Oceania
Europe
North America
Latin America
USSR
World
(2) as % of (1)
3.7
9.2
18.7
57.8
59.1
10.9
7.6
15.2
According to UN estimates in 1981, the total world hydropower production will have risen to 80% by
year 2020. It seems that this target will not be achieved. Hydropower is the most important source
energy next to thermal power, and about one quarter of the world's power requirement is at present
derived in this way.
2.3
Basin
Potential Sites in MW
Category
<40 40>60 Total
60
Tech.
HP
(GWh/y
r)
%of
Tota
l
Plant
Commission
Year
Installe
d
(MW)
Aver.
(GWh
/yr)
Tis Abbay
Fincha
Tis Abbay
(new)
1953
1973
2000
11.5
100
73
68
617
450?
Sor2
Dembi1
Yadot1
1990
1991
5
0.71
0.35
43.83
2.8
1.2
Abbay
GhibeOmo
BaroAkobo
GenaleDawa
TekezeAngereb
WabiShebele
Awash
1
74
11
44
129
78 880
48.9
16
20
35 000
22.7
17
21
41
18 900
11.7
18
31
9 300
5.8
11
20
6 000
4.2
16
5 400
3.4
Melka
Wakena
1988
153
560
33
35
4 500
2.8
Abasamuel4
1970
15
1990
Data has been obtained from Solomon(1998), WAPCOS (1995), Fitjer (1990) and summarized together
Small hydropower stations operating as self contained system (SCS)
3
Note that in Solomon(1998), Fitjer (1990), reported annual production is beyond physically impossible magnitude
4
Currently not operational
2
Koka
Awash II
Awash III
Rift
Valley
Lakes
Danakil
Ogaden
Ayisha
Total
800
0.5
173
25
10
300
159,300
100
1960
1966
1971
43.2
32
32
110
165
165
456.8
1,748
CHAPTER - III
ESTIMATION OF WATER POWER POTENTIAL
3.1
P (Q H )
1
From the available stream flow data, one can obtain flow duration curve of the stream for a given site by
plotting the discharge against the percentage duration of the time for which it is available.
Similarly, power duration curve can be plotted since power is directly proportional to the discharge and
available head.
Average flow
December
January
Power (Kw)
Discharge Q (m 3/S)
100%
Percent of time for flows equaled or exceeded
Figure 3.2 Flow\Power duration curve (Power scale multiplying factor = 9.81 .H)
Potential power resources can be characterized by values according to the discharge taken as a basis of
computation. The conventional discharges are Q100, Q95, Q50, Qm. Thus we have,
i) Minimum potential power: designated Pp100, computed from the minimum flow that is available for
100% of the time (365 days or 8760 hrs.)
ii) Small potential power: computed from the flow available for 95% of the time.
This represented by Pp 95
iii) Median potential power: is computed from the flow available for 50% of time.
This is represented by Pp 50.
iv) Mean potential power: is computed from the average of mean yearly flows for a period of 10 to 30
years. This is designated as Ppm and is also known as gross power potential.
Load curve
Peak Load
Load (MW)
Average Load
Base Load
12
Time
18
24
Maximum demand of the power determines the size of the plant and its cost. Highest
instantaneous value of demand is, strictly speaking, the peak load or peak demand.
Generally, however, peak load is defined as that carried at intensity greater than 4/3 times the
average load intensity.
Base Load is the total load continuously exceeded, where as the average load is the area under the
curve divided by the time.
Load factor is the ratio of average load to the peak load and is expressed as a daily, weakly, monthly or
yearly value. The area under a load curve is energy (KWh) and it can be plotted to obtain energy
consumption curve. Thus the load factor can also be defined as:
Load Factor = energy consumed (say during 24 hrs)
(max. demand) * 24 hrs.
Max. load - determines plant capacity
Load factor - gives an idea of degree of utilization of capacity. Thus an annual load factor of say 0.4
indicates that the machines are producing only 40% of their yearly maximum production capacity.
Capacity factor: also called plant use factor or plant factor
Capacity factor =
e.g.- If a plant with capacity of 100 MW produces 6,000,000 KWh operating for 100 hrs, its capacity
factor will be
The capacity factor for hydroelectric plant is generally between 0.25 & 0.75.
If the peak load = plant capacity, then capacity factor = load factor.
If the plant is not used to its full capacity, then load factor capacity factor.
Thus in the above example if the max. load was 75 MW instead of 100 MW then
L.F. = 6,000,000 = 0.8 or 80% against 60% C.F.
75,000*100
Utilization factor =
Power utilized
Power available
For hydroelectric plants, this factor varies from 0.4 to 0.9 depending on plant capacity, load factor &
storage.
Load Duration Curve:
This is a curve of load vs percentage of time this load or higher occurs. It is usually plotted for
long duration such as a year.
Firm Power
0%
100%
Firm Power: Also called primary power is the power which always ensured to a consumer at any hour
of the day and is thus completely dependable power. Such a power corresponds to the minimum stream
flow and is available for all times.
Secondary Power
Primary Power
0%
Firm Power
(for run-off river plant)
100%
100%
Load (MW)
Day-time
12
Night-time
Time (hrs)
18
24
Base load power stations (coal, oil, nuclear and run-of-river scheme power stations);
Average load power stations (temporary, gas and reservoir power stations);
Peak load power stations (pumped storage and peak load hydro power stations).
Base load power stations having high utilization times, they produce electric energy on a very
economical basis. The energy prime costs of peak load power stations are higher due to shorter
utilization times; their emphasis lies on instant availability. These differences affect considerably the
price of base load and peak load power.
3.3.2
Load Prediction
For the installation of a new power plant or for the expansion of the existing power plant, it is
necessary to estimate the total amount of load that would be required to be met for various purposes.
The economics of the installation or expansion of a power plant calls for the correct prediction or
forecasting of the power demand.
Load forecasting may be done either for short-term (< 5 years), or medium-term (around 10 years), or
long-term (> 20 years) periods. The short-term forecasting is usually done for operation planning of
existing power plants, while the medium-term forecast is the basis for expansion program of power
generation facilities. The long-term forecast helps in the formulation of the countrys perspective plan
for power generation.
There are three basic load forecasting techniques:
Trend analysis
End-use analysis
Econometric analysis
Each of the forecasting methods uses a different approach to determine electricity demand during
a specific year in a particular place. Each forecasting method is distinctive in its handling of the four
basic forecast ingredients: the mathematical expressions of the relationship between power demand
and the factors which influence or affect it the functions; the factors which actually influence the
power demand (population, income, price, etc.) the independent variables; power demand itself
the dependent variables; and how much power demand changes in response to population, income,
price, etc., changes the elasticities.
Trend Analysis:
Trend analysis extends past growth rates of power demand into the future. It focuses on past
changes or movements in demand and uses them to predict future changes in the demand.
The advantage of trend analysis is that it is simple, quick and inexpensive to perform. It is
useful when there is no enough data to use more sophisticated methods or when time and funding do
not allow for a more elaborate approach.
The disadvantage of trend analysis is that it produces only one result future power demand.
It doesnt help analyze why power demand behaves the way it does, and it provides no means to
accurately measure how changes in energy prices or government policies, for instance, influence the
demand.
End-Use Analysis:
The basic idea of end-use analysis is that the demand for power depends on what it is used for
(the end-use). For instance, by studying historical data to find out how much power is used for
individual electrical appliances in homes, then multiplying that number by the projected number of
appliances in each home and multiplying again by the projected number of homes, an estimate of
how much power will be needed to run all household appliances in a geographical area during any
particular year in the future can be determined.
Using similar techniques for power used in business and industry, then adding up the totals
for residential, commercial, and industrial sectors, a total forecast of power demand can be derived.
The advantage of end-use analysis is that it identifies exactly where power goes and how
much is used for each purpose.
The disadvantage of the end-use analysis is that it assumes a constant relationship between
power and end-use, for example, power used per appliance. But, in actual case, energy saving
technology or energy prices will undoubtedly change with time, and the relationship will not remain
constant. End-use analysis also requires extensive data.
Econometric Analysis:
Econometric analysis uses economics, mathematics, and statistics to forecast power demand.
It is a combination of trend analysis and end-use analysis, but it does not make the trend analysts
assumption that future power demand can be projected based on past demand. Moreover, unlike enduse method, it can allow for variations in the relationship between power input and end-use.
Econometric analysis uses complex mathematical equations to show past relationships
between demand and the factors which influence the demand. For instance, an equation can show
how power demand in the past reacted to population growth, price changes, etc. For each influencing
factor, the equation can show whether the factor caused an increase or decrease in a power demand.
The equation is then tested and fine tuned to make sure that it is a reliable a representation as possible
of the past relationships. Once this is done, projected values of demand-influencing factors
(population, income, prices) are put in to the equation to make the forecast.
The advantage of econometric analysis is that it provides detailed information on future levels
of power demand, why future power demand increases or decreases, and how power demand is
affected by all the various factors. In addition, it is flexible and useful for analyzing load growth
under different scenarios.
The disadvantage of econometric forecasting is the assumption that the changes in the power
demand caused by changes in the factors influencing that demand remain the same in the forecast
period as in the past. However, this constant elasticity assumption is hard to justify in reality.
Note:
Load forecasts should be interpreted as rough indications of the reasonable range of possible
outcomes of power growth, rather than precise computations of future power consumption.
Often it is necessary to develop a range of load growth projections that reflect the uncertainty
associated with many of the factors that influence load growth. Then, the mid-range forecast will
be used as the basis for planning and the high and low growth scenarios will be utilized for
sensitivity studies.
Exercise problems:
Example 1:
Given: Q=50 m/s
H=5 m
tot=0.8
Solution
Power, P
P = . .Q.H
P = 0.8*(1000kg/m*9.81m/s)*50.0m/s*5m
= 1962 KW
= 1.962 MW
Work, A, for a yearly operation of 7000 hrs
A = P*t
A =1962 KW*7000h
= 13.7*106 KWh
= 13.7 GWh
Example 2:
Given: Two stations sharing a common load
- one is base load station
- the other is stand by station
Base load station characteristics:
Installed capacity = 25 MW
Yearly output = 125*106 KWh
= average demand
capacity of the station
average demand = 125*106 KWh
= 14269 KW
8760 h
:. capacity factor = 14269/2500 = 0.57 = 57%
Standby station
i) annual load factor = 10.5*106 / (15,000*2500) = 0.028 = 28%
ii) plant use factor = 15*103 / 30000 = 0.5 = 50%
iii) average demand = 10.5* 106 / 2500 = 4200 KW
capacity factor = 4200/30000 = 0.14 =14%
Example 3:
A run-off-river plant operates as a peak load plant with 20% weekly load factor, and all its capacity is
firm capacity. What will be the minimum flow in the river so that the station may serve as a base load
station given that:
Installed capacity of generator = 10,000 KW
Operating head = 15m
Plant efficiency = 80%
Estimate the daily load factor of the plant if the stream flow is 15m3/s.
Solution :
When the plant operates as a peak-load plant with 20% load factor, the total energy generated for one
week will be
10,000*0.20*7*24 = 33.6 * 104 KWh
If Q is min. flow necessary for plant to run as abase load, the power P developed will be.
P = 9.81 n Q H KW
= 9.81*Q*15*0.8
= 117.6 Q KW
Total generated per week = 117.6 Q * 7 * 24 = 1.98*104 * Q KWh.
:. Q = 33.6 * 104 = 16.97 m3/s min. flow in the river.
1.98 * 104
If the stream flow is 15m3/s, the power developed = 117.6 Q
Total generated in 24 hrs = 1764*24 = 42336 KWh
:. Daily load factor =
CHAPTER - IV
CLASSIFICATION AND TYPES OF HYDROPOWER DEVELOPMENT
4.1Classification and Basis
Hydropower plants could be classified on the basis of
Location & topographical features
Presence or absence of storage
The range of operating heads
The hydraulic features of the plant
Operating features etc.
A complete understanding of the type requires information under all such categories. All the
above classification basis are not mutually exclusive.
1) Classification based on hydraulic features:
The basic hydraulic principle governs the type.
i) Conventional Hydro-plants
Use normally available hydraulic energy of the flow of the river.
Run-of river plant, diversion plant, storage plant
ii) Pumped storage plants
Use the concept of recycling the same water.
Normally used with areas with a shortage of water
It generates energy for peak load, and at off-peak periods water is pumped back for future use.
A pumped storage plant is an economical addition to a system which increases the load factor of
other systems and also provides additional capacity to meet the peak load.
iii) Unconventional Hydro-plants
a) Tidal power plant
Use the tidal energy of the sea water.
Very few have been constructed due to structural complication.
b) Wave power plant
c) Depression power plant
Hydropower generated by diverting an ample source of water in the natural depression
Water level in the depression is controlled by evaporation
2) Classification on the basis of operation:
Based on actual operation in meeting the demand one can have:
isolated plant - operating independently (not common now a days)
interconnected in to grids
Thus in a grid system, a power station may be distinguished as a base load plant or peak load
plant. Hydropower plants are best suited as peak load plants, because hydropower plants can start
relatively quickly and can thus accept load quickly.
Load (MW)
Hydropower
Nuclear
Thermal
Time (months)
Figure 4.1: Place of hydropower in a power system.
Sometimes the power house is not immediately at the toe of the dam but at some distance ( eg. the
Koka power plant). This arrangement is more expensive (due to longer conveyance) and is used only
when it offers advantages such as extra head due to advantageous topographical conditions.
Important components of a valley dam plant
1.- The dam with its appurtenance structures like spillway, energy dissipation arrangements etc.
2.- The intake with racks, stop logs, gates & ancillaries
3.- The penstock conveying water to the turbine with inlet valve & anchorage.
4.- The main power house with its components.
CHAPTER - V
WATER CONVEYANCE STRUCTURES
5.1 Intakes and Head Race
5.1.1 Water Intake, Inlet Structures
The intake is a structure constructed at the entrance of a power canal or tunnel or pipe through
which the flow is diverted from the source such as a river or reservoir. It is an essential component of
hydropower schemes and provided as an integral part or in isolation from the diversion, weir or dam.
5.1.1.1 Functions of Intakes
The main function are:
i) To control flow of water in to the conveyance system. The control is achieved by a gate or a
valve.
ii) To provide smooth, easy and vortex or turbulence free entry of water in the conveyance system
which is to minimize head loss. This can be achieved through providing bell-mouth shaped
entrance.
iii) To prevent entry of coarse river born trash matter such as boulders, logs, tree branches etc.
Provision of trash racks at the entrance achieve this function.
iv) To exclude heavy sediment load of the river from interring the conveyance system. Special devices
such as silt traps and silt excluders are used to control & trap the silt.
5.1.1.2 Types of Intakes
Intakes are conveniently classified in to the following types depending on the power plant type and its
layout.
i) Run - of - river intakes
ii) Canal intakes
iii) Dam intakes
iv) Tower intakes
v) Shaft intakes
vi) Intakes of special type
i)Run - of - river intakes
The component parts are
bell mouth entrance guarded by R.C or still grid forming the trash rack structure.
Upstream of the gate may be provided with stop-log groves for provision of access to the gate for
repair.
the inlet invert level of the intake is raised to form a sill so as to prevent entry of rolling bed load.
A skimmer wall ( a diaphragm which extends below the water surface) abstracts the floating
material from interring in to the canal.
Vertical lift gate with motorized operation are used to control the flow.
A
Spiral flow
Ground/bottom flow
Movement of bedload
Surface flow
Section A-A
1. The effectiveness of the intake in preventing sediment entry increases with the sharpness of the
bend.
2. Intakes from straight reaches can be made favorable by artificially forcing the water to follow a
curved [path.
Weir
Bend
Canal
Gate
iii)
Dam intakes
iv)
Tower Intakes
v)
Shaft intakes
This is a vertical shaft that carries water to the penstock tunnel. It consists of the following.
The entrance structure with trash rack and rounded inlet.
The vertical shaft followed by an elbow and transition connecting the shaft with the tunnel.
The intake gate (cylindrical) and sometimes a stop-log closure.
It is therefore essential that the quantity of debris which enters the conveyance system of a
hydropower scheme be minimized. This can be achieved with the help of trash racks and skimmers.
i)
Trash Racks:
A trash rack intercepts the entire flow and removes any large debris, whether it is floating,
suspended, or swept along the bottom. Frequently, it is located in the intake structure to prevent debris
from entering the water conveyance system. It can also be placed just before the inlet to the penstock to
remove smaller debris as well as other trashes which may have entered the water conveyance system
downstream of the intake.
A trash rack is made up of one or more panels, each generally fabricated of a series of evenly
spaced parallel metal bars. The bars are parallel and evenly spaced because a rake is commonly used to
clear the debris off the rack. In this case, it is essential that the teeth of the rake mesh into the parallel
bars without binding so that the rake can be pulled along the bars easily to scrape off accumulated
debris.
Trash racks can be installed by sliding them into grooves in the concrete walls of the intake,
canal, or forebay structure. They should be removable and not permanently set in concrete.
Bars on a trash rack before the inlet to the penstock should be spaced no closer than is necessary
to remove debris which might be detrimental to the turbines operation. Otherwise, head losses may be
high and the rack may fill up quickly with debris. With a Pelton turbine, the space between bars usually
is not more than half the nozzle diameter (or a quarter, if spear valve is used) to prevent the nozzle
from choking. For Francis turbines, the space between bars should not exceed the distance between the
runner vanes.
The approach velocity of flow should be kept within such limits that it will not cause damage to
the rack structure. A design approach velocity of 0.5 m/s is usually used. If a trash rack is located
immediately in front of the inlet to a penstock and the penstock velocities are significantly higher than
0.5 m/s, the trash rack can be built in a circular area to increase the area of the trash rack and
correspondingly decreases velocity through it.
Cleaning of the trash racks can be performed either manually (for small schemes) using manual
rake or mechanically (for large schemes) using automatic cleaning machines. The trash rack is usually
placed vertical or near vertical (< 25o from the vertical). Placing the trash racks in an inclined position
makes the cleaning easy apart from giving less resistance to flow.
Clogging of racks is objectionable on account of the operational trouble and loss of energy
production involved, and of the unbalanced load created on the rack causing partial or total damage
thereof. Allowing for partial clogging, racks are generally designed to withstand a head ranging from 1
to 2 m under normal conditions and from 4 to 5 m under exceptional circumstances.
ii)
Skimmers:
A skimmer wall is an obstruction placed at the water surface, usually at an angle to the stream
flow which skims floating debris from the passing water. If the water level changes markedly as, for
example, at the intake of stream, the skimmer can be a floating piece of timber secured at both ends. If
changes in water level are small, a fixed skimmer can be used.
Because some debris usually passes under the skimmer, a trash rack is still necessary. However,
a skimmer reduces the frequency with which the trash rack has to be cleaned.
Skimmer walls are made, for the most part, of reinforced concrete with a service bridge on top.
They are designed usually for a horizontal pressure of 1000 kg/m 2 acting on the submerged surface.
Vf
V2
he
C
2g
2g
5.1
t
hr K t
b
4/3
Va
sin
2g
5.5
Where, Kt is trash rack loss coefficient (a function of bar shape), t is bar thickness, b is spacing
between bars, Va is approach velocity, and is angle of inclination of bars with the horizontal.
Figure 5.9:
Rack losses
Gate Losses:
Head loss due to gates (at part gate opening) is given by:
2
1 Q
5.6
h g
2 g C d A
Where, Q is flow in the canal or conduit, A is area of gate opening, and Cd is
discharge coefficient which varies between 0.62 and 0.83.
Ys
Control gate
Bulk head
Settling Basins
The water drawn from a river for power generation may carry a suspended sediment particles.
This silt load may be composed of hard abrasive materials such as quartz and will cause damage or
wear to the hydro-mechanical elements like turbine runners, valves, and penstocks. To remove this
material a structure called settling basin should be constructed, where the velocity of the flow will be
reduced resulting in settling out of the material, which has to be periodically or continuously flushed
out.
In order to satisfy the requirement for a good hydraulic performance the basin is divided into
three main zones: inlet zone, settling zone, and outlet zone.
Inlet Zone:
The main function of the inlet is to gradually decrease the turbulence and avoid all secondary
currents in the basin. This is achieved by decreasing the flow velocity through gradually increasing the
flow cross-section, i.e., by providing gradual expansion of the width and depth (see figure 5.12).
To achieve optimum hydraulic efficiency and effective use of the settling zone, the inlet needs
to distribute the flow uniformly over the cross-section of the basin. To achieve uniform flow
distribution, the following techniques, in addition to the provision of gradual expansion, may be
adopted at the inlet zone:
Use of baffles
L
A
Power canal
W
Flushing sluice
Settling zone
Inlet
zone
Outlet
zone
Power canal
Flushing flume
Section A-A
W
Collection tank
Flushing flume
a) For continuous flushing
Note: The cross-section of a settling basin is usually tapered at the bottom forming a sedimentcollecting flume, built with a gradient in the direction of flow.
Design of Settling Basins
The hydraulic design of settling basins is broadly outlined in the following:
1.
2.
On the basis of theory and practical experience, the necessary degree of removal should be
determined. Usually, the sensitivity of plant installations, particularly the hydraulic machines,
requires that a marginal (critical) grain size dcr is not exceeded. Generally, Francis and Pelton
turbines are subject to greater wear and tear ( form of blades, higher flow velocities) than Kaplan
turbines with comparably bigger discharges and lower heads. Consequently, the sand trap/settling
basin must be dimensioned in such a way that grains with diameters bigger or equal to d l (limit
particle size) must be settled. It should be noted, however, that no standard values or specifications
have yet been developed
For medium head = (15-50m);
For head up to 100m;
Very high head >100m;
For the limit particle sizes mentioned above, the lower limits should be used if the sediment
fractions contain sharp-edged quartzite grains.
% Sieve passing
100
Degree of removal
80
60
40
20
dl
0
0.001
0.01
0.1
1
10
Particle size (mm) (Log scale)
100
3.
Having determined the basic data as suggested in above, one can proceed to establish settling
velocity of the smallest fraction, i.e., of the limit particle size to be removed. This can be
established theoretically (Stoke's law) or by experiments (Sudry graph).
Figure 5.14. Settling velocity in stagnant water plotted against the density of silty water and
the particle diameter (After L.Sudry)
The so-called horizontal-flow settling system is usually applied at power developments. For
this system the dimensions of the settling basin may in principle be determined by two
computational methods depending on whether to neglect or to take into account the turbulence
effect.
Design neglecting the effect of turbulence (simple settling theory):
Here, the effect of turbulent flow upon settling velocity is neglected. Three basic relations may
be written for the determination of the required basin dimension.
Denoting the depth of the basin by D and its width by W, the discharge passing through the
basin is:
Q W DV
5.11
5.12
Finally, the length of the basin will be governed by the consideration that water particles
entering the basin and sediment particles conveyed by them with equal horizontal velocity should only
reach the end of the basin after a period longer than the settling time. Thus, even the smallest settling
particle may reach the bottom of the basin within the settling zone. In other words, the retention period
should not be shorter than the settling time. The required length of the basin is thus:
L V t
5.13
Eliminating t from the last two equations (equation 5.12 and 5.13), two relations can be
established between the six parameters governing the hydraulic design:
Q W DV
DV
L
(5 .14 )
Obviously a solution of the problem is not possible unless four of the six quantities are known.
The discharge Q is usually known. The settling velocity is defined by the initially specified
degree of removal and, as mentioned previously, can be established by calculation (see equation
5.19/20) or experimentally (Figure 5.14). The highest permissible flow-through velocity V should also
be specified, considering that particles once settled should not picked up again. According to Camp, the
critical flow-through velocity is estimated from:
V a dl
m / s
5.15
Where, d is the equivalent diameter of the smallest sediment particle to be settled in mm and a
is a constant given as:
a 0.36 ,
for d l 1 mm
a 0.44 ,
for 0.1 mm d l 1 mm
a 0.51,
for d l 0.1 mm
[Modern tendency is to use V =0.4 to 0.6 m/s]
Depth of basin should be specified considering that long and/or wide basins are economical
than deep ones. The depth of settling basins in waterpower projects is generally between 1.5 and 4 m
with flow-through velocities not higher than 0.5 m/s. Hence W and L can be computed.
Check
From
Q=DWV
V=Q/WD
And from
L=V*t
V=L/t
Therefore
Q/WD = L/t
Q*t
= WDL
Water conveyed to tank
= Volume of tank
(m / s)
5.16
( 5.17)
D
Accordingly, the second row of equation (5.14) can be modified for the settling length as:
DV
D 3 / 2V
1/ 2
( m)
V D 0.132 V
5.18
This shows a larger settling basin is required, when compared with simple settling theory. In the
computation if the result provides negative value in the denominator, it indicates that no settling takes
place in the basin; hence dimension should be modified.
Theoretically, the following equation can be used to estimate the settling velocity:
4 gd
3 Cd
s w
1/ 2
5.19
Where, d and s, respectively, are the diameter and specific weight of the sediment particle, w is
specific weight of water, and Cd is the coefficient of drag and is a function of particle Reynolds
number R = d/, being the kinematic viscosity of the water.
Figure 5.15: Drag coefficient of spheres as a function of particles Reynolds number (note =v)
The drag coefficient in the Stokes range (R < 0.1) is given by Cd = 24/R, and equation (5.19)
can be modified for Stokes range as:
gd 2
18
s w
5.20
Canal Lining
Power canals may be lined or unlined. The lined canals are usually lined with impervious
material such as concrete, masonry, or clay.
Canal lining might be carried out to:
Reduce seepage losses
Reduce canal surface roughness
Prevent the growth of weeds
Reduce damage caused by erosion, rodents, and livestock
Reduce the required volume of excavation
Permits the use of rectangular x-section
Concrete Lining:
This is the most extensively used material in power canal lining. It is mostly used with
trapezoidal cross sections. The excavation of a canal for a thin, unreinforced concrete lining is
similar to that of an earth canal. It should be done carefully to ensure that the lining conforms
closely to the desired profile when it is completed; otherwise, the lining will require more material
than expected. The foundation should be adequately compacted and moistened before the concrete is
placed. The necessity of moistening the foundation is to prevent the sub-grade from absorbing
moisture from the freshly laid concrete making it weak and porous.
Concrete sections of a lining can be hand-formed at the site. If the side slopes exceed 1 in 1,
form works may be necessary to hold the concrete in place until it sets. The thickness of the concrete
lining may range from 10 to 20 cm, depending on the quality of the concrete and the soil conditions.
In preparing concrete for lining a canal, it is important to use the minimum amount of water
needed for workability. Excess water will cause the concrete to slump and not stay on the canal side
slopes. A mixture of a 1:3:4.5 (cement : sand : gravel) volume proportion is adequate for lining a
power canal.
Brick or Stone Masonry:
This is another most frequently used type of power canal lining. Use of stone masonry permits
savings by reducing the quantity of cement required as compared to concrete lining. Masonry lining
consumes only about 25 30 % of the amount of cement required for poured concrete. Whether
brick or stone is used depends on their relative availability and cost.
With masonry linings, a rectangular canal section is often used. In this case, the sides of the
canals are constructed as retaining walls to counteract the lateral forces of either the earth backfill or
the water within the canal.
In the construction of a power canal lined with masonry, the excavation must allow for the
thickness of the lining. Before the lining is placed, the canal bottom and sides should be properly
compacted to avoid future settling and cracking of the lining. They should also be wetted slightly to
prevent the mortar from drying too fast.
To reduce resistance to flow and possible seepage, the masonry surface shall be plastered.
Note:
In addition to the commonly used lining materials discussed above, other materials such as
bituminous mixtures, soil-cement, wood, clay, chemical sealant, shotcrete, and impermeable
membranes are also sometimes used to line power canals
In special circumstances where the canal alignment is through a terrain having seasonally high
water table or where the soils are not freely draining, under-drainage should be provided in order
to protect the lining from damage due to uplift pressures.
Due to temperature variations and shrinkage, cracks may be developed in canal linings and may
result in appreciable leakage from the canal. In order to minimize these effects, it is necessary to
provide contraction joints in the lining at suitable intervals (usually 3 to 8 m).
Canal Design
Canal design involves determination of the following:
- Carrying capacity, velocity of water in the canal & roughness coefficient of the canal surface
- Canal slopes
- Cross-sectional profile of the canal
i)
Carrying Capacity and Velocity
For the hydraulic design, the discharge is computed from continuity equation as Q=V.A.
The mean velocity, V, is determined from any of the continuity equations. The roughness
coefficient is specified from the bed material type.
A
Chezy's equation
V C RS
Several equations are available to determine the value of C.
87
i)
Bazin's formula
Where m is roughness factor
C
m
1
R
1
ii)
Maning's Formula
Where n is Maning's roughness coefficient
C R1 / 6
n
1
The Chezy-Maning equation V R 2 / 3 S 1 / 2 MR 2 / 3 S 1 / 2 Use Tables for M & n.
n
0.00281 1.811
41.65
S
n
C
iii)
Kutter Formula
in English units
n
0.00281
1
41.65
S
R
iv)
The Agroskin formula C 17.72K log R
When using Maning's n,
- add 0.001 to the values of the Table if the water carries small amount of silt
- add 0.002 if the bed load is heavy
B) Forch-Heimer Formula
Some designers prefer this formula for V and given by:
V CR 0.7 S 0.5 ,
1
n
Apart from the hydraulic computations, the flow velocities in the canal or other water conduits
in general are determined according to economic point of views (investments, head losses, wear and
tear of material, danger of erosion and silting). The velocity must be high enough to prevent
sedimentation. It has to be low enough to prevent bed erosion for unlined- and wear by abrasion for
lined-canals.Lowering the velocity keeps the head loss over the length of the canal to a minimum;
however, it increases the cost necessary to construct the canal as the cross-sectional area increases
when the velocity lowers. Table 5.1 provides permissible velocity ranges.
Maximum velocity
Minimum velocity
Vmin (m/s)
Bed Material
Vmax (m/s)
Sand
0.4
Sandy loam
0.6
Loam
0.6
To keep any sediment
Clayey loam
0.8
from settling out, the
Clay
2.0
minimum velocity in a
Gravel
3.0
canal should not be less
Masonry
3.5
than 0. 3 m/s.
Asphalt
4.0
Concrete
5.0
Table 5.1 Permissible flow velocities in a canal
As stated above, in unlined canals flow velocities are limited by the resistance of the
bed material to erosion. In unlined canals flow velocities are limited by resistance against wear.
Maximum Velocities
Critical bottom velocity (w.r.t. erosion) is given by:
Vb 2d
Strenberg:
for d is particle size in meters, =4.43
Maximum permisible mean velocity according to Bogardi and Yen is given by:
V 22.9d m4 / 9 S s 1
Where dm is mean particle size and Ss is specific gravity of particles.
Minimum Velocities
There are various recommendations for non silting velocity
1) According to Ludin
If Vmin >0.3 m/sec, there will be no silting (for silty sediments)
Vmin >0.3 to 0.5 m/sec, there will be no silting (for sandy sediments)
2) According to R.C. Kennedy
Non-scouring and non silting velocity is given by: V Ch 0.64
Where h is depth of water in meters and C is coefficient varying from 0.54 to 0.7, depending on silt
load.
3) According to E.A: Zamarian, the requirements for silting or non-silting of unlined canal is given by:
V RSV
G0 700
0
Find the actual G (sediment load ) and compare it with G0. If G > G0 there will be deposition. If G <
G0, there will be no deposition. The formulae are valid for:
1) Canal free from aquatic growth
2) Q is between 0.2 and 150 m3/s
3) V > 0.3 m/s
4) < 10 mm/sec
1) According to M.M. Grishing, approximate Vmin is given by:
Vmin AQ 0.2
Where A is coefficient, which is f () and Q is design discharge.
< 1.5
1.5 - 3.5 >3.5
For (mm/sec)
A
0.33
0.44
0.55
Table 5.2: Coefficients of velocity
ii)
Roughness coefficient
As water flows in a canal, it losses energy in the process of sliding past the walls and bed
material. The rougher the material, the more frictional loss and the greater the head drop or slope
needed for a given velocity. The roughness coefficient, n, for various canal materials are given in Table
5.3 below.
iii)
C
(q in m/sec-km)
P3h
10,000
Where C = coefficient depending on soil type and lining (see Table 5.5 below)
P = wetted perimeter of canal in m
H = depth of water in m
q
Canal
Lined
Unlined
2) B.A. Etchivery gives specific seepage coefficient based on measurements on American irrigation
canals. Higher values apply for newly constructed channels.
Material
Slightly pervious loam
Loam of moderate permeability
Pervious loam or silt
Gravely or sandy loam
Loose sand
Gravely sand
Gravel
Coarse gravel
C
Q
100
q in m/sec-km
Values of C
3 .4
Q 0 .5
1 .9
Q 0 .4
0 .7
Q 0 .3
Exercises
1. Design a settling basin for high-head power station using the simple settling theory. The basin
should serve to remove particles greater than 0.5mm diameter from the water in which the
sediment is mainly sand. Let the design discharge be 5m/s and assume an initial value of 3.2m
for the basin depth. Take the water sediment mixture density to be =1.064
2. A power canal with a slope of 0.0001044 and R=1.76 m is unlined with coarse sand bed
material. Determine the safe velocity in the canal if the heaviest bed load in the original canal of
the course is G=0.34kg/m. The water carries silt with an average diameter of 0.08 mm. Assume
dm=2.00 mm as size of bed material and h=2.5m.
3. Determine the seepage loss from a power canal constructed in a sandy soil of medium fineness
by the Davis and Wilson, Etchevery and Kostyakov methods discussed. The following data are
given:
Trapezoidal canal:
5.1.3.2 Tunnels
5.1.3.2.1 General
Tunnels are underground conveyance structures constructed by special tunneling methods
without disturbing the natural surface of the ground. In many modern high head plants, tunnels form an
important engineering feature.
In the headrace of water conveyance sytem, tunneling is popular because of the following
reasons:
i) It provides a direct and short route for the water passage thus resulting in considerable saving in cost
ii) Tunneling work can be started simultaneously at many points thus leading to quicker completion
iii)Natural land scape is not disturbed
iv)Tunneling work has become easier with development techniques of drilling and blasting and new
mechanical equipment
v) Development of rock mechanics and experimental stress analysis has given greater confidence to
engineers regarding stability of tunnels.
Tunnels of hydropower projects fall into two categories: water carrying tunnels and service tunnels.
a) Water carrying tunnels : These include head race or power tunnels, tail race tunnels or diversion
tunnels. Flows in water tunnels are usually under pressure (pipe flow), but sometimes free-flow
(open channel flow) can be experienced, especially, in tailrace tunnels. The design of free-flow
tunnels follow the same principles as used in the design of open canals.
- Head race tunnels: are tunnels that convey water to the surge tank. These are pressure tunnels
- Tail race tunnels: could be free flowing or pressure tunnels depending on the relative position of
turbine setting and tail water level.
- Diversion tunnels: are constructed for the purpose of diverting the stream flow during construction
period. Normally they are not of high pressure but should have sufficient flood carrying capacity.
Such tunnels either plugged with concrete or converted in to some use such as spillway tunnel at
the completion of the project.
b) Service tunnels: These may be:
- Cable tunnels: to carry cables from underground power house to the switch yard
- Ventilation tunnels: fitted with fans at the open end to supply fresh air to the underground
- Access or approach tunnels: this is a passage tunnel from surface to underground power house.
5.1.2.2.2 Classification of Tunnels
In addition to the above classification tunnels may be classified on the basis of shape, alignment
and design aspects.
Shape: Tunnels are either circular or non-circular in shape.
Circular tunnels: are most suitable structurally. They are more stable when the internal
pressure is very high.
Non-circular tunnels: have a flat floor, nearly vertical or gently flaring walls and an arching
roofs. The horse-shoe shape is the most popular and convenient from the point of view of construction.
a) Circular shape
b) Horseshoe shape
C) D-shape
Low-pressure tunnels
(H < 10 m)
Medium pressure tunnels (10 m < H < 100 m)
High-pressure tunnels
(H > 100 m)
In the case of low-pressure tunnels the tunnel surface may frequently be left unlined except for visible
fissures. A watertight lining is usually required for tunnels operating under medium and high heads.
Seepage is more likely to occur as the head increases, water may leak through the smallest fissures and
cracks. Moreover, under high-pressure it may penetrate the otherwise watertight rock and render it
permeable.
H r hr
h
Using a factor of safety of , H r r m
Size of tunnels cannot be reduced arbitrarily. Requirements of passability limit the maximum size.
Minimum size of Tunnel: Circular, 1.8 m
Rectangular, 2m x 1.6m.
In the case of unlined tunnels, the entire internal water pressure is resisted by the overburden
rock pressure. Where a steep valley side constitutes the overburden above the tunnel, the rule of thumb
equation, H=(0.4 to 0.8)hr has to be modified and given by:
1 r
hw
L cos
w
Where L is the shortest distance between the ground surface and the studied point of the tunnel
(or shaft) and is the average inclination of the valley side with the horizontal (see figure below).
r L cos w h w
hw
hr
Figure 5.16
In the case of concrete or steel lined tunnels, the linings are usually designed to carry part or
full load of the internal water pressure, and the above equations, given for unlined tunnels, are modified
accordingly in determining the required overburden depth. For detail see section on stress analysis
Head Loss:
Head losses in tunnels can be computed using Mannings, Darcy-Weisbach, or Hazen-Williams
formulas.
lv 2
R4/3
2
Darcy-Weisbach formula: h f l v
2 g Deq
Manning formula:
hf n2
h f 6.84
l v 1.85
C 1.85 Deq
1.17
Where, hf is head loss due to friction, L is tunnel length, V is mean velocity of flow, R is
hydraulic radius, Deq is equivalent diameter ( Deq 4A / ), A is area of the tunnel x-section, n is
Mannings roughness coefficient, is Darcy-Weisbach friction factor (can be obtained from Moody
diagram), and C is Hazen-Williams roughness coefficient.
Optimum X-section:
The optimum x-section of a tunnel or a shaft is one for which the sum of tunnel construction cost and
the economic loss due to head loss is minimum.
Cost
Total cost
Economic
loss
Construction
cost
X-section
D 0.62 Q 0.48
D 1.12
5.1.3.2.4
1
Q 0.45
H 0.12
Lining deigned to resist the full internal pressure without support from the surrounding rock
i.e. no load sharing.
Internal water pressure, P = w H
If w = t/m3 & H in m
Then P = 0.1 H kg/cm2
For circular lining, if = lining thickness (cm)
D = the internal diameter (cm)
Then the maximum stress developed is the tangential stress
1m
P
D
Figure 5.18: Tunnel Section
PD
2
A st
PD
x 100
2 ast
P .D
2
ii) If no reinforcement, since the tensile stress in homogenous concrete is usually limited to 10 kg/cm,
PD
then
Where = thickness of concrete lining in cm.
10 kg / cm 2
2
II
r
r1
r2
st
b-c
This is a more realistic approach. Referring to the following schematic sketch
Figure 5.19: Schematic sketch of lining and displacement
P P1 D
D is internal diameter
st E st
E st
st
st
r
st
P P1 D
P P1 r 2
st
r
2
E st
r1
r2
r
P1
r1 l n 2
EC
r1
The radius of the cross-section excavated in rock expands under load P2 by an amount r
r
1 m 1
1 m 1
r2 P2
r1 P1
Er m
Er m
1
, where = Poisson ratio of the rock
Since
1 b 2 r st b c
1 2 r c st
1 2
r2 p p1 r 2
P1
1 m 1
r
p
r
l
.
1 1
1 n
Er m
Ec
r
E
1 st
E st
r1 E r m E st
EC
P r r
E r2 E st m 1
1 st
ln
E c r r1 E r r m
1
Checking purposes
This equation is useful for checking purposes for a given . For designing by trial & error, is assumed
& is computed.
Load carried by steel P-P1 = P P = ( 1-)P
Compute st 1 PD must be sta
2
E
r
E
m
E st
c
1
r
r
1
P E st
r2 E st m 1
ln
Ec
r1 E r m
then
1 Pr
E sta
varies from 0 to 1
If 1 no lining is required
If 0 entire load is carried by lining
Normal values : Est = 2.1 x 106 kg/cm2
Est
10
Ec
1 2
Drilling is carried out by the percussion method. The principle is to force a drill rod with a suitable drill
bit against the tunnel face, generate a stroke in order to obtain rock spalling, then rotate the rod before
it is once again forced against the hole and a new stroke is generated. The power for the drilling thrust
and rotation is transmitted by hydraulic systems.
In tunneling, blast hole diameters of 45 to 50 mm are most common. Medium size tunnels
(about 40 m2) may require about 60 to 70 drill holes. The length of the drill holes usually varies from 3
to 5 m.
Once the drilling operation is completed, charging of the drill holes with explosives will be
performed. There are different types of explosives, the most common one being dynamite.
If the holes close to the planned contour of the tunnel are too heavily loaded with explosives, a
considerable over-break and a rough, uneven contour may result. This over-break greatly increases
the need for scaling and tunnel support. If the tunnel is unlined, it will also greatly increase the head
loss. In order to minimize the over-break in the walls and roof of the tunnel, reduced charges are used
close to the contour.
In rock blasting the main principle is to break the rock and push the rock fragments towards a
free surface. In a tunnel the degree of confinement of the blast volume is far higher than in a quarry. In
order to obtain a satisfactory result from a tunnel blast it is, therefore, necessary to include the so-called
cut in the blast hole design. These consist of holes of larger diameter than the blast holes and are
usually left unloaded.
After blasting the round, ventilation has to be carried out to lower the concentration of blasting
fumes to a satisfactory level. The fans are usually started just after the explosion. It is very seldom
possible to enter the working face area until 15 minutes after the blast, but this depends on the
ventilation capacity.
After each blast round, scaling (removing loose rocks from the roof and walls of the tunnel) is
done for the sake of safety. For small tunnels the scaling is made directly from the muck pile, in larger
it is often carried out from the wheel loader.
The selection of equipment for mucking and hauling largely depend on the cross-sectional area
and the gradient of the tunnel. For tunnels with cross-sections smaller than 16 m2, the only alternative
for transportation is rail transport system. In larger tunnels, wheel transport system shall be used. For
wheel transport in cross-sections between 16 and 30 m2 niches are required every 100 to 150 m for
the purposes of loading and turning trucks.
A major restriction for the rail transport alternative is that the maximum gradient has to be less
than 2%. For wheel transport gradients up to 15% may be tolerated.
Use of Tunnel Boring Machines (TBM):
A tunnel boring machine (TBM) is a complex and very advanced piece of machinery designed
to excavate the entire cross-section in a single operation without the use of explosives. Tunnels with
diameters of about 1.8 m to more than 11 m have been excavated with tunnel boring machines.
TBM consists of a wheel cutter head fitted with teeth or rollers to cut or spall the rock. The
wheel is slightly smaller than the bore of the tunnel and is equipped with disc-cutters to produce the
designed bore. The wheel is forced against the tunnel face by hydraulic jacks and is made to rotate. As
excavation proceeds, the rock-cuttings are picked up in buckets attached around the rim of the wheel
and are discharged on to a conveyor belt incorporated with the machine as shown in Figure 5.20.
The diameter of the cutters is normally within the range of 45 to 50 cm, and the total number of
cutters varies from 20 for smallest machines to more than 70 for the largest.
For long tunnels (> 3 km) the excavation time and the costs in many cases are considerably lower
due to a higher advance rate combined with reduced requirement for tunnel support and ventilation.
The tunnel will have a circular profile with a smooth contour, which is of particular importance in
reducing head loss in unlined water tunnels.
Potential problems due to blast vibrations are eliminated, especially in populated areas.
Less number of adits is required.
There are, however, some limitations in connection with the use of TBM in tunneling. These include:
Initial cost of the machine is high
Requires detail geological investigation than the D & B alternative
Less flexible than Conventional D & B technique in tackling stability problems.
Tunnel Supports
A basic philosophy in tunneling is that the extent of installed tunnel support should reflect the
actual rock conditions. In good quality rock the self-supporting capacity of the rock mass should be
used to its advantage, and the amount of tunnel support kept at a minimum. In poor quality rock the
design of support should be based on a sound understanding of the character and extent of the stability
problem.
The various geological factors which may influence the stability are:
The degree of jointing and their character
Weakness zones and faults
Rock stresses
Groundwater inflow
Tunnel support may be installed either at the working face (immediate support), or behind the
face (permanent support). Whenever possible the design for the immediate support should be chosen
which makes it possible to act later as permanent support.
The following support methods are the most commonly used in hydropower tunneling today:
Rock bolting
Shotcreting
Grouting
Concrete lining
Rock Bolting:
A rock bolt is a steel bar, which is inserted into a hole drilled in a rock to improve the rock
competency. The distant end has a device which permits it to firmly anchored in the hole and the
projecting end is fitted with a plate which bears against the rock surface (see Figure 5.21). The bolt is
placed in tension between the anchor and the plate, thereby exerting a compressive force on the rock.
zones, there will be no room for expansion of the swelling clay, and high swelling pressure will be
activated when the zones are exposed to water. This may easily destroy the shotcrete lining.
Grouting:
A grout is a mixture of cement and water forced in to rocks around the tunnel periphery.
Grouting may be performed ahead of the tunneling face (pre-grouting) or behind the tunneling face
(post-grouting). Pre-grouting is necessary in areas where groundwater inflow makes tunnel driving
difficult (see Figure 5.23). Probe holes are drilled ahead of the tunnel face to perform permeability
testing before deciding the necessity of pre-grouting. Post-grouting is done to improve the stability of
the rock mass behind the tunnel face.
Hs=static head
p . A . A . L .
t
h w g L
t
L v
Note:- Instantaneous Closure large pressure rise !
hw
g t
Thus the total head @ the valve = Hs + hw
L v
= Hs
g t
Considering friction and local loss, the total head becomes
2
L v
L
v
Hs
k
D
2 g g t
L 0 v0 L v0
g t c
g tc
Now, Considering that the pressure wave is propagated from the valve to the reservoir with a
speed c, the time required for the pressure wave to travel from B to A is L/c. In this time, the mass
brought to rest is .A.L. thus:
hw
0 v0
p.A A L
t/c
p max c v 0
& hwmax
p max
c vo
g
g
The above is sufficient for estimating pressure rise for rapid value closure i.e. when t c 2 l , when
c
tc
use
2L
the reflected negative pressure reduces the pressure rise at the value. In such cases one can
c
p
2L 1
.
p max
c
tc
g dt
V
. x
g
t
p C VO
p
1.
Pipe distended
D2
1
p .
L
K
4
D3
V
. L . P
4 TE
where K p / V
Combining
Vtotal
1
D2 L
D
p
.
4
T .E
K
thus L V A
1
D
3
L L p
T . E
K
p c v0
_____ Allevi expression
1
c
D
1
k
K T .E
5
ii)
iii)
Figure 5.24:
It provides a free reservoir surface close to the discharge regulation mechanism. This will cut short
& limit the conduit length liable to water hammer.
- It supplies the additional water required by the turbine during load demand (and during starting up)
until the conduit velocity has accelerated to the final steady state level.
- It sores water during load rejection i.e closure until the conduit velocity has decelerated too the new
steady state condition.
- It ensures that the water level oscillation following small and large load changes are dissipated
rapidly.
5.2.2.3 Types of Surge Tanks
Surge tanks may be classified according to :
Material of construction, example. Concrete or steel
a)
Location relative to terrain
- underground surge tank (excavated surge tank, see Figure 5.25)
- over ground surge tank ( Free standing surge tank, see Figure 5.24)
Surge Tank
Pressure Tunnel
Power House
b)
Location in the hydraulic system
- Upstream surge tank (u/s to the power house ) on the headrace tunnel (see Figures
5.25 and 5-26).
- Downstream surge tank on the tailrace tunnel(see Figure 5-26).
c)
5.2.2.4
The hydraulic design of surge tank concerns with two main aspects.
a) Its height
b) Its cross-sectional area.
These aspects are decided up on with the view to fulfilling the following criteria:
The surge tank must be locates so that the positive & negative water hammer pressures are kept
within acceptable limits.
The tank must be stable i.e. water surface oscillation must be damped out
The tank must accommodate maximu upsurge & lowest down surge
5.2.2.5 Height
The total height of the surge tank should be such that both the maximum up-surge and downsurge is contained within the surge tank height. Worst conditions should be considered to determine the
height.
For up-surge, the worst conditions are:
- Instantaneous total closure
- Reservoir level at its maximum
For down-surge, the worst conditions are:
- Instantaneous total opening
- Reservoir level at its minimum
The lowest possible level of down surge must be sufficiently above the conduit top level by a
certain height h (see Figure 5.28) in order to avoid vortex formation at entrance to the
penstock/pressure shaft.
In general, the total height of the surge tank would be (see Figure 5.28):
Z1up
HRWL
Hlive
LRWL
Z0
Z1 down
Pressure tunnel
In order to determine the surge height and thus necessary tank height, etc., it is necessary to
carry out water hammer analysis and determine corresponding surge heights under various closure and
opening (load rejection and acceptance) conditions.
5.2.2.5.1 Surge analysis in surge tank (simple surge tank):
Closure
Surge Tank +z
z1
t
Reservoir
Zo
At, Qo
As
-z
Penstock or
Pressure shaft
L
Q1
Figure 5-29:
Continuity equation
V At A s
dz
Q1
dt
A V Q1
dz
t
1
dt
As
2 gd
If at time, t, the water level is higher than that at steady state, a deceleration head is being
applied to the pipe line.
2
i.e. L V z
2 gd
Denote FT L
2 gd
h FT V 2 z
L dv
g dt
L dv
. 2
g dt
1 & 2 could be combined to give 2nd order d.e. but not analytical solution.
5.2.2.5.2 Undamped Oscillation
If Q1 = 0 & friction is ignored, (Undamped oscillation, complete valve closure) equation (1) &
(2) become.
A
dz
t V 3
dt
AS
dv g
Z 4
dt
L
dv
dt
g
z 0 5
L
This is the deferential equation for a frictionless surge tank oscillation. The equation is a linear
homogenous 2nd order d.e. With constant coefficients undamped simple harmonic motion (SHM).
c.f. with SHM
d 2z
r 2Z 0
dt 2
Z C1 cos
where
2 t
2t
C 2 Sin
T
T
T = 2/r = 2
g At
.
L As
L AS
.
g At
dz
0.
dt
Thus, Z C 2 sin 2t
T
dz
2
2t
C2
cos
dt
T
T
Hence,
and
A
dz
V T
dt
AS
V = A s C 2 2 cos 2t
AT
When t = 0, V = Vo and Vo = As C 2 2
AT
Substituting for T,
C 2 VO
Z VO
L AT .
g AS
L AT
g AS
sin
2t
T
Z mzx
At any time, t
2t
T
2t
V VO cos
T
Z Z max sin
V0
L AT
g AS
5.2.2.5.3
Damped oscillation
No general solution of the d.e. can be given since the velocity changes its sign after every half cycle
Numerical Solution
Finite difference method of solution
Consider general case of surge tank with a available area. Take a finite interval t during
which V changes by V & Z change by Z
L V
Z m FT Vm / Vm / FS VS / VS 0 1
g t
Dynamic equation:
Continuity equation: Vm AT As ,m
Z
Qm 2
t
Zm Zi
Z
t
Subscripts i indicates values at the beginning of the time interval which are known.
Qm is known since the discharge is prescribed.
Substitute Z
in to (2) yielding Vm
If the two values of Vm agree V is correct. Otherwise adjust V & repeat until agreement is
achieved, then proceed to next time interval.
OR
Estimate
From (2) Z t Vi AT T
Qm 3
AS ,m
Where Vm Vi V
2
Zi
Vi AT T V Qm FT Vi
.
g t
2 As ,m
2
2
Fs
( AT2
As1
2
V 2
V
2
Vi Vi V
2 AT Vi
Qm Qm ) 0
4
2
Rearranging
F A Q
AT
FR
t FR Vi S T2 m
4
4 As , m
As
g t
V Z i
FR FS
F
AT
Q
V i t M t FR Vi 2 S2 Qm 2Vi AT Qm 0
2 AS ,m
ZAS ,m
As
AT
AS
FT
b 2 4ac
2a
& corresponding
Note that if V becomes negative, (i.e. on the down surge) the negative values of F R is used. As
with most F.D. methods, t should be small (because of use of average values in interval). A 10 second
time interval gives a sufficiently accurate solution.
c) Other solution methods
For sudden load rejection or demand by use of dimensionless parameters method developed by
calme & Gaden ( one of several ) can be followed. This method can be summarized as:
Maximum up surge:
Z max
where
for K
K2
2
1 K 0 0 .
3
Z
Z mzx .
K 0
0 .7
or
Z max
1 K 0 ;
3
max
where K o
2 gd
P0
Z mzx
1 0.6 K 0
coefficient in v)
Z max
Qo
AS r
gAt
L AS
1
7
1 K 0
3
Z max
1 0.125 K 0
5.2.6
for K
0 .8
Characteristic oscillation in the surge tank damped by hydraulic friction in the conduits.
1
Amplitude of oscillation
.
AS
Figure 5.30 Oscillation Characteristics Related to Cross-sectional Area
The required cross-sectional area of a surge tank is determined based on stability considerations
for the surge oscillations in the tank. Stability conditions of the surge system were established by
Thoma. He stated that in order to prevent the development of unstable oscillations the cross-section of
the surge tank should exceed a certain critical magnitude.
According to Thoma, the limiting x-sectional all for small oscillation is given by:
ASc
V02 At Lt
2 g Po H 0
where
Po = hf =Zo
1
m2 R4 3
m 1 n
10
ASC
m 2 R 4 3 At
m2 D 3
2g H o
160 H o
(stable tank)
L At
2 g H o
m 2 R 4 3 At
2g H 0
*
2
43
or AS m D = 170.482 Z max
160 H o
H0
L At
g AS
5.2.7 Forebays
5.2.7.1 General
A forebay, also called a head pond, is a basin located at the end of a power canal just before the
entrance to the penstock or pressure shaft. It acts as a transition section between the power canal and
the penstock. It is formed simply by widening the power canal at the end. Figure 5.31 shows typical
forebay.
Figure 5.31
5.2.7.2
Functions of a Forebay
A forebay serves the following purposes:
It can serve as a balancing reservoir. Water is temporarily stored in the forebay in the event of a
rejection of load (turbine closure) and the stored water will be withdrawn from it when the load is
increased (turbine opening). In the case of low-head power plants, the forebay may even provide daily
pondage for the plant. It can serve as a final settling basin where any water borne debris which either
passed through the intake or was swept in to the power canal can be removed before the water passes
into the turbine. In this case, the forebay must be large enough to reduce flow velocities sufficiently for
settling to occur and to accommodate the sediment which accumulates between cleanings. It can serve
to distribute evenly the water conveyed by the power canal among the penstocks, where two or more
penstocks are provided.
5.2.7.3 Components of a Forebay
The following are the main components of a forebay:
-
the basin
used to store water and sediment (if any)
the spillway
used to dispose excess water that might enter the forebay
The spillway is usually an ogee type with stilling basin. If the discharge to be taken care of is
great and if, at the same time, prevailing conditions do not permit the construction of a long overflow
weir, water surface regulation within narrow limits can be attained by constructing a siphon type
spillway.
The spillway and the bottom outlet canal should be combined immediately at the foot of the
basin. Water spilling over the spillway crest and through the bottom outlet can be either diverted into a
suitable river bed (if any) in a nearby side valley or conveyed by a special chute.
In designing a forebay tank, it is important to keep the entrance to the penstock fully
submerged. This is to prevent air being drawn in to the penstock because of a vortex which can be
formed if the penstock entrance is closer to the water surface in the basin.
The usual components of the intake such as trashracks, flow control devices (gates or valves),
etc. must be provided at the penstock inlet. It is necessary to install an air vent behind the gate to
prevent damage to the penstock if for some reason the penstock entrance is blocked or the gate is
suddenly closed causing a low pressure inside the conduit which can make it collapse inwards. The air
vent can also help remove air from inside the penstock during startup.
5.3
PENSTOCK
5.3.1 General
The penstock is high pressure pipeline between forebay ( surge tank or reservoirs ) and the
turbine. The design principle of penstocks are the same as that of pressure vessels & tanks but water
hammer effect has to be considered. For short length, a separate penstock for each turbine is preferable.
For a moderate heads & long distances a single penstock is used to find two or more turbines through a
special branching pipe called Manifold.
2. Method of support.
3. Number of penstocks
1) Material of construction
Factors for the choice of material are: head, topography & discharge. Various materials used are steel,
R.C., asbestos cement, PVC, wood stave pipes, banded steel, etc. The following factors have to be
considered when deciding which material to use for a particular project:
2) Method of support
A penstock may be either buried or embodied underground ( or inside dams) or exposed above
ground surface & supported on piers.
Buried penstocks: are supported on the soil in a trench at a depth of 1 to 1.5m and back filled.
The general topography of the land should be gentle sloping and of loose material.
Advantages
Disadvantages
1.Continuity of support given by the soil provides
1- Difficulty in inspection
better structural storability.
2. Pipe is protected from high temperature fluctuations 2- Possibility of sliding on step slopes
3. Conservation of natural land escape
3- Difficulty in maintenance
4. Protection from slides , storms & sabotage.
4- Expensive for loge diameter in rocky soils.
Exposed penstocks: supported on piers or saddles.
Advantages
Disadvantages
1- Ease in inspection of defects & maintenance
1- Direct exposure to weather effect
2- Economy in rocky terrain & large diameters. 2- Development of longitudinal stress due to support
and anchorage, thus requiring expansion joints
3- Stability is insured with proper anchorage
When the situation warrants, partly buried system, may be adopted which combines the advantages of
both system.
3. Rigidity of connection & Support
There are three possible methods of support ,
a) Rigid pipe support : Here every support is an anchorage so that any movement is checked.
completely. This type is suitable when the temperature audition is moderate.
b) Semi- rigid pipes: Here each member of the pipe line is fixed at one and leaving the possibility of
movement over the other support.
c) Flexible support ( Flexible or loose- coupled pipes): Here expansion joint are introduced between
each adjacent section
4. Number of Penstocks
The number of penstocks used at any particular installation can be single or multiple. The
general trend at older power stations was to use as many penstocks between the forebay/surge tank and
the powerhouse as the number of units installed. The recent trend is to use a single penstock, unless the
size or thickness of the penstock involves manufacturing difficulties.
When a single penstock feeds a number of turbines, special sections called manifolds are used
at the lower end of the penstock to direct flow to individual units. The design of such sections is an
intricate job and has to be analyzed carefully.
The advantages of using a single penstock over the use of multiple penstocks are:
The amount of material required to manufacture is less, making it economical.
The cost of civil engineering components such as penstock supports and anchors is less.
On the other hand, the use of a single penstock means reduced safety of operation and complete
shutdown will become necessary in case of repair. Further more, significant losses are usually
experienced at the manifolds.
In general, the use of multiple penstocks is preferably employed for low-head plants with short
penstocks; whereas for high-head plants requiring long penstocks, provision of a single penstock with
manifold at the end usually proves economical.
5.3.3 Hydraulics
Permissible velocities.
3 to 5 m/s ( no abrasion property settled water) for properly settled water in exceptional cases
up to 5m/s may be tolerated.
Therefore:
Q0
D 2
D 1.128
v0
4
Q0
v0
Head losses
2
i) Frictional head loss => h f L v
D 2g
v
2g
k
0.10 - 0.20
0.05 - 0.25
0.20 - 0.25
0.05 - 0.15
Net head:
H = Hg - losses where H = net head, Hg = gross head.
For Hg : elevation of water level at the forebay or reservoir at the upstream end, and at d/s end free
tail water level in reaction type turbines (Francis) or elevation of jet nozzle in case of impulse/action
turbine ( Pelton)
5.3.4 Economical Diameter of Penstock
The diameter of the penstock is determined from economic consideration and then checked to see that
acceptable velocities are not exceeded
Two approaches
- Graphical (economic analysis)
- Empirical equations
i) Graphical approach : D f (capital cost, running cost)
If D is small, large hf , reduction in output, loss in revenue. If D1 is large, small hf , greater output ,
larger initial cost .
T o ta l c o s t
C os
t
E c o n o m ic
lo s s
C o n stru c tio n
co st
D ia m e te r
0.62 P 0.43
H 0.65
2) USBR
v 0.125 2 gH
v Optimum velocity
3) Donalds formula
P
D 0.176
H
4) Fahlbusch (2982)
0.466
0.43
D 0.52 H 0.17 P
5.3.5
-
From previous
C
Em
Where
1
1
D
Em
K
TE
Cv o
h
g
h
C
tc
2L
,
C
C vo 2 L
2vo L
2L
tc
g C tc
g tc
The value of water hammer pressure rise as computed above may be taken at the turbine gate,
reducing to zero at intake or surge tank level. Values at intermediate location may be calculated
assuming a straight line variation
Thus, design head H = static head plus water hammer head.
For thin walled vessels, where D 20
t
pD
2t
PD
2
pD
2 a
For protection against coating deterioration add 1 to 3mm to the above value.
For thick welded piper where D 20 , the following formula giver sufficient accuracy
t
D a 0.07 H
t
1) (1 to 3)mm
2 a 0.13H
pr
The ASME gives the formula for thickness as
t
0.15
a 0 .6 P
Where
t in cm
p pressure in kg/cm2
r internal radius in cm
a design stress in kg/cm2
joint efficiency factor
0.15cm is allowance for corrosion
In case where the negative water column gradient falls below the penstock center line, there is
danger of collapse of the penstock due to external atmospheric pressure. The external pressure p e likely
to result in collapse may be computed from the formula by Mayer
pe
3 EI
24 EI
kg / cm 2
r3
D3
1
t
2
t D3
t3
12
m3
Pe
2E
4 1
0.01D
2 2 10 6
Flanged Joints:
Flanges are fitted to each end of individual pipes during manufacture, and each flange is then
bolted to the next during installation as shown in Figure 5.34.
A gasket or other packing material is necessary between Flange joints do not allow any flexibility. They
each flange of a pair. Flange jointed pipes are easy toare generally used to join steel pipes, and
install, but flanges can add to the cost of the pipe. occasionally ductile iron pipes.
Figure 5.34
Flanged joints
Figure 5.36
Mechanical joints
Welded Joints:
Welded joints are used on penstocks made of steel. Steel pipes are brought to the site in
standard lengths, and then welded together on site. One advantage of welding on site is that changes in
the direction of the pipe can be accommodated without preparation of a special bend section. It is
relatively cheap method, but has the drawback of needing skilled site personnel.
Expansion Joints:
A penstock, specially exposed ones, will change in length depending on temperature
fluctuations. If it is fixed the thermal expansion forces are substantial. It is possible to relieve these
forces by incorporating special joints called expansion joints, which allow the pipe to expand and
contract freely.
For short penstocks, provision of a single expansion joint may be sufficient, but for long
penstocks with a multiple anchor blocks expansion joints should be placed below each anchor block.
Another alternative to take care of thermal expansion is to take in to account the forces that result from
it in designing anchors.
5.3.7
Anchor Blocks:
An anchor block consists of a mass of reinforced concrete keyed to the penstock so that the
penstock cannot move in any way relative to the block. It is designed to withstand any load the
penstock may exert on it.
Anchors are often used at bends (horizontal and vertical) and before entrance to the powerhouse
(see Figure 5.32). They can also be used along long straight sections of penstock, each one next to
expansion joint.
Because an anchor is keyed to the penstock pipe and is also frequently located at a bend in the
pipe, more forces act on an anchor than on a slide block. The major forces which act on anchor blocks
are the following:
Thrust Blocks:
These are a special form of anchor whose sole
purpose is to transmit forces primarily caused
by hydrostatic pressures at horizontal bends
along a buried penstock to undisturbed soil
which provides the reaction force (see Figure
5.38) . However, if the bend is vertical, an
anchor block is still used if the back filled soil
is not able to resist this force.
Where, H and V, respectively, are the sum of all horizontal and vertical forces, and
is the coefficient of friction between the structure and the ground often assumed as 0.5.
The structure should be safe against overturning. For this condition to be fulfilled, the
resultant force should act within the middle third of the base. In other words,
e
Lbase
6
22
CHAPTER - VI
HYDRAULIC MACHINES
(Hydraulic turbines and their selection)
6.1 General
Hydraulic turbines may be considered as hydraulic motors or prime movers of a water power
development, which convert water energy (hydropower) in to mechanical energy ( shaft power). The
shaft power developed is used in running electricity generators directly coupled to the shaft of the
turbine, thus producing electrical power.
6.2Classification
All types of turbines basically fall in to two categories impulse and reaction turbines.
Impulse turbine:
All the available potential energy is converted in to kinetic energy with the help of contracting
nozzle/s. The water after impinging on the curved vanes or bucket is discharged freely to the
downstream channel (eg. Pelton wheel)
Reaction turbines:
In this type the water enters the turbine in a circumferential direction in to the scroll case and
moves into the runner through a series of guide vanes, called wicket gates. The available energy partly
converted to kinetic energy & substantial magnitude remains in the form of pressure energy (eg.
Francis, Kaplan, Propeller, Bulb, etc)
( modern Francis )
Axial flow turbine of fixed blade ( propeller ) or movable blade ( Kaplan or bulb ) type.
Furthermore, turbines may be classified based on head, discharge, speed, specific speed.
6.3
Characteristics of Turbines
Specific speed: is useful parameter for the selection of turbine for a given condition: It is defined as the
speed at which a geometrically similar runner would rotate if it were so proportioned that it would
develop 1 Kw when operating under a head of 1m , and expressed as ( from dimensional analysis )
P
Ns N
H
where Ns
N
P
H
= Specific speed
= rotational speed. (rpm)
= Power developed (kw)
= effective head (m)
Turbine or synchronous speed: Since turbine & generator are fixed, the rated speed of the turbine is
the same as synchronous speed of the generator. The speed N, for synchronous running is given by :
N 120 f
but in rad/sec;
Therefore, DN
60 2 gH
2N
60
DN
v
2 gH
2 gH
r=D/2
D and H in m; N in rpm
84.6 H
The following table suggests appropriate values of , which give the highest efficiencies for
any turbine, the head & specific speed ranges & the efficiencies of the three main types of turbine.
Type of rammer
Impulse
Francis
Popeller
0.43 0.48
0.6 0.9
1.4-2.0
Ns
8-17
17
17-30
40 130
130-350
350-452
380-600
600-902
H (m)
>250
25-450
<60
Efficiency (%)
85-90
90
90-82
90-94
94
94-93
94
94-85
Thus in general
Pelton turbines are used for high heads & low discharges
Francis types are used for medium & high head plants (has adjustable guide vanes but the runner is
a disc with fixed passage)
Propeller & Kaplan (Kaplan has adjustable blades) types are used for lows head plants with large
discharges.
suggested
3. Calculate D from:
DN
84.6 H
If D is found to be too large, either N can be increased or more units may be adopted. For
approximate calculations of runner diameter; the following empirical formula may be used (Mosony)
D
Q
a
M
D in m; Q in m3/s;
for propeller, H in m
7 .1 Q
N s 100 3 H
1
D 38
dj
N in rpm
D
m
dj
0.542
H
N
Q
H
It is not uncommon to use a member of multiple jet wheels mounted on the same shaft so as to
develop the required power.
Hydraulic turbines (runner) is designed for optimum speed & maximum efficiency at design
head. But in reality, head and load conditions change during operation & it is extremely important to
know the performance of the unit at other heads. This is furnished by manufacturers curve.
Figure 6.4: Variation of efficiency w.r.t. % of full load for various turbines
6.5
Runaway Speed
If the external load on the machine suddenly drops to zero (sudden rejection) and the governing
mechanism fails at the same time, the turbine will tend to race up to the maximum possible speed,
known as runaway speed. This limiting speed under no-load, maximum-flow must be considered for
safe design.
Type of runner
Runaway speed
( % of normal speed )
Impulse (Renton)
Fiancs
propeller
6.6
170 - 190
65
200 - 220
50
250 - 300
50
Runaway speed and acceptable head variations
Maximum
125
150
150
Figure 6.5:Recommended dimensions of scroll casings (a) full spiral b) partial spiral
This kind of spiral case will generally used in medium and high head installations where
discharge requirement is low. See Figure 6.4 a). Spiral cases with 320<<340 are also considered full.
The design of the shape of the spiral case is governed by the flow requirements. Initial
investigation should be based on the following assumptions:
a)
spiral case of constant height
b)
an evenly distributed flow in to the turbine
c)
no friction losses
k
vt
r
where
k 30
gH
N
( from the basic Euler equation for the power absorbed by the
dq vt h0 dr k ho dr
q r0 k ho
R
dr
Q
R
Q
or ln
r
2
ro
z k ho
This shows for given vortex strength, k, a definite relationship exist between Q & R.
The most economical design of a power station substructure and the narrowest spiral case can
be obtained by choosing a rectangular section adjoining the guide vanes (entrance ring) by step
transition ( symmetrical or asymmetrical ) as shown in b.
where cot 1 cot 2
h h0 (r r0 ) h
Q
r
r01 h
2 k
dr
r
r1 H
dr
r
Knowing r1 from
,
H h0
r1 0
r0
the value of R defining the shape of the spiral case can be determined.
The height H0 at any angle may be assumed to be linearly increasing from h0 at the nose towards the
entrance. Shape at various is determined by assuming existence of uniform velocity equal to entrance
Q i
velocity,
v0 0.2 2 gH and qi
q
q
Ai i 0.18 i
v0
H
6.7
Draft Tubes
A draft tube is a conduit discharging water from the turbine runner to the tailrace. It is employed in
conjunction with reaction type turbines, and has twofold purposes:
To recover as much as possible of the velocity energy of the water leaving the runner, which
otherwise would have gone to waste as an exit loss, thus increasing the dynamic draft head.
To utilize the vertical distance between the turbine exit and the tail-water level, called the static
draft head. In other words, to allow the turbine to be set at higher elevation without losing the
advantage of elevation difference.
The most common is elbow type which minimizes the depth of substructure compared to vertical one,
it also has a desirable effect in directing the flow in the direction of the tail water.
Ys
P1 v12 Pa v 22
HL
2g
2g
v2 v2
P1 Pa
Ys 1 2 H l
2
g
2
g
v12 v 22
H d d
2g 2g
P1 Pv
.( Saturated vapor
Ns
c
Franscis runners
75
150
225
0.02
0.10
0.23
300
0.40
375
0.64
Propeller runners
375
600
750
0.64
0.8
1.5
for Francis
N
c 0.28 0.0024 s
100
for propeller
for Francis
Yt Ys 0.025 D for propeller
where D is the nominal diameter of the runner.
1,5
3.5