03 12 General Design Design of Integral Bridges PDF
03 12 General Design Design of Integral Bridges PDF
03 12 General Design Design of Integral Bridges PDF
Summary:
Volume 1 Section 3
Part 12 BA 42/96
Registration of Amendments
REGISTRATION OF AMENDMENTS
Amend
No
Page No
Amend
No
Page No
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
Volume 1 Section 3
Part 12 BA 42/96
Registration of Amendments
REGISTRATION OF AMENDMENTS
Amend
No
Page No
Amend
No
Page No
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
VOLUME 1
SECTION 3
HIGHWAY STRUCTURES:
APPROVAL PROCEDURES
AND GENERAL DESIGN
GENERAL DESIGN
PART 12
BA 42/96
THE DESIGN OF INTEGRAL BRIDGES
Contents
Chapter
1.
Introduction
2.
General
3.
Earth Pressure
4.
References
5.
Enquiries
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
Volume 1 Section 3
Part 12 BA 42/96
Chapter 1
Introduction
1. INTRODUCTION
1.1 Expansion joints in bridge decks are prone to
leak and allow the ingress of de-icing salts into the
bridge deck and substructure, thereby resulting in
severe durability problems. In principle all bridges are
to be continuous over intermediate supports and
bridges with overall lengths not exceeding 60 metres
and skews not exceeding 30 are to be integral with
their abutments. (See BD 57, DMRB 1.3). This
Advice Note covers the design of integral highway
bridges without expansion joints.
1.2 Integral bridges are designed without any
expansion joints between spans or between spans and
abutments. Resistance to longitudinal thermal
movements and braking loads is provided by the
stiffness of the soil abutting the end supports and, in
some cases by the stiffness of the intermediate
supports.
ii) Abutment
The part of a bridge structure that abuts the roadway
pavement and formation at the end of a bridge.
iii) Bank Pad Abutment
Bank seat end support for bridge constructed integrally
with deck, acting as a shallow foundation for end span
and as a shallow retaining wall for adjoining
pavements and embankment.
iv) Embedded Abutment
End support for bridge comprising of a diaphragm
wall (including contiguous, or secant or sheet pile
walls) with toe embedded in ground below lower
ground surface.
Scope
Definitions
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
1/1
Chapter 1
Introduction
Volume 1 Section 3
Part 12 BA 42/96
x) Pavement/Abutment interface
The interface between the pavement construction and
the back face of the abutment.
xi) Range
Change (of temperature, strain) between extreme
minimum and extreme maximum.
xii) Stationary Point
The point on a bridge in plan which does not move
when the bridge experiences expansion or contraction
during changes in bridge temperature.
xiii) Sub-surface Drainage
A system for draining water from within the surfacing.
xiv) Surface
The carriageway or footway surface.
xv) Surfacing
Carriageway or footway wearing course and base
course materials.
Implementation
1.7 This Advice Note should be used forthwith for
all schemes currently being prepared provided that, in
the opinion of the Overseeing Organisation, this would
not result in significant additional expense or delay
progress. Design Organisations should confirm its
application to particular Schemes with the Overseeing
Organisation.
1/2
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
Volume 1 Section 3
Part 12 BA 42/96
Chapter 2
General
2. GENERAL
2.1 Integral bridges should support all the relevant
dead loading and live loading including all
longitudinal, and in the case of structures which are
curved in plan, centrifugal loading, in accordance with
BD37, (DMRB 1.3). They should also accommodate
the effects of thermal expansion or contraction without
excessive deformation of the approach pavements.
2.2 This Advice Note has been drafted for the types
of integral abutment illustrated in Figure 2.1 and
described below:
i)
The Frame Abutment which supports the
vertical loads from the bridge and acts as a retaining
wall for embankment earth pressures. It is connected
structurally to the deck for the transfer of bending
moments, shear forces and axial loads and supported
on foundations. It may be assumed that the abutment
will rock bodily on its foundation for the purposes of
calculating thermal movements and earth pressure. If
the back edge at the top of the abutment is behind the
back of the foundation, the design of the pavement/
abutment interface should provide for vertical
movement of the abutment edge during contraction of
the deck.
ii)
The Embedded Abutment, such as a diaphragm
wall, which extends to a depth below the retained fill
and is restrained against rocking by the length of
embedment.
Longitudinal Movement
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
2/1
Chapter 2
General
Volume 1 Section 3
Part 12 BA 42/96
steel
steel with concrete deck
concrete
i)
The bridge spans and abutments are joined
during construction at a temperature within 10C of
the mean between extreme minimum and extreme
maximum shade air temperatures as specified in
BD37, (DMRB 1.3).
ii)
For concrete and composite decks, concrete with
a coefficient of thermal expansion of 0.000012/C has
been assumed.
More detailed estimates of thermal strain may be
appropriate, based on data in BD37, (DMRB 1.3), if
the design specification does not limit the temperature
at the time of joining as above, if other materials are
used, or if special circumstances apply.
2.12 Lightweight aggregate concrete, and other
materials, can have coefficients of thermal expansion
2/2
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
Volume 1 Section 3
Part 12 BA 42/96
(a)
(d)
Chapter 2
General
(c)
(d)
(b)
(e)
Embedded abutment.
(c)
(f)
HGS 960413.DS4
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
2/3
Volume 1 Section 3
Part 12 BA 42/96
Chapter 3
Earth Pressure
3. EARTH PRESSURE
General
Kp
20 forwards 20 backwards
30
35
12
40
20
45
15
37
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
3/1
Chapter 3
Earth Pressure
(b) Full height frame abutment
3.5.2 The height of the abutment means that the
magnitude of passive pressures acting on the back of
the wall is likely to be significant(10). Careful design of
the abutment is therefore important to ensure the
structure is strong enough to resist lateral pressures
that could build up behind the wall, and yet flexible
enough to accommodate movement.
3.5.3 For a portal frame structure the earth pressures
on the retained side can be represented by a
distribution analogous to that employed for calculating
compaction stresses in backfill.(11) However for
integral bridges the use of wall friction will lead to
higher earth pressures at the top of the wall which will
extend to a greater depth than compaction effects. The
suggested distribution (see Figure 3.1) comprises:
3/2
Volume 1 Section 3
Part 12 BA 42/96
3.5.6 For an embedded wall the earth pressure
distribution(11) may be represented (see Figure 3.2) by:
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
Volume 1 Section 3
Part 12 BA 42/96
Chapter 3
Earth Pressure
Pavement
Wing walls
3.11 Road pavements should be constructed in
accordance with the Specification for Highway Works
right up to the back faces of integral abutments. The
surfacing can be laid as a continuous layer over the
approach roads and over the deck water proofing.
3.12 Asphaltic plug joints complying with BD33
(DMRB 2.3.6 ) may be used in the surfacing at the
interface between the back edges of integral abutments
and adjoining flexible pavements.
Drainage
3.13 Gullies should be located in roadside channels
on the uphill side at integral abutments to catch
surface water that might flow across the pavement/
abutment interface.
3.14 Flexible pavements should have a sub-surface
drain below the surfacing along the pavement/
abutment interface. The sub-surface drainage system
should have a fall of at least 2% and shall be easily
cleaned.
3.15 Integral abutments should have a permeable
backing as specified for earth retaining structures in
Specification for Highway Works. The permeable
backing should be drained with a pipe of at least
150mm diameter which has a fall exceeding 2% and
can be cleaned readily.
Foundations
3.16 Integral abutments can be founded on spread
footings or on piles.
3.17 Piles should be designed to accommodate lateral
movement and/or rocking of the abutment while
supporting axial loads, and to support forces from
movements of the piles and/or movements of the
ground. Raking piles should not be used for
foundations that move horizontally.
3.18 Bearing pressures under foundations which slide
while supporting vertical loads, such as bank pads,
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
3/3
Chapter 3
Earth Pressure
Volume 1 Section 3
Part 12 BA 42/96
K*
Earth pressure
based on K*
(see 3.5.3
and 3.5.4)
H/2
Earth pressure
based on Ko
Ko
K*
Earth pressure
based on K*
(See 3.5.3
and 3.5.4)
2H/3
Earth pressure
based on Ko
Ko
Figure 3.2 Earth Pressure Distribution for Full Height Embedded Wall Abutments
HGS 960413A.DS4
Figure 3.2 Earth Pressure Distribution for Full height Embedded Wall Abutments
3/4
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
Volume 1 Section 3
Part 12 BA 42/96
Chapter 4
References
4. REFERENCES
1.
2.
3.
British Standard BS 5400: Part 4: 1990. Code of Practice for the Design of Bridges. BSI.
4.
British Standard BS 8002: 1994. Code of Practice for Earth Retaining Structures.BSI
5.
British Standard BS 1377: Part 4: 1990. British Standard Methods of Test for Soils for Civil Engineering
Purposes;Compaction related tests. BSI
6.
7.
Kerisel J and Absi E (1990). Active and Passive Earth Pressure Tables, Balkema, Rotterdam.
8.
Draft for development DD ENV 1997-1: 1995. Eurocode 7: Geo technical design, Part 1.General rules
(together with United Kingdom National Application Document).
9.
Darley P, D R Carder and G H Alderman (1996). Seasonal thermal effects on the abutment of an integral
bridge in Glasgow. TRL Project Report 178. Crowthorne: Transport Research Laboratory.
10.
Darley P and G H Alderman (1995). Measurement of thermal cycle movements on portal frame bridges on
the M1. TRL Project Report 165. Crowthorne: Transport Research Laboratory.
11.
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
4/1
Volume 1 Section 3
Part 12 BA 42/96
Chapter 5
Enquiries
5. ENQUIRIES
All technical enquiries or comments on this Advice Note should be sent in writing as appropriate to:
A J PICKETT
Head of Bridges Engineering Division
N B MACKENZIE
Deputy Chief Engineer
K THOMAS
Director of Highways
D OHAGAN
Assistant Technical Director
November 1996
ELECTRONIC COPY NOT FOR USE OUTSIDE THE AGENCY.
PAPER COPIES OF THIS ELECTRONIC DOCUMENT ARE UNCONTROLLED
5/1