What Matters for Successful
Integration of Distributed Generation
Thomas Ackermann
Energynautics GmbH, Germany
[email protected]Expert User of DIgSILENT PowerFactory for Power Systems Studies
Energynautics Areas of Expertise
Grid
Integration
Renewable
Energies
SUSTAINABLE DEVELOPMENT FOR POWER AND ENERGY
Decentralised
Power Plants
Energy
Markets
Agenda
1. Definition of Distributed Generation
2. Experience with Distributed Generation
3. Future Requirement: Coordinated Control
4. Additional Success Factors
Definition Distributed Generation*
the purpose of distributed generation is to provide a source of active
electric power
the location of distributed generation is defined as the installation and
operation of electric power generation units connected directly to the
distribution network or connected to the network on the customer site of
the meter
the rating of distributed generation of the DG power source is not
relevant
the power delivery area is not relevant
the technology used for DG is not relevant
the environmental impact of DG is not relevant
the mode of operation of distributed power generation is not relevant
the ownership of DG is not relevant
the penetration of distributed generation of DG is not relevant
*Source: Distributed Generation: A Definition, Ackermann et.al., Electric Power System Research, Vol.
57 (2001), pp. 195-204
4
Agenda
1. Definition of Distributed Generation
2. Experience with Distributed Generation
3. Future Requirement: Coordinated Control
4. Additional Success Factors
Examples of DG Penetration Levels:
> Germany PV (Total PV: 33 GW-min Demand in Germany: about 40 GW/max. 80 GW):
>
>
Approx. 65 % (21,5 GW) at LV level (230 V/400 V)
>
Approx. 35 % (11 GW) at MV level (11 60 kV)
>
Few plants (0,5 GW) at HV level (110 kV)
Germany Wind Power (Total Wind: 32 GW):
>
Mainly (95%) connected to MW level (11-60 kV), but changing due to repowering
>
Italy Wind+PV (Enel Distribuzion):
>
>
Approx. 20 GW at LV+ MV level
Spain Wind (Total: 20 GW):
>
Approx. 3% (0.6 GW) at MV level (11 45 kV)
>
Approx. 10% (2 GW) at MV level (66 kV)
>
Approx. 87% (17,4 GW) at HV level (110-400 kV)
Distribution of
Production Capacity in Denmark
Range of central control
Interconnections
400 kV
4 primary units:
1,488 MW
Interconnections
150 kV
5 primary units:
offshore wind:
1,914 MW
960 MW
Interconnections
60 kV
15 local CHP units:
10-20 kV
569 MW
545 local CHP units:
1,087 MW
4,074 wind power units: 2,214 MW
400 V
Non-dispatchable and beyond central control
Source: Energinet.dk
Typical Issues: Voltage Control
PV
Netzstation
MS-Netz
20 kV
0,4 kV
Substation
HAS 2
Leitung
Power Line
Trafo
Transformer
P
Q
HAS 1
Customer 1
Customer 2
P
P
UL1
1,1 p.u. = 253 V
Last 1
3~
PQ
Last 2
High feed-in, low load
Load 2
Load Like
1 above but with
PV
reactive power
1,0 p.u. = 230 V
Lnge
0,9 p.u. = 207 V
Max. load
Distance
Common & partly recommended concepts
Pffix
constant power factor
PF(P) power factor due to actual active power feed-in
Q(V) reactive power depending on actual grid voltage
8
Possible Voltage Control Solutions
Source: ABB
9
Cos - Regulation
Specification by BDEW, Germany
10
Additional Issues Identified by TSOs
Protection Coordination (bi-directional power flow) and protection relays
trip local generators after distant faults on the high-voltage transmission
grid (Solutions available);
Local grids cannot maintain normal n-1 security if local generation
exceeds local demand and if separation of generation and consumption is
insufficient (Rather small impact on system operation);
Traditional under-frequency load shedding schemes will disconnect both
load and generation (Important);
System operation and security analysis has become less accurate due to
missing information on local generation for system operator (Very
important and significant task);
Restoration after fault has become more complicated and more time
consuming (Important);
11
Agenda
1. Definition of Distributed Generation
2. Experience with Distributed Generation
3. Future Requirement: New Control Approach
4. Additional Success Factors
12
Example: The Cell Controller Concept in Denmark
The largest Smart Grid Project in Europe
Distributed on-line monitoring and control system
New Control architecture integrated into power system architecture
Efficient tool for automated DNO distribution grid management
VAR control
Voltage control
constraint management
Provides TSO services on request
reactive power import/export control (Virtual Power Plant)
emergency active power import/export (Virtual Power Plant)
Shifts to intentional island operation on trigger signal
Fully compatible with various market concepts
13
New Controll Architecture
for the Cell Concept
Agent
Agent
Agent
Level 4 (Dist. company B)
Level 5 (Energinet.dk)
Level 4 (Dist. company A)
Agent
Agent
Agent
Agent
14
Agent
Agent
Layered control hierarchy using
distributed agent technology and high
speed fiber network
Each agent consists either of an
industry CPU, a high-end RTU or an
intelligent meter
Level 3 (150/60 kV station)
Level 2 (60/10 kV stations)
Agent
Agent
Agent
Agent
Agent
Level 1 (Assets)
Agent
Agent
Agent
Level 0 (Units)
Cell test area is approx. 1000 km2 and
includes 28,000 customer meters
One 150/60 kV substation with tap changer controlled transformer
13 substations (60/10 kV) with tap changer controlled transformers
5 CHP plants with a total of 11 gas engine driven synchronous generators
totalling 33 MW
47 Danish-style wind turbines, all larger than 600 kW, with a total installed
capacity of 37 MW
One 0.8 MVA Synchronous Condenser for added voltage control
One 1.0 MW fast reacting Secondary Load Controller (i.e. dump load) for
added frequency control
All 60 kV lines and cables within the Cell area
69 load feeders (10 kV) with all loads and remaining smaller wind turbines.
15
Cell Controller Agents
mounting and site acceptance test
16
Input
150 kV
Output
150 kV
Cell
controller
60 kV
60 kV
10 kV
60 kV
60 kV
10 kV
10 kV
60 kV
60 kV
10 kV
60 kV
10 kV
60 kV
10 kV
17
Principal Controll Approach Pilot Project
18
Important Lessons Learned:
Software solutions can provide a lot of
new functions, but it needs a long time to
make the software very reliable.
19
Agenda
1. Definition of Distributed Generation
2. Experience with Distributed Generation
3. Future Requirement: Coordinated Control
4. Additional Success Factors
20
DSO Own Responsibility*
Assignment of the (full) responsibility for system stability to the
TSOs is not appropriate.
DSOs shall be responsible for stability of their own system and use
this as basis for defining technical requirements for all connected
units.
DSOs need to increase focus on all relevant aspects of local system aspects (system integrity)
DSO/TSOs should establish clear technical rules, role play and responsibilities in their common
interfaces
Example: DSOs apply formal requirements (U/Q) without properly understanding why needed
now (argument used: it may be needed in future e.g. dynamic voltage reference)
First step: Joint reflection on the issues by TSOs and DSOs
*Source: Success factors for high RES penetration at distribution level, by Eckard Quitmann (Enercon), Jens Fortmann (Repower),
Peter Christensen (Vestas), Bernard Ernst (SMA), Stephan Wachtel (GE), Frans Van Hulle (XP Wind), presented at: Renewable
Energy Integration Symposium, Mainz, June 2013
Grid Codes and Proof of Needs
Grid Codes are insufficient and imprecise.
Justification for any performance beyond
typical best practice is not given
They do not give clear guidelines for the performance needed from DG
and other connected users.
Codes, simulation models and verification methods are developed
independently in different circles
A homogenous industry practice is missing
First step: Further develop appropriate Grid Code
Requirements.
DG Capabilities
DG technologies are not fully ready to support the
distribution grid in an adequate way at high penetration
levels. Development and implementation of capabilities is
hindered both by manufacturers and network operators.
Some capabilities RES are well developed and poorly used
Reactive power
Some other issues there is room for improvement:
Fast primary reserve upwards and downwards
Further development of technology required + Incentives
Needed
Ancillary Services Provision
Providing ancillary services in distribution grids is currently not
economically viable for (RES) DG
Necessity of services at D-level? Considering that TSO requirements are pushed to
generators connected at D level
To what extent is VAR provision a service? Where do minimum capabilities end and
where do AS start?
How does AS provision fit in market based approach (unbundling)?
Which AS will exist in future grids?
Establish commercial framework to enable proper business
case for RES to provide ancillary services
Or: push for good technical best practices and then ask for
non-market based remuneration
Distribution grids upgrade/planning
should consider future DG levels
Is there a limit for DG? At the moment DG level in distribution
grid is often limited to x% of instantaneous load. Why?
Relevant aspects: controllability / stability / cost-effectiveness
Limitations arise because necessary control functionalities not yet
programmed in / how realistic is it to develop/implement the
relevant control changes?
Stability: Management possible with state-of-art DG!
EU wide (RES) DG targets often dont consider the needs for
additional control in distribution networks!
Investigate key reasons/physical obstacles for specific limit numbers
Design/test solutions - parallel solutions needed
Conclusion
Distributed Generation will play an important
role in the future power system, but a
rethinking of the overall control
architecture/integration approach is required
for high/very high penetration levels to be able
to capture all benefits of DG.
26
27
THANK YOU FOR YOUR INTEREST!
28