Transient Stability
Transient Stability
Transient Stability
November 2015
1 / 38
Introduction
2 / 38
Introduction
3 / 38
Introduction
Kd : damping torque
4 / 38
Introduction
Transient (angle) stability deals with the ability of the system to keep
synchronism after being subject to a large disturbance
typical large disturbances:
short-circuit cleared by opening of circuit breakers
more complex sequences: backup protections, line autoreclosing, etc.
the nonlinear variation of the electromagnetic torque with the phase angle of
the machines internal e.m.f. must be taken into account
numerical integration of the differential-algebraic equations is used to assess
the system response
5 / 38
Introduction
Remarks
6 / 38
Introduction
7 / 38
3
4
V + jX 0 I = E0 = E 0
Assumption # 2 constant
dt
dt
N dt
d
2H pu
dt
= pu 1
= Pmpu Ppu
8 / 38
System reduction:
replace network, loads and infinite bus by a Thevenin equivalent
merge the machine reactance with the Thevenin impedances into Zeq
take the Thevenin emf as synchronous phase angle reference.
9 / 38
Yeq =
1
= Geq +j Beq = |Yeq | e j
Zeq
in practice: /2 0
Active power produced by the machine:
Geq E 0
|Yeq |Eeq
10 / 38
symbol
v
d
p
time interval
t<0
t [0 te ]
t > te
stable equilibrium
(vo , vo = 1)
(po , po = 1)
2H
and P() changes from one configuration to another.
N
Multiplying by :
M = [Pm P()]
Integrating from 0 to t:
1 2
M
2
[Pm P()] dt = C
[P(u) Pm ]du = C
v0
At t = 0 :
= 0
and
= v0 .
1 2
M +
2
At t = te :
Hence, C = 0 and
= e and = e . Hence
Z e
1 2
M e =
[Pd (u) Pm ]du
2
v0
(1)
14 / 38
Z
[Pd (u) Pm ]du +
p0
v0
p0
{z
Vp
Vk : kinetic energy
Vp : potential energy in final configuration with reference in p0
15 / 38
16 / 38
state space, is a
for small enough te values, the system trajectory in the (, )
closed curve along which:
t te :
17 / 38
Stability condition
System stable if (e , e ) belongs to the domain of attraction of (p0 , 0), i.e. if
1 2
M e +
2
pi
[Pd (u) Pm ] +
v0
Z
[Pp (u) Pm ]du <
p0
v0
pi
[Pm Pd (u)]du +
pi
pi
[Pm Pp (u)]du = 0
[Pm Pd (u)]du +
v0
19 / 38
20 / 38
Two-machine system
M2 2 = Pm2 P2 (1 2 )
M1 1 = Pm1 P1 (1 2 )
can be combined into:
Pm1
Pm2
1 2 =
M1
M2
P1 (1 2 ) P2 (1 2 )
M1
M2
(2)
Defining:
M12
Pm12
M1 M2
12 = 1 2
M1 + M2
Pm1 M2 Pm2 M1
P1 (12 ) M2 P2 (12 ) M1
P12 =
M1 + M2
M1 + M2
22 / 38
Exercise
Exercise
Revisit the 5-bus system
1
149
-22
225
3
EQU.
-295
39
data: lf1solv.dat or
lf2solv.dat,
solveroptions.dat, dyn.dat
225
3
149
-22
150
30
450
68
observables: obs.dat
disturbance: events.dst.
24 / 38
actions in generators:
(turbine) fast valving
generation shedding
E (0 ) = E (0 ) =
(V + X 0
Q 2
P
) + (X 0 )2
V
V
Line auto-reclosing
Line auto-reclosing
Fault clearing
Fault clearing
Fault clearing delay:
should be as short as possible
typical values : 5 cycles (0.1 s at 50 Hz)
stability must be checked with respect to scenarios where primary protection
fails clearing the fault (due to protection or breaker malfunction), which is
eliminated by the slower backup protection.
Single-phase tripping-reclosing:
most of the faults (' 75 %) are of the phase-ground type
for such faults, it is of interest to open the faulted phase only and keep the
other two in service protect each phase separately
in case of 3-phase fault with malfunction of one breaker, the other two
operate and the fault changes into phase-ground (less severe, cleared by
backup protection)
at EHV level, the three poles of the breaker are usually separate (for insulation
reasons); it does not cost much to add a separate control on each phase.
28 / 38
Speed of action
mechanical torque must be decreased rapidly: typically less than 0.5 s
gates of hydro turbines cannot be moved so quickly applies to steam
turbines
delays:
to take the decision from measurements (selectivity !)
to close the valves. They are closed much faster than in normal operating
conditions by emptying the servomotor of its oil.
Decision criterion
cannot rely on rotor speed only: due to inertia it takes time to reach an
emergency value
additional signal: rotor acceleration, drop of electrical power, difference
between electrical power and an image of mechanical power.
30 / 38
Implementation
Action:
on Control Valves (CV), normally controlled by Speed Governor (SG)
on Intercept Valves (IV): fully open in normal conditions, closed to cancel the
torque developed in Medium Pressure (MP) and Low Pressure (LP) bodies
31 / 38
Temporary valving:
Pm returns to its pre-disturbance value
typical sequence:
intercept valves are closed for a short time, then re-opened
control valves are left unchanged
Sustained valving:
Pm remains at a lower than pre-disturbance value
e.g. because post-disturbance network configuration expected to be too weak
even if it produces less, the generator remains synchronized with the network
typical sequence:
intercept valves are quickly closed
control valves are closed partially and at a lower speed
intercept valves are re-opened
control valves remain partially closed.
Valve re-opening:
after some delay due to servomotors
with a limited speed to avoid wearing the turbine, but this is not an issue if
stability has been preserved.
32 / 38
implement the fast valving, assuming that the intercept valve starts closing
0.10 s after the fault inception (time to take the decision)
check that the system is stabilized
determine the new critical clearing time
the initial delay on valve closing remains at 0.10 s
34 / 38
Available measurements:
accelerating power Pa (t) = Pm Pd (t) = P(0 ) Pd (t)
rotor speed (t)
Activation criterion:
if the system is stable without the protection scheme, the latter must not act
(no false alarm)
if the system is unstable without the protection scheme, the latter should
contribute to increasing the critical clearing time
if the clearing time is still larger than the critical value, the tripping of the
generator is accepted
fast valving is triggered when the system trajectory in the (Pa , ) space
crosses a curve c(Pa , ) = 0.
Determine a few points of that curve using the set of operating points provided
(P = 450, 420, . . . 270 MW 1 : see files p450.dat, p420.dat, . . . , p270.dat)
1 all
Generation shedding
Generation shedding
Principle
Trip one or several generators in order to preserve synchronous operation of the
remaining generators
applies mainly to hydro plants
those including multiple generators
combinations of 1, 2, 3, . . . generators can be dropped
usually applies to large power plants evacuating power through long corridors.
36 / 38
Generation shedding
Assumptions:
two identical machines oscillating in phase (coherent machines)
each machine: inertia M, transient reactance X 0 , mechanical power Pm
both machines = machine of inertia 2M, reactance X 0 /2, mech. power 2 Pm
Equal-area criterion:
area ABCD > area DEF system unstable
ABCD area = energy acquired by both machines at the time the fault is
cleared.
37 / 38
Generation shedding
The right figure relates to the remaining generator. Compared to the left figure:
the P() curve has lower magnitude, since the reactance between the emf
0
and the infinite bus is Xe + X 0 instead of Xe + X2
the mechanical power is Pm instead of 2Pm .
The system is stable if area GHK is larger than half of area ABCD .
38 / 38