Bollard Pull Standard JIP PDF
Bollard Pull Standard JIP PDF
Bollard Pull Standard JIP PDF
kbasedonbollardpull5minutesfullscaleat560RPM
1.14
1.12
correctionfactork[]
L/Lt=1.0
For the determination of the bollard pull the ITS2002 Bollard Pull Trial
Code is currently the standard [1]. In this Code are described the bollard
pull trial conduct, the criteria and the corrections on the measured
bollard pull for non-ideal conditions. The completeness and corrections
applied in this Code, however, are disputable.
1.1
L/Lt=0.8
L/Lt=0.6
1.08
L/Lt=0.4
1.06
L/Lt=0.40
L/Lt=0.50
1.04
L/Lt=0.60
1.02
L/Lt=0.80
L/Lt=1.00
L/Lt=1.50
0.98
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
d/dmin[]
kbasedonbollardpull10minutesfullscaleat560RPM
1.14
1.12
With the Bollard Pull Standard JIP the relevant parameters that can be of
influence on the bollard pull will be investigated. The aim is to develop
an improved method for the bollard pull trial and bollard pull
determination which is generally accepted by all parties involved.
MARI N
P.O. Box 28
6700 AA Wageningen
The Netherlands
1.1
L/Lt=0.8
L/Lt=0.6
1.08
L/Lt=0.4
1.06
L/Lt=0.40
L/Lt=0.50
1.04
L/Lt=0.60
1.02
L/Lt=0.80
L/Lt=1.00
L/Lt=1.50
0.98
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
d/dmin[]
Black lines: ITS2002 publication and the coloured lines: current model tests.
Objectives
T +31 317 49 39 11
F +31 317 49 32 45
E [email protected]
I www.marin.nl
V. 2014/05/26_T&M
In the ITS2002 Bollard Pull Trial Code is also stated that the aim is to
start a discussion regarding bollard pull with an internationally accepted
bollard pull as the ultimate goal. However, this has never resulted in a
final standard. Currently, the bollard pull determination is interpreted
differently even by Classification Societies.
correctionfactork[]
L/Lt=1.0
Scope of work
References
[1] Bollard Pull Trial Code proposal, ITS 2002, Hannu Jukola and Anders
Skogman, Steerprop Ltd, Finland.
[2] MIIP pilot project: Bollard Pull Standard, Model tests to measure
effect of water depth and tow line length on bollard pull Trial Code,
MARIN report No. 26756-1-TM, January 2014.
Deliverables
The project will deliver specifications for the instrumentation and bollard
pull conduct standard. The corrections on the measured bollard pull that
are to be applied for the relevant parameters will be set out in a report.
Organisation
MARIN will lead this JIP in close co-operation with their participants.
Design offices, ship yards, shipping companies, suppliers and
classification societies are all invited to join this JIP.
Participant Meetings will be held every 6 months as part of the vessel
operator forum.
Schedule
The running time of the Bollard Pull Standard JIP is 1.5 years. The JIP is
scheduled to start in September 2014 and to finish in February 2016.
For more information please contact the department Trials & Monitoring;
Alfons Bruning
Henk van den Boom
T +31 317 49 33 65
+31 317 49 33 53
E [email protected]
[email protected]