Prime Cost Sum
Prime Cost Sum
Prime Cost Sum
Adjustment of Prime cost and Provisional Sums on Building Project in Nigeria: Causes,
Effects and Solutions.
Ayodele Elijah Olusegun
Principal Lecturer Dept of Quantity Surveying Fufus Giwa Polytechnic Owo, Ondo State, Nigeria.
Abstract: This paper determined the causes and effects of adjustments of prime cost and provisional sums
on building projects in Nigeria. The study was carried out by means of questionnaire and interview
administered to Quantity Surveyors and Architects who have practiced in the south west of Nigeria for
at least ten years. The fifty-six completed questionnaire retrieved resulted into data, that formed the basis
of the study and were analyses by relative importance index. The result showed that adjustments to prime
cost and provisional sums were caused by : items not detailed before tender documents were prepared,
hurry in documentation, non-preparation of designs and bill of quantities . Also, the result showed that:
cost overruns, and time overruns are the negative effects of the adjustments of prime cost and provisional
sums. Positive effect is that the sub-contractor is fully paid for work done. For the negative effects to be
drastically reduced, there must be proper pre-tender planning, the clients and consultants not being in a
hurry in contract documentation. Well thought-out designs of all the items prepared, from which the bill
of quantities is prepared for all the items, before going to tender. Adjustments of Prime Cost and
Provisional Sum on Building Projects in Nigeria.
Key words:
INTRODUCTION
The Nigeria Institute of Quantity Surveyors[7]
Nigeria Institute of Quantity Surveyors[8] and JCT[4]
Ramans[10]; Seeley[11]; defined:
i. Prime cost sum as a sum provided for work or
services to be executed by a nominated subcontractor, a statutory authority or a public
undertaking or for materials or goods to be
obtained from a nominated supplier. Sum shall be
deemed to be exclusive of any profit required by
the general contractor and provision shall be made
for the addition thereof.
ii. Provisional sum as a sum provide for work or for
cost which cannot be entirely foreseen, defined or
detained at the time the tendering documents are
issued.
Background to the Study: The finding of Ayodele[2]
showed that the adjustment of prime cost and
provisional sums are some of the causes of cost and
time overruns in the construction industry. According
to Giwa[3], allowances made for prime cost in contract
bills, cause overruns in contract sum because the actual
costs are in most cases, higher. This according to
Ogunsemi[9] is because the Quantity Surveyor usually
allowed for arbitrary figures. In fact the amount
Corresponding Author:
Ayodele Elijah Olusegun, Principal Lecturer Dept of Quantity Surveying Fufus Giwa Polytechnic
Owo, Ondo State, Nigeria.
1212
Data Analysis:
Findings: From the table 1: effects of the adjustment
of prime cost and provisional sums are: Sub-contractor
fully paid for actually executed job, cost overrun and
time overrun.
From table 2, the causes of adjustment of prime
cost and provisional sums are: item not detailed before
tender, non-preparation of drawings, non-preparation of
bill of quantities, hurry contract documentation and
inadequacy of arbitrary bill cost.
Discussion: The positive effect of adjustment of prime
cost and provisional sums i.e. sub-contractor fully paid
for executed work, is in consonance with practiced
observation on construction site, and Ogunsemi[9]. One
of the negative effects, i.e. Cost overrun, is in
agreement with Akewusola[1] whose research work on
building industry indicated that adjustment of prime
cost and provisional sums between 1972-1978
contributed 23. 57% to cost overrun, and between
1979-1983 the adjustments contributed 58. 32% to cost
overrun. The other negative effect, i.e. time overrun is
in line with Ayodele[2] whose research work on
building executed by Nigerian tertiary institutions,
discovered that adjustment of prime cost and
provisional sums resulted in time overruns.
Two of the causes of adjustment of prime cost and
provisional sums, i.e. item(s) not detailed at inception
and inclusion of arbitrary cost figures in bill of
quantities are in consonance with Giwa[3] and
Ogunsemi[9] who opined that arbitrary cost figures are
included in bill of quantities for prime cost and
provisional items because the detail of the job is not
1213
2.
1214