0% found this document useful (0 votes)
618 views3 pages

Eichleay Formula Calculations

Eichleay Formula Calculations
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
618 views3 pages

Eichleay Formula Calculations

Eichleay Formula Calculations
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

11/8/2016

Eichleayformulacalculations

|Home|ConstructionClasses.com|

EichleayFormulaCalculations

19982006,ConstructionExperts,Inc.

Thispaperisintendedtobeafairlystraightforwardexplanationofhowto
performEichleayformulacalculations.Itisnotadefinitivetextoncalculationof
delaydamages.Therearenormallymanycomponentstoconsiderwhen
calculatingdelaydamagesandtheEichleayformuladealswithonlyoneofthese
components.

Checkoutouronline
classes!

TheEichealyFormulaiswidelyusedasamethodofcalculatinghomeoffice
overheaddamagesinconstructiondelaycases.Thiscomponentofdelay
damagesoftenaccountsforaverylargeportionoftheamountsclaimed.
Ifyouarecurrentlydealingwithacaseorclaiminvolvingconstructiondelays
youwillprobablyneedmoreinformationthanispresentedhere.Construction
delayclaimsareamongthemostcomplicatedclaimsandalmostalwaysrequire
theservicesofanexperttobothdeterminedamagesandtodefendagainstthem.
Informationpresentedinthisarticleiscategorizedintothefollowingspecific
sections.

Thebasicformula
Asamplecalculation
ProblemsassociatedwithusingandapplyingEichleay
TheBasicEichleayFormula
ThebasicEichleaycalculationnormallycomesattheendofaprojectwhenall
workhasbeencompleted.Inthatcase,thefollowing3stepcalculationisusedto
determinedamages.
1.AllocableOverhead.Thisisacalculationtodeterminetheportionofthehome
officeoverheadthatshouldbeallocatedtothisproject.Thisprojectisexpected
topayit'sfairshareofhomeofficeoverheadandthisisawayofcalculatingthat
amount.

2.Dailyallocableoverhead.Next,wewanttodetermineadailyrateforthe
allocationofhomeofficeoverhead.

Manymoreonline
classesareavailableat
www.ConstructionClasses.com

3.Homeofficeoverheaddamages.Thisissimplyamatterofmultiplyingthe
numberofcompensabledelaydaysbythedailyallocableoverheadrate.

http://www.constructionguy.com/litigation/eichleay.htm#basic

1/3

11/8/2016

Eichleayformulacalculations

Asamplebasiccalculation
Let'sassumethatwehaveacontractamountof$2,700,00.Thecontractorhas
sufferedcompensabledelaysamountingto45calendardays.Duringthisperiod,
thecontractorhas5projectsunderwaywhoseaggregatevalueis$10,000,000.
Thecontractor'shomeofficeoverheadduringthisperiodtotaled$250,000.The
durationofthisproject,includingdelays,totals265days.Oursamplecalculation
ofhomeofficeoverheaddamagesfollows:
1.Thisproject'sallocableoverhead

2.Dailyallocableoverhead.

3.Homeofficeoverheaddamages.Thisissimplyamatterofmultiplyingthe
numberofcompensabledelaydaysbythedailyallocableoverheadrate.

Thus,inthiscase,ourcontractor'sclaimis$11,462incompensationforhome
officeoverheadthatshouldhavebeenallocatedtothisjobbecauseofthe
increaseddurationoftheproject.
ProblemsAssociatedwithapplyingtheEichleayFormula
1.TheEichleayformulaisconsideredanestimateoranapproximationand
it'saccuracycanbequestioned.Evenso,theEichleayformulaisgenerally
consideredtobeareasonablebasisforestimatingtheamountof
unabsorbedhomeofficeoverheadresultingfromconstructiondelays.
2.ItisreasonablewhenquestioningthevalidityofEichleaycalculationsto
demandthatthecalculationsbebaseduponauditedfinancialstatementsto
determineactualhomeofficeoverheadcosts.Manysmallcontractorsmay
nothaveauditedinformationavailableandevenlargercontractorsmaynot
haveauditedinformationavailableimmediatelyuponthecompletionofa
project.
3.Anobjectiontotheinclusionofcertaincomponentsinthevalueofhome
officeoverheadmayarise.Forexample,onpublicworksprojectswhich
areobtainedthroughhardbidding,thecostofadvertisingand
entertainmentmaybedisallowed.
4.SomestatecourtsmaynotrecognizeEichleayasanacceptablemethodfor
calculatingdelaydamages.
5.ItcanbedifficulttoacceptEichleaycalculationsifthedelayoccurslatein
theproject.Asanextremeexample,ifthedelayoccurswhentheprojectis
99%complete,itcanbearguedthatallallocablehomeofficeoverhead
expensehasalreadybeenpaidtothecontractor.

http://www.constructionguy.com/litigation/eichleay.htm#basic

2/3

11/8/2016

Eichleayformulacalculations

|Home|ConstructionClasses.com|
Lastupdated03/27/2006