Engineering Procedures For ABC Waters Design Features PDF
Engineering Procedures For ABC Waters Design Features PDF
Engineering Procedures For ABC Waters Design Features PDF
Disclaimer
The materials contained in this publication are meant for general information only. PUB assumes no
responsibility or liability in relation to anyone using the information provided in the guidelines. If the user
wishes to use any material contained in this publication, the onus is on the user to determine the suitability
and appropriateness of such material for his own purpose.
Introduction
Chapter 1 Introduction
1
Table of Contents
1.1
Introduction
1.2
1.2.1
1.2.2
1.3
Overview on Water Sensitive Urban Design (WSUD) and ABC Waters Design
1.4
Stormwater Quality
1.4.1
1.4.2
Nutrients .............................................................................................................................. 7
1.4.3
Litter .................................................................................................................................... 7
1.4.4
Metals .................................................................................................................................. 7
1.5
1.6
References
9
10
Chapter 1 Introduction
1.1
Introduction
Flood protection
Page 1
Chapter 1 Introduction
Page 2
Chapter 1 Introduction
the deposition of suspended material, which can smother aquatic habitats, increased
concentrations of nutrients, oxygen-demanding materials, micro-organism and toxic
materials and the deposition of litter. Increase catchment runoff can lead to significant
changes to the morphology of creeks and rivers leading to degradation of aquatic
habitats. Stormwater contaminants causes dissolve oxygen depletion and increased
toxicity levels with the consequential degradation of ecological health of the receiving
waters.
Singapore is progressively moving towards attaining a higher level of self sustainability
in water resources. One of the strategies to achieve this is in the consideration of
urban stormwater as a resource. PUB had therefore embarked on a project which
would convert Marina Bay, located at the heart of Singapore City, into a freshwater
reservoir that harvests stormwater from one-sixth of the area of metropolitan
Singapore. Stormwater quality management and reducing potential impacts of
stormwater pollution are therefore important water resource management
considerations in Singapore. The management of urban stormwater to meet these
objectives can fundamentally be categorised into stormwater quantity and stormwater
quality management.
There have been a number of initiatives to change the traditional means by which
urban stormwater is managed. One such initiative is the practice of Water Sensitive
Urban Design (WSUD). WSUD reflects the new paradigm in the planning and design
of urban environments that is sensitive to the issues of water sustainability and
environmental protection. Water Sensitive Urban Design is the process and Water
Sensitive Cities are the outcome. This Australian innovation of Water Sensitive Urban
Design has evolved from its early association with stormwater management to provide
a broader framework for sustainable urban water management (Wong 2006a, 2006b),
and building water sensitive cities. In line with WSUD in terms of stormwater
management, PUBs ABC Waters Design Guidelines encourage the use of ABC
Waters Design Features to slow down rain water run-off and to keep Singapores
waterways and waterbodies clean.
Like WSUD, ABC Waters Design Guidelines bring sensitivity to water into urban
design, as it aims to ensure that water is given due prominence within the urban
design process through the integration of urban design with the various disciplines of
engineering and environmental sciences associated with the provision of water
services including the protection of aquatic environments in urban areas. Community
values and aspirations of urban places necessarily govern urban design decisions and
therefore water management practices.
The practicalities of urban stormwater management often require that stormwater
quantity management issues such as flood protection, public safety and drainage
infrastructure economics are addressed. This should occur in the first instance before
stormwater quality issues are considered. This does not suggest that these two
fundamental issues are mutually exclusive. Many measures designed for stormwater
quantity control have inherent water quality management functions while others can be
retrofitted to serve the dual functions of stormwater quantity and quality management.
The guidelines for the planning and design of these stormwater quality management
systems (termed ABC Waters Design Guidelines) are to aid the developer, design
engineer or planner to meet urban stormwater management objectives. Stormwater
quality management involves the use of structural and non-structural changes to
catchment management. This document concentrates primarily on the implementation
of structural treatment measures although issues of catchment planning are discussed
in some detail in Chapter 3.
Page 3
Chapter 1 Introduction
1.3
WSUD can be best explained as the interactions between the urban built form
(including urban landscapes) and the urban water cycle as defined by the three urban
water streams of potable water, wastewater, and stormwater. This is shown in Figure
1.1, which shows how WSUD fits into an Ecologically Sustainable Development
framework and lists key WSUD initiatives to address potable water, wastewater and
stormwater issues, whereby benefits from one element can often have flow on
benefits. For example, demand management will reduce the amount of potable mains
water consumed by a household, as well as reducing the amount wastewater
generated, and thereby the wastewater treatment needed.
The guiding principles of WSUD are centered on achieving integrated water cycle
management solutions for new urban release areas and urban renewal developments
aimed at:
i)
ii)
iii) Treating urban stormwater to meet water quality objectives for reuse and/or
discharge to receiving waters.
iv) Using stormwater in the urban landscape to maximise the visual and
recreational amenity of developments.
A key principles espoused by the framework presented in Figure 1.1 is a holistic
approach to urban water cycle management that include all water flows, such as water
supply, stormwater and wastewater. Singapore has covered good mileage in area (i)
and (ii) through the Water Efficiency Strategies and NEWater initiatives. PUBs ABC
Waters Design Guidelines aim to achieve (iii) and (iv). All streams of water should be
managed as a resource as they have quantitative and qualitative impacts on land,
water and biodiversity, and the communitys aesthetic and recreational enjoyment of
waterways. This applies at all level of urban water governance, ie. community,
institutional and government.
Stormwater is to be managed both as a resource and for protection of the
environmental and use values of receiving waters. When applied to the design and
operation of urban developments, ABC Waters Design strategy adopts an integrated
approach of combining stormwater quantity and quality management measures across
the range of scale in an urban environment. The outcome is a more site-responsive
range of design solutions including detention and/or retention of stormwater at, or
near, its origin, with subsequent slow release to groundwater or downstream receiving
bodies.
This integrated approach has begun to gain favour over the traditional conveyanceoriented approach because it has the potential to reduce development costs and
minimise pollution and water balance problems by ensuring hydrological regimes are
changed minimally from pre-development conditions. However, the adoption of the
integrated approach has been constrained because it is perceived to have postdevelopment operation and maintenance costs, and in some cases can cause a
reduction in developable land.
Page 4
Chapter 1 Introduction
This reduction in developable land may be the case if detention/retention facilities are
used solely to control the amount of stormwater runoff. Detention/retention facilities
however, have increasingly been used in a multi-purpose role, providing recreational
and aesthetic value, thereby offsetting any loss in developable land by increasing land
value for nearby residential areas.
Furthermore, the integrated approach aims to control pollutants such as nutrients,
pesticides, heavy metals and bacteria. Diffuse source pollution control can be
achieved by detention/retention techniques that settle and capture particulates and
prevent erosion by maintaining the hydrological regime.
Potable Water
Wastewater
Stormwater
Wastewater
minimisation
Stormwater
management
Demand
management
Demand
management
Rain/stormwater
reuse
Rain/stormwater
reuse
Rain/stormwater
reuse
Stormwater quality
improvement
Water reuse
Water reuse
Stormwater quantity
management
Greywater
Greywater
Reclaimed
Reclaimed
Groundwater use
Infiltration inflow
reduction to protect
groundwater
Protect groundwater
quality
Page 5
Chapter 1 Introduction
1.4
Stormwater Quality
Solids
Nutrients
Fertilisers
Human Waste
Animal Waste
Vehicle Fuels and Fluids
Pathogens
DO
Demands
Metals
Vehicle Wear
Industrial and Household
Chemicals
Industrial Processes
Synthetic
Organics
Fuel Combustion
Oils
Suspended Solids
Page 6
Chapter 1 Introduction
inorganic soil particles generated from these activities are at least two to six times, and
can be up to several hundred times, pre-development levels.
Turbid waters often result from the presence of suspended solids. In general the
community associates turbid waters with environmental pollution and degradation of
the water's aesthetic value.
Nutrients and toxins such as phosphorus, heavy metals and organic chemicals utilise
sediment as the medium for transportation in urban runoff. The deposition of
sediments can result in the release of these toxins and nutrients at a later time when
the ambient conditions related to the redox potential of the sediment and water column
becomes favourable for their release. This mechanism provides the opportunity for
pollutant re-mobilisation in later flow events enhancing the risk of further downstream
degradation.
Suspended solids also reduce the penetration of light through water, and this
adversely affects the feeding and respiration of aquatic plants.
1.4.2
Nutrients
Nutrients are fed into the water system through many different sources. These include
sewerage, plant matter, organic wastes, fertilisers, kitchen wastes (including
detergents), nitrous oxides produced from vehicles exhausts and ash from bushfires.
Nutrients contain natural compounds consisting of nitrogen and phosphorus.
There are problems associated with high levels of nutrients in waterbodies. Nutrients
promote growth of aquatic plant life including floating macrophytes, which if in large
concentrations, produce algal blooms on the water surface. Algae are microscopic
plants which occur naturally in waterways. With an increase in nutrients algal growth
becomes excessive often resulting in a build up of toxins. Toxic algal blooms cause
the closure of fisheries, water farming industries and public beaches.
1.4.3 Litter
Litter is generally the most noticeable indicator of water pollution to the community.
Litter is also commonly thought of as the pollutant most detrimental to waterways
because of its visibility. Pollution of the environment including the export of litter and
gross pollutants has intensified over the last 30 years due to the production of easily
disposable, non-biodegradable packaging and household and industrial items. The
sources of litter are varied and they include dropping of rubbish, overflows of rubbish
containers and material blown away from tips and other rubbish sources.
1.4.4
Metals
Analysis of contaminants associated with urban dust and dirt by Dempsey et al (1993)
found highest concentrations of Cu, Zn and TP to be associated with particles in the
74 m to 250 m. The particle size range with high Pb association extends to 840 m.
One possible explanation for a higher contaminant concentration is that the particular
size range has a higher specific surface area (and thus contaminant binding sites).
For example, Sansalone and Buchberger (1997) found that specific surface area of
solids transported from an urban roadway surface decrease with increasing particle
size as is normally the case for spherical particles. With irregularly shaped particles,
there is the general tendency for larger sized particles to have higher specific surface
area than are normally expected.
Table 1.2 reproduces the table of particle sizes and associated pollutants presented by
Dempsey et al (1993) for dust and dirt generated from road surfaces. The data
presented in the Table 1.2 indicates that treatment measures with capability of settling
particles of sizes down to 74 m will be necessary to facilitate treatment of metals and
nutrients in stormwater runoff generated from these areas. The particle size
distribution of sediment transported in stormwater is dependent on the geology of the
catchment and other studies (eg. Oliver et al (1993)) have found high concentrations
Page 7
Chapter 1 Introduction
of nutrients in colloidal particles which are much finer than 74 m. Under such
circumstances, treatment measures involving significant periods of detention and
enhanced sedimentation, using wetland macrophytes, will be necessary (Lloyd, 1997).
Table 1.2
Pollutants Associated with Urban Dust and Dirt (mg/g per mg/L)
(ref. Dempsey et al, 1993)
Particle Size Range
Contaminant
<74 m
74-105 m
105-250 m
250-840 m
840-2000 m
>2000 m
Cu
7,100
12,000
66,000
5,900
1,600
344
Zn
28,000
41,000
31,000
11,000
4,100
371
Pd
37,000
55,000
62,000
86,000
19,000
15,000
Total P
3,000
4,800
5,400
2,500
3,000
3,900
Page 8
Chapter 1 Introduction
1.5
The specific objectives or performance targets of ABC Waters Design Strategies for
Singapore catchments are still evoluting. However, best practice involves a risk-based
approach to the protection of environmental values and beneficial uses of urban
waterways and aquatic ecosystems. In Australia, reference is made to the objectives
of ANZECC/ARMCANZ (2000) and the setting of acceptable risk ambient water quality
values based on comparison with reference ecosystems, will be a necessary first step
towards setting stormwater management objectives.
In cases of receiving water bodies of environmental significance, the relevant
management authority will prescribe water quality guidelines, developed from in-depth
investigations. It is envisaged that a similar approach directed at the protection of
urban waterbodies in Singapore such as the Marina Bay Reservoir would be
appropriate. In most cases, it will be required for land development agencies and
enterprises to demonstrate that the development and associated stormwater
management strategy has adequately addressed the environmental threats of the
project to the receiving waters, and also the opportunities for improved environmental
outcomes from the project.
Guidelines for treatment objectives for stormwater quality have been defined in many
states in Australia and overseas, to represent achievable targets using best practice.
Treatment objectives for stormwater are often expressed in mean annual reductions of
pollutant loads from typical urban areas with no stormwater treatments installed and
are summarised in Table 1.3 for Australian states. These objectives are used in
conjunction with any local site-specific conditions to determine the environmental
objectives for stormwater at a site and are recommended for interim applications in
Singapore.
It is expected that the treatment objectives will be revised progressively to reflect
expected best practice improvements in design. Achieving these objectives does not
necessarily suggest that the ultimate receiving water quality outcomes for protecting
the health of aquatic ecosystems have been attained. However, it is often seen as a
practical approach to institutionalising best practices in stormwater quality
management, particularly in built up catchments.
Table 1.3
Pollutant
Suspended solids
Total phosphorus
Total nitrogen
Litter
Coarse sediment
Page 9
Chapter 1 Introduction
1.6
References
Binney, P., Donald, A., Elmer, V., Ewert, J., Phillis, O., Skinner, R. and Young, R.
(2010) IWA Cities of the Future Program, Spatial Planning and Institutional Reform
Conclusions from the World Water Congress, Montreal, September 2010.
Dempsey, B.A., Tai, Y.L. and Harrison, S.G. (1993). Mobilisation and removal of
contaminants associated with urban dust and dirt, Water Sci. Tech., 28(3-5): 225-230.
Institution of Engineers, Australia (2001) Australian Rainfall and Runoff, D H Pilgrim
(ed)., ISBN 0 85825 761 0.
Lloyd, S.D.(1997), Influence of Macrophytes on Sediment Deposition and Flow Pattern
within a Stormwater Pollution Control Wetland, Masters of Engineering Science thesis,
Department of Civil Engineering, Monash University, 161 p.
Newman, P., (2001) Sustainable Urban Water Systems in Rich and Poor Countries:
Steps towards a new approach. Water Science and Technology, 43(4): 93-100.
Sansalone, J.J. and Buchberger, S.G.(1997), Characterisation of solid and metal
element distributions in urban highway stormwater, Water Science and Technology,
36(8-9):155-160.
Schueler, T. (1995), Site Planning for Urban Stream Protection, Center for Watershed
Protection, Silver Spring, Maryland, 232p.
Wong, T.H.F., (2006a) Introduction. In T.H.F. Wong (Ed), Australian Runoff Quality: A
Guide to Water Sensitive Urban Design, Engineers Australia, Canberra, ISBN 0 85825
852 8, April 2006, Chapter 1: 1-8.
Wong, T.H.F., (2006b) Water Sensitive Urban Design the journey thus far. Australian
Journal of Water Resources, 10(3): 213-221.
Wong, T., Allen, R., Brown, R., Deletic, A., Griggs, D., Hodyl, L., McIIrath, B.,
Montebello, T., Smith, L. (2011), Transitioning to a resilient, liveable and sustainable
greater Melbourne (localised case studies), report prepared for the Living Victoria
Ministerial Advisory Council, March 2011.
Wong, T H F and Ashley, R (2006), International Working Group on Water Sensitive
Urban Design, submission to the IWA/IAHR Joint Committee on Urban Drainage,
March 2006.
Page 10
2
Chapter 2
2.1
Introduction
2.2
2.3
Sedimentation basins
2.4
Swale/buffer systems
2.5
Bioretention swales
2.6
Bioretention basins
2.7
Sand filters
2.8
Infiltration measures
10
2.9
Constructed wetlands
11
2.10
Ponds
12
2.11
Rainwater tanks
13
2.12
References
14
2.1
Introduction
This chapter gives an overview of the Water Sensitive Urban Design stormwater
treatment elements.
The ABC Waters Design Guidelines cover the most commonly used stormwater
quality treatment elements that are applicable in Singapore. Usually, combinations of
these elements are used as a treatment train to effectively manage stormwater from a
range of different land uses.
Detailed design procedures are provided for the following ABC Waters Design
Features in the subsequent chapters:
Sedimentation basins
Bioretention swales
Cleansing Biotopes
Bioengineering
Constructed wetlands
The selection and placement of the elements within a catchment should be determined
during a concept design of a stormwater treatment strategy and is outside the scope of
this document.
Page 1
2.2
Stormwater Quality
Management
The impact of poor stormwater quality discharged to receiving environments has in the
past decade become an issue of significant concern among catchment managers. The
impacts can include increased turbidity and suspended solid concentrations,
deposition of suspended material, increased concentrations of nutrients, oxygendemanding materials, micro-organism and toxic materials, and the deposition of litter.
Deposition of suspended material and gross pollutants can smother aquatic habitats.
Stormwater contaminants can deplete dissolved oxygen and increase toxicity levels,
causing degradation of ecological health of receiving waters.
Increased magnitude and frequency of storm flows can lead to significant changes to
the morphology of creeks and rivers leading to degradation of aquatic habitats. The
problem is exacerbated by a hydraulically efficient stormwater drainage system within
the catchment, leading to frequent flash-flood flow conditions and physical disturbance
of aquatic habitats.
The nature of the effects of catchment urbanisation on stormwater and the consequent
impact on the environment are short term and long term. It is often not possible to
distinguish which of these two factors (ie. poor water quality and hydrologic change) is
the dominant cause of environmental degradation of urban aquatic ecosystems.
Singapore is progressively moving towards attaining a higher level of self sustainability
in water resources. One of the strategies to achieve this is in the consideration of
urban stormwater as a resource. Singapore Government has therefore embarked on
a project which will convert Marina Bay, located at the heart of Singapore City, into a
freshwater reservoir that will harvest stormwater from one-sixth of the area of
metropolitan Singapore. Stormwater quality management and reducing potential
impacts of stormwater pollution are therefore important water resource management
considerations in Singapore
In formulating stormwater management strategies for multiple objectives, it is vital that
the cause-and-effect relationships of stormwater-related environmental problems are
first clearly understood. Remedial and preventative measures for improving urban
stormwater quality encompass non-structural and structural interventions in urban
catchment management practices. Effective and sustainable stormwater management
requires the coordinated and integrated implementation of non-structural and structural
measures, formulated to accommodate the constraints and opportunities posed by
individual catchments.
Best practice urban stormwater management aims to meet multiple objectives
including:
removing contaminants
Page 2
Typical urbanisation produces many contaminants that can be blown or washed into
waterways and affect the health of streams and waterways. Best practice stormwater
management provides for treatment of runoff to remove waterborne contaminants, to
protect or enhance the environmental, social and economic values of receiving
waterways.
As a general rule, site conditions and the characteristics of the target pollutant(s)
influence the selection of an appropriate type of treatment measure. Climatic
conditions influence the hydrological design and ultimately the overall pollutant
removal effectiveness of the measures.
An overriding management objective can help determine what treatment process is
likely to be feasible. Error! Reference source not found. shows a relationship
between management issues, likely pollutant sizes and appropriate treatment
processes to address those pollutants.
A series of treatment measures that collectively address all stormwater pollutants is
termed a treatment train. A treatment train consists of a combination of treatment
measures that can address the range of particle size pollutant found in stormwater. A
treatment train, therefore, employs a range of processes to achieve pollutant reduction
targets (such as physical screening, filtration and enhanced sedimentation). The
selection and order of treatments is a critical consideration in developing a treatment
train. The coarse fraction of pollutants usually requires removal so that treatments for
fine pollutants can operate effectively. Other considerations when determining a
treatment train are the proximity of a treatment to its source, as well as the distribution
Figure 2.1
Page 3
Figure 2.2
Page 4
2.3
Sedimentation basins
Sedimentation basins are used to retain coarse sediments from runoff and are typically
the first element in a treatment train. They play an important role by protecting
downstream elements from becoming overloaded or smothered with sediments. They
operate by reducing flow velocities and encouraging sediments to settle out of the
water column.
They are frequently used for trapping sediment in runoff from construction sites and as
pretreatments for elements such as wetlands (e.g. an inlet pond). They can be
designed to drain during periods without rainfall and then fill during runoff events or to
have a permanent pool.
Sedimentation basins can have various configurations including hard edges and base
(e.g. concrete) or a more natural form with edge vegetation creating an attractive
urban element. They are, however, typically turbid and maintenance usually requires
significant disturbance of the system.
Maintenance of sedimentation basins involves dewatering and dredging collected
sediments. This is required every approximately every five years, but depends on the
nature of the catchment. For construction sites that produce very large loads of
sediment, desilting is required more frequently.
Sedimentation basins should be designed to retain coarse sediments only
(recommended particle size is 0.125mm).
As the highest concentrations of
contaminants such as hydrocarbons and metals are associated with fine sediments,
waste disposal costs for this material can be much higher, hence other treatment
measures that assimilate these pollutants into a substrate are usually used to target
this material.
Figure 2.3
Page 5
2.4
Swale/buffer systems
Vegetated swales are used to convey stormwater in lieu of pipes and provide a
desirable buffer between receiving waters (e.g. creek, wetland) and impervious areas
of a catchment. They use overland flows and mild slopes to slowly convey water
downstream. The interaction with vegetation promotes an even distribution and
slowing of flows thus encouraging coarse sediments to be retained. Swales can be
incorporated in urban designs along streets or parklands and add to the aesthetic
character of an area.
The longitudinal slope of a swale is the most important consideration. They generally
operate best with slopes of 2% to 4%. Milder sloped swales can tend to become
waterlogged and have stagnant ponding, although the use of underdrains can alleviate
this problem. For slopes steeper than 4%, check banks along swales can help to
distribute flows evenly across swales as well as slow velocities. Dense vegetation and
drop structures can be used to serve the same function as check dams but care needs
to be exercised to ensure that velocities are not excessively high.
Swales can use a variety of vegetation types. Vegetation is required to cover the
whole width of a swale, be capable of withstanding design flows and be of sufficient
density to provide good filtration. For best treatment performance, vegetation height
should be above treatment flow water levels. If runoff enters directly into a swale,
perpendicular to the main flow direction, the edge of the swale acts as a buffer and
provides pre-treatment for the water entering the swale.
Figure 2.4
Page 6
2.5
Bioretention swales
Bioretention swales (or biofiltration trenches) are bioretention systems that are located
within the base of a swale. They can provide efficient treatment of stormwater through
fine filtration, extended detention and some biological uptakes as well as providing a
conveyance function (along the swale). They also provide some flow retardation for
frequent rainfall events and are particularly efficient at removing nitrogen and other
soluble or fine particulate contaminants.
Bioretention swales can form attractive streetscapes and provide landscape features
in an urban development. They are commonly located in the median strip of divided
roads.
Runoff is filtered through a fine media layer as it percolates downwards. It is then
collected via perforated pipes and flows to downstream waterways or to storages for
reuse. Unlike infiltration systems, bioretention systems are well suited to a wide range
of soil conditions including areas affected by soil salinity and saline groundwater as
their operation is generally designed to minimise or eliminate the likelihood of
stormwater exfiltration from the filtration trench to surrounding soils.
Any loss in runoff can be mainly attributed to maintaining soil moisture of the filter
media itself (which is also the growing media for the vegetation). Should soil
conditions be favourable, infiltration can be encouraged from the base of a bioretention
system to reduce runoff volume.
Vegetation that grows in the filter media enhances its function by preventing erosion of
the filter medium, continuously breaking up the soil through plant growth to prevent
clogging of the system and providing biofilms on plant roots that pollutants can adsorb
to. The type of vegetation varies depending on landscape requirements and climatic
conditions.
The filtration process generally improves with denser and higher
vegetation.
Figure 2.5
Page 7
2.6
Bioretention basins
Bioretention basins or rain gardens operate with the same treatment processes as
bioretention swales except do not have a conveyance function. High flows are either
diverted away from a basin or are discharged into an overflow structure.
Like bioretention swales, bioretention basins can provide efficient treatment of
stormwater through fine filtration, extended detention and some biological uptake,
particularly for nitrogen and other soluble or fine particulate contaminants.
Bioretention basins have an advantage of being applicable at a range of scales and
shapes and can therefore have flexibility for locations within a development. They can
be located along streets at regular intervals and treat runoff prior to entry into an
underground drainage system, or be located at outfalls of a drainage system to
provide treatment for much larger areas (e.g. in the base of retarding basins).
A wide range of vegetation can be used within a bioretention basin, allowing them to
be well integrated into a landscape theme of an area. Smaller systems can be
integrated with traffic calming measures or parking bays, reducing their requirement
for space. They are equally applicable to redevelopment as well as greenfield sites.
They are however, sensitive to any materials that may clog the filter medium. Traffic,
deliveries and washdown wastes need to be kept from bioretention basins to reduce
any potential for damage to the vegetation or the filter media surface.
Figure 2.6
Page 8
2.7
Sand filters
Sand filters operate in a similar manner to bioretention systems with the exception that
they have no vegetation growing on their surface. This is because they are either
installed underground (therefore light limits vegetation growth) or the filter media does
not retain sufficient moisture. They are particularly useful in areas where space is a
premium and treatment is best achieved underground. Due to the absence of
vegetation, they require regular maintenance to ensure the surface of the sand filter
media remains porous and does not become clogged with accumulated sediments.
Prior to entering a sand filter, flows are generally subjected to a pretreatment to
remove litter, debris and coarse sediments (typically a sedimentation chamber).
Following pretreatment, flows are spread over the sand filtration media and water
percolates downwards to perforated pipes located at the base of the sand media. The
perforated pipes collected treated water for conveyance downstream. During higher
flows, water can pond of the surface of the sand filter increasing the volume of water
that can be treated. Very high flows are diverted around sand filters to protect the
sand media from scour.
Figure 2.7
Page 9
2.8
Infiltration measures
Figure 2.8
Page 10
2.9
Constructed wetlands
Constructed wetland systems are shallow extensively vegetated water bodies that use
enhanced sedimentation, fine filtration and pollutant uptake processes to remove
pollutants from stormwater. Water levels rise during rainfall events and outlets are
configured to slowly release flows, typically over three days, back to dry weather water
levels.
Wetlands generally consist of an inlet zone (sediment basin to remove coarse
sediments), a macrophyte zone (a shallow heavily vegetated area to remove fine
particulates and uptake of soluble pollutants) and a high flow bypass channel (to
protect the macrophyte zone).
Wetland processes are engaged by slowly passing runoff through heavily vegetated
areas. Plants filter sediments and pollutants from the water and biofilms that grow on
the plants can absorb nutrients and other associated contaminants. In addition to
playing an important role in stormwater treatment, wetlands can also have significant
community benefits. They provide habitat for wildlife and a focus for recreation, such
as walking paths and resting areas. They can also improve the aesthetics of a
development and be a central feature in a landscape.
Wetlands can be constructed on many scales, from house block scale to large regional
systems. In highly urban areas they can have a hard edge form and be part of a
streetscape or forecourts of buildings. In regional settings they can be over 10
hectares in size and provide significant habitat for wildlife.
Figure 2.9
Page 11
2.10 Ponds
Ponds (or lakes) promote particle sedimentation, adsorption of nutrients by
phytoplankton and ultra violet disinfection. They can be used as storages for reuse
schemes and urban landform features for recreation as well as wildlife habitat. Often
wetlands will flow into ponds and the water bodies enhance local landscapes.
In areas where wetlands are not feasible (eg. very steep terrain), ponds can be used
for a similar purpose of water quality treatment. In these cases, ponds should be
designed to settle fine particles and promote submerged macrophyte growth. Fringing
vegetation, while aesthetically pleasing, contributes little to improving water quality.
Nevertheless, it is necessary to reduce bank erosion. Ponds still require pretreatment
such as a sedimentation basin that need to be maintained more regularly than the
main open waterbody.
Ponds are well suited to steep confined valleys where storage volumes can be
maximised. Some limitations for ponds can be site specific for example; proximity to
airports, as large numbers of flocking birds can cause a disturbance to nearby air
traffic. They also require regular inspection and maintenance to ensure that their
aesthetic value is not diminished.
Page 12
Supply and demand conditions such as a low roof area to occupancy ratio
(e.g. high density development) can result in large tank volumes to provide a
reliable supplementary water supply to the end-uses connected to a tank.
Available space - small lots with large building envelopes may preclude the
use of external, above ground, rainwater tanks.
Figure 2.11
Page 13
2.12
References
Page 14
3
Chapter 3
3.1
Stormwater Quality
3.1.1
Suspended Solids
3.1.2
Nutrients
3.1.3
Litter
3.1.4
Metals
3.2
3.2.1
General
3.2.2
3.2.3
3.2.4
10
3.2.5
11
3.3
13
3.3.1
General
13
3.3.2
Rainfall in Singapore
14
3.3.3
16
3.4
17
3.4.1
17
3.4.2
Data requirements
17
3.4.2.1
Climate data
17
3.4.2.2
17
3.4.2.3
17
3.4.2.4
18
3.4.3
18
3.4.4
18
3.5
References
19
3.1
Stormwater Quality
Solids
Nutrients
Fertilisers
Human Waste
Animal Waste
Vehicle Fuels and Fluids
Pathogens
DO
Demands
Metals
Synthetic
Organics
Fuel Combustion
Oils
Vehicle Wear
Industrial Processes
3.1.1
Suspended Solids
Suspended solids comprise of inorganic and organic materials. Sources of inorganic
suspended solids include soil particles from erosion and land degradation, streets,
households and buildings, and airborne particulate matter. Contributors to organic
suspended solids are bacteria and microorganisms such as those found in sewage.
The level of suspended solids in urban runoff is comparable to raw sewage and,
inorganic soil particles are particularly of concern. Large amounts of inorganic soil
particles are often associated with urban construction and the development of
supporting services including roads, sewers and drainage systems. Levels of
inorganic soil particles generated from these activities are at least two to six times, and
can be up to several hundred times, pre-development levels.
Turbid waters often result from the presence of suspended solids. In general the
community associates turbid waters with environmental pollution and degradation of
the water's aesthetic value.
Nutrients and toxins such as phosphorus, heavy metals and organic chemicals utilise
sediment as the medium for transportation in urban runoff. The deposition of
sediments can result in the release of these toxins and nutrients at a later time when
Page 1
the ambient conditions related to the redox potential of the sediment and water column
becomes favourable for their release. This mechanism provides the opportunity for
pollutant re-mobilisation in later flow events enhancing the risk of further downstream
degradation.
Suspended solids also reduce the penetration of light through water, and this
adversely affects the feeding and respiration of aquatic plants. Duncan (2006)
presents typical concentrations of suspended solids in urban stormwater runoff from
different land use, expressed as a log-normal distribution (Figure 3.).
Suspended Solids
Mean 1 Standard Deviation
All Roads(37)
Urban Roads(29)
Rural Roads(8)
All Roofs(11)
All Urban(247)
Residential(109)
Industrial(12)
Commercial(25)
Other Urban(101)
All Rural(50)
Agricultural(14)
Forest(11)
Other Rural(25)
1
Figure 3.1
10
100
Concentration (mg/L)
1000
3.1.2 Nutrients
Nutrients are fed into the water system through many different sources. These include
sewerage, plant matter, organic wastes, fertilisers, kitchen wastes (including
detergents), nitrous oxides produced from vehicles exhausts and ash from bushfires.
Nutrients contain natural compounds consisting of nitrogen and phosphorus.
There are problems associated with high levels of nutrients in waterbodies. Nutrients
promote growth of aquatic plant life including floating macrophytes, which if in large
concentrations, produce algal blooms on the water surface. Algae are microscopic
plants which occur naturally in waterways. With an increase in nutrients algal growth
becomes excessive often resulting in a build up of toxins. Toxic algal blooms cause
the closure of fisheries, water farming industries and public beaches.
Key nutrients of interest in managing urban waterways are phosphorus and nitrogen.
Phosphorus concentration in urban stormwater is often expressed as Total
Phosphorus (TP) and is the sum of dissolved and particulate phosphorus. Each
Page 2
Total Phosphorus
Mean 1 Standard Deviation
All Roads(20)
Urban Roads(16)
Rural Roads(4)
All Roofs(6)
All Urban(206)
Residential(90)
Industrial(9)
Commercial(23)
Other Urban(84)
All Rural(60)
Agricultural(14)
Forest(13)
Other Rural(33)
0.01
Figure 3.2
0.1
1
Concentration (mg/L)
10
Page 3
Total Nitrogen
Mean 1 Standard Deviation
All Roads(12)
All Urban(139)
Residential(58)
Industrial(6)
Commercial(13)
Other Urban(62)
All Rural(52)
Agricultural(14)
Forest(12)
Other Rural(26)
0.1
Figure 3.3
1
10
Concentration (mg/L)
100
3.1.3 Litter
Litter is generally the most noticeable indicator of water pollution to the community.
Litter is also commonly thought of as the pollutant most detrimental to waterways
because of its visibility. Pollution of the environment including the export of litter and
gross pollutants has intensified over the last 30 years due to the production of easily
disposable, non-biodegradable packaging and household and industrial items. The
sources of litter are varied and they include dropping of rubbish, overflows of rubbish
containers and material blown away from tips and other rubbish sources. Allison et al.
(1998) define gross pollutants as the material that would be retained by a fivemillimetre mesh screen, thus eliminating practically all sediment except that attached
to litter and other large debris. Figure 3. 4 shows the gross pollutant load generated in
urban catchments in Australia.
Gross Pollutants
1.8
1.6
Event Dry Load (kg/ha)
Total
1.4
1.2
Organic
1
0.8
0.6
0.4
Litter
0.2
0
0
10
20
30
40
50
60
Figure 3. 4
Gross Pollutant Event Loads vs Rainfall (redrawn from Allison et al. (1998))
Page 4
3.1.4 Metals
Analysis of contaminants associated with urban dust and dirt by Dempsey et al (1993)
found highest concentrations of Cu, Zn and TP to be associated with particles in the
74 m to 250 m. The particle size range with high Pb association extends to 840 m.
One possible explanation for a higher contaminant concentration is that the size range
is the higher specific surface area (and thus contaminant binding sites) of particles in
this range. For example, Sansalone and Buchberger (1997) found that specific
surface area of solids transported from an urban roadway surface decrease with
increasing particle size as is normally the case for spherical particles. With irregularly
shaped particles, there is the general tendency for larger sized particles to have higher
specific surface area than are normally expected.
Table 3.2 reproduces the table of particle sizes and associated pollutants presented by
Dempsey et al (1993) for dust and dirt generated from road surfaces. The data
presented in the Table 3.2 indicates that treatment measures with capability of settling
particles of sizes down to 74 m will be necessary to facilitate treatment of metals and
nutrients in stormwater runoff generated from these areas. The particle size
distribution of sediment transported in stormwater is dependent on the geology of the
catchment and other studies (eg. Oliver et al (1993)) have found high concentrations
of nutrients in colloidal particles which are much finer than 74 m. Under such
circumstances, treatment measures involving significant periods of detention and
enhanced sedimentation, using wetland macrophytes, will be necessary (Lloyd, 1997).
Table 3.2 Pollutants Associated with Urban Dust and Dirt (mg/g per mg/L)
(ref. Dempsey et al, 1993)
Particle Size Range
Contaminant
<74 m
74-105 m
105-250 m
250-840 m
840-2000 m
>2000 m
Cu
7,100
12,000
66,000
5,900
1,600
344
Zn
28,000
41,000
31,000
11,000
4,100
371
Pb
37,000
55,000
62,000
86,000
19,000
15,000
Total P
3,000
4,800
5,400
2,500
3,000
3,900
Total Copper
Total Zinc
Total Lead
All Roads(23)
All Roads(40)
All Roads(44)
Urban Roads(17)
Urban Roads(28)
Urban Roads(32)
Rural Roads(5)
Rural Roads(11)
Rural Roads(11)
All Roofs(25)
All Roofs(24)
Urban Roofs(11)
Rural Roofs(5)
All Urban(140)
Residential(59)
Industrial(11)
Urban Roofs(18)
Zinc Roofs(7)
All Roofs(16)
Non-zinc Roofs(10)
Unknown Roofs(7)
All Urban(156)
Residential(68)
All Urban(181)
Residential(78)
Industrial(11)
Commercial(22)
Industrial(10)
Commercial(14)
Rural Roofs(7)
Other Urban(70)
Commercial(19)
Other Urban(56)
Other Urban(59)
All Rural(17)
Agricultural(4)
All Rural(6)
0.001
All Rural(8)
0.01
0.1
1
Concentration (mg/L)
Figure 3.5
10
0.01
Other Rural(11)
0.1
1
10
Concentration (mg/L)
100
0.0001
0.001
0.01
0.1
Concentration (mg/L)
Page 5
3.2
3.2.1
Formulating a Stormwater
Management Strategy
General
Structural and non-structural stormwater management measures take many forms and
can often be directed at addressing specific problems. In most instances, a number of
management measures can be implemented in series or concurrently forming a
treatment train approach to stormwater management. Figure 3.1 shows the various
types of treatment works within an overall regional management flow chart, which
could form an integrated catchment management strategy.
The correct utilisation of the various components of the treatment train is a vital design
consideration and requires a holistic approach to their performance specifications and
positions in the treatment train. An overview of common elements of the stormwater
treatment train may be summarised as follows:Source Controls
Community awareness
Land use planning and regulation
Street cleaning
Sewer leakage management
Isolation of high pollutant source
areas
Construction site management
Landfill management
Litter traps
On-site detention basins
Stormwater infiltration systems
Buffer strips
In-transit Controls
End-of-pipe Controls
Gross pollutant traps
Lakes
Floating booms
Ponds and wetlands
Receiving water management
Page 6
Key issues for the implementation of stormwater quality initiatives are outlined as
follows:
Use ABC Waters Design Features in the urban landscape to maximise the
visual and recreational amenity of developments.
Page 7
Source Control
Structural Measures
Infiltration system
Stormwater reuse
On-site detention
Litter traps
Buffer strips
Structural Measures
Non-Structural Measures
Community awareness
Source identification
Landuse planning &
control
Permissible discharges
Street cleaning
Isolation of high
pollutant source area
Construction site
management
Detention
Screening
Sediment basins
Wetlands
Retarding basins
Ponds
Swale drains
Stormwater Management
Strategy
Figure 3.1
The layout of the combination of Best Management Practice (BMPs) included within a
'treatment train' may be viewed as Best Planning Practice (BPP), although the two are
not mutually exclusive as indicated by Figure 3.2. The selection of appropriate BMPs
to include within a treatment train involves an assessment made within a variety of
disciplines in order to account for site specific characteristic and limitations. This
procedure is illustrated in Figure 3.3 and Figure 3.4.
Stormwater characteristics are highly varied and the effectiveness of individual BMPs
and the treatment train as a whole will differ from one event to another. A statistical
approach is probably the most appropriate method of evaluating the performance of
the treatment train. A number of approaches can be adopted in evaluating the
effectiveness of the stormwater management strategy ranging from detailed
continuous model simulations to simplified flow frequency/mean event pollutant
concentrations.
Engineering Procedures for ABC Waters Design Features
Page 8
Design
Technology
Water Sensitive
Design
Efficient,
Sustainable &
Attractive
Figure 3.2
ECOLOGIST
ENGINEERS
WATER
SENSITIVE
URBAN DESIGN
LANDSCAPE
ARCHITECTURE
PLANNER
Figure 3.3
Study Teams Involved in Water Sensitive Urban Design (ABC
Waters Design)
Page 9
DESIGN OBJECTIVES
PERFORMANCE STANDARDS
ECOLOGIST
SITE
CHARACTERISTICS
ENGINEERS
DEVELOPMENT
CHARACTERISTICS
STORMWATER
MANAGEMENT PRACTICE
LANDSCAPE
ARCHITECT
PLANNERS
WATER SENSITIVE
SITE LAYOUT
Figure 3.4
While WSUD elements or ABC Waters Design Features (in Singapore context) may
have a landtake of up to 5% of the site area, implementing them into the urban design
can optimise outcomes, due to:
ABC Waters Design Features being integrated into streetscapes and not
requiring larger areas at the outlet of developments
Page 10
Utilise POS to provide links between public and private areas and community
activity nodes.
For water sensitive or ABC Waters landscape design the following natural landscape
values should be considered:
fauna habitat provision should be made for fauna habitat measures such as
wetlands, ponds, shrubs and nest boxes.
3.2.5
Roads account for a significant percentage of the overall impervious area created
within a typical urban development and therefore can significantly change the way
water is transported through an area. These areas also generate a number of water
borne stormwater contaminants that can adversely impact on receiving waterway
health (e.g. metals and hydrocarbons). Consequently, it is important to mitigate the
impact of stormwater runoff generated from road surfaces. By carefully planning road
alignments and streetscapes, ABC Waters Design features such as bioretention
systems and vegetated swales can be used to collect, attenuate, convey and treat the
runoff before discharge to receiving waterways.
Key principles in selecting road alignments and
streetscapes for ABC Waters Design depend on the
natural topography and overall masterplan for the
development. Some general considerations include:
Page 11
Page 12
3.3
3.3.1
Page 13
scenarios, based on a ABC Waters Design approach, and benchmarking against the
performance of a conventional urban water cycle management design approach.
3.3.2 Rainfall in Singapore
Figure 3.5 shows the location of Singapore rainfall stations and annual rainfall isohyets
(cm) in 2006. The distribution of the 2006 annual rainfall shows a significantly high
variability, ranging from 2200 mm to 3800 mm.
Monthly rainfall for 5 geographically spaced sites over 5 years were analysed to gain a
better understanding of the monthly rainfall patterns of these station. January and
December were generally the wettest months and there is a tendency for lower rainfall
during the middle months of the year. The analysis found significant variations in
monthly rainfall patterns amongst the stations. Furthermore, monthly rainfall patterns
also vary significantly from year to year for a given station. The characteristics (Figure
3.6) are symptomatic of climatic conditions where rainfall is events are dominated by
spatially random local thunderstorm activities.
Figure 3.5
Page 14
500
2000
400
2001
2002
300
2003
2004
2005
average
200
100
0
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Month
Rainfall (mm/month)
500
400
Station 06 2000
Station 23 2000
Station 24 2000
Station 25 2000
Station 79 2000
300
200
100
0
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Month
Rainfall (mm/month)
500
400
Station 79 2000
Station 79 2001
Station 79 2002
Station 79 2003
300
Station 79 2004
Station 79 2005
200
100
0
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Month
Figure 3.6
Page 15
3.3.3
11
87
5
6
43
84
78
31
39
74
24
64
40
25
23
7, 8, 80
72
88
0
2000
2200
2400
2600
2800
3000
3200
3400
Figure 3.7
From Figure 3.7, it is evident that despite the significant range in annual rainfall of the
stations tested, there was only a weak trend of increasing treatment area with rainfall
observed. The sizes of bioretention area necessary to deliver a 45% reduction in
mean annual TN load falls generally between 4% and 5% (with the exception of
Station 88 and Station 47, both stations having near-average annual rainfall). Given
this result, there appears little benefit in creating different design zones for Singapore.
Thus it was considered reasonable to develop a single set of design curves based
around the upper limit (ie. 5% for bioretention systems) that applicable for all regions in
Singapore for each treatment measure. This would for a simple sizing guide for the
treatment measures and the guideline would recommend that users adopt a modelling
approach with local rainfall data should they want to refine the sizing further, which
would generally lead to a reduction in required area.
The performance curves used as a checking guide in subsequent chapters in this
document have been based on adopting a factoring the performance of the reference
station factored by 1.1 to reflect this conservative simple approach to sizing
stormwater treatment systems.
Page 16
3.4
Data requirements
Event mean and dry weather pollutant concentrations (default values are
provided from the worldwide literature (Duncan, 2006).
Alternatively, the entire source node simulation may be bypassed by importing a file of
flow and concentration data appropriate to the site.
3.4.2.3 Treatment node properties
MUSIC users specify the design properties of a given treatment node, such as the
inlet, storage and outlet properties. Advanced parameters can also be accessed, to
modify the default modelling parameters (such as the k and C* values in the Universal
Stormwater Treatment Model). MUSIC also allows users to create a Generic
Treatment Node, to simulate the performance of a stormwater treatment measure
Page 17
Page 18
3.5
References
Dempsey, B.A., Tai, Y.L. and Harrison, S.G. (1993). Mobilisation and removal of
contaminants associated with urban dust and dirt, Water Sci. Tech., 28(3-5): 225-230.
Duncan, H (2006), Chapter 3 Urban Stormwater Pollutant Characteristics, in Australian
Runoff Quality: A guide to Water Sensitive Urban Design, Editor-in-Chief Wong, T H
F, ISBN 0 85825 852 8, Engineers Australia, Canberra, Australia, 2006
Lawrence, I and Breen, P (2006), Chapter 2 Stormwater Contaminant Processes and
Pathways, in Australian Runoff Quality: A guide to Water Sensitive Urban Design,
Editor-in-Chief Wong, T H F, ISBN 0 85825 852 8, Engineers Australia, Canberra,
Australia, 2006.
Lloyd, S.D.(1997), Influence of Macrophytes on Sediment Deposition and Flow Pattern
within a Stormwater Pollution Control Wetland, Masters of Engineering Science thesis,
Department of Civil Engineering, Monash University, 161 p.
Oliver, R.L., Hart. B.T., Douglas, G.B and Beckett, R. (1993), Phosphorus speciation in
the Murray and Darling Rivers, Water Chemistry in Australia, August, pp.392-297.
Sansalone, J.J. and Buchberger, S.G.(1997), Characterisation of solid and metal
element distributions in urban highway stormwater, Water Sci. Tech., 36(8-9):155-160.
Page 19
Sedimentation Basins
4
Chapter 4 Sedimentation Basins
4.1
Introduction
4-1
4.2
Design Considerations
4-2
4.2.1
4-2
4.2.2
4-2
4.2.3
Sediment Storage
4-3
4.2.4
Outlet Design
4-3
4.2.5
Landscape Design
4-4
4.2.6
Vegetation Specification
4-4
4.2.7
Maintenance
4-4
4.3
Design Process
4-6
4.3.1
4-7
4.3.2
4-7
4.3.3
4-9
4.3.3.1
4.3.3.2
Internal Batters
4.3.3.3
4-9
4-9
4-11
4-12
4.3.4
4-13
4.3.5
4-13
4.3.3.4
4.3.5.1
4-13
4.3.5.2
4-15
4.3.5.3
4-15
4-16
4.3.6
4.3.7
4-16
4.3.8
4-17
4.4
Checking tools
4-18
4.5
4-18
4.6
Construction Advice
4-20
4.6.1
4-20
4.6.2
4-20
4.6.3
Maintenance access
4-20
4.6.4
Solid base
4-20
4.6.5
4-20
4.6.6
Inlet checks
4-21
4.6.7
4-21
4.6.8
Weed Control
4-21
4.6.9
4-21
4.7
Maintenance Requirements
4.8
4-24
4-25
4-26
4.7.1
4.8.1
4-26
4.8.2
Calculation Steps
4-27
4.8.3
4-33
4.8.4
Construction drawings
4-34
4.9
References
4-35
4.1
Introduction
Page 4-1
nd Embankment
Spillway Outletaand
Embankment
Control Outlet
Permanent Pool
4.2
4.2.1
Design Considerations
Role of sedimentation basins in the stormwater treatment train
Sedimentation basins have two key roles when designed as part of a stormwater
treatment train. Its primary function is to capture coarse to medium sized sediment as
pre-treatment to waters entering a downstream treatment systems (e.g. macrophyte
zone of a constructed wetland or a bioretention basin) configured for removal of finer
particulates and soluble pollutants.
The pre-treatment ensures that downstream treatment systems are not smothered by
coarse sediment which may hamper their effectiveness to target finer particulates,
nutrients and other pollutants.
The second function of sedimentation basins is the control or regulation of flows
entering the downstream treatment system during design operation and above
design conditions. The outlet structures of sedimentation basin are designed such
that flows up to the design operation flow (typically the 1 year ARI) enter the
downstream treatment system, whereas above design flows are bypassed around the
downstream treatment system. In providing this function, the sedimentation basin
protects the downstream treatment system against scour during high flows. The
configuration and design of outlet structures in sedimentation basins are described in
Section 4.2.4.
4.2.2
The size of a sedimentation basin is typically calculated to match the settling velocity
of a target sediment size for a given design flow. In urban stormwater management,
this design flow typically corresponds to the 1 year ARI peak flow. As a pretreatment
facility, it is recommended that particles of 125m or larger be the selected target
sediment size.
This recommendation is based on the following considerations:
Page 4-2
Almost all sediment bed loads are larger than this target sediment size. By
targeting this particle size for pre-treatment, containment of a significant
proportion of sediment inflow is within the sedimentation basin.
Where the sedimentation basin forms part of a treatment train (i.e. inlet zone of a
constructed wetland) and when available space is constrained, it is important to
ensure that the size of the sedimentation basin is not reduced. If the sedimentation
basin is not sized adequately, larger sediments will not be trapped effectively and the
downstream treatment system is at risk of becoming smothered.
Conversely, a sedimentation basin should not be grossly oversized, as smaller
particles may be allowed to settle (due to longer residence times) and special cleanout and disposal procedures would be required. Experiences have also shown that
grossly oversized sedimentation systems may also be subject to poor water quality
outcomes including the occurrence of algal blooms.
4.2.3 Sediment Storage
A further consideration in the design of a sedimentation basin is the provision of
adequate storage for settled sediment to prevent the need for frequent desilting.
Typically, a basin is designed to have frequency of desilting (clean-out frequency)
ranging from annually to once every five years (generally triggered when sediment
accumulates to half the basin pool depth).
The volume of accumulated sediment can be estimated from regular monitoring of
sediment levels with a measuring post and reference against the top water level.
Review of global literature suggests that a developing catchment can typically be
expected to discharge between 50m3 and 200m3 of sediment per hectare each year.
In a built-up catchment, the annual sediment export is generally one to two orders of
magnitude lower.
No data is available to help estimate the expected sediment load generated from
Singapore urban catchments and data from other sources have been used in the
interim to estimate the required sediment storage. In Australia, an expected mean
3
annual rate of 1.60m /ha has been suggested (Engineers Australia, 2006).
Sediment loading rate for Singapore catchments may be higher than typically
observed in Australian catchments, owing to higher intensity and magnitude of rainfall.
Preliminary modeling suggests a sediment loading rate as high as 3 m3/ha/year may
be more appropriate for Singapore conditions.
4.2.4 Outlet Design
An outlet structure of a sedimentation basin can be configured in many ways and is
generally dependant on its intended operation. In most cases, the outlet design of a
sedimentation basin will consist of a control outlet structure and a spillway outlet
structure:
The control outlet can either be an overflow pit with pipe connection or a weir.
This structure conveys flows up to the design operation flow (Section 4.3.1)
to the downstream treatment system(s).
The spillway outlet weir structure configured to ensure that flows above the
design operation flow (Section 4.3.1) are discharged to a channel or pipe
Page 4-3
Vegetation Specification
The role of vegetation in sedimentation basin design is to provide scour and erosion
protection to the basin batters and littoral zone (i.e. the area around the shallow
margin of the sedimentation basin). Terrestrial planting may also be recommended to
screen areas and provide a barrier to steeper batters.
Plant species should be selected based on the water level regime, soil types of the
region, and the life histories, physiological and structural characteristics, natural
distribution, and community groups of the plants. A list of suggested plant species
suitable for sedimentation basins will be developed in consultation with National Parks
Board of Singapore and form an separate guidelines.
Only the waters edge and batters of sedimentation basins should be planted and care
needs to be taken in species selection to ensure vegetative growth will not spread to
cover the deeper water zones. Similarly, floating or submerged macrophytes should
be avoided.
4.2.7 Maintenance
Sedimentation basins are designed with a sediment storage capacity to ensure
sediment removal frequency is acceptable (i.e. typically between once per year to
once every five years, refer to Section 4.2.3).
Maintenance is focus on ensuring inlet erosion protection is operating as designed,
monitoring sediment accumulation and ensuring that the outlet is not blocked with
debris. Cleaning of the sedimentation basin is typically triggered when sediment
accumulates to half the basin depth, determined from regular monitoring of sediment
depth with a measuring post during maintenance visits.
Accessibility for maintenance is an important design consideration. If an excavator is
able to reach all parts of the basin from the top of the batter then an access ramp may
not be required; however, an access track around the perimeter of the basin will be
required and will need to be accommodate in the overall landscape design. If
sediment collection requires earthmoving equipment to enter the basin, a stable ramp
will be required into the base of the sedimentation basin (maximum slope 1:10).
Page 4-4
Page 4-5
4.3
Design Process
The following sections detail the design steps required for sedimentation basins. Key
design steps following the site planning and concept development stages are:
Page 4-6
Design Operation Flow for sizing the basin area and to size a control outlet
structure when discharging directly into a treatment system (e.g. wetland or
bioretention system). The 1 year ARI peak discharge is recommended as the
Design Operation Flow.
Above Design Flow for design of the spillway outlet structure to allow for
bypass of high flows around a downstream treatment system. This is defined by
either the:
Major flood flow (50 to 100 year ARI) is conveyed by major canal and
waterways and/or designated overland flow paths or floodways within the
urban area that is engaged when the capacity of the local drainage
infrastructure is exceeded. In Singapore, this is either the 50 year or 100 year
ARI peak discharge depending on the catchment land use. This design flow
should be adopted as the Above Design Flow for the sedimentation basin
where both the minor and major drainage systems discharge into the basin.
Page 4-7
1800
1600
1400
Basin Area (m 2)
1200
1000
600
200
0
0
0.5
1.5
2.5
3.5
400
Basin Area (m 2)
300
200
100
0
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
Figure 4.3 Sedimentation Basin Area Vs Design Discharges for varying capture
efficiencies of 125
m sediment
Page 4-8
4.3.3
Figure 4.4
Hydraulic Efficiency,
Page 4-9
For water depths > 150 mm and maximum slope of 5:1 (H:V) or less, no
fencing is required.
For water depths > 150 mm and maximum slope > 5:1 (H:V) fencing is
required.
Figure 4.5 Design considerations for soft edge treatment for open waterbodies
(Source: GBLA 2004)
Figure 4.6 Design considerations for hard edge treatment for open waterbodies
(Source: GBLA 2004)
Page 4-10
(d e + d p )
1 v
R = 1 1 + s
*
n Q/AS (d e + d )
Equation 4.1
Where
R
vs
Q/AS
de
dp
d*
depth below the permanent pool level that is sufficient to retain the target
sediment (m) adopt 1.0 m or dp whichever is lower.
1
n
1
n =
1
= 1
Equation 4.2
The concept design stage will generally guide the selection of the fraction of target
sediment removed (R) and permanent pool depth (dp) depending on water quality
objectives and the nature of local catchment geology. The selection of the target
sediment size will led to the determination of the theoretical settling velocity of the
target particle size for use in Equation 4.1 to compute removal efficiency for a given
size basin.
Table 4.1 lists the typical settling velocities (vs) of sediments under ideal conditions
(velocity in standing water).
Page 4-11
Settling velocities
(mm/s)
2000
200
Coarse sand
1000
100
Medium sand
500
53
Fine sand
250
26
125
11
Coarse silt
62
2.3
Medium silt
31
0.66
Fine silt
16
0.18
0.04
Clay
0.011
V =
dp
2
( Ab + AT )
2
Equation 4.3
Where
Ab
AT
The basin areas are determined based on the surface dimensions and the batter
slopes.
The volume of accumulated sediments over period before the basin is desilted (Vs) is
established by gaining an understanding of the sediment loads entering the
sedimentation basin and applying the fraction of target sediment removed (R):
Vs = A c R Lo Fc
Equation 4.4
Where
Vs
Ac
Page 4-12
Lo
Fc
4.3.5.1 Design of Control Outlet - Overflow Pit and Pipe Outlet Configuration
For a sedimentation basin that operates as a pre-treatment within a treatment train
configuration, the control outlet structure discharging to the downstream treatment
system (e.g. constructed wetland) is an overflow pit and pipe with the following design
criteria:
Ensure that the crest of the overflow pit is set at the permanent pool level of
the sedimentation basin.
The overflow pit is sized to convey the design operational flow (e.g. the 1 year
ARI peak discharge from the catchment). The dimension of the outlet pit is
determined by considering two flow conditions: weir and orifice flow as
expressed in Equation 4.5 and Equation 4.6.
Page 4-13
Qdes
B Cw h3 / 2
Equation 4.5
Where
P
Qdes
CW
Qdes
Equation 4.6
B Cd 2 g h
Where
Cd
Ao
Orifice area (m )
Qdes
Page 4-14
The pipe that connects the sedimentation basin to the downstream treatment system
(e.g. macrophyte zone of a constructed wetland or bioretention system) should have
sufficient capacity to convey the design operational flow (i.e. the 1 year ARI peak flow)
when downstream water level is at the permanent pool level. This ensures the
majority of flows have the opportunity to enter the downstream treatment system
before the bypass system is engaged. As downstream water level increases due to
the filling of the extended detention of the downstream treatment system, the capacity
of the connecting pipe may reduce and ultimately triggering a by-pass from the
sedimentation basin (see Chapter 9 Constructed Wetlands).
An energy dissipater is usually required at the end of the pipes to reduce velocities
and distribute flows into the downstream treatment system.
If the outlet of the connection pipe is submerged, an energy loss equation can be used
to estimate the pipe velocity using the following:
h=
k V 2
2 g
Equation 4.7
Where:
h
head level driving flow through the pipe (defined as the spillway outlet level
minus the normal water level in the downstream treatment system)
The area of pipe required to convey the design operation flow (1 year ARI) is then
calculated by dividing the above design operation flow by the velocity. Alternatively, if
the pipe outlet is not fully submerged, the orifice equation should be used (Equation
4.6) to estimate the size of the connection pipe.
4.3.5.2 Design of Control Outlet Weir Configuration
If a weir outlet structure is to be used instead of an overflow pit and pipe configuration,
the required length of the weir for control outlet operation can be computed using the
weir flow equation (Equation 4.5) and the design operation flow (Section 4.3.1).
Depending on the width of the weir, a weir blockage factor may still be required in
which case a factor of 0.5 is recommended.
4.3.5.3 Design of Spillway Outlet Weir Configuration
For operation under above-design conditions, a spillway outlet weir will required to
safely convey above-design flows.
For sedimentation basins serving as pre-treatment to downstream systems, this
spillway will form part of the high flow bypass system, which protects the downstream
treatment system from scouring during above design storm flows. The spillway
outlet weir level should ideally be set at the top of the extended detention level of the
downstream treatment system.
The length of the spillway outlet weir is to be sized to safely pass the maximum flow
discharged into the downstream treatment system (as defined by the above design
flow in Section 4.3.1). The water level above the crest of the bypass weir plus
freeboard provision (typically 0.3 m) sets the elevation of the embankment crest of the
sedimentation basin.
The required length of the spillway outlet weir can be computed using the weir flow
equation (Equation 4.5) and the above design flow (Section 4.3.1). No provision for
Page 4-15
blockage is necessary (i.e. blockage factor of 1.0). The spillway outlet weir should be
designed using standard methods to avoid scour and erosion. Typically, a concrete sill
is required with rock protection on the downslope sides of the sill. Figure 4.8 shows
typical spillway structures of sedimentation basins providing a means of bypassing
above design flows around downstream constructed wetlands.
A list of suggested plant species suitable for sedimentation basin littoral zones will be
developed for Singapore in consultation with National Parks Board of Singapore.
4.3.7 Step 7: Maintenance Plan and Schedule
Consider how maintenance is to be performed on the Sedimentation Basin (e.g. how
and where is access available, where is litter likely to collect etc.). A specific
maintenance plan and schedule should be developed for the basin, either as part of a
maintenance plan for the whole treatment train, or for each individual asset. Guidance
on maintenance plans is provided in Section 4.7.
Page 4-16
CALCULATION CHECKSHEET
CALCULATION TASK
OUTCOME
CHECK
Catchment characteristics
- Land Uses
Residential
Commercial
Roads
Ha
Ha
Ha
- Fraction Impervious
Residential
Commercial
Roads
Weighted average
Conceptual Design
Basin Area
Notional permanent pool depth
Permanent pool level of sedimentation basin
Basin extended detention
Overflow level
m
m
m
m
m
year
year
minutes
mm/hr
mm/hr
m /s
3
m /s
m
L:W (1)
m
V:H (1)
Vs>Vs,5year
Sediment clean-out frequency, given Vs
years
LxB
m
-
- Connection Pipe
Connection pipe dimension
Connection pipe invert level
mm dia
m
m
m
m
m
6. Vegetation Specification
Page 4-17
4.4
Checking tools
The following sections provide a number of checking aids for designers and referral
authorities.
Design assessments
4.5
Design assessment checklist
The checklist below presents the key design features that should be reviewed when
assessing a design of a sedimentation basin either for temporary or permanent use.
These considerations include configuration, safety, maintenance and operational
issues that should be addressed during the design phase.
Where an item results in an N when reviewing the design, referral should be made
back to the design procedure to determine the impact of the omission or error.
In addition to the checklist, a proposed design should have all necessary permits for its
installations. The referral agency should ensure that all relevant permits are in place.
These can include permits to clear vegetation, to dredge, create a waterbody, divert
flows or disturb downstream aquatic habitats.
Page 4-18
Area:
TREATMENT
BASIN CONFIGURATION
Inlet pipe/structure sufficient for maximum design flow (minor and/or major flood event)?
Scour protection provided at inlet?
Basin located upstream of treatment system (i.e. macrophyte zone of wetland)?
Configuration of basin (aspect, depth and flows) allows settling of particles >125 m?
Basin capacity sufficient for desilting period (i.e. >= twice sedimentation accumulation over clean out
frequency?)
Maintenance access allowed for into base of Sedimentation Basin?
Public access to basin prevented through dense vegetation or other means?
Gross pollutant protection measures provided on inlet structures where required?
Freeboard provided to top of embankment?
Public safety design considerations included in design and safety audit of publicly accessible areas
undertaken?
Overall shape, form, edge treatment and planting integrate well (visually) with host landscape?
HYDRAULIC STRUCTURES
'Control' outlet structure required?
'Control' outlet structure sized to convey the design operation flow?
Designed to prevent clogging of outlet structures (i.e. provision of appropriate grate structures)?
'Spillway' outlet control (weir) sufficient to convey 'above design flow'?
'Spillway' outlet has sufficient scour protection?
Visual impact of outlet structures has been considered?
COMMENTS
Page 4-19
4.6
Construction Advice
This section provides general advice for the construction of sedimentation basins. It is
based on observations from construction projects around Australia.
4.6.1 Building phase damage
It is important to have protection from upstream flows during construction of a
Sedimentation Basin. A mechanism to divert flows around a construction site,
protection from litter and debris is required.
Page 4-20
Page 4-21
Date:
Time:
Constructed
by:
Weather:
Adequate
Items inspected
Checked
Adequate
Items inspected
Y
DURING CONSTRUCTION
Preliminary works
Earthworks
5. Integrity of banks
Vegetation
Structural components
Page 4-22
FINAL INSPECTION
1. Confirm levels of inlets and outlets
COMMENTS ON INSPECTION
ACTIONS REQUIRED
1.
2.
3.
4.
Page 4-23
4.7
Maintenance Requirements
Sedimentation basins treat runoff by slowing flow velocities and promoting settlement
of coarse to medium sized sediments. Maintenance is focus on ensuring inlet erosion
protection is operating as designed, monitoring sediment accumulation and ensuring
that the outlet is not blocked with debris.
Inspections of the inlet configuration following storm events should be made soon after
construction to check for erosion. In addition, regular checks of sediment build up will
be required as sediment loads from developing catchments or construction sites vary
enormously. The basins should be cleaned out if more than half full of accumulated
sediment.
Similar to other types of practices, debris removal and weed control is an ongoing
maintenance function. Debris, if not removed, can block inlets or outlets, and can be
unsightly if located in a visible location. Inspection and removal of debris should be
done regularly, but debris should be removed whenever it is observed on the site.
Weed management in sedimentation basins is important to ensure that weeds do not
out-compete the species planted for the particular design requirements.
Page 4-24
1 to 6 monthly
Date of Visit:
Location:
Description:
Site Visit by:
INSPECTION ITEMS
Litter accumulation?
Sediment accumulation at inflow points?
Sediment requires removal (record depth, remove if >50%)?
All structures in satisfactory condition (pits, pipes, ramps etc)?
Evidence of dumping (building waste, oils etc)?
Littoral vegetation condition satisfactory (density, weeds etc)?
Replanting required?
Weeds require removal from within basin?
Settling or erosion of bunds/batters present?
Damage/vandalism to structures present?
Outlet structure free of debris?
Maintenance drain operational (check)?
Resetting of system required?
COMMENTS
Page 4-25
4.8
Catchment Description
The sedimentation basin receives stormwater from road runoff. Road runoff is
conveyed by conventional stormwater pipes (up to the 100 year ARI event) and there
are two freeway outfall pipes that discharge to the sedimentation basin. Each outfall
services about 500m length of the 40 m wide freeway, giving a total contributing area
of 2Ha (100% impervious) to each outfall.
Design Objectives
All stormwater runoff will be subjected to primary treatment, by sedimentation of
coarse to medium size sediment.
As the sedimentation basins form part of a treatment train the design requirements of
the sedimentation basin system are to:
Provide for by-pass operation when the inundation of the downstream macrophyte
zone reaches the design maximum extended detention depth with a discharge
capacity corresponding to the 100-year ARI peak discharge.
The site is triangular in shape with a surface area of 500 m as shown in Figure 4.10.
The site of the sedimentation basin has a fall of approximately 2m (from RL 5 m to RL
3 m) towards a degraded watercourse.
The conceptual design process established the following key design elements to
ensure effective operation of the constructed wetland and sedimentation basin:
Sedimentation basin permanent pool level (control outlet pit level) 0.3m (RL
3.7m) above the permanent pool level of the wetland
Spillway outlet weir set 0.3 m above the permanent pool of the sedimentation
basin at RL 4.0m such that the spillway is aligned with the top of the extended
detention for the wetland (RL 4.0m) and triggering a by-pass when the water level
in the wetland reaches then top of extended detention.
Landscape Requirements
Landscape design will be required and this will include the following:
-
Terrestrial vegetation
Page 4-26
geway
Freeway Carria
Inlet 2
6.0
5.0
Inlet 1
4.0
Site of Sedimentation
Basin & Wetland
System
20 m
3.0
Creek
50 m
Step 1
Step 2
Step 3
Step 4
Step 5
Step 6
Details for each calculation step are provided below. A design calculation summary
has been completed for the worked example and is given at the conclusion of the
calculation steps.
Page 4-27
The procedures in Singapores Code of Practice on Surface Water Drainage (Part II)
(the Rational Method) are used to determine design flow rates. The coefficients
prescribed in the code of practice are based on land use within the catchment.
The site has two contributing catchments, each catchment being 2Ha in area, 500m
long (along the freeway) and drained by culverts. The time of concentration (tc) of the
catchment consists of the overland flow time (to) plus the drain flow time from the most
remote drainage inlet to the point of design (td), viz. tc = to + td.
Overland flow time has been estimated to be relatively short (~ 4 min). A drain flow
velocity of 2m/s was assumed for the purposes of estimating the time of concentration
(tc).
500m 1 min
tc = 4 +
8 min
2m / s 60 s
Rainfall intensities for Singapore (for the 1yr and 100yr average recurrence intervals)
are estimated using the IDF curves1 for Singapore, with the time of concentration
equaling 8 minutes. The 1 year ARI rainfall intensity was extrapolated using a log
normal probability scale from the IDF data available:
I1 ~ 110 mm/hr
The runoff coefficients for the 1 year and 100 year ARI events were assumed to be 1.0
as given in the Code of Practice for Surface Water Drainage for roads and freeways.
The rational method is described by
Q =
CIA
360
Q1 = 1.2 m /s
Q100 = 3.1m /s
In summary, the design flow rates for the sedimentation basin are
Operation Design Discharge
1.2m3/s
1.2m /s
3.1m3/s
An initial estimate of the sedimentation basin area can be established using the curves
provided in Figure 4.3. Assuming a notional permanent pool depth of 2m, a
2
sedimentation basin area of approximately 260m is required to capture 90% of the
3
125m particles for flows up to the design operation flow of 1.2m /s.
Page 4-28
(d e + d p )
1 v
R = 1 1 + s
*
n Q/AS (d e + d )
Given
vs
0.011m/s
Q/AS
0.0046m /s/m
de
0.3m
dp
2m
d*
An aspect ratio of 1 (W) to 4 (L) is adopted based on the available space (Figure 4.10).
Using Figure 4.4 (configuration I), the hydraulic efficiency () is estimated to be
approximately 0.4. This value is less than desirable; however, site constraints prevent
any other configuration. The turbulence factor (n) is computed from Equation 4.2 to be
1.67 and the corresponding removal efficiency to be 88%. This is reasonably close to
the design removal efficiency of 90% but it may be necessary to increase the size of
the basin to compensate for the lower than desired hydraulic efficiency. To achieve
90% capture efficiency, the required basin area would be approximately 300 m2.
Sedimentation Basin storage
The sedimentation basin storage volume (Vs) is defined as the storage available in the
bottom half of the sedimentation basin permanent pool depth.
Considering the relatively small size of the sedimentation basin (8m width), it is not
possible to achieve the notional permanent pond depth of 2m using the 5:1 (H:V)
required for public safety (Section 4.3.3.2). Therefore 4:1 (H:V) batter is to be adopted
for the ground above the permanent pool level and to 0.2m below permanent pool
level. A 2:1 (H:V) internal batter slope is to be adopted for 0.2m to 2m below the
permanent pool level. The sedimentation basin will be fenced around most of its
perimeter to ensure public safety.
Given a 2:1 (H:V) internal batter slope below the permanent water level, the area of
2
the basin at 1m depth (i.e. half the permanent pool depth) is 115m and at 2m depth
2
(base of basin) is 2m .
The sedimentation basin storage volume Vs calculated using Equation 4.3 is
3
approximately 58m and corresponds to the approximately 11 years of accumulated
sediment (adopting a sediment generation rate of 3 m3/ha/yr and a capture efficiency
of 87%)
The dimensions for the sedimentation basin are summarised below.
260m2
Basin length
32m
Basin width
8m
2m
Page 4-29
To prevent scour of deposited sediments from piped inflows, rock protection and
benching is to be placed at the pipe headwall as shown in Figure 4.11.
Storm w ater
pipe
25 m m dia.
w eephole
W ing W all
C oncrete
outlet apron
P=
Qdes
B Cw h3 / 2
1.2
0.5 1.7 0.3 3 / 2
P = 8.6m
P=
Ao =
Ao =
Qdes
B Cd 2 g h
1.2
Page 4-30
A 1.5m by 3m overflow pit would have an opening area of 4.5 m . In this case, the
2
orifice flow condition with a 1.7 m area would be sufficient to convey the design
discharge.
The top of the pit is to be fitted with a grate.
The size of the outlet pipe or connection pipe to the wetland macrophyte zone can be
calculated by firstly estimating the velocity in the outlet/connection pipe using the
following (Equation 4.7 ):
h=
2 V2
2g
Where
h
head level driving flow through the pipe (defined as the spillway outlet level
minus the higher of the normal water level in the downstream treatment
system or the obvert of the pipe)
The above equation gives a pipe flow velocity of 2.4 m/s, giving a required pipe area of
0.5m2 to convey a flow of 1.2 m3/s. This area is equivalent to an 800mm diameter
pipe. To accommodate this pipe diameter, a pit dimension of 1.5 m x 1.5 m will be
required.
If the sedimentation basin is the inlet zone of a wetland system, the obvert of the pipe
is to be set just below the permanent water level in the wetland macrophyte zone (RL
3.4m) meaning the invert is at RL 2.6m.
In summary, the control outlet structure will be an overflow pit, 1.5m by 1.5m with the
crest level at RL 3.7m and a raised grated cover set at RL 3.8m.
The
outlet/connection pipe to the wetland will be 800mm in diameter, the invert set at RL
2.6m.
Design of Spillway Outlet - Weir Outlet
The above design flow controlled discharge will be provided by a spillway outlet weir
designed to convey the above design flow (100 year ARI). The crest of the spillway is
set at 0.3 m above the permanent pool of the sedimentation basin.
The length of the spillway outlet weir determines the afflux for the 100 year ARI peak
discharge and sets the top of embankment of the sedimentation basin. It is common
practice to allow for 0.3 m of freeboard above the afflux level when setting the top of
embankment elevation.
An afflux of 0.3 m has been adopted in defining the length of the spillway weir. This
value was adopted as a tradeoff between the bank height and the width of the weir. A
bank height of 0.9 m (0.3 m afflux and 0.3 m freeboard plus 0.3 m extended detention)
above the normal water level was deemed acceptable. The elevation of the crest of
the spillway is RL 4.0m. The weir length is calculated using the weir flow equation
(Equation 4.5) substituting outlet perimeter P with weir length L and blockage factor
B=1 (no blockage):
L=
Q100 yr
Cw h3/ 2
3.1
1.7 0.33 2
L = 11m
L=
Page 4-31
The spillway outlet is located adjacent to the inflow culvert to minimise risk of
sediment scour.
Step 6 Vegetation Specification
The vegetation specification for the littoral zone of a sedimentation basin will be advised
once the list of recommended plantings has been established by National Parks Board of
Singapore.
Page 4-32
CALCULATION CHECKSHEET
CALCULATION TASK
OUTCOME
CHECK
Catchment characteristics
- Land Uses
Residential
Commercial
Roads
0
0
4
Ha
Ha
Ha
Residential
Commercial
Roads
Weighted average
0
0
1
1
260
2
RL 3.8
0.3
RL 4.1
m
m
m
m
m
- Fraction Impervious
Conceptual Design
Basin Area
Notional permanent pool depth
Permanent pool level of sedimentation basin
Basin extended detention
Overflow level
1
100
year
year
minutes
mm/hr
mm/hr
Singapore
110
283
1
1
1.2
3.1
m /s
3
m /s
87%
260
4
0.4
2
m
L:W (1)
m
- Internal batters
Cross Section Batter Slope (below permanent pool depth)
V:H (1)
86
52
yes - OK
Vs>Vs,5year
Sediment clean-out frequency, given Vs
4. Design inflow systems
Scour protection and/or energy dissipation provided
years
yes
1.5m x 3m
RL 3.8
yes
LxB
m
-
- Connection Pipe
Connection pipe dimension
Connection pipe invert level
802
RL 2.7
mm dia
m
RL 4.1
11
0.3
0.3
m
m
m
m
6. Vegetation Specification
HOLD
Page 4-33
4.8.4
Construction drawings
Page 4-34
4.9
References
Page 4-35
Page 1
5
Chapter 5
Contents
5.1
Introduction............................................................................................................. 3
5.2
5.2.1
5.2.2
5.2.3
5.2.4
5.2.5
5.2.6
5.2.7
5.3
5.3.1
5.3.2
5.3.3
5.3.4
5.3.5
5.3.6
5.3.7
5.3.8
5.3.9
5.3.10
5.4
5.4.1
5.4.2
5.4.3
5.4.4
5.5
5.6
5.6.1
5.6.2
5.6.3
5.7
5.7.1
5.7.2
5.7.3
5.7.4
5.7.5
5.7.6
5.7.7
5.7.8
5.7.9
5.7.10
5.8
References ............................................................................................................. 35
Page 2
5.1 Introduction
Vegetated swales are used to remove coarse and medium sediments and convey stormwater in
lieu of or with underground pipe drainage systems. They are commonly combined with buffer
strips and bioretention systems (refer Chapter 6 - Bioretention Swales). Swales utilise overland
flow and mild slopes to convey water slowly downstream. They protect waterways from
damage by erosive flows from frequent storm events because swale flow velocities are slower
than piped systems.
The interaction between stormwater flow and vegetation within swale systems facilitates
pollutant settlement and retention. Even swales with relatively low vegetation height (such as
mown grass) can achieve significant sediment deposition rates provided flows are well
distributed across the full width of the swale and the longitudinal grade of the swale is kept low
enough (typically less than 4 % grade) to maintain slower flow conditions.
Swales alone cannot provide sufficient treatment to meet current stormwater treatment/ water
quality objectives, but can enable water quality objectives to be met by providing an important
pretreatment function for other ABC Waters Design Features in a treatment train. Swales are
particularly good at coarse sediment removal and can provide the necessary pretreatment for
tertiary treatment systems such as wetlands and bioretention basins. Some examples of
swales are provided in Figure 5.1.
Buffer strips (or buffers) are areas of vegetation through which runoff flows (as overland flow) to
a discharge point. Sediment is deposited as flow passes through vegetation over a shallow
depth. Effective treatment relies upon well distributed sheet flow. Vegetation slows flow
velocities, encouraging coarse sediments to settle out of the water column. With the
requirement for uniformly distributed flow, buffer strips are suited to treat road runoff in
situations where road runoff is discharged via flush kerbs or through regular kerb cut-outs. In
these situations, buffer strips (located in the swale batter) can form part of a roadside swale
system that receives the distributed inflows from the adjoining road pavement. The coverage of
buffer strips in this chapter is limited to their application as part of a roadside swale system only.
The reader is referred to Australian Runoff Quality (Engineers Australia 2006) for additional
discussion on buffer strip design and for worked examples.
Page 3
Landscape Design
Swales may be located within parkland areas, easements, car parks or along roadway corridors
within footpaths or centre medians. Landscape design of swales and buffer strips along the road
edge can assist in defining the boundary of road or street corridors as well as enhancing
landscape character. The landscape design of swales and buffers must address stormwater
quality objectives whilst also incorporating landscape functions. As such, it is important that
swales and buffers are carefully designed to integrate with the surrounding landscape
character.
5.2.2
Hydraulic Design
Typically, swales are applicable for smaller scale contributing catchments up to 1 ha. If larger
than this, flow depths and velocities are such that the water quality improvement function of the
swale, and its long-term function may be compromised. For water quality improvement, swales
need only focus on ensuring frequent storm flows (typically up to the 3 month ARI flow) are
conveyed within the swale profile. In most cases, however, a swale will also be required to
provide a flow conveyance function as part of a minor drainage and/or major drainage system.
In particular, swales located within road reserves must also allow for safe use of adjoining
roadway, footpaths and bike paths by providing sufficient conveyance capacity to satisfy current
engineering infrastructure design requirements as defined by the Code of Practice on Surface
Water Drainage (PUB 2006). In some cases, flows will encroach onto the road surface to
acceptable levels. It may also be necessary to augment the capacity of the swale with
underground pipe drainage to satisfy the road drainage criteria. This can be achieved by
locating overflow pits (field inlet pits) along the invert of the swale that discharge into an
underlying pipe drainage system. Careful attention should be given to the design of overflow
pits to ensure issues of public safety (particularly when raised grates are being used) and
aesthetic amenity are taken into account.
The longitudinal slope of a swale is another important hydraulic design consideration. Swales
generally operate best with longitudinal slopes of between 1 % and 4 %. Slopes milder than
this can become waterlogged and have stagnant ponding. However, the use of subsoil drains
beneath the invert of the swale can alleviate this problem by providing a pathway for drainage of
any small depressions that may form along the swale. For longitudinal slopes steeper than 4 %,
check banks (e.g. small rock walls) along the invert of the swale, or equivalent measures, can
help to distribute flows evenly across the swales, as well as reduce velocities and potential for
scour. Check dams are typically low level rock weirs (e.g. 100 mm) that are constructed across
the base of a swale. It is also important to protect the vegetation immediately downstream of
check dams. Rock pitching can be used to avoid erosion.
A rule of thumb for locating check dams is for the crest of a downstream check dam to be at 4
% grade from 100 mm below the toe of an upstream check dam (refer Figure 5.2). The impact
of check dams on the hydraulic capacity of the swale must be assessed as part of the design
process.
4% slope
Check dams (100mm high)
100mm
Swale base
Page 4
depth x velocity within the swale, at crossings and adjacent to pedestrian and bicycle pathways
to ensure public safety criteria are satisfied. These are:
depth x velocity < 0.6 m2/s for low risk locations and 0.4 m2/s for high risk locations (e.g.
where pedestrian traffic is expected to be high)
5.2.3
Vegetation Types
Swales can use a variety of vegetation types including turf, sedges and tufted grasses.
Vegetation is required to cover the whole width of the swale, be capable of withstanding design
flows and be of sufficient density to prevent preferred flow paths and scour of deposited
sediments (Figure 5.3).
Figure 5.3
Swale systems: heavily vegetated (left), use of check dams (centre), grass
swale with elevated crossings (right)
Turf swales are commonly used in residential areas. Turf swales should be mown and well
maintained in order for the swale to operate effectively over the long term. Swales that are
densely vegetated with tall vegetation offer improved sediment retention by slowing flows more
and providing enhanced sedimentation for deeper flows. However, densely vegetated swales
have higher hydraulic roughness and therefore require a larger area and/ or more frequent use
of swale field inlet pits to convey flows compared to turf swales. Densely vegetated swales can
become features of the urban landscape and once established, require minimal maintenance
and are hardy enough to withstand large flows (Figure 5.4).
Figure 5.4
The reader should consult the National parks Board of Singapore more specific guidance on the
selection of appropriate vegetation for swales and buffers.
5.2.4
Driveway Crossings
A key consideration when designing swales along roadways is the requirement for provision of
driveway crossings (or crossovers). Driveway crossings can be at-grade or elevated. Atgrade crossings follow the profile of the swale (e.g. like a ford), while elevated crossings are
raised above the invert of the swale (e.g. like a bridge deck or culvert, see Figure 5.5).
Page 5
Crossings constructed at-grade reduce the maximum allowable swale batter slopes to
approximately 1 in 9 to ensure vehicles can traverse the crossing without bottoming out. This
means the swale will have a shallow profile thus reducing its flow conveyance capacity. Atgrade crossings are typically cheaper to construct than elevated crossings, however they need
to be constructed at the same time as the swale to avoid damaging the swale. This imposes a
fixed driveway location on each allotment, which can potentially constrain future house layouts.
At-grade crossings are best suited to developments where the spacing between crossings is
typically more than 15 m.
Figure 5.5
At-grade (left) under construction with trees yet to be established, preconstructed at-grade (centre) and elevated driveway crossings to allow
vehicle access across swales (right)
Elevated crossings are not appropriate in all street applications; however, where appropriate,
they can be designed as streetscape features. They also provide an opportunity for locating
check dams (to distribute flows) or to provide temporary ponding above a bioretention system
(refer Chapter 6 Bioretention Swales). A major limitation with elevated crossings can be their
high life cycle costs compared to at-grade crossings (particularly in dense urban
developments) due to the need for on-going maintenance. Safety concerns with traffic
movement adjacent to elevated crossings and the potential for blockages of small culvert
systems beneath the crossing are other possible limitations. These limitations can be overcome
by careful design through the use of spanning crossings rather than using small culverts and
through the use of durable decking materials in place of treated timber.
5.2.5
Traffic Controls
Another design consideration is keeping traffic and building materials off swales (particularly
during the building phase of a development). If swales are used for parking then the topsoil will
be compacted and the swale vegetation may be damaged beyond its ability to regenerate
naturally. In addition, vehicles driving on swales can cause ruts along the swale that can create
preferential flow paths that will diminish the swales water quality treatment performance as well
as creating depressions that can retain water and potentially become mosquito breeding sites.
To prevent vehicles driving on swales and inadvertent placement of building materials, it is
necessary to consider appropriate traffic control solutions as part of the swale design. These
can include planting the swale with dense vegetation that will discourage the movement of
vehicles onto the swale or, if dense vegetation cannot be used, providing physical barriers such
as kerb and channel (with breaks to allow distributed water entry to the swale) or bollards and/
or street tree planting.
Kerb and channel should be used at all corners, intersections, cul-de-sac heads and at traffic
calming devices to ensure correct driving path is taken. For all of these applications, the kerb
and channel is to extend 5 m beyond tangent points. The transition from barrier or lay back type
kerb to flush kerbs and vice versa is to be done in a way that avoids creation of low points that
cause ponding onto the road pavement.
Where road edge guide posts or bollards are used, consideration should be given to
intermixing mature tree plantings with the bollards to break the visual monotony created by a
Page 6
Figure 5.6
5.2.6
Traffic bollards mixed with street trees to protect swale from vehicles
Roof water should be discharged onto the surface of the swale for subsequent conveyance and
treatment by the swale (and downstream treatment measures) before being discharged to
receiving aquatic environments. Depending on the depth of the roof water drainage system and
the finished levels of the swale, this may require the use of a small surcharge pit located within
the invert of the swale to allow the roof water to surcharge to the swale. Any residual water in
the surcharge pit can be discharged to the underlying subsoil drainage by providing perforations
in the base and sides of the surcharge pit. If a surcharge pit is used, an inspection chamber
along the roof water drainage line is to be provided within the property boundary. Surcharge pits
are discussed further in Section 5.3.4.3.
Roof water should only be directly connected to an underground pipe drainage system if an
appropriate level of stormwater treatment is provided along (or at the outfall of) the pipe
drainage system.
5.2.7
Services
Swales located within standard road reserves are to have services located within the services
corridors in accordance with government requirements. Sewers located beneath swales are to
be fully welded polyethylene pipes with rodding points. Care should be taken to ensure the
service conduits do not compromise the performance of the swale. Consideration will also need
to be given to access to services for ongoing maintenance without the need to regularly disrupt
or replace the swale.
Page 7
5. Verify design
a. Scour velocity checks
b. Safety checks - depth x velocity; maximum depth over crossings
c. Confirm treatment performance
Each of these design steps is discussed in the following sections. A worked example
illustrating application of the design process on a case study site is presented in
Section 5.7.
Page 8
5.3.1
Before commencing detailed design, the designer should first undertake a preliminary
check to confirm the swale outlined on the concept design is adequate to deliver the
level of stormwater quality improvement inferred within the concept design
documentation. The swale treatment performance curves shown in Figure 5.7 to
Figure 5.9 can be used to undertake this verification check.
The curves in Figure 5.7 to Figure 5.9 were derived using the Model for Urban
Stormwater Improvement Conceptualisation (MUSIC), assuming the swale is a stand
alone system (i.e. not part of a treatment train). The curves show the total suspended
solid (TSS), total phosphorus (TP) and total nitrogen (TN) removal performance for a
typical swale design, being:
Base width 1 m
Side slopes 1 in 9
The curves in Figure 5.7 to Figure 5.9 are generally applicable to swale applications
within residential, industrial and commercial land uses.
If the configuration of the swale concept design is significantly different to that
described above, then a stormwater quality model such as MUSIC should be used in
preference to the curves in Figure 5.7 to Figure 5.9. The detailed designer should also
use the stormwater quality model to verify swale concept designs that are part of a
treatment train.
Swales should form part of the stormwater treatment train as they will not achieve
load-based pollutant reduction objectives on their own. Therefore, other stormwater
quality best management practices should be incorporated into the surrounding
catchment to augment the stormwater treatment performance of any proposed swale
system.
Page 9
Ve g e t at io n H e ig h t = 0.25m
% T S S R educ tion
70%
60%
50%
40%
30%
1% Slo p e
20%
3% Slo p e
10%
5% Slo p e
0%
0
10
12
% T S S R educ tion
70%
60%
50%
40%
0.05m Ve g
30%
0.15m Ve g
0.25m Ve g
20%
0.5m Ve g
10%
0%
0
10
12
Figure 5.7
Page 10
Ve g e t at io n H e ig h t = 0.25m
80%
% T P R educ tion
70%
60%
50%
40%
30%
1% Slo p e
20%
3% Slo p e
10%
5% Slo p e
0%
0
10
12
L o n g it u d in al Slo p e = 3%
80%
% T P R educ tion
70%
60%
50%
40%
0.05m Ve g
30%
0.15m Ve g
0.25m Ve g
20%
0.5m Ve g
10%
0%
0
10
12
Figure 5.8
Page 11
% T N R educ tion
70%
60%
50%
40%
30%
1% Slo p e
20%
3% Slo p e
10%
5% Slo p e
0%
0
10
12
Lo n g it u d in al Slo p e = 3%
80%
0.05m Ve g
70%
% T N R educ tion
0.15m Ve g
0.25m Ve g
60%
0.5m Ve g
50%
40%
30%
20%
10%
0%
0
10
12
Figure 5.9
Page 12
5.3.2
Two design flows are required to be estimated for the design of a swale, particularly
where they are designed within a road reserve. These are to size the swale for
conveyance of flows rather than treatment:
minor flood flow (2-10 year ARI; typically the 5 year ARI peak discharge) to allow
minor floods to be safely conveyed
major flood flow (50-100 year ARI) to check flow velocities, velocity depth criteria,
conveyance within road reserve, and freeboard to adjoining property.
The Code of Practice on Surface Water Drainage (PUB 2006) identifies the Rational
Method as the procedure most commonly used to estimate peak flows from small
catchments in Singapore.
5.3.3
Allowable width given the proposed road reserve and/ or urban layout
How flows will be delivered into a swale (e.g. cover requirements for pipes or
kerb details)
Vegetation height
Longitudinal slope
Provision of crossings
Depending on which of the above characteristics are fixed, other variables may be
adjusted to derive the optimal swale dimensions for the given site conditions. The
following sections outline some considerations in relation to configuring a swale.
5.3.3.1
The maximum swale width needs to be identified early in the design process as it
dictates the remaining steps in the swale design process. The maximum width of
swale is usually determined from an urban layout and at the concept design stage.
Where the swale width is not constrained by an urban layout (e.g. when located within
a large open space area), then the width of the swale may be selected based on
consideration of landscape objectives, maximum side slopes for ease of maintenance
and public safety, hydraulic capacity required to convey the desired design flow, and
treatment performance requirements.
Selection of an appropriate side slope for swales located in parks, easements or
median strips is heavily dependent on site constraints, and swale side slopes are
typically between 1 in 10 and 1 in 4.
For swales located adjacent to roads, side slopes will typically be dictated by the
driveway crossing. Where there are no driveway crossings then the maximum swale
side slopes will be established from ease of maintenance and public safety
considerations. Where elevated crossings are used, swale side slopes would
typically be between 1 in 6 and 1 in 4. Elevated crossings will require provision for
drainage under the crossings with a culvert or similar. Where at grade crossings are
used, swale side slopes are typically 1 in 9. The selection of crossing type should be
made in consultation with urban and landscape designers.
Page 13
5.3.3.2
Provided the water quality function of the swale is met, the maximum length of a swale
is the distance along a swale before an overflow pit (field inlet pit) is required to drain
the swale to an underlying pipe drainage system.
The maximum length of a swale located within parkland areas and easements is
calculated as the distance along the swale to the point where the flow in the swale
from the contributing catchment (for the specific design flood frequency) exceeds the
bank full discharge capacity of the swale. For example, if the swale is to convey the
minor flood flow without overflowing, then the maximum swale length would be
determined as the distance along the swale to the point where the minor flood flow
from the contributing catchment is equivalent to the bank full flow capacity of the swale
(bank full flow capacity is determined using Mannings equation as discussed below).
The maximum length of a swale located along a roadway is calculated as the distance
along the swale to the point where flow on the adjoining road pavement (or road
reserve) no longer complies with PUB road design standards (for both the minor and
major flood flows) as defined by the Code of Practice on Surface Water Drainage
(PUB 2006).
5.3.3.3
Mannings equation is used to calculate the flow capacity of a swale. This allows the
flow rate and flood levels to be determined for variations in swale dimensions,
vegetation type and longitudinal grade. Mannings equation is given by:
Q=
A R2/3 S1/2
n
Equation 5.1
Page 14
10
20
40
60
80
90
105
200
5.3.4
Inflows to swales can be via distributed runoff (e.g. from flush kerbs along a road) or
point outlets such as pipe culverts. Combinations of these two inflow pathways can
also be used.
5.3.4.1
Distributed Inflow
Page 15
5.3.4.2
Buffer Requirements
There are several design guides that may to be applied to ensure buffers operate to
improve water quality and provide a pretreatment role. Key design parameters of
buffer systems are:
Maintaining flow depths less than vegetation heights. This may require flow
spreaders, or check dams.
Minimising the slope of the buffer. It is best if slopes can be kept below 5 %,
however buffers can still perform well with slopes up to 20 % provided flows are
well distributed. The steeper the buffer the more likely flow spreaders will be
required to avoid rill erosion.
Road edge
Buffer strip
5.3.4.3
Concentrated Inflow
Page 16
need to be accessible so that any build up of coarse sediment and debris can be monitored and
monitored and removed if necessary.
Figure 5.13 shows an example of a typical surcharge pit discharging into a swale.
Surcharge pits are not considered good practice, due to additional maintenance issues
and mosquito breeding potential and should therefore be avoided where possible.
Secured grate
Drainage holes to be drilled
in base of pit
PLAN
ELEVATION
Figure 5.13 Example of Surcharge Pit for Discharging Concentrated Runoff into
a Swale
Surcharge pits are most frequently used when allotment runoff is required to cross a
road into a swale on the opposite side of the road or for allotment and roof runoff
discharging into shallow profile swales. Where allotment runoff needs to cross under a
road to discharge into a swale it is preferable to combine the runoff from more than
one allotment to reduce the number of crossings required under the road pavement.
5.3.5
5.3.5.1
Potential scour velocities are checked by applying Mannings equation to the swale
design to ensure the following criteria are met:
less than 0.5 m/s for minor flood (2 to 10 year ARI; typically the 5 year ARI)
discharge
less than 2.0 m/s and typically less than 1.0 m/s for major flood (50 to 100
year ARI) discharge.
5.3.5.2
As swales are generally accessible by the public, it is important to check that depth x
velocity within the swale, at crossings and adjacent to pedestrian and bicycle
pathways, satisfies the following public safety criteria:
2
depth x velocity of < 0.4 m /s is not exceeded for all flows up to the major
design event, as defined in relevant local government guidelines
5.3.5.3
If the previous two checks are satisfactory then the swale design is adequate from a
conveyance function perspective and it is now necessary to reconfirm the treatment
performance of the swale by reference back to the information presented in Section
5.3.1.
Page 17
5.3.6
To size a swale field inlet pit, two checks should be made to test for either drowned or
free flowing conditions. A broad crested weir equation can be used to determine the
length of weir required (assuming free flowing conditions) and an orifice equation used
to estimate the area between openings required in the grate cover (assuming drowned
outlet conditions). The smaller of the two pit configurations would normally suffice
although other consideration such as the required pit to fit the stormwater pipe
conveying overflows to the receiving waters need also to be considered. In addition a
blockage factor is to be used, that assumes the field inlet is 50 % blocked.
Q weir = B Cw L h3/2
Where
Qweir
Equation 5.2
= flow over weir (pit) (m3/s)
Cw
Once the length of weir is calculated, a standard sized pit can be selected with a
perimeter at least the same length of the required weir length.
For drowned outlet conditions (orifice equation):
Q orifice = B Cd A 2 g h
Where
Equation 5.3
Qorifice
Cd
= 9.80665 m/s2
When designing grated field inlet pits reference should be made to the procedure
described in the Code of Practice on Surface Water Drainage (Public Utilities Board
2006)
5.3.7
The reader should consult the National Parks Board for guidance of appropriate plant
species and planting densities applicable for stormwater swales in Singapore.
5.3.9
Consider how maintenance is to be performed on the swale (e.g. how and where is
access available, where is litter likely to collect etc.). A specific maintenance plan and
Page 18
schedule should be developed for the swale, either as part of a maintenance plan for
the whole treatment train, or for each individual asset. Guidance on maintenance
plans is provided in Section 5.5.
5.3.10 Design Calculation Summary
The following design calculation table can be used to summarise the design data and
calculation results from the design process.
Calculation Task
Catchment Characteristics
Catchment Area
Catchment Land Use (i.e. residential, Commercial etc.)
Catchment Slope
ha
%
Conceptual Design
Swale Top Width
Swale Length
Swale Location (road reserve/ park/other)
Road Reserve Width
1
m
m
m
%
%
%
minutes
Minor Storm (I2 I10
Major Storm (I50-100
year ARI)
year ARI)
mm/hr
mm/hr
m /s
3
m /s
m
%
mm
Verification Checks
Velocity for 2-10 year ARI flow (< 0.25 - 0.5 m/s)
Velocity for 50-100 year ARI flow (< 2 m/s)
2
Velocity x Depth for 50-100 year ARI (< 0.4 m /s)
Depth of Flow over Driveway Crossing for 50-100 year ARI (< 0.3 m)
Treatment Performance consistent with Step 1
Yes/ No
m/s
m/s
2
m /s
m
LxW
Page 19
5.4
Typical Values
1 % to 4 %
1 in 4 to 1 in 10
Maximum 1 in 9
1 in 4 to 1 in 10
0.15 to 0.3
0.03 to 0.05
0.25 - 0.5 m/s
1.0 - 2.0 m/s
Construction advice
This section provides general advice for the construction of swales. It is based on
observations from construction projects around Australia.
5.4.1
Ensure traffic and deliveries do not access swales during construction. Traffic can
compact the soil and cause preferential flow paths, deliveries can smother vegetation.
Wash down wastes (e.g. silt, concrete) can disturb vegetation and cause uneven
slopes along a swale. Swales should be protected during construction phase and
controls implemented to avoid wash down wastes.
5.4.3
It is good practice to check the operation of inlet erosion protection measures following
the first few rainfall events. It is important to check for these early in the systems life,
to avoid continuing problems. Should problems occur in these events the erosion
protection should be enhanced.
5.4.4
Page 20
Routine inspection of inlet points (if the swale does not have distributed
inflows), surcharge pits and field inlet pits to identify any areas of scour, litter
build up and blockages.
Removal of plants that have died and replacement with plants of equivalent
size and species as detailed in the plant schedule.
Inspections are also recommended following large storm events to check for scour. All
maintenance activities must be specified in a maintenance plan (and associated
maintenance inspection forms) to be developed as part of the design procedure.
Maintenance personnel and asset managers will use this plan to ensure the swales
continue to function as designed. Maintenance plans and forms must address the
following:
inspection frequency
maintenance frequency
equipment needs
Page 21
maintenance techniques
public safety
access issues
design details
5.6
Checking tools
This section provides a number of checking aids for designers and approval
authorities. In addition, advice on construction techniques and lessons learnt from
building swale systems are provided.
Checklists are provided for:
Design assessments
5.6.1
The Design Assessment Checklist on the following page presents the key design
features that are to be reviewed when assessing a design of a swale. These
considerations include configuration, safety, maintenance and operational issues that
need to be addressed during the design phase. If an item receives an N when
reviewing the design, referral is made back to the design procedure to determine the
impact of the omission or error. In addition to the checklist, a proposed design is to
have all necessary permits for installation.
5.6.2
Construction Checklist
The Construction Checklist on the following page presents the key items to be
reviewed when inspecting the swale during and at the completion of construction. The
checklist is to be used by Construction Site Supervisors and compliance inspectors to
ensure all the elements of the swale have been constructed in accordance with the
design. If an item receives an N in satisfactory criteria then appropriate actions must
be specified and delivered to rectify the construction issue before final inspection signoff is given.
5.6.3
The Operation and Maintenance forms on the following pages should be used
whenever an inspection is conducted and kept as a record on the asset condition and
quantity of removed pollutants over time. Inspections should occur every 1 to 6
months depending on the size and complexity of the swale system, and the stage of
development (i.e. inspections should be more frequent during building phase and until
the swale landform has stabilised).
Page 22
DA No.:
Swale Location:
3
Hydraulics:
Area:
Swale Area (m ):
TREATMENT
Page 23
Inspected by:
Date:
Site:
Time:
Weather:
Constructed By:
Contact during visit:
Checked
Items Inspected
Satisfactory
Items Inspected
Checked
Satisfactory
Structural Components
13. Location and levels of pits as
designed
14. Safety protection provided
15. Location of check dams as designed
16. Swale crossings located/ built as
designed
17. Pipe joints/ connections as designed
18. Concrete and reinforcement as
designed
19. Inlets appropriately installed
20. Inlet erosion protection installed
21. Set down to correct level for flush
kerbs
B. EROSION AND SEDIMENT CONTROL
22. Silt fences and traffic control in place
23. Stabilisation immediately following
earthworks
C. OPERATIONAL ESTABLISHMENT
Vegetation
FINAL INSPECTION
1. Confirm levels of inlets and outlets
5. Vegetation as designed
COMMENTS ON INSPECTION
ACTIONS REQUIRED:
Page 24
1 to 6 monthly
Date of Visit:
Location:
Description:
Site Visit by:
INSPECTION ITEMS
Page 25
Page 26
100m
7m
Road
5m
15m
35m
Swale
Footpat
h
Allotment
(Max 1 in 10 side
slopes with 1.2m base)
Buffer
Figure 5.14
The contributing catchment area includes 35 m width and 100m length residential
allotments on one side, a 7m wide road pavement surface and a 1.5 m footpath and
5.0 m swale and services easement (depicted in Figure 5.14, examples of similar
systems are illustrated in Figure 5.15). The area is 100 m long with a 3 % slope.
Allotment runoff is to be discharged under a footpath via a conventional stormwater
pipe directly into the swale system with appropriate erosion control.
Page 27
Figure 5.15
Provide traffic management measures that will preclude traffic damage (or
parking) within the buffer or swale (e.g. bollards or parking bays);
Provide check dams to control velocities and spread flows (potentially using
crossings);
Convey 5-year ARI flows within the swale and underground pipe system.
This worked example focuses on the design of the buffer strip and vegetated swale
conveyance properties. Analyses to be undertaken during the detailed design phase
include the following:
Select vegetation such that the hydraulic capacity of the swale is sufficient
Configure the street kerb details such that sheet flow is achieved through the
buffer strip
Swale shall convey at least all flows up to the peak 5-year ARI storm event.
Page 28
5.7.1.2
Site Characteristics
Catchment area:
3,500 m2
850 m
500 m
Total = 4,850 m
(lots)
(roads and concrete footpath)
(swale and services easement)
Land use/surface type Residential lots, roads/concrete footpaths, swale and service
easement.
Overland flow slope:
Total main flow path length = 100m @ 3% slope
Soil type:
Clay
Fraction impervious:
lots f = 0.65
roads/footpath f = 1.00
5.7.2
Interpretation of Figure 5.7 to Figure 5.9 with the input parameters below is used to
estimate the reduction performance of the swale system to ensure the design will
achieve target pollutant reductions. To interpret the graphs the area of swale base to
the impervious catchment needs to be estimated. For a base width of 1.2 m, the area
of swale base as percentage of the contributing impervious catchment area:
1.2 x 100/ [(0.65 x 3500) + (1.0 x 850) + (0.1 x 500)] = 3.8 %
From the figures using an equivalent area in the reference site, it is estimated that,
depending on the height of the vegetation, pollutant reductions are between 70% and
82% for TSS, 47% to 59% for TP and 13% to 22% for TN respectively.
5.7.3
Page 29
ARI
Intensity
5yr
166 mm/hr
100yr
275 mm/hr
5.7.4
5.7.4.1
0.2m
1
10
2m
5.7.4.2
1
10
1.2m
2m
The capacity of the swale is firstly estimated at the most downstream point. It is
considered to be the critical point in the swale as it has the largest catchment and has
the mildest slope. Flow velocities will also need to be checked at the downstream end
of the steep section of swale.
The worked example firstly considers the swale capacity using a turf grass surface
with a vegetation height of 100 mm. An extension of the worked example is to
investigate the consequence of using 300mm tall vegetation (e.g. sedges) instead of
grass.
A range of Mannings n values are selected for different flow depths appropriate for
grass. It is firstly assumed that the flow height for a 5-year ARI storm will be above the
Page 30
vegetation and therefore Mannings n is quite low. A figure of 0.04 is adopted. The
flow depth will need to be checked to ensure it is above the vegetation.
= (AR2/3So1/2)/n
Table 5.2 Mannings n and flow capacity variation with flow depth turf
3
Mannings n
Flow (m /s)
0.05
0.30
0.006
0.1
0.30
0.02
0.15
0.06
0.252
0.2
0.04
0.674
Page 31
adopted Mannings n values and the corresponding flow capacity of the swale for
different flow depths.
Table 5.3
Mannings n
Flow (m3/s)
0.05
0.35
0.004
0.1
0.32
0.002
0.15
0.30
0.05
0.2
0.30
0.09
It can be seen in Table 5.3 that the swale with current dimensions is not capable of
conveying a 5-year discharge of 0.15 m3/s if sedges are to be planted. Either the
swale depth would need to be increased or overflow pits provided to allow excess
water to bypass the swale.
This worked example continues using 100mm turf for the remainder.
5.7.5
There are two ways for flows to reach the swale, either directly from the road surface
or from allotments via an underground 100mm pipe.
Direct runoff from the road enters the swale via a buffer (the grass edge of the swale).
The pavement surface is set 60 mm higher than the start of the swale and has a taper
that will allow sediments to accumulate off the pavement surface in the first section of
the buffer. Flows from allotments will discharge into the base of the swale and
localised erosion protection is provided with grouted rock at the outlet point of the pipe.
5.7.6
5.7.6.1
Two velocity checks are performed to ensure vegetation is protected from erosion at
high flow rates. 5-year and 100-year ARI flow velocities are checked and need to be
kept below 0.5m/s and 2.0 m/s respectively.
Velocities are estimated using Mannings equation:
Firstly, velocities are checked at the most downstream location for the 5-year ARI (i.e.
3
slope = 3%, n = 0.07, Q5 = 0.15 m /s)
d5-year = 0.13 m
V5-year = 0.46 m/s < 0.5 m/s therefore OK
Secondly, velocities are checked at the most downstream location for the 100-year
3
ARI (i.e. slope = 3%, n = 0.04, Q5 = 0.24 m /s)
D100-year = 0.143 m
V100-year = 0.645 m/s < 2.0 m/s therefore OK
5.7.6.2
Check at critical points (bottom of entire swale) that velocity depth product is less than
0.4 during a 100-year ARI flow.
At bottom of swale:
V= 0.645 m/s, d= 0.143m; therefore V.d = 0.092 m2.s <0.4 therefore OK.
ABC Waters Stormwater Quality Management Guidelines
Page 32
5.7.6.3
As there has been no requirement to alter the swale geometry established for Swales
1 and 2 in Step 3, the same treatment performance identified in Step 1 still applies.
Where modifications to the swale geometry occur during the previous design steps, a
check of the new configuration with procedures identified in Step 1 is required to
ensure treatment performance is adequate.
5.7.7
As the swale can carry a five-year ARI discharge, overflow structures are not required
for this worked example. See Chapter 5 for an example including the design of an
overflow pit.
5.7.8
Traffic control in the worked example is achieved by using traffic bollards mixed with
street trees.
5.7.9
To compliment the landscape design of the area, a turf species is to be used. For this
application a turf with a height of 100 mm has been assumed. The landscape designer
will select the actual species. The establishment of vegetation in swales should be in
consultation with the National Parks Board of Singapore.
Page 33
Calculation Task
Catchment Characteristics (Swale 1)
Catchment Area
Catchment Land Use (i.e. residential, Commercial etc.)
Catchment Slope
0.485
Res
3
ha
%
Conceptual Design
Swale Top Width
Swale Length
Swale Location (road reserve/ park/other)
Road Reserve Width
1
5
100
Road res
13.5
m
m
m
Swale Area
TSS Removal
TP Removal
TN Removal
125
70
47
13
m
%
%
%
10
10
minutes
minutes
minutes
minutes
Swale 2
2-10 year ARI
50-100 year ARI
Identify Rainfall intensities
Swale 1
I2-10
I50-100
year ARI
I2-10
I50-100
year ARI
year ARI
166
275
mm/hr
mm/hr
Swale 2
mm/hr
mm/hr
year ARI
0.65
0.65
0.15
0.24
m /s
3
m /s
Base Width
Side Slopes 1 in
Longitudinal Slope
Vegetation Height
1.0
10
3
100
Mannings n
Swale Capacity
Maximum Length of Swale
0.04
0.63
<100
m3/s
m
Flush
Yes
N/A
Yes/ No
0.46
0.71
0.11
0.15
Yes
%
mm
m/s
m/s
2
m /s
m
LxW
LxW
Page 34
5.8
References
Barling RD & Moore ID 1993, 'The Role of Buffer Strips in the Management of
Waterway Pollution', in Woodfull J et al. (eds), The Role of Buffer Strips in the
Management of Waterway Pollution from Diffuse Urban and Rural Sources, LWRRDC
Occasional Paper No. 01/93, Canberra
CRCCH (Cooperative Research Centre for Catchment Hydrology) 2005, MUSIC: User
Guide, Manual for MUSIC Version 3.0, CRCCH, Melbourne
Duncan HP 1995, A Review of Urban Storm Water Quality Processes, Cooperative
Research Centre for Catchment Hydrology, Report 95/9, Melbourne, Australia
Engineers Australia 2006,
ACT,http://www.arq.org.au/
Australian
Runoff
Quality,
Engineers
Australia,
Public Utilities Board (2006). Code of Practice on Surface Water Drainage. Singapore.
50p.
Weibel SR, Weidner RB, Cohen JM & Christianson AG, 1996, Pesticides and Other
Contaminants in Rainfall and Runoff, Journal American Water Works Association, vol.
58, no. 8, August 1966, pp. 1075-1084
Page 35
Bioretention Swales
6
Chapter 6 Bioretention Swales
6.1
Introduction
6-1
6.2
6-4
6.2.1
6.2.2
6.2.3
6.2.4
6.2.5
6.2.6
6.2.7
6.3
6-8
6.3.1
6.3.2
Step 2: Determine Design Flows for the Swale Component ................................................ 6-12
6.3.3
Step 3: Dimension the Swale Component with Consideration to Site Constraints .............. 6-13
6.3.4
Step 4: Design Inflow Systems to Swale and Bioretention Components ............................. 6-15
6.3.5
6.3.6
6.3.7
6.3.8
6.3.9
6.3.10
6.3.11
6.3.12
6.4
6-27
6.4.1
6.4.2
6.4.3
6.4.4
6.5
Maintenance Requirements
6.5.1
6.6
6-33
6-36
6.6.1
6.6.2
6.6.3
6.6.4
6.6.5
6.6.6
6.6.7
6.6.8
6.6.9
6.6.10
6.6.11
6.6.12
6.6.13
6.7
References
6-48
6.1
Introduction
Figure 6.1
The bioretention swale treatment process operates by firstly filtering stormwater runoff
through surface vegetation associated with the swale. The bioretention component
then operates by percolating the runoff vertically through a prescribed filter media,
Page 6-1
which provides treatment through fine filtration, extended detention treatment and
biological uptake.
Bioretention swales also act to reduce flow velocities compared with piped systems
and thus provide protection to natural receiving waterways from frequent storm events
by disconnecting impervious areas from downstream waterways. The bioretention
component is typically located at the downstream end of the overlying swale cell (i.e.
immediately upstream of the swale overflow pit(s) as shown on Figure 6.2 or can be
provided as a continuous trench along the full length of a swale).
bioretention
Vegetated swale
Overflow pit
Road surface
bioretention
Vegetated swale
Filter media
Overflow
pit
Drainage layer
Figure 6.2
The choice of bioretention location within the overlying swale will depend on a number
of factors, including available area for the bioretention filter media and the maximum
batter slopes for the overlying swale. Typically, when used as a continuous trench
along the full length of a swale, the desirable maximum longitudinal grade of the swale
is 4%. For other applications, the desirable longitudinal slope of the bioretention zone
is either horizontal or as close as possible to encourage uniform distribution of
stormwater flows over the full surface area of bioretention filter media and allowing
temporary storage of flows for treatment.
Page 6-2
Bioretention swales are not intended to be infiltration systems in that the intent is to
prevent excessive stormwater exfiltrate from the bioretention filter media to the
surrounding in-situ soils. Rather, the typical design intent is to recover the percolated
stormwater runoff at the base of the filter media, within perforated under-drains, for
subsequent discharge to receiving waterways or to a storage facility for potential
reuse. Thus these systems are suited even when close to structures as long as steps
are taken to prevent exfiltration to surround soils through the use of a impervious liner
where necessary.
In some circumstances however, where the in-situ soils are appropriate and there is a
particular design intention to recharge local groundwater, it may be desirable to permit
the percolated stormwater runoff to infiltrate from the base of the filter media to the
underlying in-situ soils.
Page 6-3
Landscape Design
Hydraulic Design
Page 6-4
If the selected saturated hydraulic conductivity of the bioretention filter media is less
than 10 times that of the surrounding soils, it may be necessary to provide an
impermeable liner. Flexible membranes or a concrete casting are commonly used to
prevent excessive exfiltration. The greatest pathway of exfiltration is through the base
of a bioretention trench. If lining is required, it is likely that only the base and the sides
of the drainage layer (refer Section 6.2.5) will need to be lined.
A subsurface pipe is often used to prevent water intrusion into a road sub-base. This
practice is to continue as a precautionary measure to collect any water seepage from
bioretention swales located along roadways.
Bioretention system built on highly porous landscape may suitably promote exfiltration
to surrounding soils. In such circumstances, the designer must consider site terrain,
hydraulic conductivity of the in-situ soil, soil salinity, groundwater and building setback.
Further guidance in this regard is provided in Chapter 9 Infiltration.
6.2.4
Vegetation Types
Bioretention swales can use a variety of vegetation types including turf (swale
component only), sedges and tufted grasses. Vegetation is required to cover the
whole width of the swale and bioretention filter media surface, be capable of
withstanding design flows and be of sufficient density to prevent preferred flow paths
and scour of the media surface. Turf grasses should ideally be avoided where the soil
filter is as these are shallow rooted systems with inadequate penetration to the full
depth of the filter media and the turf stems inadequately prevent clogging at the
surface of the filter media. Therefore it is preferred that the vegetation for the
bioretention component of bioretention swales is sedges. The National Parks Board of
Singapore should be consulted on suitable vegetation species for bioretention
systems.
Dense vegetation planted along the swale component can also offer improved
sediment retention by reducing flow velocity and providing enhanced sedimentation for
deeper flows. However, densely vegetated swales have higher hydraulic roughness
and this will need to be considered in assessing their discharge capacity. Densely
vegetated bioretention swales can become features of an urban landscape and once
established, require minimal maintenance and are hardy enough to withstand large
flows.
6.2.5
Page 6-5
saturated hydraulic conductivity does not become too high such that it can no longer
sustain healthy vegetation growth.
The maximum saturated hydraulic conductivity should not exceed 500 mm/hr (and
preferably be between 50 - 200 mm/hr) in order to sustain vegetation growth.
The concept design stage will have established the optimal combination of filter media
saturated hydraulic conductivity and extended detention depth using a continuous
simulation modelling approach (i.e. MUSIC). Any adjustment of either of these two
design parameters during the detailed design stage will require the continuous
simulation modelling to be re-run to assess the impact on the overall treatment
performance of the bioretention basin.
As shown in Figure 6.3, a bioretention system can consist of three layers. The filter
media is the primary soil layer consisting typically of sandy-loam material. In addition
to the filter media, a drainage layer is also required to convey treated water from the
base of the filter media to the outlet via a perforated under-drains unless the design
intent is to allow the filtered water to discharge (exfiltrate) into insitu soil. The drainage
layer surrounds perforated under-drains and consist typically of fine gravel of 2-5 mm
particle size. In between the filter media layer and the drainage layer is the transition
layer consisting of clean sand (1mm) to prevent migration of the base filter media into
the drainage layer and into the perforated under-drains.
[Refer to the Bioretention Media Guidelines produced by FAWB1 (2007) for more
information.]
Vegetated swale
0.2-0.5 m
1-3 m
0.3-0.7 m
0.1 m
0.2 m
0.6-2.0 m
Figure 6.3
6.2.6
Traffic Controls
Another design consideration is keeping traffic and building material deliveries off
swales, particularly during the building phase of a development. If bioretention swales
are used for parking, then the surface will be compacted and vegetation damaged
beyond its ability to regenerate naturally. Compacting the surface of a bioretention
swale will reduce the hydraulic conductivity of filter media and lead to reduced
treatment. Vehicles driving on swales can cause ruts that can create preferential flow
paths that diminish the water quality treatment performance as well as creating
depressions that can retain water and potentially become mosquito breeding sites.
A staged construction and establishment method (see Section 6.4.2) affords protection
to the sub-surface elements of a bioretention swale from heavily sediment laden runoff
during the subdivision construction and allotment building phases. However, to
prevent vehicles driving on bioretention swales and inadvertent placement of building
1
Page 6-6
Services
Bioretention swales located within footpaths (i.e. road verges) must consider the
standard location for services within the verge and ensure access for maintenance of
services. Typically it is acceptable to have water and sewer services located beneath
the batters of the swale with any sewers located beneath bioretention swales to be
fully welded polyethylene pipes with rodding points.
Page 6-7
Page 6-8
6.3.1
Before commencing detailed design, the designer should first undertake a preliminary
check to confirm the bioretention swale treatment area from the concept design is
adequate to deliver the required level of stormwater quality improvement. A
conceptual design of a bioretention basin is normally typically undertaken prior to
detailed design. The performance of the concept design must be checked to ensure
that stormwater treatment objectives will be satisfied.
The treatment performance curves shown in Figure 6.4 to Figure 6.6 reflect the
treatment performance of the bioretention component only and will be conservative as
they preclude the sediment and nutrient removal performance of the overlying swale
component. Notwithstanding this, the performance of the swale component for
nitrogen removal is typically only minor and thus the sizing of the bioretention
component will typically be driven by achieving compliance with best practice load
reduction targets for Total Nitrogen. Therefore, by using the performance curves
below, the designer can be confident that the combined performance of the swale and
bioretention components of a bioretention swale will be similar to that shown in the
curves for total Nitrogen and will exceed that shown for Total Suspended Sediment
and total Phosphorus.
These curves are intended to provide an indication only of appropriate sizing and do
not substitute the need for a thorough conceptual design process. Nevertheless it is a
useful visual guide to illustrate the sensitivity of bioretention treatment performance to
the ratio of bioretention treatment area and contributing catchment area. The curves
allow the designer to make a rapid assessment as to whether the bioretention trench
component size falls within the optimal size range or if it is potentially under or oversized.
The curves in Figure 6.4 to Figure 6.6 show the total suspended solid (TSS), total
phosphorus (TP) and total nitrogen (TN) removal performance for a typical bioretention
basin design with the following configurations:
Filter media saturated hydraulic conductivity (k) = 180 mm/hr (0.5 x 10-4 m/s)
and 360mm/hr (1 x 10-4 m/s)
The curves in Figure 6.4 to Figure 6.6 are generally applicable to bioretention swale
applications within residential, industrial and commercial land uses.
If the characteristics of the bioretention component of the bioretention swale concept
design are significantly different to that described above, then the curves in Figure 6.4
to Figure 6.6 may not provide an accurate indication of treatment performance. In
these cases, the detailed designer should use MUSIC to verify the performance of the
bioretention swale.
Page 6-9
k s at=180mm/hr
100%
90%
80%
T S S R emoval (% )
70%
60%
50%
40%
No E xtended D etention
30%
20%
10%
0%
0
k s at = 360mm/hr
100%
90%
80%
T S S R emoval (% )
70%
60%
50%
40%
30%
No E xtended D etention
100mm E xtended D etention
20%
200mm E xtended D etention
10%
0%
0
Figure 6.4 Bioretention system TSS removal performance (Reference: Station 43)
Page 6-10
k s at=180mm/hr
90%
80%
70%
T P R emoval (% )
60%
50%
40%
30%
No E xtended D etention
100mm E xtended D etention
20%
200mm E xtended D etention
300mm E xtended D etention
10%
0%
0
k s at=360mm/hr
80%
70%
60%
T P R emoval (% )
50%
40%
30%
No E xtended D etention
100mm E xtended D etention
20%
10%
0%
0
Figure 6.5
Page 6-11
k s at=180mm/hr
60%
55%
50%
45%
T N R emoval (% )
40%
35%
30%
25%
20%
No E xtended D etention
100mm E xtended D etention
15%
10%
300mm E xtended D etention
5%
0%
0
k s at=360mm/h
50%
45%
40%
T N R emoval (% )
35%
30%
25%
20%
No E xtended D etention
15%
10%
5%
0%
0
Figure 6.6
6.3.2
6.3.2.1
Minor (frequent) storm conditions (typically 5 year ARI) to size the hydraulic
structures to safely convey storm flows of frequent/minor events within the
Page 6-12
swale and not increase any flooding risk compared to conventional stormwater
systems
6.3.2.2
Major flood flow (50 to 100 year ARI) to check flow velocities, velocity depth
criteria, conveyance within road reserve, and freeboard to adjoining property.
Design Flow Estimation
A range of hydrologic methods can be applied to estimate design flows. As the typical
catchment area should be relatively small (<50 ha) the Rational Method design
procedure is considered to be a suitable method for estimating design peak flows.
6.3.3
allowable width given the proposed road reserve and/ or urban layout
how flows are delivered into a swale (e.g. cover requirements for pipes or kerb
details)
vegetation height
longitudinal slope
Depending on which of the above factors are fixed, the other variables can be adjusted
to derive the optimal swale dimensions for the given site conditions. The following
sections outline some considerations in relation to dimensioning a swale.
6.3.3.1
The maximum width of swale is usually determined from an urban layout and at the
concept design stage, and should be in accordance with relevant local guidelines or
standards of the Public Utilities Board. Where the swale width is not constrained by an
urban layout (e.g. when located within a large parkland area) then the width of the
swale can be selected based on consideration of landscape objectives, maximum side
slopes for ease of maintenance and public safety, hydraulic capacity required to
convey the desired design flow, and treatment performance requirements. Swale side
slopes are typically between 1 in 10 and 1 in 4. The maximum swale width needs to
be identified early in the design process as it dictates the remaining steps in the swale
design process.
For swales located adjacent to residential roads, the types of driveway crossing used
will typically dictate batter slopes. Where there are no driveway crossings, the
maximum swale side slopes will be established from ease of maintenance and public
safety considerations. Generally at-grade crossings, are preferred which require the
swale to have 1:9 side slopes with a nominal 0.5 m flat base to provide sufficient
transitions to allow for traffic movement across the crossing. Flatter swale side slopes
can be adopted but this will reduce the depth of the swale and its conveyance
capacity. Where elevated crossings are used, swale side slopes would typically be
between 1 in 6 and 1 in 4. Elevated crossings will require provision for drainage under
the crossings with a culvert or similar. The selection of crossing type should be made
in consultation with urban and landscape designers.
Page 6-13
6.3.3.2
The maximum length of a swale is the distance along a swale before an overflow pit
(or field inlet pit) is required to drain the swale to an underlying pipe drainage system.
The maximum length of a swale located along a roadway is calculated as the distance
along the swale to the point where flow on the adjoining road pavement (or road
reserve) no longer complies with the local standards for road drainage (for both the
minor and major flood flows). This is often related to the discharge capacity of the
swale and is calculated as the distance along the swale to the point where the flow in
the swale (for the specific design flood frequency) exceeds the bank full capacity of the
swale. For example, if the swale is to convey the minor flood flow (typically the 5 year
ARI event in accordance to the Singapore Code of Practice for Surface Drainage)
without overflowing, then the maximum swale length would be determined as the
distance along the swale to the point where the 5 year ARI flow from the contributing
catchment is equivalent to the bank full flow capacity of the swale (bank full flow
capacity is determined using Mannings equation as discussed section 6.3.3.3).
6.3.3.3
The flow capacity of a swale can be calculated using Mannings equation. This allows
the flow rate (and flood levels) to be determined for variations in swale dimensions,
vegetation type and longitudinal slope.
Q=
A R2 / 3 S1/ 2
n
Where
Equation 6.1
2
Q = flow (m /s)
Mannings n is a critical variable in Mannings equation relating to roughness of the
channel. It varies with flow depth, channel dimensions and vegetation type. For
constructed swale systems, typical Mannings n values are between 0.15 and 0.4 for
flow depths shallower than the vegetation height (preferable for treatment) and
significantly lower for flows with greater depth than the vegetation (e.g. 0.03 for flow
depth more than twice the vegetation height).
Figure 6.7 shows a plot of Mannings n versus flow depth for a grass swale with
longitudinal grade of 5 % which is also applicable for other swale configurations. The
bottom axis of the plot has been modified from Barling and Moore (1993) to express
flow depth as a percentage of vegetation height. Further discussion on selecting an
appropriate Mannings n for a swale is provided in Appendix E of the MUSIC User
Guide (CRCCH 2005).
Page 6-14
10
20
40
60
80
90
105
200
Figure 6.7
6.3.4
Inflows to bioretention swales can be via distributed runoff (e.g. from flush kerbs on a
road) or point outlets such as pipe outfalls. Combinations of these inflow pathways
can also be used. Uniform distribution of inflow would generally provide better
operating conditions of bioretention swales owing to their long linear configuration.
6.3.4.1
Distributed Inflow
maintaining flow heights lower than vegetation heights (this may require flow
spreaders, or check dams)
minimising the slope of buffer, best if slopes can be kept below 5 %, however
buffers can still perform well with slopes up to 20 % provided flows are well
distributed. The steeper the buffer the more likely flow spreaders will be
required to avoid rill erosion.
Page 6-15
Depth as % of
Sediment accumulation
vegetation area
height
60 mm set down
Road surface
Road edge
Buffer strip
Figure 6.8
Figure 6.9
Page 6-16
Concentrated Inflow
Page 6-17
Secured grate
PLAN
ELEVATION
Figure 6.11
6.3.5
6.3.5.1
Page 6-18
found to contain high levels of salt (see last bullet point), extremely low
levels of organic carbon (< 3%), or other extremes considered retardant
to plant growth and microbial activity should be rejected. The base soil
must also be structurally sound and not prone to structural collapse as
this can result in a significant reduction in saturated hydraulic
conductivity. The risk of structural collapse can be reduced by ensuring
the soil has a well graded particle size distribution with a combined clay
and silt fraction of < 12%.
The required content of sand or clay (by weight) to be mixed to the base
soil will need to be established in the laboratory by incrementally
increasing the content of sand or clay until the desired saturated
hydraulic conductivity is achieved. The sand or clay content (by weight)
that achieves the desired saturated hydraulic conductivity should then be
adopted on-site. A minimum of five samples of the selected base soil
and sand (or clay) content mix must be tested in the laboratory to ensure
saturated hydraulic conductivity is consistent across all samples. If the
average saturated hydraulic conductivity of the final filter media mix is
within 20% of the design saturated hydraulic conductivity then the filter
media can be adopted and installed in the bioretention system.
Otherwise, further amendment of the filter media must occur through the
addition of sand (or clay) and retested until the design saturated
hydraulic conductivity is achieved.
The salt content of the final filter media (as measured by EC1:5) must be
less than 0.63 dS/m for low clay content soils like sandy loam. (EC1:5 is
the electrical conductivity of a 1:5 soil/ water suspension).
Page 6-19
Transition Layer
The particle size difference between the filter media and the underlying
drainage layer should be not more than one order of magnitude to avoid the
filter media being washed through the voids of the drainage layer. Therefore,
with fine gravels being used for the drainage layer (which will be at least two
orders of magnitude coarser than the likely average particle size of the filter
media), a transition layer is recommended to prevent the filter media from
washing into the perforated pipes. The material for the transition layer is
sand/coarse sand. An example particle size distribution (% passing) is
provided below (typical specification only):
1.4 mm
100 %
1.0 mm
80 %
0.7 mm
44 %
0.5 mm
8.4 %
the use of a sand drainage layer and/or perforated pipes with smaller
slot sized may need to be considered (Section 6.3.5.2).
Drainage Layer
The drainage layer is used to convey treated flows to the outlet via a
perforated under-drainage system. The composition of the drainage layer is
to be considered in conjunction with the selection and design of the
perforated under-drainage system (refer to Section 6.3.5.2) as the slot sizes
in the perforated pipes may determine the minimum drainage layer particle
size to avoid washout of the drainage layer into the perforated pipe system.
Gravel is the preferred media for the drainage layer to match with the typical
slot size of typical perforated or slotted under-drains.
However, there may be circumstances where site conditions constraint the
depth of the bioretention system. In such cases, it may be possible to use
sand as the drainage layer media to avoid having to provide a transition layer
between the filter media and the drainage layer. The drainage layer is to be
a minimum of 200 mm thick and it is advisable that the drainage media is
washed prior to placement in bioretention system to remove any fines.
6.3.5.2
The maximum spacing of the perforated pipes in wide bioretention trenches is 1.5 m
(centre to centre) to ensure effective drainage of the bioretention system.
By installing parallel pipes, the capacity of the perforated pipe under-drain system can
be increased. The recommended maximum diameter of the perforated pipes is 100
mm to minimise the required thickness of the drainage layer. Either flexible perforated
pipe (e.g. agricultural pipe) or slotted PVC pipes can be used, however care needs to
be taken to ensure that the slots in the pipes are not too large that sediment would
Page 6-20
freely flow into the pipes from the drainage layer. This is also a consideration when
specifying the drainage layer media.
To ensure the slotted or perforated pipes are of adequate size, several checks are
required:
Ensure perforations are adequate to pass the maximum filtration rate of the
media.
Ensure the pipe itself has capacity to convey the design flow (ie. the maximum
filtration rate multiplied by the surface area).
Ensure that the material in the drainage layer will not be washed into the
perforated pipes.
6.3.5.3
The maximum filtration rate represents the maximum rate of flow through the
bioretention filter media and is calculated by applying Darcys equation (Equation 6.2)
as follows:
hmax + d
d
Equation 6.2
3
Qmax
Ksat
Wbase
hmax
The capacity of the perforated under-drains need to be greater than the maximum
filtration rate to ensure the filter media drains freely and the pipe(s) do not become the
hydraulic control in the bioretention system (i.e. to ensure the filter media sets the
travel time for flows percolating through the bioretention system rather than the flow
through the perforated under-drainage system).
To ensure the perforated under-drainage system has sufficient capacity to collect and
convey the maximum infiltration rate, it is necessary to determine the inflow capacity of
combined slotted area or perforation area of the under-drainage system. To do this,
the sharp edged orifice equation can be used, i.e.
the maximum driving head (being the depth of the filtration media plus the
depth of extended detention).
Qperf = B Cd A 2 g h
Equation 6.3
Where
3
Qperf
Page 6-21
Cd
It is essential that adequate inflow capacity is provided to enable the filtered water to
drain freely into the drainage layer.
After confirming the capacity of the under-drainage system to collect the maximum
filtration rate, it is then necessary to confirm the conveyance capacity of the underdrainage system is sufficient to convey the collected runoff. To do this, Mannings
equation (Equation 6.1) can be used assuming pipe full flow conditions and a nominal
friction slope of 0.5%. The Mannings roughness used will be dependent on the type
of pipe used.
One end of the under-drains should be extended vertically to the surface of the
bioretention system to allow inspection and maintenance when required. The vertical
section of the under-drain should be a non-perforated or slotted pipe and capped to
avoid short circuiting of flows directly to the drain.
6.3.5.4
The saturated hydraulic conductivity of the natural soil profile surrounding the
bioretention system should be tested together with depth to groundwater, chemical
composition and proximity to structures and other infrastructure. This is to establish if
an impermeable liner is required at the base (only for systems designed to preclude
exfiltration to in-situ soils) and/or sides of the bioretention basin (refer also to
discussion in Section 6.2.5). If the saturated hydraulic conductivity of the filter media
in the bioretention system is more than one order of magnitude (10 times) greater than
that of the surrounding in-situ soil profile, no impermeable lining is required.
6.3.6
6.3.6.1
Potential scour velocities are checked by applying Mannings equation (Equation 6.1)
to the bioretention swale design to ensure the following criteria are met:
less than 0.5 m/s for minor flood (2-10 year ARI) discharge
less than 2.0 m/s for major flood (50-100 year ARI) discharge .
6.3.6.2
depth x velocity < 0.6.m /s for low risk locations and 0.4 m /s for high risk
locations
This is consistent with the recommendation in the Singapore Code of Practice for Surface Drainage which stipulates
that the maximum velocity for a earth drain and concrete-lined drain should not exceed 1.5 m/s and 3 m/s respectively.
Page 6-22
6.3.6.3
If the previous two checks are satisfactory then the bioretention swale design is
satisfactory from a conveyance function perspective and it is now necessary to confirm
the treatment performance of the bioretention swale by reference to the performance
information presented in Section 6.2.5
6.3.7
In a bioretention swale system, overflow pits are used to control innundation depth.
The crest of the pit is set raised above the surface of the bioretention filter media to
establish the design extended detention depth.
Grated pits are typically used and the allowable head for discharges into the pits is the
difference in level between the pit crest and the maximum permissible water level to
satisfy the minimum freeboard requirements of the Public Utilities Board. Depending
on the location of the bioretention swale, the design flow to be used to size the
overflow pit could be the maximum capacity of the swale, the minor flood flow (5 year
ARI) or the major flood flow (50-100 year ARI).
To size an overflow pit, two checks should be made to test for either drowned or free
flowing conditions. A weir equation can be used to determine the length of weir
required (assuming free overflowing conditions) and an orifice equation used to
estimate the area between openings required in the grate cover (assuming drowned
outlet conditions). The larger of the two pit configurations should be adopted. In
addition, a blockage factor is to be used, that assumes the grate is 50% blocked.
For free overfall conditions (weir equation):
Q weir = B Cw L h3 / 2
Where
Equation 6.4
Qweir
Cw
Once the length of weir is calculated, a standard sized pit can be selected with a
perimeter at least the same length of the required weir length.
For drowned outlet conditions (orifice equation):
Qorifice = B Cd A 2 g h
Equation 6.5
Cd
When designing grated field inlet pits, refer to relevant guidelines or standards for
grate types for inlet pits.
Page 6-23
6.3.8
Refer to Section 6.2.4 and the National Parks Board of Singapore for advice on
selecting suitable plant species for bioretention swales in Singapore. Consultation with
landscape architects is recommended when selecting vegetation to ensure the
treatment system compliments the landscape design of the area.
6.3.10 Step 10: Consider Maintenance Requirements
Consider how maintenance is to be performed on the bioretention swale e.g. how and
where is access available, where is litter likely to collect etc.. A specific maintenance
plan and schedule should be developed for the bioretention swale in accordance with
Section 6.5.
6.3.11 Design Calculation Summary
The following design calculation table can be used to summarise the design data and
calculation results from the design process.
Page 6-24
Calculation Task
Catchment Characteristics
Catchment Area
Catchment Land Use (i.e. residential, Commercial etc.)
ha
Conceptual Design
Bioretention area
Filter media saturated hydraulic conductivity
Extended detention depth
1
m
mm/hr
mm
2
m
%
%
%
minutes
mm/hr
mm/hr
m /s
3
m /s
m
%
mm
mm
mm
3
m /s
mm
3
m /s
3
m /s
mm/hr
mm/hr
Verification Checks
Velocity for 2-10 year ARI flow (< 0.5 m/s)
Velocity for 50-100 year ARI flow (< 2 m/s)
2
Velocity x Depth for 50-100 year ARI (< 0.4 m /s)
Treatment Performance consistent with Step 1
mm/hr
mm
mm
m/s
m/s
2
m /s
LxW
Page 6-25
Typical Values
1% to 4 %
Maximum 1 in 9
Maximum 1 in 3
0.15 to 0.3
0.03 to 0.05
0.5 m/s
2.0 m/s
100 mm (maximum)
1-5 mm diameter
0.7 1.0 mm
diameter
Page 6-26
6.4
This section provides a number of checking aids for designers and referral authorities.
In addition, advice on construction techniques and lessons learnt from building
bioretention systems are provided.
Checklists are provided for:
6.4.1
Design assessments
The checklist overleaf below presents the key design features that should be reviewed
when assessing a design of a bioretention basin. These considerations include
configuration, safety, maintenance and operational issues that should be addressed
during the design phase.
Where an item results in an N when reviewing the design, referral should be made
back to the design procedure to determine the impact of the omission or error.
In addition to the checklist, a proposed design should have all necessary permits for
its installations. The referral agency should ensure that all relevant permits are in
place. These can include permits to clear vegetation, to dredge, create a waterbody,
divert flows or disturb habitat.
Land ownership and asset ownership are key considerations prior to construction of a
stormwater treatment device. A proposed design should clearly identify the asset
owner and who is responsible for its maintenance. The proposed owner should be
responsible for performing the asset transfer checklist (see Section 0).
Page 6-27
Hydraulics:
Area:
Bioretention Area (m ):
TREATMENT
Page 6-28
6.4.2
Construction Advice
This section provides general advice for the construction of bioretention basins. It is
based on observations from construction projects around Australia.
6.4.2.1
Perforated Pipes
Suitable perforated pipes can be either a PVC pipe with slots cut into the length of it or
a flexible ribbed pipe with smaller holes distributed across its surface (an AG or
agricultural pipe). PVC pipes have the advantage of being stiffer with less surface
roughness therefore greater flow capacity; however the slots are generally larger than
for flexible pipes and this may cause problems with filter or drainage layer particle
ingress into the pipe. Stiff PVC pipes however can be cleaned out easily using simple
plumbing equipment. Flexible perforated pipes have the disadvantage of roughness
(therefore flow capacity) but have smaller holes and are flexible which can make
installation easier. Blockages within the flexible pipes can be harder to dislodge with
standard plumbing tools.
6.4.2.3
Tolerances
Protection of filtration media and vegetation is important during the building phase.
Uncontrolled building site runoff is likely to cause excessive sedimentation, introduce
weeds and litter and require replanting following the building phase. Where possible,
a staged implementation should be adopted, i.e. during the site
development/construction phase, use geofabric and some soil and instant turf (lay
perpendicular to flow path) to provide erosion control and sediment trapping.
Following the building phase, temporary measures and sediments would be removed
and bioretention swale is revegetated in accordance with design planting schedule. It
is also possible to reuse the instant turf in the subsequent stages.
If these systems are not staged to be part of the sediment control system during
construction, it is advisable that stormwater flow during the site construction phases be
diverted around the bioretention swales to sediment controls system to avoid
smothering of planted vegetation by sediment loads from the construction site.
6.4.2.5
Ensure traffic and deliveries do not access bioretention swales during construction.
Traffic can compact the filter media and cause preferential flow paths, deliveries (such
as sand or gravel) that can block filtration media is delivered onto the surface of the
bioretention filter media. Washdown wastes (e.g. concrete) can also cause blockage
of filtration media and damage vegetation. Bioretention areas should be fenced off
during building phase and controls implemented to avoid washdown wastes.
Management of traffic during the building phase is particularly important and poses
significant risks to the health of the vegetation and functionality of the bioretention
system. Measures such as those proposed above (e.g. staged implementation of final
landscape) should be considered.
Page 6-29
6.4.2.6
Where flush kerbs are to be used, a set-down from the pavement surface to the
vegetation should be adopted. This allows a location for sediments to accumulate that
is off the pavement surface. Generally, a set down from kerb of 60mm to the top of
vegetation (if turf) is adequate. Therefore, total set down to the base soil is
approximately 100 mm (with approximately 40mm turf on top of base soil).
6.4.2.7
It is good practice to check the operation of inlet erosion protection measures following
the first few rainfall events. It is important to check for these early in the systems life,
to avoid continuing problems. Should problems occur in these events the erosion
protection should be enhanced.
6.4.2.8
Erosion Control
Week 1-2
3 visits/ week
Week 3-6
2 visits/ week
Week 7-12
1 visit/ week
After this initial three month period, watering may still be required, particularly during
the first winter (dry period). Watering requirements to sustain healthy vegetation
should be determined during ongoing maintenance site visits.
Page 6-30
6.4.3
Construction checklist
Inspected by:
Site:
Date:
Time:
Constructed by:
Weather:
Contact during site visit:
Checked
Items inspected
Satisfactory
Y
Checked
Items inspected
Satisfactory
Y
Structural components
Preliminary Works
1. Erosion and sediment control plan adopted
2. Temporary traffic/safety control measures
specification
following
terrestrial
C. OPERATIONAL ESTABLISHMENT
Vegetation
layers
and
7. Under-drainage working
4. Vegetation as designed
ACTIONS REQUIRED
1.
2.
Inspection officer signature:
Page 6-31
6.4.4
ASSET INFORMATION
Design Assessment Checklist provided?
As constructed plans provided?
Copies of all required permits (both construction and operational) submitted?
Proprietary information provided (if applicable)?
Digital files (eg drawings, survey, models) provided?
Asset listed on asset register or database?
Page 6-32
6.5
Maintenance Requirements
Routine inspection of inlet points (if the swale does not have distributed
inflows), surcharge pits and field inlet pits to identify any areas of scour, litter
build up and blockages.
Repairing any damage to the swale profile resulting from scour, rill erosion or
vehicle damage.
Removal of plants that have died and replacement with plants of equivalent
size and species as detailed in the plant schedule.
Page 6-33
inspection frequency
maintenance frequency
equipment needs
maintenance techniques
occupational health and safety
public safety
environmental management considerations
access issues
stakeholder notification requirements
data collection requirements (if any)
design details
Page 6-34
6.5.1
The form below should be used whenever an inspection is conducted and kept as a
record on the asset condition and quantity of removed pollutants over time.
1 to 6 monthly
Date of Visit:
Location:
Description:
Site Visit by:
INSPECTION ITEMS
Page 6-35
6.6
6.6.1
CELL A
35m
13m
30m
3
House lots
footpath
4m
Service
ServiceRoad
Road
7m
swale
bioretention
Collector Road
collector
service
verge
lot
Figure 6.12 Catchment area layout and section for worked example
Site Description
The site comprised of the arterial road and a service road separated by a median of
some 6m width. The median area offers the opportunity for a local treatment
Engineering Procedures for ABC Waters Design Features
Page 6-36
measure. The area available is relatively large in relation to the catchment and is
elongated in shape. The catchment area for the swale and bioretention area includes
the road reserve and the adjoining allotment (of approximately 30m depth and with a
fraction impervious of 0.6).
Three crossings of the median are required and the raised access crossings can be
designed as the separation mounds between the swale and bioretention treatment
system, thus resulting in a two-cell system.
Each bioretention swale cell will treat its individual catchment area. Runoff from the
arterial road is conveyed by a conventional kerb and gutter system into a stormwater
pipe and discharged into the surface of the swale at the upstream end of each cell.
Runoff from the local street can enter the swale as distributed inflow (sheet flow) along
the length of the swale.
As runoff flows over the surface of the swale, it receives some pretreatment and
coarse to medium sized particles can be expected to be trapped by vegetation on the
swale surface. Stormwater inflow exceeding the filtration rate of the soil media in the
bioretention system will temporarily pond on the bioretention zone at the downstream
end of each cell. Filtered runoff is collected via a perforated pipe in the base of the
bioretention zone. Flows in excess of the capacity of the filtration medium overflow
into the piped drainage system at the downstream end of each bioretention cell.
Simulation using MUSIC found that the required area of bioretention system to meet a
desired target of 80% reduction in TSS and 45% reduction in TP and TN is
approximately 61 m2 and 22 m2 for Cell A and B respectively. The filtration medium
used is sandy loam with a notional saturated hydraulic conductivity of 180 mm/hr. The
required area of the filtration zone is distributed to the two cells according to their
catchment area.
6.6.1.2
Design Objectives
The design treatment objectives for the bioretention swale are as follows:
To meet the desired target of 80%, 45% and 45% reductions of TSS, TP and
TN respectively
Sub-soil drainage pipe to be designed to ensure that the capacity of the pipe
exceeds the saturated infiltration capacity of the filtration media (both inlet and
flow capacity)
Design flows within up to 5-year ARI range are to be safely conveyed into a
piped drainage system without any inundation of the adjacent road.
The hydraulics for the swale need to be checked to confirm flow capacity for
the 5-year ARI peak flow.
The flow conditions are to attain acceptable safety and scouring behaviour for
100 year ARI peak flow.
6.6.1.3
6.6.1.4
Site Characteristics
Page 6-37
Land use
Soil
Clay
Catchment areas:
Cell A
Allotments
35m x 30m
Collector
road
35m x 7m
Local road
35m x 7m
Footpath
35m x 4m
Swale
103m x 7.5m
Cell B
13m x 30m
13m x 7m
13m x 7m
13m x 4m
44m x 7.5m
Fraction impervious
6.6.2
Nominated bioretention areas for Cell A and Cell B are 61 m2 and 22 m2 respectively.
Interpretation of Figure 6.4 to Figure 6.6 with the input parameters below is used to
estimate the reduction performance of the bioretention system to ensure the design
will achieve target pollutant reductions.
From the graphs, the expected pollutant reductions are 93%, 77% and 49% for TSS,
TP and TN respectively and exceed the design requirements of 80%, 45% and 45%.
6.6.3
Cell B the tc calculations include overland flow across the lots and road and
swale/bioretention flow time.
Page 6-38
Fraction impervious
Cell A:
Area (m2)
fi
Allotments
1050
0.6
630
Collector Road
245
0.9
220.5
Local Road
245
0.9
220.5
Footpath
140
0.5
70
Swale
773
0.0
TOTAL
1680
1141
fi
Cell B:
Allotments
390
0.6
234
Collector Road
91
0.9
81.9
Local Road
91
0.9
81.9
Footpath
52
0.5
26
Swale
330
0.0
624
TOTAL
423.8
Runoff Coefficient
While the effective fraction impervious is 0.68, the runoff coefficients adopted were in
accordance to those for a densely built-up urban area, as outlined in Code of Practice
on Surface Water Drainage (Public Utilities Board 2006).
Design ARI
5
100
Cell A
0.8
0.8
Cell B
0.8
0.8
Page 6-39
Design Flows
The design flows for the two cells, computed using the Rational Method (Q = 0.00278.
C.I.A) are summarised below:
Design ARI
6.6.4
Cell A (m /s)
Cell B (m /s)
0.06
0.02
100
0.10
0.04
The swales need to be sized such that they can convey the 5 year ARI peak discharge
without water encroaching on the road. Mannings equation is used to compute the
discharge capacity of the swale.
In determining the dimensions of the swale, the depth of the swale were determined
by the requirement for it to enable allotment drainage to be discharged to the surface
of the swale. Given the cover requirements of the allotment drainage pipes as they
flow under the service road (600 mm minimum cover), it set the base of the
bioretention systems at 0.76m below road surface.
The following are the
characteristics of the proposed swale:
Grass vegetation mown to height of 0.1m (assume n = 0.045 for 5 year ARI
with flows above grass height)
The approach taken is to size the swale to accommodate flows in Cell A and then
adopt the same dimension for Cell B for aesthetic reasons (Cell B has lower flow
rates).
The maximum capacity of the swale (Qcap) is estimated adopting a 150mm freeboard3
(i.e. maximum depth is 0.61m).
Qcap = 2.19 m3/s >> 0.10 m3/s
Therefore, there is adequate capacity given the relatively large dimensions of the
swale to accommodate allotment runoff connection.
With a base width of 1 m, the lengths of the bioretention system in Cells A and B will
need to be 61 m and 22 m respectively to attain the required areas to meet the water
quality objectives.
6.6.5
There are two mechanisms for flows to enter the system, firstly underground pipes
(either from the upstream collector road into Cell 1 or from allotment runoff) and
secondly direct runoff from road and footpaths.
Flush kerbs with a 60 mm set down are intended to be used to allow for sediment
accumulation from the road surfaces.
Grouted rock is to be used for scour protection for the pipe outlets into the system.
The intention of these is to reduce localised flow velocities to avoid erosion.
The Singapore Code of Practice for Surface Drainage would normally stipulate a freeboard of 15% of the depth of the
drain, ie. 0.15 x 760 = 110mm
Engineering Procedures for ABC Waters Design Features
Page 6-40
6.6.6
6.6.6.1
Three layers of soil media are to be used. A sandy loam filtration media (600mm), a
medium to coarse sand transition layer (100mm) and a gravel drainage layer
(200mm).
6.6.6.2
The filter media is to be a sandy loam with the following criteria (from FAWB 2007):
The material shall meet the geotechnical requirements set out below:
Hydraulic conductivity between 50-200 mm/hr
Particle sizes of between: clay 2 4 %, silt 4 8 %, sand < 85 %
Organic content between 3% and 10%
pH 5.5 7.5
6.6.6.3
Transition layer material shall be coarse sand material. A typical particle size
distribution is provided below:
% passing
1.4 mm 100 %
1.0 mm 80 %
0.7 mm 44 %
0.5 mm 8.4 %
6.6.6.4
The maximum filtration rate reaching the perforated pipe at the base of the soil media
is estimated by using the hydraulic conductivity of the media and the head above the
pipes and applying Darcys equation.
Saturated hydraulic conductivity = 180 mm/hr
Flow capacity of the filtration media = (1-) As kh
Qmax = k LWbase
hmax+d
d
0.2 + 0.6
Qmax = 5 10 5 L Wbase
0.6
where:
k
hmax
Page 6-41
6.6.6.6
Estimate the inlet capacity of sub-surface drainage system (perforated pipe) to ensure
it is not a choke in the system. To build in conservatism, it is assumed that 50% of the
holes are blocked. A standard slotted pipe was selected that is widely available. To
estimate the flow rate an orifice equation is applied using the following parameters:
Assuming drainage layer is saturated, driving head is half the depth of the drainage
layer H = 0.1m
Assume sub-surface drains with half of all pipes blocked
Product specification Clear Opening
= 2100 mm2/m
= 1050mm2/m
Slot Width
= 1.5 mm
Slot Length
= 7.5 mm
Diameter
= 100 mm
The Colebrook-White equation is applied to estimate the flow rate in the perforated
4
pipe. A slope of 0.5% is assumed and a 100mm perforated pipe (as above) was
used. Should the capacity not be sufficient, additional pipes would be required. The
capacity of this pipe needs to exceed the maximum filtration rate of the media.
Estimate applying the Colebrook-White Equation
0.5
0.5
Sf
= slope (0.005m/m)
-6
Qcap = 0.01 m /s (for one pipe) > 0.004 m /s (Cell 1); 0.001 m /s (Cell 2), and hence 1
pipe is sufficient to convey the maximum infiltration rate for both Cell A and B.
4
A slope of 0.5% is adopted simply for convenience. In reality, the discharge capacity is reached when the soil is
saturated and water ponded to the full extended detention depth. Bioretention systems can operate equally effectively
with the underdrain laid at near-zero (but positive) slopes.
Page 6-42
Adopt 1 x 100 mm slotted pipe for the underdrainage system in both Cell A and Cell
B.
6.6.6.8
Typically flexible perforated pipes are installed using fine gravel media to surround
them. In this case study, 2-5mm gravel is specified for the drainage layer. This media
is much coarser than the filtration media (sandy loam) therefore to reduce the risk of
washing the filtration layer into the perforated pipe, a transition layer is to be used.
This is to be 100 mm of coarse sand.
6.6.6.9
In this catchment the surrounding soils are clay to silty clays with a saturated hydraulic
conductivity of approximately 3.6 mm/hr. The sandy loam media that is proposed as
the filter media has a hydraulic conductivity of 50 - 200 mm/hr. Therefore the
conductivity of the filter media is > 10 times the conductivity of the surrounding soils
and an impervious liner is not required.
6.6.7
6.6.7.1
Assume Q5 and Q100 will be conveyed through the swale/bioretention system. Check
for scouring of the vegetation by checking that velocities are below 0.5m/s during Q5
and 2.0 m/s for Q100.
Using Mannings equation to solve for depth for Q5 and Q100 gives the following
results:
Q5 = 0.062 m3/s, depth = 0.12 (with n = 0.06), velocity = 0.38m/s < 0.5m/s
therefore, OK
Q100 = 0.103 m3/s, depth = 0.14m (with n = 0.045), velocity = 0.52m/s <
2.0m/s therefore, OK
Hence, the swale and bioretention system can satisfactorily convey the peak 5 and
100-year ARI flood, with minimal risk of vegetation scour.
6.6.7.2
Check velocity depth product in Cell A during peak 100-year ARI flow for pedestrian
safety criteria.
V = 0.52m/s (calculated previously)
D = 0.14m
V.D = 0.52 x 0.14 = 0.07 < 0.6m2/s
Therefore, velocities and depths are OK.
6.6.8
The overflow pits are required to convey 5 year ARI flows safely from above the
bioretention systems and into an underground pipe network. Grated pits are to be
used at the downstream end of each bioretention system.
There are standard pit sizes to accommodate connection to the underground
stormwater pipe. For a minimum underground pipe of 300 mm diameter, a 450 mm x
450 mm pit will be required for both Cell A and Cell B.
Page 6-43
To check the adequacy of this pit to convey the 5 year ARI peak discharge, two flow
conditions need to be check. The assumed water level above the crest of the pit is the
depth of water from the road surface, less freeboard and the extended detention (i.e.
0.76 (0.15 + 0.2) = 0.41m).
First check using a weir equation
Qweir
= B.C.L.H3/2
6.6.9
Page 6-44
CALCULATION SUMMARY
CALCULATION TASK
OUTCOME
CHECK
10
61 and 22
200
180
year
m2
mm
mm/hr
slope
1680
624
1.3
m2
m2
%
Cell A
Cell B
0.68
0.68
Catchment characteristics
Fraction impervious
Cell A - 10
Cell B - 8
Singapore
A - 275, B - 283
A - 166, B - 173
minutes
mm/hr
mm/hr
10
Inlet details
adequate erosion and scour protection?
rock pitching
0.38
0.52
0.07
m/s
m/s
m2/s
Overflow system
system to convey minor floods
Surrounding soil check
soil hydraulic conductivity
filter media
MORE THAN 10 TIMES HIGHER THAN SOILS?
3.6
180
yes
mm/hr
mm/hr
11
m3/s
yes
pipe diameter
100
number of pipes
1
pipe capacity
0.01
capacity of perforations 0.055 (A); 0.020 (B)
soil media infiltration capacity
0.004, 0.001
8
m3/s
m3/s
Swale design
appropriate Manning's n used?
sandy-loam
sand
gravel
turf
Plant selection
Page 6-45
Page 6-46
Page 6-47
6.7
References
Barling, R. D., & Moore, I. D., 1993, The role of buffer strips in the management of
waterway pollution. Paper presented at the The role of buffer strips in the
management of waterway pollution from diffuse urban and rural sources, The
University of Melbourne
CRCCH (Cooperative Research Centre for Catchment Hydrology), 2003, Model for
Urban Stormwater Improvement Conceptualisation (MUSIC) User Guide, Version 2.0,
December
FAWB - Facility for Advancing Water Biofiltration (2007). Bioretention and Tree Pit
Media Specifications, http://www.monash.edu.au/fawb/products/.Update March 2007.
Engineers Australia, 2006, Australian Runoff Quality: A guide to Water Sensitive
Urban Design, Editor-in-Chief Wong, T H F, ISBN 0 85825 852 8, Engineers
Australia, Canberra, Australia, 2006
Institution of Engineers Australia 2001. Australian Rainfall and Runoff - A Guide to
Flood Estimation. Barton, ACT, Engineers Australia. Editor in Chief Pilgram, D.H.
Public Utilities Board (2006). Code of Practice on Surface Water Drainage. Singapore.
50p.
Page 6-48
Bioretention Basins
7
Chapter 7 Bioretention Basins
7.1
Introduction
7-1
7.2
7-2
7.2.1
7-2
7.2.2
7-4
7.2.3
7-5
7.3
7-6
7.3.1
Landscape Design
7-6
7.3.2
Hydraulic Design
7-6
7.3.3
7-7
7.3.4
Vegetation Specification
7-7
7.3.5
7-7
7.3.6
7-8
7.4
Design Process
7-9
7.4.1
7-10
7.4.2
7-14
7.4.2.1
Design Flow
7-14
7.4.2.2
7-14
7.4.3
7-14
7-14
7.4.3.1
7.4.3.2
7-15
7.4.3.3
Streetscape Applications
7-16
7.4.4
7.4.4.1
7.4.5
7-16
7-16
7-19
7-19
7.4.5.1
7.4.5.2
7-20
7.4.5.3
7-21
7.4.5.4
7-21
7-22
7.4.6
7.4.7
7-22
7.4.8
7-24
7.4.9
7-24
7.4.10
7-25
7.5
Checking Tools
7-26
7.5.1
7-26
7.5.2
Construction Advice
7-26
7.5.2.1
7-26
7.5.2.2
7-26
7.5.2.4
7-28
7.5.2.5
Planting Strategy
7-28
7.5.2.6
Perforated Pipes
7-28
7.5.2.7
Inspection Openings
7-28
7.5.2.8
7-28
7.5.2.9
7.5.3
7.5.3.1
7.6
7-28
7.5.2.3
Maintenance Requirements
Operation & Maintenance Inspection Form
7-28
7-30
7-30
7-32
7-32
7.6.1
7.6.2
Calculation Steps
7-34
7.6.3
Calculation summary
7-40
7.6.4
Construction drawings
7-41
7.7
References
7-42
7.1
Introduction
Bioretention basins use ponding above a bioretention surface to maximise the volume
of runoff treated through the filtration media. Their operation for treatment is in the
same way as for bioretention swales, but are predominantly detention systems with
flood flows bypassing the filtration surface or diverted into stormwater drains.
Bioretention basins operate by filtering stormwater runoff through densely planted
surface vegetation as a means of pre-treatment before they infiltrate/percolate through
a prescribed filter media. During percolation, pollutants are retained through fine
filtration, adsorption and some biological uptake. The vegetation in a bioretention
system is a vital functional element of the system both in terms of maintaining the
hydraulic conductivity of the filter media and the improving soil capacity for chemical
and biological removal of stormwater contaminants. Vegetation facilitates the
transport of oxygen to the soil and enhances soil microbial communities which
enhance biological transformation of pollutants.
Bioretention basins are generally not intended to be infiltration systems that
discharge from the filter media to surrounding in-situ soils. Rather, the typical design
intent is to recover stormwater at the base of the filter media in perforated underdrains and discharge to receiving waterways or to storages for potential reuse. In
some circumstances however, where the in-situ soils allow and there is a particular
design intention to recharge local groundwater, it may be desirable to allow
stormwater to infiltrate from the base of a filter media to underlying in-situ soils.
Bioretention basins can be installed at various scales, ranging from planter boxes, to
streetscape raingardens integrated with traffic calming measures, to system contained
within retarding basins. In larger applications, it is considered good practice to have
pretreatment measures upstream of the basin to reduce the maintenance frequency of
the bioretention basin. For small system this is not required. Example applications
are given in Figure 7.1
This chapter describes the design, construction and maintenance of a bioretention
basins.
Page 7-1
Figure 7.1
Sites where exfiltration is not possible. This may arise where there is a
need to protect built infrastructure or whereby interactions with shallow
groundwater is undesirable.
If systems are designed for NOx removal or if receiving waters are highly
sensitive to Cu or ZN.
Page 7-2
Figure 7.2
A lined bioretention system may also be designed to include a submerged zone with
the submerged zone comprising of sand (Figure 7.3) or gravel. This type of
bioretention basin should be used for the following situations;
-
Sites where exfiltration is not possible. This may arise where there is a
need to protect built infrastructure or whereby interactions with shallow
groundwater is undesirable.
Climates that have very long dry spells. The submerged zone is able to
act as a water source for up to five weeks, supporting the plants and
microbial community.
If systems are designed for NOx removal or if receiving waters are highly
sensitive to Cu or ZN.
Figure 7.3
Page 7-3
Figure 7.4
Unlined bioretention systems may also include a submerged zone (Figure 7.5). The
addition of a submerged zone is appropriate whereby exfiltration is permissible and
the local climate yields long dry spells. These systems have unlined sides, however
the submerged zone must be lined to maintain saturation.
Figure 7.5
Page 7-4
Unlined bioretention systems do not contain collection pipes in the drainage layer.
Where possible, unlined bioretention systems are preferable to standard, non
vegetated infiltration systems due to the increased nutrient removal and are therefore
highly recommended whereby appropriate.
Figure 7.6
Page 7-5
7.3
A typical design for a bioretention basin is given in Figure 7.7. Key to the design is the
hydraulic operation, the filter media, the vegetation and the interaction of the basin
within the urban space. These design considerations are discussed further in the
following sections. Design considerations are similar to that presented in Chapter 6
Bioretention Swales and are presented in both chapters for ease of reference.
Mass Planting
ground cover vegetation
Overflow pit
Typical Depths
Filter Media
0.3 1.0m
Filter Media
Figure 7.7
Outlet pipe
connected to
stormwater
drainage
The finished surface of the bioretention filter media must be horizontal (i.e.
flat) to ensure full engagement of the filter media by stormwater flows and to
prevent concentration of stormwater flows within depressions.
Where possible, the overflow pit or bypass pathway should be located near
the inflow zone to prevent high flows passing over the surface of the filter
Page 7-6
media. If this is not possible, then velocities during the minor (5 year ARI) and
major (50-100 year ARI) floods should be maintained sufficiently low
(preferably below values of 0.5 m/s and not more than 2.0 m/s for major flood)
to avoid scouring of the filter media and vegetation.
Where the inlet to a bioretention system is required to convey the minor storm
flow (i.e. is part of the minor drainage system), the inlet must be designed to
avoid blockage, flow conveyance and public safety issues.
For streetscape applications, the design of the inflow to the bioretention basin
must ensure the kerb and channel flow requirements are preserved.
7.3.3
Preventing Exfiltration to In-Situ Soils
Bioretention basins can be designed to generally preclude exfiltration of treated
stormwater to the surrounding in-situ soils. The amount of water potentially lost from
bioretention trenches to surrounding in-situ soils is largely dependent on the
characteristics of the surrounding soils and the saturated hydraulic conductivity of the
bioretention filter media (see Section 7.3.5).
If the saturated hydraulic conductivity of the filter media is one to two orders of
magnitude (i.e. 10 to 100 times) greater than that of the insitu soil, the flow path of
stormwater percolation will be effectively contained within the bioretention filter media
and through to the drainage layer. As such, there will be little exfiltration to the
surrounding soils.
If the selected saturated hydraulic conductivity of the bioretention filter media is less
than 10 times that of the surrounding soils, it may be necessary to provide an
impermeable liner. Flexible membranes or a concrete casting are commonly used to
prevent excessive exfiltration.
A subsurface pipe is often used to prevent water intrusion into a road sub-base. This
practice is to continue as a precautionary measure to collect any water seepage from
bioretention swales located along roadways.
7.3.4 Vegetation Specification
Vegetation is a key component of a bioretention basin, servicing the following
processes:
Scour protection
Generally, the greater the density and height of vegetation planted in a bioretention
basin the better will be the treatment especially when extended detention is provided
in the design. When the extended detention is engaged, the contact between
stormwater and vegetation results in enhanced sedimentation of suspended
sediments and some adsorption of associated pollutants.
Bioretention basins should be planted to cover the whole bioretention filter media
surface. Vegetation should be of sufficient density to prevent preferred flow paths,
scour and re-suspension of deposited sediments. Turf grasses should ideally be
avoided as these are shallow rooted systems with inadequate penetration to the full
depth of the filter media and the turf stems inadequately prevent clogging at the
surface of the filter media.
The National Parks Board of Singapore should be consulted in determining suitable
plantings for bioretention basins in Singapore.
7.3.5 Bioretention Filter Media
Selection of an appropriate bioretention filter media is a key design step that involves
consideration of the following three inter-related factors:
Page 7-7
[Refer to the Bioretention Media Guidelines produced by FAWB (2007) for more
information.]
7.3.6 Maintenance and Access
The performance of a bioretention system will be affected by impeded flow. Driving
over or storing construction material on the bioretention basin can cause the filter
media to become impacted (compacted) and the vegetation damaged. The design of
a bioretention system should consider means of preventing or discouraging the
bioretention basin as becoming a trafficable and/or storage area.
Page 7-8
7.4
Design Process
The following sections detail the design steps required for bioretention basins. Key
design steps following the site planning and concept development stages are:
8. Specify vegetation
Page 7-9
7.4.1
Step 1: Confirm treatment size given in conceptual design
A conceptual design of a bioretention basin is normally typically undertaken prior to
detailed design. The performance of the concept design must be checked to ensure
that stormwater treatment objectives will be satisfied.
The treatment performance curves shown in Figure 7.3 to Figure 7.reflect the
treatment performance of the bioretention basin. The performance curves provide an
indication only of appropriate sizing and do not substitute the need for a thorough
conceptual design process. Nevertheless it is a useful visual guide to illustrate the
relationship of bioretention treatment performance to the ratio of bioretention treatment
area and contributing catchment area. The curves allow the designer to make a rapid
assessment as to whether the bioretention basin size falls within the optimal size
range.
The curves in Figure 7.8 to Figure 7.10 show the total suspended solid (TSS), total
phosphorus (TP) and total nitrogen (TN) removal performance for a typical
bioretention basin design with the following configurations:
Filter media saturated hydraulic conductivity (k) = 180 mm/hr and 360mm/hr or
-4
-4
0.5 x 10 m/s and 1 x 10 m/s
The curves in Figure 7.8 toFigure 7.Figure 7.10 are generally applicable to
bioretention basin applications within residential, industrial and commercial land uses.
If the characteristics of the bioretention component of the bioretention swale concept
design are significantly different to that described above, then the curves in Figure 7.8
to Figure 7.10 may not provide an accurate indication of treatment performance. In
these cases, the detailed designer should use MUSIC to verify the performance of the
bioretention swale.
Page 7-10
k s at=180mm/hr
100%
90%
80%
T S S R emoval (% )
70%
60%
50%
40%
No E xtended D etention
30%
20%
10%
0%
0
k s at = 360mm/hr
100%
90%
80%
T S S R emoval (% )
70%
60%
50%
40%
30%
No E xtended D etention
100mm E xtended D etention
20%
200mm E xtended D etention
10%
0%
0
Figure 7.8
Page 7-11
k s at=180mm/hr
90%
80%
70%
T P R emoval (% )
60%
50%
40%
30%
No E xtended D etention
100mm E xtended D etention
20%
200mm E xtended D etention
300mm E xtended D etention
10%
0%
0
k s at=360mm/hr
80%
70%
60%
T P R emoval (% )
50%
40%
30%
No E xtended D etention
100mm E xtended D etention
20%
10%
0%
0
Figure 7.9
Page 7-12
k s at=180mm/hr
60%
55%
50%
45%
T N R emoval (% )
40%
35%
30%
25%
20%
No E xtended D etention
100mm E xtended D etention
15%
10%
300mm E xtended D etention
5%
0%
0
k s at=360mm/h
50%
45%
40%
T N R emoval (% )
35%
30%
25%
20%
No E xtended D etention
15%
10%
5%
0%
0
Figure 7.10
Page 7-13
7.4.2
7.4.2.1
Minor (frequent) storm conditions (typically 5 year ARI) to size the overflows to
allow minor floods to be safely conveyed and not increase any flooding risk
compared to conventional stormwater systems
Major flood conditions (typically 100 year ARI) to check that flow velocities are
not too large in the bioretention system, which could potentially scour
pollutants or damage vegetation
7.4.2.2
A range of hydrologic methods can be applied to estimate design flows. With typical
catchment areas being relatively small, the Rational Method Design Procedure is
considered to be a suitable method for estimating design flows.
7.4.3 Step 3: Design Inflow System
The design of the inflow systems to bioretention basins needs to consider a number of
functions:
Each of these functions and the appropriate design responses are described in the
following sections.
7.4.3.1
Page 7-14
1
4
Voids to be planted with
rush/reed species (subject to
landscape design)
0.3D
0.75D
4D
Figure 7.11
7.4.3.2
Coarse sediment may accumulate near the basin inflow where stormwater runoff from
the catchment is delivered directly to the bioretention basin without pre-treatment
(through vegetated swale or buffer treatment). To mitigate these effects, it is
recommended that a coarse sediment forebay be incorporated into the design of a
bioretention basin. The forebay should be designed to:
-
Remove particles that are 1mm or greater in diameter from the 3 month ARI
storm event.
Page 7-15
The area of the sediment forebay (As) is calculated by solving the following expression
(modified version of Fair and Geyer (1954)):
1 v
R = 1 1 + s
n Q/AS
-n
Equation 7.1
Where
R
vs
settling velocity of target sediment (100 mm/s or 0.1 m/s for 1 mm particle)
As
Streetscape Applications
Page 7-16
The required content of sand or clay (by weight) to be mixed to the base
soil will need to be established in the laboratory by incrementally
increasing the content of sand or clay until the desired saturated
hydraulic conductivity is achieved. The sand or clay content (by weight)
that achieves the desired saturated hydraulic conductivity should then be
adopted on-site. A minimum of five samples of the selected base soil
and sand (or clay) content mix must be tested in the laboratory to ensure
saturated hydraulic conductivity is consistent across all samples. If the
average saturated hydraulic conductivity of the final filter media mix is
within 20% of the design saturated hydraulic conductivity then the filter
media can be adopted and installed in the bioretention system.
Otherwise, further amendment of the filter media must occur through the
addition of sand (or clay) and retested until the design saturated
hydraulic conductivity is achieved.
The salt content of the final filter media (as measured by EC1:5) must be
less than 0.63 dS/m for low clay content soils like sandy loam. (EC1:5 is
the electrical conductivity of a 1:5 soil/ water suspension).
Page 7-17
1.4 mm
100 %
1.0 mm
80 %
0.7 mm
44 %
0.5 mm
8.4 %
the use of a sand drainage layer and/or perforated pipes with smaller
slot sized may need to be considered.
Drainage Layer
The drainage layer is used to convey treated flows to the outlet via a
perforated under-drainage system. The composition of the drainage layer is
to be considered in conjunction with the selection and design of the
perforated under-drainage system (refer to Section 7.4.5) as the slot sizes in
the perforated pipes may determine the minimum drainage layer particle size
to avoid washout of the drainage layer into the perforated pipe system.
Gravel is the preferred media for the drainage layer to match with the typical
slot size of typical perforated or slotted under-drains.
However, there may be circumstances where site conditions constraint the
depth of the bioretention system. In such cases, it may be possible to use
sand as the drainage layer media to avoid having to provide a transition layer
between the filter media and the drainage layer. The drainage layer is to be
a minimum of 200 mm thick and it is advisable that the drainage media is
washed prior to placement in bioretention system to remove any fines.
Page 7-18
Submerged Zone
The submerged zone should be comprised of a mix of medium to coarse
sand and carbon, or a mix of fine gravel and carbon. The carbon source
should be a mix of 5% mulch and 5% hardwood chips, by volume.
A depth of 450mm has been shown to be optimal (Zinger et al., 2007),
however the feasibility of this will be determined by site conditions. A
minimum of 300mm is required for this zone to be effective. A submerged
zone of 300mm will protect against drying for up to five weeks of continuous
null inflow. In climates where dry periods are likely to exceed five weeks, the
submerged zone should be increased in depth bby 120mm for every
additional week of expected zero inflows. It is also important to note that a
50mm transition layer should separate the filter media and submerged zone.
This will prevent the leaching of pollutant and nutrients by ensuring that the
filter media does not become permanently saturated.
7.4.5 Step 5: Under-drain design and capacity checks
The slotted collection pipes at the base of bioretention filter media collect treated water
for conveyance downstream. The collection pipes are sized to ensure flow through
the filter media is not choked (or impeded) by the collection system.
The recommended maximum diameter of the perforated pipes is 100 mm to minimise
the required thickness of the drainage layer. Either flexible perforated pipe (e.g.
agricultural pipe) or slotted PVC pipes can be used, however care needs to be taken
to ensure that the slots in the pipes are not too large that sediment would freely flow
into the pipes from the drainage layer.
To ensure slotted or perforated pipes are of adequate size, several checks are
required:
Ensure the perforations are adequate to pass the maximum filtration rate of
the media
Ensure the pipe itself has sufficient capacity to convey the design flow (ie. the
maximum filtration rate multiplied by the surface area).
Ensure that the material in the drainage layer will not be washed into the
perforated pipes.
Qmax = k Lb Wbase
hmax + d
d
Equation 7.2
Where
k
W base
average width of the ponded cross section above the soil filter (m)
Lb
hmax
Page 7-19
Page 7-20
Perforated pipes should not use a geofabric wrapping, as this is a potential location for
blockage and would require a complete resetting of the bioretention system. Where
perforated pipes are supplied with geofabric wrapping, it is to be removed before
installation.
7.4.5.3
To ensure the perforated under-drainage system has sufficient capacity to collect and
convey the maximum filtration rate, it is necessary to determine the capacity for flows
to enter the under-drainage system via the perforations in the pipes. If the capacity of
the drainage system is unable to collect the maximum filtration rate additional underdrains will be required.
To calculate the flow through the perforations, orifice flow can be assumed and the
sharp edged orifice equation used as given in the following equation.
Q perf = B C d Ao 2 g h
Equation 7.3
Where
Qperf
Cd
Ao
hw
The total area of the orifice (Ao) is a function of the number of perforations in the pipe.
This information is typically provided in the manufacturers specifications. The
maximum driving head is equal to the depth of the filter media plus the extended
detention depth, if extended detention is provided.
It is conservative, but reasonable to use a blockage factor to account for partial
blockage of the perforations by the drainage layer media. A blockage factor of 0.5 is
considered adequate.
7.4.5.4
After confirming the capacity of the under-drainage system to collect the maximum
filtration rate, it is necessary to confirm the conveyance capacity of the under-drainage
system is sufficient to convey the collected runoff. The Colebrook-White equation can
be applied to estimate the flow rate in the perforated pipe.
Q pipe = A p 2(2 gD p S f
0.5
k
2.51v
log
+
3.7 D D(2 gDS
f
0.5
Equation 7.4
Where
3
Qpipe
Ap
Dp
Sf
Hydraulic roughness
Page 7-21
One end of the under-drains should be extended vertically to the surface of the
bioretention system to allow inspection and maintenance when required. The vertical
section of the under-drain should be a non-perforated or slotted pipe and capped to
avoid short-circuiting of flows directly to the drain.
7.4.6 Step 6: Check requirements for impermeable lining
The saturated hydraulic conductivity of the natural soil profile surrounding the
bioretention system should be tested together with depth to groundwater, chemical
composition and proximity to structures and other infrastructure. This is to establish if
an impermeable liner is required at the base (only for systems designed to preclude
ex-filtration to in-situ soils) and/or sides of the bioretention basin. If the saturated
hydraulic conductivity of the filter media in the bioretention system is more than one
order of magnitude (10 times) greater than that of the surrounding in-situ soil profile,
no impermeable lining is required.
It is important to note that for unlined bioretention systems with submerged zones, the
bottom and sides of the submerged zone will need to be lined in order to maintain a
permanent pool of water.
7.4.7 Step 7: Size overflow pit
The intention of the high flow design is to convey safely the minor floods (eg. 5-year
ARI flows) with the same level of protection that a conventional stormwater system
provides. Bioretention basins are typically served with either grated overflow pits or
conventional side entry pits (located downstream of an inlet) to transfer flows into an
underground pipe network (the same pipe network that collects treated flows).
The location of the overflow pit is variable but it is desirable that flows do not pass
through extensive section of the bioretention basin enroute to the overflow pit. Grated
pits can be located near the inlet to minimize the flow path length for above design
flows. A level of conservatism should be built into the design grated overflow pits by
placing the crest of the pit at least 100 mm below the invert of the street gutter. This
allows the overflow pit to convey a minor flood prior to any afflux effects in the street
gutter. The overflow pit should be sized to pass a five year ARI storm with the
available head below the gutter invert (i.e. 100 mm).
Overflow pits can also be located external to bioretention basins, potentially in the
form of convention side entry pits associated with the street kerb and gutter
immediately downstream of the inlet to the basin. In this way the overflow pit can
operate in the same way as a conventional drainage system, with flows entering the
pit only when the bioretention system is at maximum ponding depth. This is illustrated
in Figure 7.12.
Page 7-22
Figure 7.12
A grated overflow pit is sized based on the governing flow condition; weir flow or
submerged flow conditions. A weir equation can be used to determine the length of
weir required (assuming free overfall conditions). An orifice equation is used to
estimate the required area between openings in the grate cover (assuming drowned
outlet conditions). The larger of the resulting required dimensions to accommodate
the two flow conditions should be adopted. In sizing the overflow pit for both drowned
and free flowing conditions, it is recommended that a blockage factor that assumes the
orifice is 50% blocked be used.
The weir equation for free flowing conditions is given by:
Qmin or = Qweir = B C w L hw
3/ 2
Equation 7.5
Where
3
Qweir
Cw
hw
A standard sized pit can be selected with a perimeter at least the same length as the
required weir length.
The orifice equation for drowned outlet conditions is given by:
Equation 7.6
Where
Qgrate
Page 7-23
Agrate
hw
Page 7-24
Page 7-25
7.5
Checking Tools
The following sections provide a number of checking aids for designers and referral
authorities. Additional advice on construction and maintenance is provided.
Checklists have been provided for:
-
Design assessments
Page 7-26
Hydraulics:
Area:
TREATMENT
Page 7-27
Page 7-28
Time:
Weather:
Constructed By:
Items inspected
Adequate
Y
N
Checked Adequate
Y N
Y
N
Items inspected
and
Structural components
sediment control plan
as
Vegetation
FINAL INSPECTION
1. Confirm levels of inlets and outlets
7. Under-drainage working
4. Vegetation as designed
COMMENTS ON INSPECTION
ACTIONS REQUIRED
Page 7-29
Maintaining vegetation
Fertilising plants
Page 7-30
1 to 6 monthly
Date of Visit:
Location:
Description:
Site Visit by:
INSPECTION ITEMS:
Page 7-31
7.6
Footpath
Footpath
Figure 7.13
Figure 7.14
Road Pavement
Page 7-32
Catchment Description
Each of the individual bioretention basins (pods) has a contributing catchment of
100m2 road and footpath pavement and 300m2 of adjoining properties. Runoff from
adjoining properties (approx. 60% impervious) is discharged into the road gutter and,
together with road runoff, is conveyed along a conventional roadside gutter to the
bioretention pod.
Area (m )
% Impervious
Car Park
100
0.9
Allotment
300
0.6
Total
400
0.68
Design Objectives
The aim of the design is to facilitate effective treatment of stormwater runoff while
maintaining a level of flood protection for the local street during frequent storm events
up to the 5yr ARI event. Effective stormwater quality treatment is described in terms
of pollutant load reductions for total suspended solids (TSS), total phosphorous (TP)
and total nitrogen (TN).
The key design elements for effective operation of the bioretention basins are:
configuring and designing a system for above design operation that will
provide the required 5year ARI flood protection for the local street
1% typical
Soil:
clay
Page 7-33
7.6.2
Calculation Steps
The design of a bioretention system has been divided into the following 9 calculations
steps:
Step 1 Confirm treatment size given in conceptual design
Step 2 Determine design flows
Step 3 Design inflow system
Step 4 Specify the bioretention media characteristics
Step 5 Under-drain design and capacity checks
Step 6 Check requirements for impermeable lining
Step 7 High flow route and by-pass design
Step 8 Vegetation Specification
Step 9 Verification checks
Details for each calculation step are provided below. A design calculation summary
has been completed for the worked example and is given at the conclusion of the
calculation steps.
Step 1 Confirm treatment size given in conceptual design
The sizing of the bioretention system determined during conceptual design was
verified using the sizing curves given in Figure 7.8 to Figure 7.10. The sizing curves,
developed for Singapore conditions, give an estimate of the pollutant load reduction
for a given treatment size (defined in terms of impervious treatment area). Verification
using the sizing curves requires the following information:
14m 2
= 5%
[(0.9 100) + (0.6 300)]
The expected pollutant reductions given in the sizing curves for the above criteria are
93%, 77% and 49% for TSS, TP and TN respectively and exceed the design
requirements of 80%, 45% and 45%.
Step 2 Determine design flows
Minor and major flood estimation
With a small catchment, the Rational Method is considered an appropriate approach to
estimate the 5 and 100 year ARI peak flow rates. The calculation steps are given
below.
a. Time of concentration (tc)
The time of concentration is associated with overland flow and kerb and gutter
travel times. In this worked example, the time of concentration is estimated to
be approximately 10 minutes.
b. Design rainfall intensities
The rainfall intensity for the 5 year and 100 year ARI event is calculated from
the Singapore IDF curve. Data for the 1year flow is extrapolated from the
curve. Rainfall intensities for the 100year, 5year and 1year ARI event for
10min storm duration are given below.
Page 7-34
Intensity (mm/hr)
100yr
5yr
1yr
271
166
106
CIA
360
0.74 166 400 10 4
Q5 =
360
3
= 0.01m / s
Q =
Q100 =
The critical design flow rate for a bioretention system is defined to be the 3
month ARI storm event. The 3 month ARI flow is calculated assuming:
360
3
= 0.004m / s
Maximum filtration rate
The maximum filtration rate, or the flow reaching the perforated pipe in the drainage
layer, is estimated by applying Darcys equation (Equation 7.2) at the saturated
hydraulic conductivity of the filter media (assuming no blockage of the media) and the
head above the base of the filter media:
Qmax = k Lb Wbase
hmax + d
d
Given
k
LbW base
average area of the ponded section above the sand filter (14m2)
hmax
Page 7-35
Remove particles that are 1mm or greater in diameter from the 3mth ARI
storm event.
The size of the sediment forebay (As) is determined by solving Equation 7.1 for a
capture efficiency of 80%, i.e.
nQ
(1 R )1 n 1
Vs
As =
Where
R
Vs
As
As =
(0.5)(0.004)
(1 0.8)1 0.5 1 = 0.48m 2
0.1
The volume of the sediment forebay is calculated by adopting a mean depth of 0.3 m,
ie.
Page 7-36
pH neutral
%Passing
1.4mm
100%
1.0mm
80%
0.7mm
44%
0.5mm
8.4%
1.125x10-5m2/hole
Numbers of holes
Page 7-37
Q = A p 2(2 gDpS f
0 .5
k
2.51v
log
+
3.7 Dp Dp (2 gDpS f
0 .5
Where
Dp = 0.10m
Sf = 0.005m/m
2
g = 9.81m /s
k = 0.007m
v = 1.007 x 10-6
Ap= 0.009m2
3
The flow capacity of the pipe is 0.003 m /s, which is greater than the infiltration rate.
Hence, the perforated pipe specified is adequate for the under-drainage system.
Step 6 Check requirements for impermeable lining
The soils found in Singapore are typically clay with the saturated hydraulic conductivity
expected to be ~3.6mm/hr. The sandy loam media that is proposed as the filter media
has a hydraulic conductivity of approximately 180 mm/hr. Therefore the conductivity
of the filter media is > 10times the conductivity of the surrounding soils and an
impervious liner is not considered to be required.
Step 7 High flow route and by-pass design
The overflow pit is required to convey 5 year ARI flows safely from above the
bioretention system into an underground pipe network. Grated pits are to be used at
the upstream end of the bioretention system. There are standard pit sizes to
accommodate connection to the underground stormwater pipe.
3
For the existing 450 mm diameter stormwater pipe, 600 x 600 mm pit will be required.
The size of the pit necessary to convey the overflow is computed assuming both free
overfall weir flow and submerged flow conditions. For the free overflow condition, a
weir equation is used with the maximum headwater depth (h) above the weir being set
by the level difference between the crest of the overflow pit and the invert level of the
inflow kerb opening (i.e. 100mm).
A slope of 0.5% is adopted simply for convenience. In reality, the discharge capacity is reached when the soil is
saturated and water ponded to the full extended detention depth. Bioretention systems can operate equally effectively
with the underdrain laid at near-zero (but positive) slope.
3
Size of overflow pit should match the pipes connected to it. It should be sized to facilitate ease of maintenance.
Page 7-38
Qmin or = Qweir = B C w L hw
3/ 2
For the 5year ARI event, assuming a blockage factor (B) and weir coefficient (C) of 0.5
and 1.7, respectively, the weir length is
L=
Qmin or
B.CW .H
3
2
0.01
3
2
= 0.05m
A 0.05m weir length is equivalent to a 130mm by 130mm pit smaller than the
standard 600 mm by 600 mm pit.
For drowned outlet conditions, the orifice equation is used:
Q = B.C d . A 2 gh
For the minor flow event, given a discharge coefficient of 0.6, the required area of the
pit is
A=
0.01
0.5 0.6 2 9.81 0.1
= 0.03m 2
The equivalent pit dimensions for the drowned outlet condition are 180mm by 180mm
smaller than the standard 600 mm by 600 mm pit.
Hence, the 600mm by 600mm pit is to be adopted.
Step 8 Vegetation Specification
Consultation with the National Parks Board is required in determining the list of
suitable plant species for the proposed bioretention basin.
Step 9 Verification Checks
Flows for the 5yr ARI (Q5) and 100yr ARI (Q100) storm events may be conveyed
through the bioretention system. A check for vegetation scouring is completed by
checking that velocities through the bioretention system are below 0.5m/s and 1.0 m/s
for the 5yr ARI and 100yr ARI event, respectively. The scour check is performed
using Equation 7.6.
Given the width of the basin is 2m and the extended detention is 0.2m, the susceptible
flow area is 0.4m2. Hence,
v5 year =
Q5
= 0.03m / s < 0.5m / s
A
v100 year =
Q100
= 0.05m / s < 1.0m / s
A
Hence, bioretention system can satisfactorily convey the peak 5yr and 100yr ARI
flood, minimising the potential for scour.
Page 7-39
Residential
Commercial
Roads
300
0
100
m
2
m
m2
Residential
Commercial
Roads
Weighted average
0.6
0
0.9
0.74
Basin Area
Maximum width
maximum ponding depth (extended detention)
Filter media type (hydraulic conductivity)
14
2
0.2
180
m2
m
m
mm/hr
5
100
year ARI
year ARI
93
77
49
%
%
%
10
minutes
mm/hr
mm/hr
mm/hr
- Fraction Impervious
Conceptual Design
Singapore
166
271
106
0.74
0.01
m3 /s
Qmajor
0.022
m /s
Q infil
0.0009
m /s
3
3
yes
yes
0.14
y/n
Volume (Vs)
Area (As)
0.48
Depth (D)
0.5
m2
m
m3
Check flow widths in upstream channel
Minor storm flow width
CHECK ADEQUATE LANES TRAFFICABLE
0.95
OK
0.62
Kerb opening width
4. Specify bioretention media characteristics
Filter media hydraulic conductivity
Filter media capacity
Filter media depth
Drainage layer media (sand or fine screenings)
Drainage layer depth
Transition layer (sand) required
Transition layer depth
180
0.0009
600
gravel
200
yes
100
mm/hr
m3 /s
mm
mm
mm
100
1
0.003
0.02
OK
mm
m3 /s
3
m /s
10
180
yes
mm/hr
mm/hr
600x600
LxW
8. Vegetation Specification
9. Verification Checks
Velocity for Minor Storm (<0.5m/s)
Velocity for Major Storm (<2.0m/s)
Treatment performance consistent with Step 1
0.03
0.06
yes
m/s
m/s
Page 7-40
Page 7-41
7.7
References
CRCCH (Cooperative Research Centre for Catchment Hydrology), 2003, Model for
Urban Stormwater Improvement Conceptualisation (MUSIC) User Guide, Version 2.0,
December
Engineers Australia, 2003, Australian Runoff Quality Guidelines, DRAFT, June
FAWB (2009), Adoption Guidelines for Stormwater Biofiltration Systems, Facility for
Advancing Water Biofiltration, Monash University, ISBN 978-0-9805831-1-3, June
2009.
Institution of Engineers Australia, 1997, Australian Rainfall and Runoff A guide to
flood estimation, Editor in Chief Pilgram, D.H.
Leinster, S 2006, Delivering the Final Product Establishing Water Sensitive Urban
Design Systems, 7th International Conference on Urban Drainage Modelling and 4th
International Conference on Water Sensitive Urban Design Book of Proceedings,
Volume 2, A Deletic and T Fletcher (eds), Melbourne.
Public Utilities Board (PUB), 2000, Code of Practice on Surface Water Drainage, Fifth
Edition
Page 7-42
Cleansing Biotopes
EngineeringProceduresforABCWatersDesignFeatures
Chapter8CleansingBiotopes
EngineeringProceduresforABCWatersDesignFeatures
Chapter8CleansingBiotopes
8
Chapter 8 Cleansing Biotopes
8.1
INTRODUCTION
8.2
8-1
8.2.1.1
8.2.1.2
8-4
8.2.1.3
8-5
8-7
8.2.2
8.2.2.1
8.2.2.2
8.2.2.3
8.2.2.4
8.2.3
8.2.2.4.1.
8.2.2.4.2.
Design Discharge
8-10
Specifications
8-10
8.2.3.1
Multi-layered Liner
8-10
8.2.3.2
Pipes
8-10
8.2.3.3
8.2.3.4
Plants
8-13
8.3
8.4
8.4.2
EngineeringProceduresforABCWatersDesignFeatures
Chapter8CleansingBiotopes
8.4.3
8.4.4
8.5
Introduction 8-16
8.5.2
8.5.2.1
8.5.2.2
Design Outflow
8-18
Planting Scheme
8-19
REFERENCES
8-20
8.5.3
8.6
EngineeringProceduresforABCWatersDesignFeatures
8.1
Chapter8CleansingBiotopes
INTRODUCTION
GeneralDescriptionofCleansingBiotopeSystems
Cleansingbiotopesareaformofartificiallyconstructedwetlands.Theyconsistofnutrientpoor
substrates that are planted with wetland plants which are known for their water cleansing
capacity.Becauseofthehighperformancepotentialofsuchnaturalcleansingsystemstheycan
beimplementedinavarietyofsituations,suchastherevitalizationoflakesandthecleansing
ofurban waterbodies.Waterbodies thatareonlyslightlypolluted can be treated especially
efficientlywiththistypeofsystem.
Inspiredbynature,cleansingbiotopesoffereffectivewatertreatmentwithasoftandnatural
aesthetic.Maintenancerequirementsarelowandeasytocarryout.Thesepracticalandvisual
aspectscombinedwiththeircleansingpotentialmakethemanattractiveelementofawater
system.
EngineeringProceduresforABCWatersDesignFeaturesPage81
Chapter8CleansingBiotopes
Theycanbeimplementedinavarietyofsituations:
outdoorareas,suchasparks,openfields,pondsandlakes
rooftopgardens,wintergardensinbuildinginteriors,openplazasnexttobuildingsor
evenunderelevatedstructures
subdivided into smaller areas (such as small skygardens and planters) that work
togetherinsequenceforincrementalcleaning.
BENEFITS
canbeconstructedsimply
completelyflexibleinformcanbesubdividedintosmallerbiotopeareas
highlyecologicalwateriscleansednaturallywithouttheuseoftoxicchemicalssuch
aschlorineorozone(Mechanicaltreatmentprocesses,suchasmechanicalfiltrationor
UVtreatmentcan,dependingontheappliedsystem,generallybedonewithout.)
8.2
DESIGNPROCESS
This segment outlines the general steps for determining the overall design of a cleansing
biotope, highlighting the different factors that has to be taken into considerations. Land
availability,sitetopography,landuseandurbanplanningparameterswouldpresentlimitsand
opportunities for locating and sizing the cleansing biotope. On the other hand, the primary
motivationforcleansingthewater,whetheritisforonsitereuseortoaidinachievinggreater
national stormwater management efficiency, would determine the desired level of water
purificationand,subsequently,thehydraulicflow,detentiontime,pipingsystem,aswellasthe
typesofsubstrateandvegetationtobeused.
EngineeringProceduresforABCWatersDesignFeaturesPage82
Chapter8CleansingBiotopes
EngineeringProceduresforABCWatersDesignFeaturesPage83
8.2.1
Chapter8CleansingBiotopes
LANDSCAPEDESIGNCONSIDERATION
8.2.1.1 SiteSurvey
Adetailedlandsurveyofthesiteshouldbeundertakentoidentifyexistingsiteconditionsthat
maypresentconstraintsaswellasnaturallyconduciveopportunitiesfortheoptimumlocation
andsizeofthecleansingbiotope:
TopographyNaturaldepression,existingslopesandchangesinlevelsthatwould
advantagethedesiredflowofwater,particularlyinmultitieredcleansingbiotope
systems.
Soil content availability of material suitable for substrate (refer to substrate
specification).Variationstotechniquesofsoilcompacting.Plasticityofsoilwould
determine the types and rigidity of structures, such as concrete foundations,
berms,tobedesignedasedges.
VegetationDetermineexistingvegetationswhichcanbetransplantedforusein
the cleansing biotope. Where comparable, indigenous plants are preferred over
introducingnewspeciesintothesite.Thiscouldbeseenasaneffortinconserving
the ecological heritage of the site. More practically, this would minimize any
adjustmentsthattherestofthelocalfloraandfaunahavetomake,thusensuring
acontinuityoftheecology.Diversityofplantsratherthanmonoculture.
Immediate Surrounding area future changes possible expansion. Existing elements
(streams,reservoirsetc.)
8.2.1.2 Determineurbanplanningparameters
Precise information of the following must also be obtained from relevant governmental
authorities,andverifiedagainstthesitesurvey:
Locationsofthesiteboundary
Locationsofanydrainagereservesandexistingdrains,includingtheirculvertlevels
and required hydraulic capacity. This is especially important for designing the
hydraulic flow of the cleansing biotope, particularly in its interface with the
existingsystem(inflowanddischargepoints).
Locationsofanyroadreservesandsetbackswherethedevelopmentisadjacent
to a road, care must be taken to ensure that no structures are within any road
reservesandsetbacks.
Athoroughunderstandingof,andadherenceto,thebasicauthorityrequirementsiscitical.
Itis imperativethat the relevantauthoritiesareconsultedduring thecommencement of
thedesignprocess.Theseinclude,butarenotlimitedto,thefollowing:
EngineeringProceduresforABCWatersDesignFeaturesPage84
Chapter8CleansingBiotopes
ObtainingplanningapprovalfromtheUrbanRedevelopmentAuthority(URA),
8.2.1.3 ConfirmTreatmentPerformance
Thefollowingliststhetypesofpollutantsthatcanberemovedusingcleansingbiotopes
OrganicLoad:
Cleansingbiotopesareveryefficientatbreakingdownbothparticulateanddissolvedorganic
materials. Thedegradationoforganic carbon composites occurswith thehelp ofoxygenfed
microorganisms.Microfaunaliveinsymbiosiswithplantrootsinthevirtuallyinfinitelylarge
surfaceofthesubstratematrix.Thenecessaryoxygeninputintothesystemoccursthroughthe
waterthatistobetreated.Theplantscontributesignificantlytotheoxygenloadthroughtheir
rootsystems.Carbonisextrudedfromthesysteminformofcarbondioxide.
Phosphate:
Aspecificchemicalcompositionofthesoilmatrixcanbeachievedthroughacontrolledmixing
of substrates. Dependingon thechemical composition of the soil matrix a good phosphate
bondingcharacteristiccanbeachieved.Theadditionofmetallicoxidesorredlavarockwithan
ironcontentofupto15%cansignificantlyincreasethephosphatebindingcapability.Theyear
round input of oxygen into the system prevents the rerelease of phosphates. An effective
bindingcapacityofthesoilmatrixcanbeassumedformanyyears.
Nitrogencomposites:
In the presence ofoxygen bacteria nitrify ammonium. The following bacterial denitrification
canonlyoccurtoaverysmallextentinaerobicconditions.Theplantswillpartiallyfeedoffof
thenitrates.
PathogenicBacteria:
Pathogenscannotreproducethemselvesoutsideofhumanoranimalorganisms.Toisolateand
remove them effectively, it is hence important that the water is retained in the cleansing
biotopeforasufficientlylongtime.Inaddition,thetransitionbetweenaerobicandanaerobic
zonesprovidesahighlevelofbacteriadestruction.
WATERQUALITYSTANDARDS
Therearevariousreasonsforwantingtoincludeacleansingbiotopeinadevelopment.
Itcouldbemotivatedbysocialresponsibility:thedesiretocontributetotheefficiencyofthe
national stormwater management system andPUBs ABC strategyof diversification (refer to
EngineeringProceduresforABCWatersDesignFeaturesPage85
Chapter8CleansingBiotopes
ABCWatersGuidelines).Insuchacircumstance,thecleansedwaterfromthecleansingbiotope
isintendedtobedischargedimmediatelyintothepublicstormwaterinfrastructure,andwould
thus require a lower level of water purification. Nevertheless, it is recommended that a
sufficientlevelofpurificationisaccomplishedtoenhancethehealthygrowthofdownstream
ecology.
In some cases, the cleansing biotopes are meant to recycle the water for reuse onsite.
Commonly, these local uses include irrigation and the flushing of toilets, or to supply and
replenishthewaterinaestheticpondsandwaterfeatures.Thepossibilityofhumaninteraction
(butnotconsumption)necessitatesahigherlevelofpurification.
Cleansing biotopes have also been successfully implemented to purify water for water
playgrounds,wherechildrenarelikelytounintentionallyconsumemouthfulsofwater.Amore
stringentstandardofwaterpurificationwould,insuchsituations,havetobekept.
Asexplainedabove,standardsofwaterqualityaretypicallysetaccordingtoitsintendeduse.
Thesedifferentstandards includebenchmarksfordifferent typesofcontaminantsand water
qualityindicators.
Theseincludes:
For drinking water colour, alkalinity, dissolved metals, salts and organics matters, heavy
metals
ForenvironmentalwaterpHlevel,salinity,dissolvedoxygen,pesticides
ISOStandards
The International Organization for Standardization (ISO) has established standards of water
quality for various uses and situations, including potable water, industrial discharge and
sewagewater.ThesearespecificallycoveredinsectionICS13.060.
http://www.iso.org/iso/iso_catalogue/catalogue_ics/catalogue_ics_browse.htm?ICS1=13&ICS
2=060
LocalStandards
The following provides local standards that have been set by the National Environment
Agency:
NEAFrequentlyAskedQuestions(FAQ)onWaterQuality
http://app.nea.gov.sg/cms/htdocs/category_sub.asp?cid=38
NEAEnvironmentalPollutionAct
http://app.nea.gov.sg/cms/htdocs/category_sub.asp?cid=189
EngineeringProceduresforABCWatersDesignFeaturesPage86
Chapter8CleansingBiotopes
PipedDrinkingWaterUnit
http://app2.nea.gov.sg/topics_dwu.aspx
NEAWaterQualityStandardsforSwimmingPool
http://app.nea.gov.sg/cms/htdocs/article.asp?pid=2934
RecreationalWaterQualityGuidelinesForRecreationalBeachesAndFreshWaterBodies
http://app.nea.gov.sg/cms/htdocs/article.asp?pid=3039
NEA Allowable Limits for Trade Effluent Discharge to Sewer / Watercourse / Controlled
Watercourse
http://app.nea.gov.sg/cms/htdocs/article.asp?pid=1644
NEANewTradeEffluentStandardsforDischargeintoWatercourseandControlled
Watercourse
http://app.nea.gov.sg/cms/htdocs/article.asp?pid=2538
Onceadesiredlevelofwaterpurificationisdecided,theotherfactorsthatcontributetoitcan
thenberesolved.Thesevariablesincludethehydraulicflow,detentiontime,pipingsystem,as
wellasthetypesofsubstrateandvegetationtobeused.Differentcombinationsofeachcould
be employed to achieve the desired water purification level, and it is recommended that a
landscape architect and hydrology specialist be engaged to determine the most suitable
combination.
8.2.2
HYDRAULICDESIGNCONSIDERATIONS
8.2.2.1 DetermineDetentionTime
As explainedabove, thedetentiontime withinacleansingbiotope has immediate effectson
thelevelofwaterpurification.
Detention time is a measure of how long a particular molecule of water stays within a
cleansingbiotopefromthetimethatitwasintroducedtothetimethatitisdischarged.Thisis
commonly measuredusingthePlugflowmethod,whichassumesconstant velocityof water
flowacrossanycrosssection.Itisthusassumedthatthefirstmoleculeenteringthecleansing
biotopewouldalsobethefirstmoleculeexitingfromit.
As a general gauge, wastewater that is highlypolluted requiresabout 23 daysof detention
time,whereaswaterthatismoderatelypolluted(equivalenttolakewater)wouldonlyrequire
about12hrs.
Ahydrologistshouldbeengagedtodeterminethespecificamountofdetentiontimeneeded
toachievetheminimumdesiredlevelofwaterpurification.
EngineeringProceduresforABCWatersDesignFeaturesPage87
Chapter8CleansingBiotopes
8.2.2.2 SizeCleansingBiotopeandDetermineDesignFlows
Detention timeisproportionalto the size ofthe cleansing biotope.As such, the most direct
way of achieving a higher level of purification would be to increase the detention time by
increasingthesizeofthecleansingbiotope.
Q=flowrate(m3/hr)
V=Volumeofwaterincleansingbiotope(m3)
T=detentiontime(hr)
V=Volumeofwaterincleansingbiotope(m3)
A=filtersurface/cleansingbiotopearea(m2)
H=depthofwaterincleansingbiotope(m)
Wherespaceisplentiful,thecleansingbiotopecanbesizedtoachievethenecessarydetention
time. Where there is insufficient space to implement the required size of cleansingbiotope,
othervariables,suchasfilterdepthandfiltermaterial,couldalsobeadjustedaccordingly.
A=filtersurface
Q=flowrate
kf=saturatedhydraulicconductivity
H=waterdepth
s=filterdepth
dh=leveldeviation
D=permanentwaterlevel
EngineeringProceduresforABCWatersDesignFeaturesPage88
Chapter8CleansingBiotopes
8.2.2.3 ShapeofCleansingBiotope
A constant and evenlydistributed flow of water in the biotope is necessary for optimum
cleansingeffectiveness.Segmentingacleansingbiotopeintoseveral(usuallythree)areashas
thebenefitofextendingitslifecycle.Runningthesegmentsinturnallowseachtoconsistently
haveaperiodofregenerationthatguaranteesthelongtermpermeabilityofthetoplayerof
the filter substrate. For example, water could be fed to each area for a period of 4 days
followedbyabreakof2days.Assuch,inathreesegmentsystem,twoareasareinoperation
whilethethirdisregenerating.
8.2.2.4 DetermineDesignFlow
8.2.2.4.1
DesignInflow
Regulatingwatervolume
Inspecificinstances,thevelocityofinflowisfixed.Forexample,acleansingbiotopefedbya
stream that has a bypass channel or flume would not have to worry about variable water
inflow. In other cases where water level is susceptible to fluctuations, cleansing biotopes
wouldhavetobeimplementedincombinationwithregulatingdevices,suchasholdingponds
orweirs,inordertomaintainaneveninflowofwater.Thisistoensureaconstantdetention
timethathasadirecteffectonthelevelofwaterpurification.
Inflowloading
Dependingonvariousfactors,polluted
water can be introduced into the
cleansingbiotopesin2generalways:
topflow waterisintroducedfrom
the top of the bed, either as an
overflow from the higher terraces, or
usingdistributionplates.Ashallowfilm
of water is visible above the biotope
bed which then percolates down
throughthesubstrate.
Distributionplate
EngineeringProceduresforABCWatersDesignFeaturesPage89
Chapter8CleansingBiotopes
Sideflowwaterispipedintothecleansingbiotopesfromoneendofthesideofthebed,
such that the pipes are submerged in the substrate. In this case, the polluted water flows
throughthesubstrateataslowerrateandisnotvisibleonthesurfaceofthecleansingbiotope
aswaterleveldoesnotriseaboveit.Thisisespeciallyeffectivefortreatingblackwater.
8.2.2.4.2.
DesignDischarge
In the topflow model, water is collected using perforated pipes at the bottom of the
substrate,andisthenconveyedtoitsdesiredlocation.Itsfinaldestinationcanbemoderately
far away, up to several hundred metres or several kilometres, as long as there is sufficient
pressureforitsconveyance.
8.2.3
SPECIFICATIONS
8.2.3.1 MultiLayeredLiner
MultiLayeredLineristobecomprisedofthefollowing:
1.
Anchors:Formembranesecurement;steelrod,6mmdia.
2.
Stabilisationmat:10mmthick,nondecaying,forstabilisingslopes
3.
Waterproofingmembrane.
4.
Geotextilemat:levellingandprotectivelayer.
5.
Wiremeshblankets:Protectionagainstrodents,plasticcoatedagainstcorrosionmesh
8.2.3.2 Pipes
PressurePipes
PressurePipesaretohavethefollowingcharacteristics:
a)
Comesinaroll
b)
Material:Polyethylene(PE)
Pressurepipesshouldbeconnectedtogetherwithelectrical
weldedfittings.Theycanbeflushedthroughwithhighflow
pressurizedwaterfromthecontrolroomandallpipesareto
beaccessible.
EngineeringProceduresforABCWatersDesignFeaturesPage810
Chapter8CleansingBiotopes
DrainagePipes
Drainage Pipes on the floor of the cleansing
biotope are to have the following
Characteristics:
a)
b)
Material:Polyethylene(PE)
GravityPipes
Gravity Pipes are to have the following
Characteristics:
a)
Material:Polypropylene(PP)
b)
Dimensions:varies
Gravitypipesuponinstallationtobeabletobe
flushedthrushfromoutletmanholes.Pipesare
to be laid with a gradient and be capable of
conveyingwaterwithoutpressure.
8.2.3.3 FilterSubstrate
Cleansing Biotope substrates contributes to the purificationprocess through multiple micro
functions:
Secondly,theysupportbacterialgrowth
Theyalsoremovecontaminantsthroughaprocessofsurfaceabsorptionandcomplexation.In
thisparticularprocess,thereisaninverserelationshipbetweenthesizeoftheparticlesandits
EngineeringProceduresforABCWatersDesignFeaturesPage811
Chapter8CleansingBiotopes
purification effectiveness. As particle size decreases, total surface area increases, which
effectivelyincreasessurfaceabsorptionrates.
This,however,hastobebalancedwithhydraulicconductivity,whichhasadirectrelationship
with the size of the substrate particle. As particle size decreases, the less permeable the
substrateandtheslowertheflowofwaterthroughit.
Asaruleofthumb,themostsuitablesubstratewouldbecomprisedofthesmallestparticle
thatcanstillmeettheminimumhydraulicconductivity.Empirically,coarsetomediumsized(1
3mmdiameter)sandhasproventobeveryeffectiveinachievingthisbalance.Thechemical
makeupofthesubstratemustalsobetakenintoconsideration.
Depending on availability, various combinations of materials can be used to achieve similar
results.Thefollowing3formulasdefinetherelationshipbetweentheflowrateofthewater,
permeabilityandparticlesizeofthesubstrate.
ThefollowingisanexampleofwhathasbeenspecifiedfortheKallangRiverBishanParkcase
study. This is just one example of what would be suitable for Singapore. Each site would
present different requirements and a specialist should be engaged to determine the
appropriatesubstratecomposition.
The Filter substrate is to be mixed offsite and brought onto site and should consist of the
following:
a)
Sand
i)
particlesize13mm
EngineeringProceduresforABCWatersDesignFeaturesPage812
ii)
b)
Chapter8CleansingBiotopes
chalkcontent020%
Lava
i)
particlesize24mm
ii)
ironcontent010%
TheFiltersubstrateisnottobecompactedduringconstructionstageorpostconstruction.
8.2.3.4 Plants
Itisimportantthatthefiltersubstrateisthoroughlywashedbeforelayingtopreventanystray
foreignparticlesfromcloggingup/affectingthechemicalcompositionofthesubstrate.Filter
substrateshouldalsonotbecompactedduringconstructionoraftercompletion.
Planting
The planting of the cleansing biotope is an important element of the overall system and
ensures the longterm performance and theinfiltration capacityof the substrate.Depending
onsiteconditionsandplantrequirements,nearlyallwetlandplantscanbeused.Thecommon
reed(Phragmitesaustralis)isthemostcommonlyusedplant.
In water bodies with low nutrient loads the planting should be relatively dense and potted
plantsshouldbeplantedsoastobalanceouttheinitiallownutrientlevelsandcompensatefor
anyrelatedlossofplant material. Theplantingneeds little maintenance. Thechief taskis to
removedeadandcutplantmaterial.
PlantSpecies
Diversityispreferredovermonoculture
Wherepossible,indigenousplantshouldbeincluded
Wetlandspeciesthatarecapableforadaptingtofluctuatingwaterlevelshasahigher
chanceofsurvivalandrobustgrowth
Plantswithdeeprootswillaidinsupportingthesubstrate
The Kallang River Bishan Park project is the pilot implementation of a cleansing biotope in
Singapore.RefertoKallangRiverBishanPark(KRBP)casestudyforalistofsuggestedspecies.
KRBP is the pilot implementation of a cleansing biotope in Singapore, and is currently
EngineeringProceduresforABCWatersDesignFeaturesPage813
Chapter8CleansingBiotopes
undergoing construction. As such, the plants are currently being tested for suitability to
Singapore climate. Other aquatic plants may also be appropriate, but would have to be
verified.AconsultationwithNParksisrecommendedtodetermineanyothersuitablespecies.
8.3
CONSTRUCTIONPROCESS
Constructionofterraces
Layingofliner
Layingofpipes
Addingfirstlayerofsubstrate
Leveling
Addingsecondlayerofsubstrateand
topsoil
Preparationforplanting
EngineeringProceduresforABCWatersDesignFeaturesPage814
Chapter8CleansingBiotopes
8.4
MAINTENANCEREQUIREMENTS
Cleansing biotopes perform best when there are no suspended solids in the inflow, as they
tend to clog the substrate. The polluted water can be passed through a settling tank or a
skimmertoremovethesuspendedsolidsbeforebeingfedintothecleansingbiotope.
Ageneralmanagementregimethatincludesthefollowingsteps:
8.4.1
Waterqualityandquantitymonitoring
8.4.2
SubstrateMaintenance
EngineeringProceduresforABCWatersDesignFeaturesPage815
Chapter8CleansingBiotopes
8.4.3
Plantmaintenance
Plant maintenance is minimal, and generally involves basic regimes, such as inspection for
signsofinsectdamageorinfestation,theremovalofdeadplantsandpruning.
Fertilizing,bothduringandafterplantestablishment,isnotnecessary.
8.4.4
MosquitoControl
In both models of cleansing biotopes, mosquito control is not necessary as there are no
stagnantwaterformosquitobreeding.Inthetopflowmodel,waterisconstantlyinmotion
andpercolating to thebottomof the substrate. Inthesideflowmodel,wateriscontained
beneath the surface of the cleansing biotope, such that neither mosquito, not algae growth
couldoccur.
8.5 WORKEDEXAMPLEBishanPark,Singapore
8.5.1
Introduction
EngineeringProceduresforABCWatersDesignFeaturesPage816
Chapter8CleansingBiotopes
8.5.2
DesignFlow
8.5.2.1 DesignInflow
Watertothecleansingbiotopeismainlyfedfromthepond,throughapumproom.Water
fromtheendofthepondisalsorecirculatedbacktothecleansingbiotope.
EngineeringProceduresforABCWatersDesignFeaturesPage817
Chapter8CleansingBiotopes
8.5.2.2 DesignOutflow
The cleansing biotope at Bishan Park is aimed at improving the quality of the water in
threedifferentlocations:
Waterplayground
Locatedtotheeastsideofthecleansingbiotope,thewaterplaygroundisintendedfor
kidsofallages.Assuch,thequalityofthewatermustmeetpotabledrinkingstandards.
Ponds
Thepondsarehome to manyof theaquatic fauna foundinBishanPark.Thewater in
thelakeshouldthereforemeetenvironmentalhealthstandards.Theseriesofpondsis
alsodesignedtoendinawatercascade/overflowthatwillgivevisualprominenceto
moving water as part of a wider water recirculation system, thus potentially attract
humanpeopletowadeandplayinit.Assuch,alevelofwaterqualitysufficientforsafe
humaninteractionisalsonecessary.
KallangRiver
Water discharged to the Kallang River would eventually flow downstream towards
Marina Barrage, passing through channels and streams where diverse wildlife and
ecologythrive.Itisthereforedesignedtoalsomeetenvironmentalhealthstandards.
EngineeringProceduresforABCWatersDesignFeaturesPage818
Chapter8CleansingBiotopes
8.5.3
PlantingScheme
GROUP
BOTANICALNAME
COMMONNAME
Group1
Pontederiacordata
PickerelWeed
Typhaminima
SingaporePink
Cyperushaspanvar.vivipurus
Trimeziamartinicensis
TigerEyeIris
Pontederiacordata
PickerelWeed
Thaliadealbata
Thalia
Acrostichumspeciosum
MangroveFern
Lycopodiumcernuum
CreepingClubMoss
Thaliadealbata
Thalia
Cyperushaspanvar.vivipurus
Lycopodiumcernuum
CreepingClubMoss
Trimeziamartinicensis
TigerEyeIris
Typhonodorumlindleyanum
Group2
Group3
Group4
Thefollowingarepossibleedgeconstructionfortheterraces.
OptionB:Plantedbanks
OptionC:Concrete/stoneslabs
EngineeringProceduresforABCWatersDesignFeaturesPage819
8.6
Chapter8CleansingBiotopes
REFERENCES
Kadlec,R.R.Knight.1996.TreatmentWetlands,LewisPublishers,Chelsea,M.I.
EngineeringProceduresforABCWatersDesignFeaturesPage820
Bio-engineering
9.1
INTRODUCTION
9.2
DESIGN PROCESS
9.2.1
Determine Application
Site Survey
9.2.2.1 Topography
9.2.2.2 Geology
9.2.2.3 Wind / Hydraulic Condition
9.2.2.4 Existing Vegetation
9.2.3
9.2.3.1 N-values
9.2.3.2 Slope and Rigidity
9.3
9.2.4
Determine Techniques
9.2.5
Specifications
9.2.6
Maintenance
TECHNIQUES
9.3.1
9.3.2
9.3.3
9.3.4
9.3.5
9.3.6
Multiple Fascines
9.3.7
Reed Roll
9.3.8
9.3.9
9.5
REFERENCES
-)(
%"%!#
' %
%
# '
*% %
% '+
#%
*
$
+
* !
+'
#
'
# %
%#
'
!
&%%'
# # !
(%
% !
#
% ! !' !
*% # #% % $ ! '+
##
('
-(,
Chapter 9 Bio-engineering
9.2 DESIGNPROCESS
Page 9-3
#!2.-!
&!$!#
&!$!#!#
!(!"&!#"!&"($#(*
#( ! # # # ( #!* "$#! #!# #", !"#( !
#"! $("##!&#*#$"!!#("####!,"
!!$#$*#!%!"#(#!"!*#!"$##&
!#(#!,
!"(!""#)#,
&!$!#!$
"
! "-"#)# ! & # ! " $#" ## &!
-- % #!$ # ! # $", "
$#"$+
!###""$!!!"$"(##"/"&*!*&&#!*
&0
$#%#(&#!&
##"###"#""#"
#"#'#$!"!%#""
!#"#$!%#!#$!#"#"!-!
#"!##(#!$#!##$#!#"
"!!!
$##$$"#"#!$#$!"
!""#!#(#!$!##&!"
!%#! $#(
&!$!#!%
! " " %#" #" # #" #$!, "# #(
!%!#"!!#!#(##$#(-#!"$"##(
"("#,
#!#""$#$%!#*!#$#"##
!%!##%,
&!$!$
# " !## ## #!$ "# "$!%( " !! $# !! # "#!$# #* "
# !# ## " #! &$ # # "" $! # " !"", #
&$"##!#$#"!"#!#"!##"#+
!!$!"!#!""#$!"2-1
4.-
(!%!%!$
(!%!&
" % *"+ ! /! '
! ' '!0 $ !)
! ! ! )%" "
% )
! % "
" ! $ !
! )
(!%!&!$
#
!- !%! # #" %
' (
#(
- "" %/,0
" ! 2)1
!-
%!!/0
# ! %!/,0
!
!
4-3
#!9/.!
* # # " n* " !( !%
#"%!"(!!####%#(#&#!&,
&!"#(.%$"!%!$"#(""+
"0"#$!*"!#!""1
3,347
3,353
3,357
!"#!"0*"#!#*!#"1
3,347
3,353
3,355
'%#
3,347
3,357
3,363
0"#(##*&("1
" ! # $ &$ % !!" .%$
&$ # # & &#! !#(, ! $# # #
"!# $"(##(%##$",
" !
!# $"%%!(!#""#)##",
&"!$!$## $""&#"#!*!#
#!"$##("#)""%!(!#",
#
!"#$"&#$##
"
.#'#&#""
.#'#&#!!
!$"
##!""
#.&-.!&#$##
!"#
!&
##!!"
&
"" ! !" ! " # # # #! #& #
# # &#!, ( !%# #$!$ # #" " #$"
!## # " ! !", ( ! #(( $" #" &# .
#'#!$"##!""",
""3+1 "!" #"!# ""#!+
%!$
""3+1 "!" !"#!+
! ! " "! " %" ! ")
"! ''!#!")!- #")%"#""
&!!$ "+
" "! $ " $! !
!"(")""!"" %"!!$ !+
!" #"# !) %$ ) %" %'! ! $) '
! "!+ $"! /++ !"! ! $
'%" $"'0!""/ !!"! "
!) " "0 ! "# " " $ +
' #"
#"') "/ "! !)" "!"
$" "+0!!! '+ " !##"%*
" " ' ) # !) !) !# "! "" !
!! '" """"!," !,"# +
" " ) #"') #! "!) " !)
!!)! #!"#
""# !,!"!'+
# ! " !!"# !
3-2
!3)(
% !
" *
+!!!
!!"!
#
"!
"!
!
o
'$ !$
o !!
o .1(/1!*" "+
o '2-(.--&
o ! '1-(2-&!
#" !!*/(1+
!&$%!
o
'
#
!
!
" ! !" 3(2
6('
5*)
/'
$
%
"
('
0'
!
$
+
#'0.,
'
1'
$' $
'
$
3.'
2'
$ !
%
$
$ " ' #' 3
!!$0'
/.
!
$'
5)//
3('
"!!
!
%!
-&
#
&
#2,'-,,%!
"&/,'0,
&
#
&
.&
&
!
&
!
#
&
!
#
!
#
!!
!&
/&
#
%
"&.,'/,
!
&
0&
#
#
!
& !
&
3'-/
!6*)
5)(
%"$
o &
#
o
"
$!
5(.3
4('
!6+*
!%!
#!&"!"!! ,3//*6//-
!
"!%#!
0) !#" "!!!&!
!) ! #& 5/*0// ' ! $ " ! ! ! "
%) 2/*3/ ! ! 3 ) " !! ! #
!!&"'!!! !)
1) !!! !'!!$!#) "!!
! " ! ! !$ ! ! ! & !
!" !!!)
! " !
"$&!!! !$#!"&#$!$!
$! )
2)
!(&" !!'!"%)1/*2/
!!$!!#! "!!!!!)
3) ! ! ! & " " ! &
# $ ! ! !!)
$" #! !
!)
" ! !" 6*06
6*)
2' '
'
3' ! % +$'02$02,& #
) ' 2 # !
! !( '
4' ! % % & % !
! '
5' % " & ! 0/)02 "
# ' 2/ " "&
% ! ! # &
! !( '
!
!
6)1/
!8,+
!
#*" !!-2+5.
!%!
#!&"!"!!
!
1) !#" "!!!&!
!) ! #& 70+100 ' ! $ " ! ! ! "
%) 30+40 ! ! 4 ) " !! ! #
!!&"'!!! !)
2) !!! !'!!$!#) "!!
! " ! ! !$ ! ! ! & !
!" !!!)
! " !
"$&!!! !$#!"&#$!$!
$! )
3)
!(&" !!'!"%)20+30
!!$!!#! "!!!!!)
4) ! ! ! & " " ! &
# $ ! ! !!)
$" #! !
!)
5) #! $!&! !&$+
%)!60+100)
" ! !" 8+22
"%#=0!/ #
!;-,
!
" "
o )
!%!
"!! .922+4/
!
!$ !
3* !%*72%72! !*
4* # ( $ ! ! ! ! !*
$
! ! ( " # !$,! !
! #!&!!"( !322,342!# *
5*
& ! !%! ! !( $! ! !
!*
!!!! !$!!*
6* !" + !!! 5,7!
!. '/*
7* !!%!#! ! " !%*52,
:2!*"!" !$ ! *
8* !" + !! !%*6,7! +
4*
9* %!!!%!!! !!!!!#! !
#!!!*"!" ! ! !%*
6 ! +4( "!!! "42,52#!$
! ! !%!* ! ! !%! ! !
"!!!! *
5'&
-,
(4,&-,,
)#(1&-,
)
-,%/ "
-,%0
$
-%
"(!%.,
)%
.%
"# "
&
( )%
"
&%
/% "
"
# " "
#
#
"
%!%1
".
%-,
""%
0% %
1%
%
5&.3
!7.-
"$ !
!
21 "!! !!/51-2110( ! &#
22 #" !!/3-60
23 !($&!
23*4 )
!
)!" !!"/#!26.310
!!") -#%!"/1-3110
!
&&-!%!(-$#-"
5*)
"!
!!) 72 & 72 %( !" , " !
"&"!
, "
o ,!'""
o "!!"!" "%"
, "&"
o " "$ ' ,!
o
"$!&"""&"
"!
!" !
#"
!:,+
4*)
o !$
o !$%
(!
o #'.--)/--
o #'0--)2--
"
.' $$&""
!'
/' ! $ )"&
"!& #'3-7!$"'
0' ! (!"
" '
4)01
"%#<2!1 #
! %
&%%!&"# % #/$""#!'
%!
$% #$
6. # % $%# %! $# "#!. )'% % )%# 85 !(
$#'%!!!%! %$.
7.
$% (# $ ! % #$ $ * $ #!($ %! % # $&#,
$&# &"%( %.
8. % (# $ ! % #$ (% $%! !$ % $&#* &$ ' +
(#!#!# %! &%&##/$#! %! .
9. &# % %!" #!( ! ! % %! % !(# ! $ * (' ' + (#$
%( %.
:. %%! %%!%#!& &$ $%" $!#$%%* $$#*.
5*)
/1 +4.)/..,%+3)/.,
/1'1 $!
+!3.)4.,
&
o )!# +.)0..,
o !&/0(/3
)"&
o )!# +.)0..,
/' $ $ #' 0. +
",'
" #'/3.*0..'
0'
$%"
"% $% '
1' $ 3. '
$'
2' ! " "
'
3' ""!'#
"'
5)15
$(&>4#3""&"
""&"&#)&'#&(&''"()&'>3<9
+('
# $ #$ %
!
# !
'$
$$"##!
%
!$ "
!
"" ! #
#!%
#$#""""%
"$ &!""
"!%! "
"
""
#"$"
%
*'&
*%$
"
"
"
#&
'#
! "
#
*$()
+'&
!
" !"""
" % " $
%
! ! ! & !
&
%
$
&
#
%
Chart showing simulation of river flow and water levels in relation to different n-values for
the existing and proposed Kallang River.
+('
#
! ' ! "
! !
# #! " !
$ $
" &
"
%#
# "
! !
%
! #" " !" #"" ! !!" ! " "! !# # "
#" ! !"(" #! " " !'!"+
#! #"" ! !"
"$ "" "#!%"!# ! "+
" -$)%" - !!"" $ ,!""! '"!# $$
% ")"""!&"""!"
" ""!"+" ' !""!" )!!%" -" "
!!#!+
!!""!!!" " '$)"" !
" #""' !( # ) ' "! %" $"'
! $
!+
%"!%!"!!% !"" ""!" !
!"!" " ! +
#!!+
!#!"#!
&#"
!
!
&"%$
!1)(
! !$ !"!%.--1!! !$!! " &!$!
! ! !"! ! & $ ! "% !
%!!! ! ! #! " %
!$!$ "$!"'
!" !"! .*.--1+
!! ! .*".--1+
!%#@2 1#
% # % %$% # &$%#% %% % #% %"&$ %$% 3## %
!@1;> #%%"&$4(#$% ! )! #%0$&%$
$ $ (%%$ !$%%)($$%$(.%!%$$!$%$%'
# ((0$ %'&$% %&%$ %#'#.
(($&# $%#&% ( & !%)97880
$
@>?1:1>9?81:7<<1=
977>.' $&'## -#
94 #/ $%#&% )!&
#
8@@<2&# !#% # #
3(%*#.#).&$%#.
%).!4
10
Constructed Wetlands
Chapter 10
Constructed Wetlands
10
Chapter 10
Constructed Wetlands
10.1
Introduction....................................................................................................10-1
10.2
10.2.1
10.2.2
10.2.3
10.2.4
10.2.5
10.2.6
10.2.7
10.2.8
10.2.9
Design Process...............................................................................................10-8
10.3
10.3.1
10.3.2
10.3.2.1
10.3.2.2
10.3.3
10.3.4
10.3.4.1
10.3.4.2
10.3.4.3
10.3.4.4
10.3.5
10.3.5.1
10.3.5.2
10.3.5.3
10.3.6
10.3.7
10.3.7.1
10.3.7.2
10.3.8
10.3.9
10.3.10
10.4
10.4.1
10.5
10.5.1.2
10.5.1.3
10.5.1.4
Chapter 10
Constructed Wetlands
10.5.1.5
Tolerances ..............................................................................................................................10-23
10.5.1.6
Transitions ..............................................................................................................................10-23
10.5.1.7
10.5.1.8
10.5.1.9
10.5.1.10
10.5.1.11
10.5.1.12
10.5.2
10.6
10.6.1
10.7
10.7.1
10.7.2
10.7.3
10.8
10.1
Introduction
The use of constructed wetlands for urban stormwater quality improvement is widely
adopted in many urban environments, many of which have been successfully
incorporated into the urban landscape. Design considerations include the interaction
between the wetland hydrology and hydrodynamic behaviour with the various physical,
chemical and biological treatment processes. The operating conditions of these
systems are stochastic in nature, with intermittent and highly variable hydraulic and
pollutant loading.
Constructed wetland systems are shallow extensively vegetated water bodies that use
enhanced sedimentation, fine filtration and pollutant uptake processes to remove
pollutants from stormwater.
Wetlands generally consist of an inlet zone (sedimentation basin to remove coarse
sediments see Chapter 4 Sedimentation Basins), a macrophyte zone (a shallow
heavily vegetated area to remove fine particulates and uptake of soluble pollutants)
and a high flow bypass channel (to protect the macrophyte zone). They are designed
primarily to remove stormwater pollutants associated with fine to colloidal particulates
and dissolved contaminants. Figure 10.1 shows an example layout of a wetland
system.
Page 10-1
Discharge water from the inlet zone into the macrophyte zone for removal of
fine particulates and dissolved contaminants through the processes of
enhanced sedimentation, filtration, adhesion and biological uptake.
Ensure that the required detention period is achieved for all flow though the
wetland system through the incorporation of a riser outlet system.
Hydrodynamic Design
Page 10-2
Bypass Spillway
GPT
By-pass
Channel
Permanent
pool
Wetland Outlet
Riser outlet
Extended detention
Inlet pool
Wetland section
Inlet Zone
Figure 10.
10.2
Outlet pool
Macrophyte Zone
Page 10-3
Design Issues
Remarks
Scour protection
10.2.2
Detention time is the time taken for an idealized parcel of water entering the wetland
to travel through the macrophyte zone assuming plug flow conditions. Simulations
using computer models, are often required to optimize, for a given site area, the
relationship between wetland detention time1 and wetland hydrologic effectiveness to
ensure treatment performance is maximised. Hydrologic effectiveness is a term used
to quantify the mean annual volume of stormwater runoff captured and treated within
the wetland and is expressed as a percentage of the mean annual runoff volume
generated from the contributing catchment. For well-designed wetlands without any
site constraints, the hydrologic effectiveness of constructed wetlands should be
greater than 80%.
The relationship between notional detention time and pollutant removal efficiency is
largely influenced by the settling velocity of the target particulates, although defining
the settling velocity of fine to colloidal particulates is not a straight forward exercise.
Standard equations for settling velocities often do not apply for fine particulates owing
to the influence of external factors such as wind and water turbulence. It is therefore
recommended that a notional detention time should preferably be 48 - 72 hours (and
not less than 48 hours) to remove nutrients effectively from urban stormwater.
1 It should be noted that detention time is rarely a constant and the term notional detention time is used
throughout this chapter to provide a point of reference in modelling and determining the design criteria for
riser outlet structures.
Engineering Procedures for ABC Waters Design Features
Page 10-4
The bathymetry of the macrophyte zone should be designed so that all marsh
zones are connected to a deeper open water zone to allow mosquito
predators to seek refuge in the deeper open water zones during periods of
extended dry weather.
Particular attention should be given to the placement of the inlet and outlet
structures, the length to width ratio of the macrophyte zone and flow control
features to promote a high hydraulic efficiency within the macrophyte zone.
Page 10-5
Provision to drain the macrophyte zone for water level management during the
plant establishment phase should also be considered.
Providing access for mosquito predators, such as fish and predatory insects,
to all parts of the water body (avoid stagnant isolated areas of water).
Providing a deep sump of permanent water (for long dry periods or for when
water levels are artificially lowered) so that mosquito predators can seek
refuge and maintain a presence in the wetland.
Page 10-6
Maintaining natural water level fluctuations that disturb the breeding cycle of
some mosquito species, but be aware that this may suit other mosquito
species.
Where possible, incorporating a steep slope into the water, preferably greater
than 30 or 3:1 horizontal to vertical. Note that steep edges may be
unacceptable for public safety reasons, and a slope of up to 8:1 horizontal to
vertical is generally used.
Wave action from wind over open water will discourage mosquito egg laying
and disrupt the ability of larvae to breathe.
Providing a bathymetry such that regular wetting and drying is achieved and
water draws down evenly so isolated pools are avoided.
Providing sufficient gross pollutant control at the inlet such that human derived
litter does not accumulate and provide breeding habitat.
Providing ready access for field operators to monitor and treat mosquito
larvae.
Ensuring overflow channels dont have depressions that will hold water after a
storm event.
Each case has to be considered on its own merits. It may be possible that a well
established constructed wetland will have no significant mosquito breeding associated
with it; however, changes in climatic and vegetation conditions could change that
situation rapidly.
Maintaining awareness for mosquito problems and regular
monitoring for mosquito activity should be considered as a component of the
management of these sites. Effective and environmentally sound control products are
available for control of mosquito larvae in these situations.
10.2.9 Designing for Maintenance Access
Access to all areas of a constructed wetland is required for maintenance. In particular,
inlet zones and gross pollutant traps require a track suitable for heavy machinery for
removal of debris and desilting as well as an area for dewatering removed sediments
(refer to Chapter 4 Sedimentation Basins). The track should be permanent and have
a maximum slope 1:10.
To aid maintenance, it is recommended that the inlet zone is constructed with a hard
(i.e. rock) bottom. This is important if maintenance is performed by driving into the
basin. It also serves an important role by allowing excavator operators to detect when
they have reached the base of the inlet zone during desilting operations.
Macrophyte zones require access to the areas for weeding and replanting as well as
regular inspections. Commonly, these access tracks can be incorporated with walking
paths around a wetland system. Maintenance access to constructed wetland needs to
be considered when determining the layout of a wetland system.
Page 10-7
7. Verify design
a. Macrophyte zone resuspension protection
b. Confirm treatment performance
8. Specify vegetation
Page 10-8
The performance of a concept design is checked using sizing curves. Sizing curves
for TSS, TP and TN removal for a range of feasible extended detention depths are
given in Figure 10.3 to Figure 10.5.
The curves for Singapore were derived using the Model for Urban Stormwater
Improvement Conceptualisation (MUSIC; CRCCH 2003), assuming the system
receives direct runoff with pre-treatment through an inlet zone and with the
macrophyte zone of 0.25 m average permanent pool depth and a notional detention
time of 72 hours. The curves provide the detailed designer with a useful visual guide
to illustrate the sensitivity of constructed wetland performance to the ratio of
macrophyte zone treatment area and contributing catchment area.
The curves given in Figure 10.3 to Figure 10.5 allow the detailed designer to make a
rapid assessment as to whether the concept design falls within the optimal size
range or if it is potentially under or over-sized, i.e.
an over-sized system suggests the concept design of the wetland may have
been inadvertently sized the wetland such that it is operating well beyond its
point of diminishing performance (i.e. where incremental increases in
wetland size, and thus cost, result in only a marginal increase in treatment
performance). In this instance, the detailed designer should confirm whether
or not the wetland size can be reduced or if additional treatment devices may
be required.
100%
90%
80%
T S S R emoval (% )
70%
60%
50%
40%
30%
750m m E x t De t
20%
500m m E x t De t
250m m E x t De t
10%
0%
0
10
12
14
16
18
20
Page 10-9
100%
90%
80%
T P R emoval (% )
70%
60%
50%
40%
30%
750m m E x t De t
20%
500m m E x t De t
250m m E x t De t
10%
0%
0
10
12
14
16
18
20
100%
90%
80%
T N R emoval (% )
70%
60%
50%
40%
30%
750m m E x t De t
20%
500m m E x t De t
250m m E x t De t
10%
0%
0
10
12
14
16
18
20
Page 10-10
Design operation flow (1 year ARI) for sizing the inlet zone (i.e. sedimentation
basin) and the control outlet structure (i.e. overflow pit and pipe connection)
discharging to macrophyte zone.
Above design flow for design of the high flow bypass around the macrophyte
zone. The discharge capacity for the bypass system may vary depending on
the particular situation but will typically correspond to one of the following:
-
Minor design flow (5 year ARI) for situations where only the minor
drainage system is directed to the inlet zone. Relevant local
government guidelines should be referred to for the required design
event for the minor design flow.
Major flood flow (100 year ARI) for situations where both the minor
and major drainage system discharge into the inlet zone.
Inlet zone connection to the macrophyte zone (or control structure as defined
in Chapter 4) normally consisting of an overflow pit within the inlet zone
connected to one or more pipes through the embankment separating the inlet
zone and the macrophyte zone.
High flow bypass weir (or spillway outlet structure) to deliver above design
flood flows to the high flow bypass channel.
For more information and design guidance for each of the inlet zone elements listed
above, the reader is referred to Chapter 4 Sedimentation Basins. When applying the
design procedure outlined in Chapter 4, the following should be used as a guide:
The inlet zone typically must comprise a deep open water body (> 1.5 m) that
operates essentially as a sedimentation basin designed to capture coarse to
medium sized sediment (i.e. 125m or larger).
Page 10-11
It may be necessary for a Gross Pollutant Trap (GPT) to be installed such that
litter and large debris can be captured at the interface between the incoming
waterway (or pipe) and the open water of the inlet zone. This is particularly
necessary if the open water of the inlet zone also serves a landscape feature
of high visibility.
The crest of the overflow pit must be set at the permanent pool level of the
inlet zone. It is common practice to set the permanent pool level in the inlet
zone to be above the permanent water level of the downstream, receiving
macrophyte zone to provide for unimpeded inflow to the macrophyte zone. As
the macrophyte zone progressive become inundated over its extended
detention depth, the overflow pit in the inlet zone will become submerged
where downstream water levels will influence subsequent discharge rates into
the wetland, ultimately causing the bypass operation to be activated.
The overflow pit and connecting pipe between the inlet zone and macrophyte
zone should be designed to convey the design operation flow (i.e. 1 year ARI
peak discharge). Assuming inlet control operation:
the pipe size that connects the inlet zone to the macrophyte zone is
determined by assuming the macrophyte zone is at the permanent
pool level and with upstream water level at the crest of the overflow
pit.
The inlet zone is to have a structural base (e.g. rock) to define the base when
desilting and provide support for maintenance plant/ machinery when entering
the basin for maintenance.
The high flow bypass weir (spillway outlet) is to be set at the same level as
the top of extended detention in the macrophyte zone.
Page 10-12
Macrophyte Zone
Inlet connection to
macrophyte zone
Inlet Zone (sedimentation
basin)
Overflow Pit
Energy Dissipater
Bypass Weir
Connection Pipe(s)
High Flow
Bypass
Channel
Design Surface
Natural Surface
Page 10-13
Page 10-14
Deep marsh
Pool
Marsh
Shallow marsh
Ephemeral marsh
Inflow
Inlet zone
Macrophyte zone
Figure 10.8
2004)
Figure 10.9 Schematic layout of a constructed wetland (see also Figure 10.
10.2)
10.3.4.3 Macrophyte Zone Edge Design for Safety
The batter slopes on approaches and immediately under the permanent water level
have to be configured with consideration of public safety (refer to Figure 10.10).
Page 10-15
It is recommended that a gentle slope to the water edge and extending below the
water line be adopted before the batter slope steepens into deeper areas. An
alternative to the adoption of a flat batter slope is to provide a 3 m safety bench that
is less than 0.2 m deep below the permanent pool level be built around the wetland.
Safety requirements for individual wetlands may vary from site to site, and it is
recommended that an independent safety audit be conducted of each design.
Q max riser =
Equation 10.1
It should be noted that detention time is never a constant and the term notional detention time is used to provide a
point of reference in modelling and determining the design criteria for riser outlet structures.
Page 10-16
Ao =
Qmax
riser
Cd 2 g h
Equation 10.2
As the outlet orifices can be expected to be small, it is important that the orifices are
prevented from clogging by debris. Some form of debris guard is recommended as
illustrated in the images below.
Page 10-17
Qmax riser
< 0.05m/s
A section
Equation 10.3
Where
Qmax riser
Asection
Page 10-18
Page 10-19
Page 10-20
Design assessments
Page 10-21
Area:
TREATMENT
Page 10-22
Page 10-23
Page 10-24
Date:
Time:
Constructed by:
Weather:
Contact During Visit:
Items inspected
Checked Adequate
Y
N Y
N
Items inspected
Checked Adequate
Y
N Y
N
DURING CONSTRUCTION
Preliminary Works
1. Erosion and sediment control plan adopted
2. Limit public access
3. Location same as plans
4. Site protection from existing flows
5. All required permits in place
Earthworks
6. Integrity of banks
7. Batter slopes as plans
8. Impermeable (eg. clay) base installed
9. Maintenance access to whole wetland
10. Compaction process as designed
11. Placement of adequate topsoil
12. Levels as designed for base, benches,
banks and spillway (including freeboard)
13. Check for groundwater intrusion
14. Stabilisation with sterile grass
Structural components
15. Location and levels of outlet as designed
16. Safety protection provided
17. Pipe joints and connections as designed
18. Concrete and reinforcement as designed
19. Inlets appropriately installed
20. Inlet energy dissipation installed
21. No seepage through banks
FINAL INSPECTION
1. Confirm levels of inlets and outlets
2. Confirm structural element sizes
3. Check batter slopes
4. Vegetation planting as designed
5. Erosion protection measures working
6. Pre-treatment installed and operational
7. Maintenance access provided
COMMENTS ON INSPECTION
ACTIONS REQUIRED
Page 10-25
Maintaining vegetation
Page 10-26
6 monthly
Date of Visit:
Location:
Description:
Site Visit by:
INSPECTION ITEMS
Page 10-27
Promote sedimentation of particles larger than 125m within the inlet zone.
Page 10-28
Optimise the relationship between detention time, wetland volume and the
hydrologic effectiveness of the system to maximise treatment given the
wetland volume site constraints.
Ensure that the required detention period is achieved for all flow though the
wetland system through the incorporation of a riser outlet system.
Provide for by-pass operation when the inundation of the macrophyte zone
reaches the design maximum extended detention depth.
Inlet zone permanent pool level of 11.7m, which is 0.2m above the permanent
pool level of the macrophyte zone
Bypass weir (spillway outlet) level of 12.0m set at the top of extended
detention in the wetland macrophyte zone and 0.3 m above the inlet zone
permanent pool level
Landscape Requirements
In addition, a landscape design will be required and they include:
Terrestrial vegetation.
Page 10-29
Design flows are established using the Rational Method, as given in the Code of
Practice on Surface Water Drainage (PUB, 2000). The rational method is given by
Q=
CIAc
360
Where
C
Runoff coefficient
Ac
a. time of concentration
The time of concentration of the catchment was determined to be 10min.
b. Runoff coefficients
The Code of Practice on Surface Water Drainage describes runoff coefficients based
on the degree and type of development within the catchment. The catchment for the
worked example is densely developed with residential and industrial developments.
The corresponding runoff coefficient is 0.8.
c. Rainfall Intensities
The rainfall intensity at a time of concentration of 10minutes for the 1yr ARI and 100yr
ARI event are determined from the IDF curve for Singapore contained in Appendix 2 of
the Code of Practice on Surface Water Drainage (2000), i.e.
I1 = 106 mm/hr
d. Design flows
Applying the Rational Method for the above parameters and a catchment area of 10ha
gives the following design flows:
Q1 = 2.3 m3/s
Page 10-30
Assuming a sediment loading rate of 3.0 m /ha/yr and a capture efficiency of 90%, the
cleanout frequency I computed to be:Cleanout frequency (years) =
272
= 10 years
3 10 0.9
OK
Inlet zone permanent pool level (overflow pit crest level) = 11.7m which is
0.2m above the permanent pool level of the macrophyte zone
Bypass weir (spillway outlet) crest level = 12m which is the top of extended
detention for the wetland and 0.3 m above the inlet zone permanent pool
level.
It is common practice to allow for 0.3m of freeboard above the afflux level when setting
the top of embankment elevation.
Overflow Pit
Two possible flow conditions need to be checked for overflow conditions: weir flow
conditions (with extended detention of 0.3 m) and orifice flow conditions.
a. Weir Flow Conditions
The required perimeter of the outlet pit to pass the 1yr ARI flow (2.3 m3/s) with an
afflux of 0.3 m can be calculated using the following equation assuming 50%
blockage:
P=
Q des
B Cw h3 / 2
2.3
0.5 1.7 0.3 3 / 2
P = 16.5m
P=
Ao =
Ao =
Qdes
B Cd 2 g h
2.3
0.5 0.6 2 9.81 0.3
Ao = 3.2m 2
In this case the weir flow condition is limiting. Considering the overflow pit is to convey
the design operation flow (1yr ARI) or slightly greater, a minimum pit of 1.8m x 1.8m
2
will be required (area 3.2 m ). The top of the pit is to be fitted with a letter box grate.
This will ensure large debris does not enter the control structure while avoiding the
likely of blockage of the grate by smaller debris.
c. Connection Pipe(s)
As the connection pipe (i.e. between the inlet zone and the macrophyte zone) is to be
submerged, the size can be determined by first estimating the required velocity in the
connection pipe using the following:
Page 10-31
h=
2V
2g
Where
h
head level driving flow through the pipe (defined as the spillway outlet level
minus the normal water level in the downstream treatment system)
Note: the coefficient of 2 in the equation is a conservative estimate of the sum of entry and exit loss
coefficients (Kin + Kout).
Back calculating gives a velocity of 2.2m/s in the connection pipe. The pipe size
3
2
required to carry the 1yr ARI design flow of 2.3 m /s is hence 1.1m . It is
recommended that multiple pipes be used to connect the inlet and the macrophyte
zones. Three pipes of 750 mm diameter will be required.
The obvert of the pipes is to be set below the permanent water level in the wetland
macrophyte zone (11.5 m) meaning the invert is set at 10.80 m. The dimension of the
over pit to accommodate the pipe connection is thus 3 m by 1.5 m.
In summary, the control outlet structure will be an overflow pit, 3m by 1.5m with the
crest level at RL 11.5m and a raised grated cover set at RL 11.6m. The
outlet/connection pipe to the wetland will be three 750mm in diameter pipes with their
inverts set at RL 10.8m.
High Flow Bypass Weir
All flows in excess of the design operation flow and up to the above design flow are
to bypass the wetland macrophyte zone. This is facilitated by a high flow bypass weir
(spillway outlet) designed to convey the above design flow (100yr ARI) with the weir
crest level 0.3 m above the permanent pool of the inlet pond (RL 12.0m).
Assuming a maximum afflux of 0.3 m, the weir length is calculated using the weir flow
equation
L=
L=
Q100 yr
Cw h 3 / 2
6
3
1.7 0.3 2
L = 22m
To ensure no flows breach the embankment separating the inlet zone and the
macrophyte zone the embankment crest level is to be set at 12.6 m AHD (i.e. 0.3 m
freeboard on top of the maximum afflux level over the high flow bypass weir).
Summary of inlet zone dimensions
The dimensions for the sedimentation basin are summarised below.
2
520m
Basin width
45m
Basin length
12m
Depth of permanent
pool
1.5m
Overflow pit
Page 10-32
The bathymetry across the four marsh zones is to vary gradually over the
length of the macrophyte zone, ranging from 0.2 m above the permanent pool
level (ephemeral zone) to 0.5 m below the permanent pool level (Table 10.2).
The ephemeral marsh zone is to be located adjacent to the pathway and
bridge crossing mid way along the wetland.
The permanent pools upstream and downstream of the ephemeral zone are to
be connected via the maintenance drain to ensure the upstream permanent
pool can drain down to RL11.5 m following a rainfall event.
The depth of the open water zone in the vicinity of the outlet structure is to be
1 m below the permanent pool level.
The marsh zones are arranged in bands of equal depth running across the
flow path to optimise hydraulic efficiency and reduce the risk of shortcircuiting.
Proportion of Macrophyte
Zone Surface Area (m)
10%
10%
20%
20%
20%
20%
Generally, batter slopes of 1(V):8(H) from the top of the extended detention
depth to 0.3 m beneath the water line has been adopted.
The general grade through the wetland below the waterline is 1(V):8(H) or
flatter.
The batters directly adjacent and within the open water zones of the
macrophyte are limited to 1(V):8(H).
Page 10-33
Q max riser =
Page 10-34
0.125
0.25
0.375
Orifice diameter
40
40
30
30
Number of orifices
Area/orifice
Position No.
Water depth
(m)
6
4
5
3
1.3E-03
1.3E-03
7.1E-04
7.1E-04
-3
-3
-4
(1.310 )
(1.310 )
(7.110 )
(7.110-4)
Flow at given extended detention depth
(L/s)
Volume
(m3)
0.125
1875
7.08
0.25
3750
10.02
0.375
5625
12.27
6.68
3.32
0.5
7500
14.17
8.18
4.70
m (above 11.5m)
(mm)
(-)
(m2)
Total Flow
(L/s)
tdet
(hrs)
0
4.72
1.99
7.1
74
14.7
71
22.3
70
29.0
72
0.6
0.5
0.4
0.3
0.2
0.1
0
0
10
15
20
25
30
35
Discharge (L/s)
Q=
3750
= 87 L / s
12 3600
The size of the maintenance drain can be established using the Mannings equation
assuming the drain/ pipe is flowing full and at 0.5 % grade:
Page 10-35
Q=
A R S
n
1
2
Where
3
Hydraulic radius (m), equivalent to the cross sectional area divided by the
wetted perimeter
Q
Cd 2 g h
Flow (m3/s)
Cd =
Ao =
= 9.81 m/s2
The valve area is calculated as 0.06m , given the discharge coefficient is 0.6 and h is
one third the hydraulic head. The equivalent diameter is 270mm.
Discharge Pipe
The discharge pipe of the wetland conveys the outflow of the macrophyte zone to the
receiving waters (or existing drainage infrastructure). Under normal operating
conditions, this pipe will need to have sufficient capacity to convey the larger of the
discharges from the riser (30L/s) or the maintenance drain (87L/s). Considering the
maintenance drain flow is the larger of the two flows the discharge pipe size is set to
the size of the maintenance drain (320mm pipe at 0.5% as calculated above).
Summary of Macrophyte Zone Outlet
Riser outlet = 225mm diameter pipe with following orifice detail:
Level
Orifices
Orifice Diameter
RL11.5 m
40 mm
RL11.625 m
40 mm
RL11.75 m
30 mm
RL11.875 m
30 mm
Maintenance drain
Maintenance control
Discharge pipe
Page 10-36
Q=
A R S
n
1
2
Where
3
Hydraulic radius (m), equivalent to the cross sectional area divided by the
wetted perimeter
A turf finish is to be adopted for the bypass channel. A Mannings n of 0.035 (for earth
with gravel and weeds) stipulated in the Singapore Code of Practice on Surface Water
Drainage is considered appropriate for flow depths more than double the height of the
grass.
Assuming there is a 0.3m drop from the bypass weir crest to the upstream invert of the
bypass channel and 5(H):1(V) batters, the base width of the bypass channel can be
established by setting the maximum flow depth in the bypass channel at 0.3m. This
ensures flow in the channel does not backwater (i.e. submerge) the bypass weir.
3
For a base width of 19m, the flow through the channel is calculated as 9.0m /s, which
is greater than the 100yr ARI flow. Hence, the bypass channel is adequately sized.
Step 7 Verification Checks
Macrophyte Zone Re-suspension Protection
A velocity check is to be conducted for when the wetland is at the top of the extended
detention level and the riser is operating at design capacity. This check is to ensure
velocities through the macrophyte zone (Vmacrophyte zone) are less than 0.05 m/s to avoid
potential scour of biofilms from the wetland plants (macrophytes) and re-suspension of
the sediments (Equation 10.3).
The flow rate through the riser was calculated as 30L/s. The cross sectional area
refers to the narrowest section of the wetland measured from the top of the extended
detention. The narrowest point in the wetland is the ephemeral marsh (refer to Figure
10.14). If the minimum depth at the top of the ephemeral marsh is 0.3m, and the
length of the wetland is 50m (given a cross sectional area of 15,000m2 and a width to
length ratio of 1:6), the cross sectional area is 15m2. The velocity is calculated to be:
0.03
= 0.0020.05m / s
15
Confirm Treatment Performance
The key functional elements of the constructed wetland developed as part of the
conceptual design (i.e. area, extended detention depth) were not adjusted as part of
the detailed design. Therefore, the performance check undertaken in Step 1 still
applies.
Step 8: Vegetation Specification
The vegetation specification for the various zones within the wetland will be advised
once the list of recommended plantings has been established by National Parks Board
of Singapore.
Engineering Procedures for ABC Waters Design Features
Page 10-37
Page 10-38
10.8 References
CRCCH (Cooperative Research Centre for Catchment Hydrology), 2003, Model for
Urban Stormwater Improvement Conceptualisation (MUSIC) User Guide, Version 2.0,
December
Engineers Australia, 2003, Australian Runoff Quality Guidelines, DRAFT, June
GbLA Landscape Architects, 2004, Preliminary drawings for Mernda Wetland, Report
for Stockland
Institution of Engineers Australia, 1997, Australian Rainfall and Runoff A guide to
flood estimation, Editor in Chief Pilgram, D.H.
Persson, J., Somes, N.L.G. and Wong T.H.F., 1999, Hydraulic efficiency and
constructed wetland and ponds, Water Science and Technology Vol 40 No 3 pp 291
289
Public Utilities Board (PUB), 2000, Code of Practice on Surface Water Drainage, Fifth
Edition
Page 10-39
11
Infiltration
11
Chapter 11 Infiltration Systems
11.1 Introduction ..................................................................................................................4
11.2 Design Considerations ....................................................................................................7
11.2.1.
11.2.2.
11.2.3.
11.2.4.
11.2.5.
11.2.6.
In-Situ Soils......................................................................................................................9
11.2.7.
Groundwater ..................................................................................................................10
11.2.8.
11.2.9.
11.3.
11.3.1.
11.3.2.
11.3.3.
11.3.4.
11.3.5.
11.3.6.
11.3.7.
11.3.8.
11.3.9.
11.3.10.
11.3.11.
11.3.12.
11.4.
11.4.1.
11.5.
Checking Tools........................................................................................................22
11.5.1.
11.5.2.
11.5.3.
11.5.4.
11.6.
11.6.1.
11.6.2.
11.6.3.
11.6.4.
11.6.5.
11.6.6.
11.6.7.
11.6.8.
11.6.9.
11.6.10.
11.6.11.
11.6.12.
11.6.13.
11.6.14.
11.7.
References .............................................................................................................37
11.1 Introduction
Stormwater infiltration systems capture stormwater runoff and encourage infiltration into
surrounding in-situ soils and underlying groundwater. This has the benefit of reducing
stormwater runoff peak flows and volumes, reducing downstream flooding, managing the
hydrologic regime entering downstream aquatic ecosystems and improving groundwater
recharge.
The purpose of infiltration systems in a stormwater management strategy is as a
conveyance measure (to capture and infiltrate flows), NOT as a stormwater treatment
system. Appropriate pre-treatment of stormwater entering infiltration systems is required
to avoid clogging and to protect groundwater quality.
Infiltration systems generally consist of a detention volume and an infiltration area (or
infiltration surface):
The detention volume can be located above or below ground and is designed to
detain a certain volume of runoff and make it available for infiltration. When the
detention volume is exceeded, the system is designed to overflow to the
downstream drainage systems and the receiving environment.
The infiltration area is the surface or interface between the detention volume
and the in-situ soils through which the collected water is infiltrated.
The application of infiltration systems is best suited to moderately to highly permeable insitu soils (i.e. sandy loam to sandy soils); however, infiltration systems can still be applied
in locations with less permeable soils by providing larger detention volumes and
infiltration areas.
There are four basic types of infiltration systems:
Leaky Well
A leaky well is typically used in small scale residential applications and consists of a
vertical perforated pipe (concrete or PVC) and an open base (Figure 11.1). Pretreated
stormwater enters via an inlet pipe at the top of the well and when the detention volume
is full, an overflow pipe delivers excess waters to the downstream drainage system. The
perforations in the open pipe and the base are covered with a geotextile (non-woven) and
the pipe is surrounded by a ring of clean gravel (5 - 10 mm particle size diameter).
Figure 11.1
Page 4
Infiltration Trench
Infiltration trenches consist of a trench, typically 0.5 - 1.5 m deep, filled with gravel or
modular plastic cells lined with geotextile (non-woven) and placed under 300 mm of
backfill (topsoil or sandy loam). Pretreated runoff enters the trench either directly or via
an inlet control pit, with excess waters delivered downstream via an overflow pipe. If the
trench contains gravel fill then a perforated distribution pipe is incorporated into the
system to ensure effective distribution of stormwater into the detention volume. A typical
configuration of an infiltration trench is shown in Figure 11.2.
Figure 11.2
Infiltration Soak-away
Soak-aways are similar to trenches in operation but have a larger plan area, being
typically rectangular, and of shallower depth (Figure 11.3). Infiltration soak-aways can be
applied across a range of scales from residential allotments through to open space or
parklands.
Figure 11.3
Page 5
Infiltration Basin
Infiltration basins are typically used in larger scale applications where space is not a
constraint (e.g. parklands). They consist of natural or constructed depressions designed
to capture and store stormwater runoff on the surface (i.e. the detention volume is located
above ground) prior to infiltration into the in-situ soils (Figure 11.4).
A typical section through an infiltration basin is provided in Figure 11.5. Infiltration basins
are best suited to sand or sandy-clay in-situ soils and can be planted out with a range of
vegetation to blend into the local landscape. Pre-treatment of stormwater entering
infiltration basins is required with the level of pre-treatment varying depending on in-situ
soil type and basin vegetation. Further guidance in this regard is provided in
Section11.2.4.
Figure 11.4
Infiltration Basin
Gravel
(optional)
In-situ soil
Figure 11.5
Page 6
Design Objectives
The design objective will vary from one location to another and will depend on site
characteristics, development form and the requirements of the receiving ecosystems. It is
essential that these objectives are established as part of the conceptual design process
and approved by the Public Utilities Board prior to commencing the engineering design.
11.2.2.
Selection of the type of infiltration system for a particular application must occur as part of
the conceptual design process (i.e. Site Based Stormwater Management Plan) by
assessing the site conditions against the relative merits of the four basic types of
infiltration systems described in Section 0. There is a range of resources available to
assist with this selection process, including Australian Runoff Quality (Engineers Australia
2006), Water Sensitive Urban Design: Basic Procedures for Source Control of
Stormwater (Argue 2004) and Water Sensitive Urban Design: Technical Guidelines for
Western Sydney (UPRCT 2004).
In general, selection of the type of infiltration system is determined by the size of the
contributing catchment. Table 11.1 provides guidance on selection by listing the type of
infiltration systems against typical scales of application.
Allotment Scale
(< 0.1 ha)*
Medium Scale
(0.1 - 10 ha)*
Large Scale
(> 10 ha)*
Page 7
Page 8
Table 11.2
*Hydrologic Effectiveness
Method
11.2.3.1.
*Design Storm
Method
Where the design objective is the infiltration of a specific proportion of the mean annual
runoff, the hydraulic effectiveness approach can be adopted for sizing infiltration systems.
For a given catchment area and meteorological conditions, the hydrologic effectiveness
of an infiltration system is determined by the combined effect of the quality and quantity
of runoff, the detention volume, in-situ soil hydraulic conductivity and infiltration area.
The hydrologic effectiveness of an infiltration system requires long term continuous
simulation which can be undertaken using the Model for Urban Stormwater Improvement
Conceptualisation (MUSIC) (CRCCH 2005). However, in most situations, where a
number of the design considerations can be fixed (i.e. frequency of runoff, depth of
detention storage, saturated hydraulic conductivity); hydrologic effectiveness curves can
be generated and used as the design tool for establishing the infiltration system size.
The hydrologic effectiveness curves derived for infiltration systems (with defined
parameters) located in Singapore are presented in Section 11.3.6.1 and represent Step 6
in the design steps required for infiltration measures.
11.2.3.2.
Where the design objective for a particular infiltration system is peak discharge
attenuation or the capture and infiltration of a particular design storm event (e.g. 3-month
ARI event), then the design storm approach can be adopted for sizing the infiltration
system.
This method involves defining the required detention volume by comparing the volume
of inflow and outflow for a particular design storm, and then calculating the infiltration
area to ensure the system empties within a specified period of time. This approach
requires further development for application in Singapore and therefore, unless otherwise
approved by Public Utilities Board, the Hydrologic Effectiveness Method must be used.
9.1.111.2.4.
Pre-treatment of Stormwater
Page 9
Level 2 pre-treatment applies to leaky wells, infiltration trenches and infiltration soakaways. It also applies to most infiltration basin applications. However, level 2 pretreatment is not required if the infiltration system can be designed to function as a
bioretention system i.e. where basins are located on sandy loam to clay soils of low
hydraulic conductivity (<180 mm/hr) and the depth to groundwater is greater than 1.0 m.
The system can be planted out with rush and reed species and pollutant removal takes
place prior to waters entering the underlying groundwater. A summary of pre-treatment
requirements for each of the infiltration system types is presented in Table 11.3.
Table 11.3
Leaky Well
Infiltration Trench
Infiltration Soak-away
Infiltration Basin
- Sandy clay to clay soils (Ksat < 180 mm/hr) + dense
ground cover
- Sandy clay to clay soils (Ksat < 180 mm/hr) + turf ground
cover
- Sandy soils (Ksat > 180 mm/hr)
Note
Level 1
Pre-treatment
Level 2
Pre-treatment
11.2.4.11.2.5.
Site Terrain
Infiltration into steep terrain can result in stormwater re-emerging onto the surface at
some point downslope. The likelihood of this pathway for infiltrated water is dependent on
the soil structure. Duplex soils and shallow soil over rock create situations where reemergence of infiltrated water to the surface is most likely to occur. These soil conditions
do not necessarily preclude infiltrating stormwater, unless leaching of soil salt is
associated with this process. The provision for managing this pathway will need to be
taken into consideration at the design stage to ensure hazards or nuisance to
downstream sites are avoided.
Additionally, the introduction of infiltration systems on steep terrain can increase the risk
of slope instability. Installation of infiltration systems on slopes greater than 10 % will not
be approved by the Public Utilities Board unless a detailed engineering assessment has
been undertaken.
11.2.5.11.2.6.
In-Situ Soils
11.2.5.1.11.2.6.1.
Hydraulic Conductivity
Hydraulic conductivity of the in-situ soil is the rate at which water passes through a soil
medium. It influences both the suitability of infiltration systems and the size of the
infiltration area. Therefore, it is essential that field measurement of hydraulic conductivity
be undertaken to confirm assumptions of soil hydraulic conductivity adopted during the
concept design stage. The determination of hydraulic conductivity must be undertaken in
accordance with procedures which provides an estimate of saturated hydraulic
conductivity (Ksat)(i.e. the hydraulic conductivity of a soil when it is fully saturated with
water). The typical ranges of saturated hydraulic conductivities for homogeneous soils
are provided in Table 11.4.
Page 10
Table 11.4
Soil Type
Coarse Sand
Sand
Sandy Loam
Sandy Clay
Medium clay
Heavy Clay
When assessing the appropriateness of infiltration systems and the type of in-situ soils,
the following issues must be considered:
Soils with a saturated hydraulic conductivity of 3.6 mm/hr to 360 mm/hr are preferred for
infiltration application.
Infiltration systems are neither appropriate nor functional where the in-situ soils are very
heavy clays (i.e. < 0.36 mm/hr).
Soils with a low hydraulic conductivity (0.36 - 3.6 mm/hr) do not necessarily preclude the
use of infiltration systems even though the required infiltration/ storage area may become
prohibitively large. However, soils with lower hydraulic conductivities will be more
susceptible to clogging and will therefore require enhanced pre-treatment to remove
sediment.
11.2.5.2.11.2.6.2.
Soil Salinity
Infiltration systems must be avoided in areas with poor soil conditions, in particular sodic/
saline and dispersive soils, and shallow saline groundwater. If the Site and Soil
Evaluation (refer to Section 11.3.1) identifies poor soil conditions, then the Public Utilities
Board will not approve the use of infiltration systems.
11.2.5.3.11.2.6.3.
Infiltration systems must not be placed in locations where soils are underlain by rock or a
soil layer with little or no permeability (i.e. Ksat < 0.36 mm/hr). In locations where fractured
or weathered rocks prevail, the use of infiltration systems may be approved by the Public
Utilities Board provided detailed engineering testing has been carried out to ensure the
rock will accept infiltration.
11.2.6.11.2.7.
Groundwater
11.2.6.1.11.2.7.1.
Groundwater Quality
As outlined in Section 11.2.4, the suitability of infiltrating stormwater and the necessary
pre-treatment requires assessment of the groundwater quality. The principle legislation
governing the management of groundwater quality is that there should be no
deterioration in groundwater quality. This means the stormwater being infiltrated must be
of equal or preferably superior quality to that of the receiving groundwater in order to
ensure the groundwater quality and values are protected. To determine an appropriate
level of pre-treatment for stormwater, assessment of the groundwater aquifer quality,
possible uses and suitability for recharge is required and must be approved by the public
Utilities Board.
11.2.6.2.11.2.7.2.
Groundwater Table
Page 11
that the base of the infiltration system be a minimum of 1.0 m above the seasonal high
water table.
If a shallow groundwater table is likely to be encountered, investigation of the seasonal
variation of groundwater levels is essential. This should include an assessment of
potential groundwater mounding (i.e. localised raising of the water table in the immediate
vicinity of the infiltration system) that in shallow groundwater areas could cause problems
with nearby structures.
11.2.7.11.2.8.
Infiltration systems should not be placed near building footings to avoid the influence of
continually wet sub-surface or greatly varying soil moisture content on the structural
integrity. Australian Runoff Quality (Engineers Australia 2006) recommends minimum
distances from structures and property boundaries (to protect possible future buildings in
neighbouring properties) for different soil types. These values are shown in Table 11.5.
Table 11.5 Minimum Setback Distances (adapted from Engineers Australia 2006)
Soil Type
Sands
Sandy Loam
Sandy Clay
Medium to Heavy Clay
11.2.8.11.2.9.
Saturated Hydraulic
Conductivity
(mm/hr)
>180
36 to 180
3.6 to 36
0.0 to 3.6
Flow Management
The following issues should be considered when designing the hydraulic control
structures within infiltration systems:
For large scale systems (i.e. infiltration basins), the surface of the infiltration
area must be flat to ensure uniform distribution of flow and to prevent hydraulic
overloading on a small portion of the infiltration area.
For gravel filled infiltration systems, flow should be delivered to the detention
volume via a perforated pipe(s) network that is located and sized to convey the
design flow into the infiltration systems and allow distribution of flows across the
entire infiltration area.
Where possible, above design flows will bypass the infiltration systems. This
can be achieved in a number of ways. For smaller applications, an overflow pipe
or pit, which is connected to the downstream drainage system, can be used. For
larger applications, a discharge control pit can be located upstream of the
infiltration system. This will function much like the inlet zone of a constructed
wetland to regulate flows (i.e. 1 year ARI) into the infiltration systems and bypass
above design flows (i.e. > 1 year ARI).
Page 12
Page 13
11.3.1.
As outlined in Section 11.2.6, there are a range of site and soil conditions which influence
infiltration system design. To define the sites capability to infiltrate stormwater, a Site
and Soil Evaluation must be undertaken. The evaluation should provide the following:
Soil type
Hydraulic conductivity
11.3.2.
This step involves confirming the design objectives, defined as part of the conceptual
design, to ensure the correct infiltration system design method is selected (refer to Table
11.2).
11.3.3.
This step involves selecting the type of infiltration system by assessing the site conditions
against the relative merits of the four infiltration systems described in Section 0. In
general, the scale of application dictates selection of the infiltration system. Table 11.1
provides guidance in this regard.
For further guidance in selecting infiltration systems, designer should refer to Australian
Runoff Quality (Engineers Australia 2006), Water Sensitive Urban Design: Basic
Procedures for Source Control of Stormwater (Argue 2004) and the Water Sensitive
Urban Design: Technical Guidelines for Western Sydney (UPRCT 2004).
11.3.4.
As outlined in Section 11.2.4 and Table 11.3, both Level 1 Pre-treatment (minimising risk
of clogging) and Level 2 Pre-treatment (groundwater protection) are required for all
infiltration systems except for specific infiltration basin applications. To determine Level 2
requirements, an assessment of the groundwater must be undertaken to define existing
water quality, potential uses (current and future) and suitability for recharge.
Pre-treatment measures for roof runoff include the provision of leaf and roof litter guards
along the roof gutter and rainwater tanks. Pre-treatment for urban runoff includes
sediment basins, vegetated swales, bioretention systems or constructed wetlands as
outlined in the other chapters of this guideline.
11.3.5.
11.3.5.1.
Design Flows
To configure the inflow system and high flow bypass elements of the infiltration system
the following design flows generally apply:
Design operation flow for sizing the inlet to the infiltration system. This will
typically correspond to one of the following:
o
1 year ARI or less for situations where a discharge control pit is used to
regulate flows into the infiltration system and bypass larger flows
2 - 10 year ARI (minor design flow, typically the 5 year ARI event in
Singapore) for situations where the minor drainage system is directed
to the infiltration system.
Page 14
Above design flow for design of the high flow bypass around the infiltration
system. The discharge capacity for the bypass system may vary depending on
the particular situation but will typically correspond to one of the following:
o
2 - 10 year ARI (minor design flow) for situations where only the minor
drainage system is directed to the infiltration system.
50 - 100 year ARI (major design flow) for situations where both the
minor and major drainage system discharge to the infiltration system.
As outlined in Section 11.2.3, there are two design methods available for establishing the
size of the detention volume and infiltration area of infiltration systems: the hydrologic
effectiveness method and the design storm method. Unless otherwise approved by the
Public Utilities Board, the hydrologic effectiveness method must be used when designing
infiltration systems.
9.1.2.111.3.6.1. Hydrologic Effectiveness Method
Figure 11.6 below shows the relationship between the hydrologic effectiveness,
infiltration area and detention storage for a range of soil hydraulic conductivities,
detention storage depths and detention storage volumes (adjusted for media porosity) for
the reference station 43 in Singapore. The curves were derived using the Model for
Urban Stormwater Improvement Conceptualisation.
The curves in Figure 11.6 are generally applicable to infiltration measure applications
within residential, industrial and commercial land uses. If the configuration of the
infiltration measure concept design is significantly different to that described below then
the curves may not provide an accurate indication of performance and the detailed
designer should use MUSIC to size the infiltration system.
The curves were derived conservatively assuming that the systems have the following
characteristics:
detention volume area was confined to the space allocated for the infiltration
area
These curves can be used to establish the size of both the detention volume and
infiltration area of the infiltration systems to achieve a particular hydrologic effectiveness.
The designer is required to select the relevant hydrologic effectiveness curve by
establishing the likely configuration and form of the infiltration system, namely whether it
will be an open void detention volume (porosity = 1.0) or gravel filled (porosity = 0.35).
If linear interpolation between the curves is used to estimate the infiltration area required
for systems with hydraulic conductivities between those shown on the charts, it should be
noted that the relationship between the curves is not linear. As a result, these
interpolations do not provide an exact representation of the size of infiltration area as a %
Page 15
of catchment area. Designers must be careful not to under size infiltration areas through
this process.
90%
80%
70%
60%
50%
40%
S aturated Hydraulic
C onduc tivity of in-s itu
s oil
3.6m m /h r
30%
36m m /h r
20%
360m m /h r
1800m m /h r
10%
3600m m /h r
0%
0
10
12
Infiltration B as in Area (% impervious c atc hment (as s umed to be 1m effec tive depth - ac c ounting for media poros ity)
Figure 11.6
11.3.6.11.3.7.
This step involves locating the infiltration system in accordance with the requirement set
out in Section 11.2.8 and Table 11.5 to minimise the risk of damage to structures from
wetting and drying of soils (i.e. swelling and shrinking of soils and slope stability).
11.3.7.11.3.8.
Cover (i.e. depth of soil above top of infiltration system) Minimum cover of 0.3
m. For systems created using modular plastic cell storage units, an engineering
assessment is required.
11.3.8.11.3.9.
The following design and specification requirements must be documented as part of the
design process for leaky wells, infiltration trenches and soak-aways.
11.3.8.1.11.3.9.1.
Gravel
Where the infiltration detention volume is created through the use of a gravel-filled
trench then the gravel must be a uniform size of between 25 - 100 mm diameter and
must be clean (free of fines).
11.3.8.2.11.3.9.2.
Where the infiltration detention volume is created through the use of modular plastic cells,
the design must be accompanied by an engineering assessment of the plastic cells and
Page 16
their appropriateness considering the loading above the infiltration system. A minimum
150 mm thick layer of coarse sand or fine gravel must underlie the base of the plastic
cells.
11.3.8.3.11.3.9.3.
Geofabric
Geofabric must be installed along the side walls and through the base of the infiltration
detention volume to prevent the migration of in-situ soils into the system. For this reason,
in infiltration systems the use of non-woven geofabric with a minimum perforation or
mesh of 0.25 mm is most appropriate.
11.3.8.4.11.3.9.4.
Inspection Wells
Table 11.6
Infiltration Type
Leaky Wells
Infiltration Trenches
Infiltration Soak-aways
Infiltration Basins
Direct inflow
Discharge
control pit
Overflow/ Bypass
Discharge
Overflow pipe/ pit
control pit
Note: For gravel filled infiltration systems, flow should be delivered to the detention volume via a perforated
pipe network.
Ensure the pipe itself has capacity to convey the design operation flow
Page 17
Ensure the perforations are adequate to pass the design operation flow.
It is recommended that the maximum spacing of the perforated pipes is 3 m (centres) and
that the minimum grade is 0.5 % from the inflow point. The inflow pipes should be
extended to the surface of the infiltration system to allow inspection and maintenance
when required. The base of the infiltration system must remain flat.
Perforated Pipe Conveyance
To confirm the capacity of the perforated pipes to convey the design operation flow,
Mannings equation can be used (which assumes pipe full flow but not under pressure).
When completing this calculation it should be noted that installing multiple perforated
pipes in parallel is a means of increasing the capacity of the perforated pipe system.
Perforated Pipe Slot Conveyance
The capacity of the slots in the perforated pipe needs to be greater than the maximum
infiltration rate to ensure the slots does not become the hydraulic control in the
infiltration system (i.e. to ensure the in-situ soils and detention volume set the hydraulic
behaviour rather than the slots in the perforated pipe). To do this, orifice flow can be
assumed to occur through the slots and the sharp edged orifice equation used to
calculate the flow through the slots for the full length of perforated pipe. Firstly, the
number and size of perforations needs to be determined (typically from manufacturers
specifications) and used to estimate the flow rate out of the pipes, with the driving head
being the difference between the overflow level and the invert of the perforated pipe. It is
conservative, but reasonable, to use a blockage factor to account for partial blockage of
the perforations. A 50 % blockage should be used.
Q perf = B Cd A 2 g h
Equation 11-1
Where
Qperf
Cd
If the capacity of the perforated pipe system is unable to convey the design operation
flow then additional perforated pipes will be required.
11.3.9.3.11.3.10.3. Overflow Pit
To size an overflow pit, two checks should be made to test for either drowned or free
flowing conditions. A broad crested weir equation can be used to determine the length of
weir required (assuming free flowing conditions) and an orifice equation used to estimate
the area between openings required in the grate cover (assuming drowned outlet
conditions). A blockage factor is to be used that assumes the grate is 50 % blocked.
While the smaller of the two would normally suffice, the larger of the two pit
configurations should be adopted to provide a level of conservatism. Furthermore, the
size of the pit should also be selected to ensure that it would adequately accommodate
the stormwater pipe draining from it.
For free overfall conditions (weir equation):
Q weir = B Cw L h 3 / 2
Equation 11-2
Page 18
Where
3
Qweir
Cw
Once the length of weir is calculated, a standard sized pit can be selected with a
perimeter at least the same length of the required weir length.
Q orifice = B Cd A 2 g h
Equation 11-3
Where B, g and h have the same meaning as above
Qorifice
Cd
When designing grated field inlet pits, reference is to the requirements of the Public
Utilities Board.
11.3.9.4.11.3.10.4. Overflow Weir
In applications where infiltration systems require a discharge control pit, a spillway outlet
weir will form part of the high flow bypass system to convey the above design flow. The
spillway outlet weir level will be set at the top of the detention storage to ensure
catchment flows bypass the infiltration system once the detention volume is full. The
length of the spillway outlet weir is to be sized to safely pass the maximum flow
discharged to the discharge control pit (as defined the above design flow in Section
11.3.5).
The required length of the spillway outlet weir can be computed using the weir flow
equation (Equation 11.2) and the above design flow (Section 11.3.5).
11.3.10.11.3.11.
Consider how maintenance is to be performed on the infiltration system (e.g. how and
where is access available, where sediment likely to collect etc.). A specific maintenance
plan and schedule should be developed for the infiltration system, either as part of a
maintenance plan for the whole treatment train, or for each individual asset. Guidance on
maintenance plans is provided in Section 11.4.1.
Page 19
11.3.11.11.3.12.
Following is a design calculation summary sheet for the key design elements of an
infiltration system to aid the design process.
Outcome
Check
Catchment Characteristics
Catchment area
ha
year ARI
mm/hr
m HD
m below surface
Groundwater quality
Groundwater uses
2
Pre-treatment design
Level 1 Pre-treatment (avoid clogging)
Level 2 Pre-treatment (groundwater quality protection)
year ARI
year ARI
Time of concentration
minutes
Identify rainfall intensities
'Design operation flow' - I1 year ARI
mm/hr
mm/hr
m /s
m3/s
Depth
Page 20
Outcome
'Infiltration Area'
'Detention Volume'
m3
Check
2
Width
Length
m HD
Groundwater level
m HD
m below surface
m HD
m HD
Cover
mm diam.
m3/s
mm diam.
Inflow pipe
Pipe capacity
Pipe size
m3/s
mm diam.
Overflow pipe
Pipe capacity
Pipe size
m /s
mm diam.
Overflow pit
Pit capacity
Pit size
m /s
mm x mm
mm
mm x mm
m
Page 21
Construction traffic and other works can result in damage to the infiltration
measures.
Routine inspection to identify any surface ponding after the design infiltration
period, which would indicate clogging/ blockage of the underlying aggregate or
the base of the trench.
Routine inspection of inlet points to identify any areas of scour, litter build up,
sediment accumulation or blockages.
Page 22
Page 23
Hydraulics:
Area:
Infiltration Area (m ):
Page 24
Inspected by:
Site:
Date:
Time:
Constructed by:
Weather:
Contact during
visit:
Items inspected
Checked
Satisfactory
Items inspected
Checked
Satisfactory
DURING CONSTRUCTION
A. FUNCTIONAL INSTALLATION
Structural components
Preliminary Works
Earthworks
5. Excavation as designed
Pre-treatment
C. OPERATIONAL ESTABLISHMENT
FINAL INSPECTION
1. Confirm levels of inlets and outlets
7. No surface clogging
4. Gravel as specified
ACTIONS REQUIRED
1.
2.
3.
4.
5.
Inspection officer signature:
Page 25
1 to 6 monthly
Date of Visit:
Location:
Description:
Site Visit by:
INSPECTION ITEMS
Page 26
ASSET INFORMATION
Design Assessment Checklist provided?
As constructed plans provided?
Copies of all required permits (both construction and operational) submitted?
Proprietary information provided (if applicable)?
Digital files (eg drawings, survey, models) provided?
Asset listed on asset register or database?
Page 27
Figure 11.7
Page 28
5KL
rainwater
tank
Figure 11.8
Site Layout
2
Of the impervious surfaces, roof areas make up a total of 2100 m , while on-ground
2
impervious surfaces make up the remaining 2900 m . There is no formal stormwater
drainage system, with stormwater runoff discharging into a small table drain in the
front of the property. The design objective of the infiltration system is retention of
stormwater runoff from the allotment with a hydrologic effectiveness of 95%.
Stormwater flows in excess of the detention capacity of the infiltration system are
directed towards the road table drain at the front of the property.
Roof runoff is directed to a 5 kL rainwater tank. Although rainwater tanks can provide
significant peak discharge reduction owing to their available storage capacity, in this
worked example an assumption is made that the 5kL tank will be full. The design
criteria for the infiltration system are to:
Ensure that the inlet configuration to the infiltration system includes provision
for by-pass of stormwater when the infiltration system is operating at its full
capacity.
This worked example focuses on the design of the infiltration system and associated
hydraulic structures.
11.6.2. Step 1: Site and Soil Evaluation
The site characteristics are summarised as follows:
5000 m (pervious)
10000 m (Total)
Page 29
Groundwater details (depth, quality and uses) = water table 5 m below surface
(5 m HD), moderate water quality with local bores used for irrigation.
Size infiltration trench to retain 95% of the mean annual runoff volume from
the site.
Design the inlet and outlet structures to convey the peak 3-month ARI flow
from the critical (flow rate) storm event. Ensure the inlet configuration includes
provision for stormwater bypass when the infiltration system is full.
Design appropriate ground cover and terrestrial vegetation over the infiltration
trench.
Page 30
Design flows and Runoff Coefficients were estimated using the Rational Method as
described in the Code of Practice on Surface Water Drainage (Public Utilities Board
2006).
Catchment area
= 10000 m
tc
~ 6 min
= 0.65
= 60.6 mm/hr
I100
= 275 mm/hr
= 0.109 m /s
3
= 0.497 m /s
The available site area is approximately 48 m and therefore, the effective depth to
3
achieve storage of 195m is 4.1 m. A gravel-filled trench will be used and will have a
porosity of 0.35. The resulting actual depth of the infiltration tank will need to be
11.7m.
The proposed layout of the infiltration system is shown in Figure 11.9.
Page 31
5KL
rainwater
tank
16 x 3m
infiltration unit
Discharge
control pit
Overflow
connected to
drain
Figure 11.9
Pre-treatment
vegetated
landscaped area
Gravel - clean (fines free) stone/ gravel with a uniform size of 5 mm diameter.
Geofabric - Geofabric must to be installed along the side walls and through the
base of the infiltration detention volume to prevent the migration of in-situ soils
into the system. Geofabric must be non-woven type with a minimum
perforation or mesh size of 0.25 mm.
Inflow pipe - connection between the pit and the infiltration basin sized to
convey design operation flow (3-month ARI)
overflow weir flows above the 3-month ARI to bypass the infiltration system
and to be directed to the street table drain.
Page 32
Compacted Soil
Internal Weir
500
600
400
Discharge
Control Pit
1200
Mesh Screen
300m UPVC
Outlet pipe
Gravel-filled
soakaway
Figure 11.10
Peak 3-month design flow = 0.109 m /s (calculated previously) and assuming pervious
3
area not contributing any runoff. There will be approximately 0.046 m /s discharging
3
from the rainwater tank overflow and 0.063 m /s from other paved areas.
There are two inlets to the infiltration system, i.e. one from the rainwater tank and the
second from the driveway (see Figure 11.9). These inlets are to be designed to
discharge flows up to 0.063 m3/s each into the infiltration trench with overflows
directed to the table drain on the street in front of the property.
Pipe connections from the inlet pits to the infiltration system and street table drain are
computed using the orifice flow
Ao =
Q
C d 2 gh
Cd
Ao
Orifice area (m )
This gives an orifice area (Ao) of 0.062 m , equivalent to a 280 mm diameter pipe
adopt 300 mm diameter uPVC pipe.
9.1.311.6.12.
To ensure appropriate distribution of flows into the gravel filled detention volume,
three 300 mm diameter perforated pipes laid in parallel (0.75 m apart) are to accept
flows from the 300 mm diameter RCP.
Two design checks are required:
Ensure the pipe has capacity to convey the design operation flow (0.109 m /s).
Ensure the perforations are adequate to pass the design operation flow.
Page 33
Q=
A.R 3 .S
n
Mannings equation
QTotal
= 0.960 m /s (for three pipes) > 0.109 m /s, and hence OK.
Q orifice = B Cd A 2 g h
Where:
Head (h)
= 0.4 m
Blockage (B)
Area (A)
= 1575 mm2/m
Slot Width
= 1.5 mm
Slot Length
= 7.5 mm
Pipe diameter
= 300 mm
Coefficient (Cd) = 0.61 (assume slot width acts as a sharp edged orifice).
Bypass Design
An overflow weir (internal weir) located within the discharge control pit (Figure 11.11)
separates the inflow pipe to the infiltration system from the overflow pipe that conveys
excess flows to the street table drain. The overflow internal weirs in discharge control
pits are to be sized to convey the peak 3-month ARI flow and the overflow weir is
designed to provide at least 150m freeboard i.e.
Page 34
(For conservative design, choose the larger flow for design of discharge control pit,
3
0.063 m /s)
3
Q weir = B Cw L h 3 / 2
So, using the
3
Cw
= 1.66
= 0.3 m
=0.40 m;
= 0.126 m /s
=1
= 9.81
Cd
This gives an orifice area (A) of 0.075 m2, equivalent to a 310 mm diameter pipe
adopt 450 mm diameter uPVC pipe.
Discharge control pit
600
250
High
flows
300mm UPVC
Figure 11.11
Page 35
11.6.13.11.6.14.
CALCULATION SUMMARY
Calculation Task
Outcome
Check
Catchment Characteristics
Catchment area
Catchment landuse (i.e residential, commercial etc.)
Storm event entering infiltration system (minor or major)
1
0.1
ha
3-month
Residential
year ARI
mm/hr
360
No
Presence of rock/shale
No
3
RL 5
5
Sandy-loam
m below surface
Groundwater quality
Moderate
Groundwater uses
Irrigation
95% HE
Infiltration Trench
Infiltration 'Soak-away'
Infiltration Basin
4
Pre-treatment design
3-month
year ARI
100
year ARI
minutes
Time of concentration
Identify rainfall intensities
'Design operation flow' - I1 year ARI
60.6
mm/hr
275
mm/hr
0.65
0.65
0.109
m /s
0.497
m /s
95
0.35
2
48
19.5
Page 36
CALCULATION SUMMARY
Calculation Task
7
Outcome
1.2
Width
Length
16
RL10
Groundwater level
RL 5
m below surface
Check
1.2
RL 4.5
RL 3.3
Cover
0.5
1.7
mm diam.
Overflow pit/pipe
Discharge control pit
Discharge pipe
Pipe capacity
Pipe size
0.126
450
m3/s
mm diam.
Inflow pipe
Pipe capacity
Pipe size
0.063
300
m /s
mm diam.
Overflow pipe
Pipe capacity
Pipe size
0.126
450
m /s
mm diam.
Overflow pit
3
Pit capacity
m /s
N/A
Pit size
mm x mm
N/A
3
300
mm
mm x mm
N/A
N/A
Page 37
11.7. References
Argue JR (ed) 2004, Water Sensitive Urban Design: Basic Procedures for Source
Control of Stormwater, AWA, University of South Australia
CRCCH (Cooperative Research Centre for Catchment Hydrology), 2003, Model for
Urban Stormwater Improvement Conceptualisation (MUSIC) User Guide, Version 2.0,
December
DPI, IMEA & BCC (Department of Primary Industries Water Resources, Institute of
Municipal Engineers Australia Qld Division & Brisbane City Council) 1992,
Queensland Urban Drainage Manual (QUDM), prepared by Neville Jones &
1
Associates and Australian Water Engineering for DPI, IMEA & BCC, Brisbane .
Engineers Australia 2006,
ACT,http://www.arq.org.au/
Australian
Runoff
Quality,
Engineers
Australia,
2005.
CSIRO
Public Utilities Board (2006). Code of Practice on Surface Water Drainage. Singapore.
50p.
Standards Australia 2000, AS/NZS 1547:2000: On-site domestic wastewater
management, Standards Australia
UPRCT (Upper Parramatta River Catchment Trust) 2004, Water Sensitive Urban
Design: Technical Guidelines for Western Sydney, prepared by URS Australia Pty Ltd
for UPRCT, NSW
Page 38