KENCANA SQUARE

HANGER, ANCHORS AND SUPPORTS


SECTION AC-140
Page 1

1.0

GENERAL

1.1

DESCRIPTION
.1

1.2

1.3

Work of this Section shall conform to the requirements of the Contract


Documents.

WORK INCLUDED
.1

Hangers.

.2

Structure Attachments,

SUBMITTALS
.1

Product Data: Manufacturer's latest published data for materials,


equipment and installation.

.2

Shop Drawings: Submit details of pipe hangers, anchors and supports for
each pipe size and pipe service. Submit details of support methods and
point loadings, and anchor reactions.

2.0

PRODUCT

2.1

PIPE SUPPORTS & ANCHORS


.1

All piping shall be supported by means of pipe supports in accordance


with the relevant British Standard Specification.

.2

All pipes supports shall be steel, adjustable for height and prime coated
with rust preventive paint and finish coated black, in the types shown in
the following table. This table does not apply for buried pipes.
Services

Pipe Size

Type of Support

Chilled Water

All Sizes

Clevis Hanger (Single)


Trapeze (Multiple)

Hot Water

12mm to 150mm

-do-

Hot Water

More than 150mm

Roller or Spring

Steam

12mm to 50mm

Clamp

Steam

More than 65mm

Roller or Spring

Drain

6mm-up

Clamp

Compressed Air

6mm-up

Clamp

Water (Drinking
or Condensing)

Saddle or clamp or
otherwise as approved

DAMANSARA CITY MIXED DEVELOPMENT (PARCEL 2)


HANGER, ANCHORS AND SUPPORTS
SECTION AC-140
Page 2

.3

All buried pipes shall be laid in accordance with manufacturers


recommendations and/or local codes and ordinances.

.4

Vertical risers when passing through each floor slab shall be supported to
the floor by means of clamps, collars or pipe guides attached to the pipe
which in turn shall be attached to angles as per the following schedule:
Service

Support

Chilled Water

Spring(Within Chilled Water Plantroom)


Vibration Isolator (Other areas)

Hot Water

Spring

Steam

Spring

Cold Water Pipe

Cradles

Drain Pipes

12mm Rubber Pad

Compressed Air

12mm Rubber Pad

Condensing Water Pipes

Spring or as approved

Medical Gases

Pipes Clips to walls

Vertical risers shall be supported at the lowest point in accordance with


the following schedule unless otherwise stated.
Height of Riser

Pipes Size

Type of Support

Under 20

Up - 4

Hanger at Elbow

Under 20

6- 8

Support or concrete block

Under 20

10- up

Foot elbow

Over 20

Up to 1

Hanger at elbow

Over 20

1 6

Support or concrete

Over 20

7 and up

Foot elbow

.5

In instances where the pipes and clamp are of different materials, an


approved type of gasket shall be inserted between the pipe and clamp.

.6

Insulated pipes shall be supported such that the insulation is not


damaged due to undue pressure on it. Care shall be taken to ensure that
the vapour seal around the supports is uninterrupted.

.7

The hangers shall be fixed to the main structure by means of expanding


metal plugs and steel bolts and arranged to be loaded in shear.

.8

All piping shall generally be graded to eliminate air pockets or gas locks
depending on the service.

.9

The piping installation shall incorporate provisions for the venting of high
points and drawings of low points.

KENCANA SQUARE
HANGER, ANCHORS AND SUPPORTS
SECTION AC-140
Page 3

3.0

EXECUTION

3.1

INSTALLATION
.1

Support horizontal piping in accordance with the following schedule:


Pipe Size

Maximum Hanger
Spacing

Minimum Rod
Size

25mm and smaller

1800mm

10mm

32mm to 50mm

2700mm

10mm

65mm to 80mm

3000mm

15mm

100mm to 125mm

3600mm

15mm

150mm

3600mm

20mm

200mm to 300mm

3600mm

25mm

350mm to 400mm

3600mm

25mm

450mm

3600mm

30mm

500mm

3600mm

35mm

600mm

3600mm

40mm

750mm

3600mm

40mm

1000mm

3600mm

50mm

1200mm

3600mm

50mm

.2

Provide hangers at each change in direction and both sides of each valve.

.3

Provide drilled expansion type inserts to the reinforced concrete.


structural slab for pipe supports.

.4

Regardless of the type of construction (i.e., concrete, concrete-deck-steel


or other variations) take particular care to support all main lines and all
large and heavy pipes in an approved manner, including the furnishing
and installation of supplementary steel, if required. Supplementary steel
sections are to be mill-rolled. Submit shop drawings, indicating support
methods, point loadings to the building structure and hanger locations for
review sufficiently in advance of concrete pouring schedules to permit
evaluation, critique and any necessary changes to handling and support
methods.

.5

Provide approved roller support, floor stands, wall brackets, etc., for all
lines running near the floor or near walls, which can be properly
supported or suspended by the floors or walls. Pipelines near walls may
also be hung by hangers carried from approved wall brackets at a level
higher than the pipe.

.6

Do not hang piping from other piping. Support of hangers by means of


vertical expansion bolts is not permitted.

DAMANSARA CITY MIXED DEVELOPMENT (PARCEL 2)


HANGER, ANCHORS AND SUPPORTS
SECTION AC-140
Page 4

.7

Wherever hangers using pipe rolls are used provide approved steel pipe
covering protection saddles, spot welded to the piping at each hanger
location.

.8

Anchor piping and as required to localise expansion or to


strain on piping and branches. Anchors to be entirely
hangers. All anchor designs to be submitted for approval
piping reactions which respective anchors are capable
Provide all indicated or required expansion loops.

.9

Support all lines for copper tubing individually by approved type hangers
not more than 2m apart, or as shown on the drawings. Use hangers
especially designed for copper tubing and of exact outside diameter of
tubing. On hangers for covered tubing, use broad straps fitting outside of
covering.

.10

Hangers used for cold piping will support the pipe without piercing the
insulation. Use insulation shields to protect the insulation on cold pipes.
Weld insulation protection saddles to insulated hot pipes, or any piping
subject to axial movement, at roller supports. Space between pipe and
saddle to be filled with insulation.

.11

For piping 100mm and larger, support the elbows of the piping adjacent to
the pumps with steel base elbow supports from the inertia base which
pump is on to prevent loading heavy weights of piping on pump casing.
Where inertia base is not provided, base elbows to be supported on floor
with 25mm neoprene pad.

.12

Scratches and cut ends to be field touched up with protective paint or


galvanising agent.

END OF SECTION AC-140