SECTION PB-490 - Test Adjusting Balancing
SECTION PB-490 - Test Adjusting Balancing
SECTION PB-490 - Test Adjusting Balancing
GENERAL
1.1
DESCRIPTION
.1
1.2
1.3
1.4
WORK INCLUDED
.1
.2
.3
.4
.5
.6
.7
QUALITY ASSURANCE
.1
During the progress of the work, make tests as specified herein and as
required by authorities having jurisdiction, including local authorities
Inspection Department or E.R. Include all qualified personnel, equipment
apparatus, and services required to perform the tests.
.2
All field test instruments to have calibration certificate not more than 6
months old and issued by a recognised independent testing authority
prior to testing and/or balancing.
SUBMITTALS
.1
Submit the following at least six (6) months prior to the execution of
testing:
.1
.2
.3
KENCANA SQUARE
PLUMBING TESTING, ADJUSTING AND BALANCING
SECTION PB-490
Page 2
.2
.3
2.0
Inspection reports.
PRODUCTS
NOT USED
3.0
EXECUTION
3.1
GENERAL
.1
.2
.3
.4
A minimum of fourteen (14) days notice shall be given to the E.R. to verify
the test result at site. Should the E.R. find discrepancies between the
recorded test results and the measurement demonstrated to him, further
tests shall be repeated at no additional cost.
.5
.6
Should any failure occur due to or arising from faulty materials or poor
workmanship, the E.R. shall decide if further tests will be required after
remedial works have been successfully carried out.
KENCANA SQUARE
PLUMBING TESTING, ADJUSTING AND BALANCING
SECTION PB-490
Page 3
3.2
.7
.8
Furnish all fuel, water, and electricity required in performing the testing,
balancing and adjustment mechanical systems.
.9
When the final tests have been successfully carried out, two (2) copies of
all test results, shall be submitted in loose leaf bound form to the E.R.
within two weeks of completion of tests. Tests which are to be carried out
under certain atmospheric conditions may be submitted later for insertion
into the test binder. All test data shall be on A4 size sheet paper.
Manufacturers literature, apart from published drafts or tables will not be
accepted. All test data shall be tabulated with design requirements and
shall be signed and dated.
.10
.11
Use calibrated test gauges with at least 100mm diameter dial. Gauge
range not to be more than three (3) times test pressure.
.12
.13
.14
In the event of any dispute with regard to scope of testing, adjusting and
balancing, the decision of the E.R. shall be taken as correct and final.
TESTING
.1
General
.1
.2
.2
KENCANA SQUARE
PLUMBING TESTING, ADJUSTING AND BALANCING
SECTION PB-490
Page 4
.3
.3
.4
.5
.1
.2
Vibration Test
Take vibration and alignment field measurements on every pump.
Readings shall include shaft alignment, equipment vibration,
bearing housing vibration and foundation vibration. Readings shall
be made using portable IRD (or as approved) equipment capable
of filtering out various unwanted frequencies. Maximum vibration
at any point listed above, or where specified, shall not exceed 2
mils on pumps, unless otherwise specified. Equipment
manufacturers shall certify in writing that the field readings, which
do not exceed the maximum specified, are acceptable.
.7
Pipework Test
.1
.6
Tank shall be filled up with water and checked for leaks at panel
joints. Check sides and edges of sectional tank for any distortion.
Pumps Tests
.1
Pumps
Adjust each pump for design flow and record flow, head and
power absorbed. Check alignment before putting them in
operation.
KENCANA SQUARE
PLUMBING TESTING, ADJUSTING AND BALANCING
SECTION PB-490
Page 5
.2
Motors
Test for quietness and correct operation. Adjust all controls to
maintain designed condition. Check direction of rotation of all
motors. Check actual current being drawn.
.3
.4
.5
.2
.3
.4
.5
Impeller size
.6
.7
.8
Record the following data from pumps and pump motors installed:
.1
.2
Impeller size.
.3
.4
.5
.6
Equipment location.
Record the following data for pumps and pump motors installed at
final balanced conditions :
.1
.2
.3
.4
KENCANA SQUARE
PLUMBING TESTING, ADJUSTING AND BALANCING
SECTION PB-490
Page 6
.8
.5
.6
Electrical Test
.1
.2
The system control, safety devices, etc., shall be fully tested, the
latter by stimulation of faults.
.3
.4
Insulation resistance
.2
Verification of polarity.
.3
.4
Effectiveness of earth.
.5
.6
.7
.8
.9
.10
.11
KENCANA SQUARE
PLUMBING TESTING, ADJUSTING AND BALANCING
SECTION PB-490
Page 7
.5
3.3
.12
.13
.14
.15
.2
.3
.6
Motor starter over-load relay setting shall be 10% above the actual
load current but shall not exceed the rated full load current of the
motor.
.7
BALANCING
.1
.2
KENCANA SQUARE
PLUMBING TESTING, ADJUSTING AND BALANCING
SECTION PB-490
Page 8
3.4
.3
Before any hydronic balancing work is done, install clean strainers, check
proper pump rotation, proper control valve installation and operation.
Verify that each system is adequately bled and vented, proper system
static pressure is available to assure a full system, flow meter and check
valve is properly installed. Maintain throttling devices and control valves
open at this time as required and appropriate.
.4
After piping systems have been installed, tested, cleaned and flushed,
complete with all pumps, piping, valves, and other items as herein
specified, make adjustments as required to deliver the water volumes at
each piece of equipment to within 5% of design flow as shown on the
Drawings, or as required to properly balanced the load throughout the
areas.
.5
Do not perform balancing until the entire system has been pressure
tested, flushed and cleaned.
FINAL REPORT
.1
Demonstrate to the E.R. that all systems and/or equipment have been
balanced and adjusted properly, and that the system and/or equipment is
in compliance with the Contract Documents.